HomeMy WebLinkAbout07/06/2010 14C 12th Avenue Sewer Improvements, Final Payment, West Coast Construction, Inc, WW2234 BUSINESS OF THE CITY COUNCIL YAKIMA, WASHINGTON AGENDA STATEMENT • Item No. ■f For Meeting Of 7/6/10 ITEM TITLE: Final Contract Payment for West Coast Construction, Inc. – 12 Avenue Sewer Improvements City Project No.` WW2234 (Standard Motion V -B – Accept the project and approve the final payment) SUBMITTED BY: Michael Morales – Director of Community & Economic Development CONTACT PERSON /TELEPHONE: Doug Mayo – City Engineer 509- 576 -6678 SUMMARY EXPLANATION: This project provided for the construction of a new sewer main and associated sewer services within 12 Avenue so as to provide sanitary sewer service to the residents along the west side of 12 Avenue between King Street and Mead Avenue. Final inspection for this project was made and the recommendation is that the project be accepted. This Council action is to accept the project and approve the final construction costs. Contractor: West Coast Construction, Inc. Contract Award: 11/20/09 Contract Cost: • $105,319.72 Final Contract Cost: $107,922.95 Amt. This Payment: -0- The above total contract cost is for construction only and does not include engineering and other costs. Resolution Ordinance X Other (Specify) Final Contract Payment Contract — to (name and address): Funding Source Wastewater Fund 476 APPROVED FOR SUBMITTAL: , N • City Manager STAFF RECOMMENDATION: Accept the project and approve final estimate. COUNCIL ACTION: Ili • • City of Yakima 'PROJECT TITLE 12th Avenue Sewer Improvements City Engineering Division • 129 N 2nd Street City Project No.: WW2234 . Yakima, WA 98901 TO, West Coast Construction Progress Estimate No.: Agenda Final Date: April 14, 2010 • Total ' ;,, To Date , /o.of „Amount ,: Previous . Pr evious ' " T T ; Amo "'" „ x; u unt ' Aect Umt Quarts ;Pnce ;, Amo unt � Quantrt Contract - ! � ,.- �..: - ua tY°�_ � � Y.. . ,,.: <..��• �., Q � .Payments .,, .this perrod.:�„. Due '�. 1 SPCC Plan LS 1 $1.00 $ 1.00 1 100% $ 1.00 .2 Mobilization LS 1 $9,000.00 $ 9,000.00 1 100% $ 9,000.00 3 Project Temporary Traffic Control LS 1 $8,000.00 $ 8,000.00 1.00 100% $ 8,000.00 4 Removal of Structure and Obstruction LS 1 $5,900.00 $ 5,900.00 1 100% $ 5,900.00 • 5 Saw -Cut Per Inch Depth LF 1,760 $0.20 $ 352.00 1475 84% .$ 295.00 6 Controlled Density Fill CY' 62 $90.00 $ 5,580.00 40 65% $ 3,600.00 7 Crushed Surfacing Top Course TON 172 $15.00 $ 2,580.00 480.74 280% $ 7,211.10 8 Pavement Repair SY 588 $30.00 . • $ 17,640.00 575 98% $ 17,250.00 9 Manhole 48" Diem. Type 1 . EA 3 $2,800.00 $ 8,400.00 3 100% $ 8,400.00 10 Shoring or Extra Excavation Class B LF 580 $2.00 $ 1,160.00 772 133% $ 1,544.00 11 Structure Excavation Class B, Incl. Diam. CY 605 $1.00 $ 605.00 605 100% $ 605.00 . 12 PVC Sanitary Sewer Pipe, 8 -inch Diam. LF 500 $48.00 $ 24,000.00 500 100% $ 24,000.00 13 PVC Sanitary Sewer Pipe, 4 -inch Diam. . LF 240. $38.00 $ 9,120.00 _ 272 113% $ 10,336.00 14 Repair or Replacement FA 1 $5,000.00 $ 5,000.00 3601.85 72% $ 3,601.85 Subtotal $ 97,338.00 $ 99,743.95 • . Sales Tax 8.2% $ 7,981.72 $ 8,179.00 Total $ 105,319.72 102% $107,922.95 •