HomeMy WebLinkAbout06/03/2008 17B Level 2 Domestic Water System Improvements Phase 2 Final Contract Payment, Project #2096 BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
II AGENDA STATEMENT
Item No. *178
For Meeting Of 6/3/08
ITEM TITLE: Final Contract Payment for Level 2 Domestic Water System Improvements
— Phase 2 — Project #2096
SUBMITTED BY: Water /Irrigation Department
CONTACT PERSON /TELEPHONE: Dave Brown — Water /Irrigation Manager
509 -576 -6204
SUMMARY EXPLANATION:
This project consisted of the construction of approximately 320 linear feet of new 16 -inch D.I.
water main, rehabilitation of reservoir overflow standpipes and access ladders; removal of
existing surge tower structure, manholes, pipe, valve, and fittings; abandonment of existing
piping; and repair of existing gravel surfacing; and other associated work.
Final inspection for this project was made and the recommendation is that the project be accepted.
® This Council action is to accept the project and approve the final construction costs.
Contractor: TTC Construction, LLC
Contract Award: 12/5/07
Contract Cost: $153,233.00
Final Contract Cost: $140,527.54
Amt. This Payment: -0-
The above total contract cost is for construction only and does not include engineering and other
costs.
Resolution Ordinance X Other (Specify) Final Contract Payment
Contract Mail to (name and address):
Funding Source Domestic Water Improvement Fund
APPROVED FOR SUBMITTAL: ,4e,4 City Manager
0 STAFF RECOMMENDATION: Accept the project and approve final estimate.
COUNCIL ACTION:
City of Yakima LEVEL 2 DOMESTIC WATER SYSTEM IMPROVEMENTS - PHASE 2 ,
Water and Irrigation Division
® 2301 Fruitvale Boulevard
City Project No.: WA2096
HLA Project No.: 060288 -C
Yakima, WA 98902
Progress Estimate No.: 5 and FINAL
TO: , TTC Construction, LLC
P.O. Box 365 Date: May 6, 2008
2208 Jerome Avenue
Yakima, WA 98907
•
tit m!5 q IFr I °" £7 ... 0 , i �� ?s t ' a�`�31, IAIr !� ' , Contract a� ; `+Estimate ; Quantityta I �' , tract
; . ; + „g g, i >,',; I, ? ,x „ De -o ,,,,x ,, i,,� F ' { tUjlet, Quanti I. .1f, `'PCICfl ' # ' Quantity t 1 t 0 Date :AIM IM i..Un � Con
i .Quiiiti1}(�'
1 Mobilization LS 1 $12,689.43 0% 100% $12,689.43 100%
2 Clearing and Grubbing LS 1 $4,265.66 0% 100% '$4,265.66 100%
3 Removal of Structures and Obstructions LS 1 . $13,684.24 0% 100% $13,684.24 100%
4 16 -Inch D.I. Water Main and Fittings, in Place LF 320 • $114.55 0 320 $36,656.00 100%
5 16 -Inch Butterfly Valve and Valve Box EA 1 $3,231.28 0 • 1 $3,231.28 100%
6 Reservoir Penetration for Pipe LS 1, • $4,484.05 0% 100% $4,484.05 100%
7 Combination Air Valve Assembly EA 1 $3,820.54 0 1 $3,820.54 100%
8 Replace Overflow Standpipe EA 2 $1,283.97 0 1 $1,283.97 50%
9 Replace Access Ladders EA 4 $3,222.00 0 4 • $12,888.00 100%
10 Abandon North Penetration - Reservoir No. 2 LS 1 $4,765.00 0% 100% $4,765.00 100%
11 Abandon Existing Irrigation Box • LS 1 $3,429.40 0% 100% $3,429.40 100%
12 Select Backfill, as Directed TN 500 . $18.73 0.0 132.8 $2,487.34 27%
13 Shoring or Extra Excavation LF 380 $2.63 0 320 $841.60 84%
14 Concrete Pipe Plug EA 9 • $972.71 0 9 $8,754.39 100%
15 Future Security Provisions • LS r, 1 $5,930.21 0% 100% $5,930.21 100%
0 16 Asphalt Roadway Repair SY 25 . $77.64 0 35.8 $2,779.51 143%
17 Gravel Surface Repair SY 875 $4.83 0 875 $4,226.25 . 100%
18 Project Temporary Traffic Control LS 1 $2,922.36 0% 100% $2,922.36 100%
19 Minor Changes FA EST. $5,000.00 0.00 7,030.87 $7,030.87 141%
. SUBTOTAL, WORK TO DATE $136,170.10
•
G:IPROJECTS1200610602OB -C TTCIPROGRESS ESTIMATES \050705 PROGRESS ESTIMATE 5 AND FINAL 1
Huibregtse,• Louman Associates, Inc.
•
veltm Contract .�Untt Est e ,Quantt � ontract:
''h `� a �i3 '� .0 m - °a � t 3w 1`�;i g
tlni .,.F P ice,..„ Itouanfit o ate'. h,:�q"moun0 ,Quantity;
SUBTOTAL, WORK TO DATE $136,170.10
PLUS MATERIALS ON HAND $0.00
SUBTOTAL AMOUNTS $136,170.10
8.2% STATE SALES TAX $11,165.95
TOTAL $147,336.05
LESS TOTAL RETAINAGE $6,808.51
LESS AMOUNTS PREVIOUSLY PAID $140,527.54
AMOUNT NOW DUE $0.00
•
Progress Estimate No. 1 $ 57,091.47
Progress Estimate No. 2 $ 46,689.67
Progress Estimate No. 3 $ 15,579.30
Progress Estimate No. 4 $ 21,167.10
Progress Estimate No. 5 and FINAL $ 0.00
I hereby certify that the foregoing is a true and correct statement of the work performed under this Contract.
4;YK.,
Gene W. Soules, PE
• •
ACCEPTED:
I hereby accept this Final Progress Estimate and Final Contract Voucher Certification, in accordance with Section 1 -09.9 of the
WSDOT Standard Specifications.
i
TTC Construction, LLC Date:
•
•
•
GAPROJECTS120DSIDS028B"C TTCWROGRESS ESTIM■TES1050708 PROGRESS ESTIMATE 5 AND FINAL 2
•
Huilbregtse, Louman Associates, Inc.
•
410 City of Yakima LEVEL 2 DOMESTIC WATER SYSTEM
Water and Irrigation Division IMPROVEMENTS - PHASE 2
2301 Fruitvale Boulevard
Yakima, WA 98902 City Project No.: WA2086
• HLA Project No.: 06028B -C
TTC Construction, LLC Progress Estimate No.: 5 and FINAL
P.O. Box 365
2208 Jerome Avenue
Yakima, WA 98907 Date: May 6, 2008
MINOR CHANGES
� i �: E § :_:: qt r � � f:- P t z ' � d W'x`t� 7 r� � 5 n .�' } . � ,'€rc^u":w ItC n a*�"'�. � � � � t� l �e / �. ± $,'�' °#t ! � S,*�� •, y - g � KN�� s ��i?�
f, ? �` .> ; ,f f"w :�7 .� �A,? ? t ! f p: � P rA a r l � $' Y 9 It t "z¢s 4 r '` `� � r � ke P r �"YZ'��y #i"" l � ` G fi r: P5 ,f 1 d 11 1 .' a AL tYF.. � +l
s a 1 'Ptti S '6J € k » , ,� �xfi S Y �Md0N 11t' t b1J
.Q I � f ��a�...���'�.. �' ... r.'..r� . ;,�� ^��_� y'��'. s...N .� .�.�� �aPi4�tD „SAS, � :�.: A <�....7'.. `� ,.������1NI. _ NT {���.�
Manhole steps Item 19 $188.70 $188.70
Field lock gaskets for pressure testing- 2 @ $332.72 Item 19 $665.44 $665.44
At the Surge Tower, fabricate plug and grout • Item 19 $536.00 $536.00
Repair 24” pipe at Booster Pump Station Item 19 $88.50 $88.50
Temporary driveway for access to the residence at the reservoir Item 19 $224.00 $224.00
site
Safety Grate at Reservoir 2 East Item 19 $1,376.80 $1,376.80
® Add nylon spacer blocks to make ladder fit the out of plumb Item 19 ' $348.70 $348.70
reservoir wall
Fabricate new overflow pipe brackets due to conflicts with the Item 19 $118.00. $118.00
ladder
Remove and reset hood to clear ladder. Item 19 $282.00 $282.00
Add electrical junction box at the booster pump station Item 19 $423.63 $423.63
Additional coring costs for 18" wall thickness shown vs. 33" Item 19 $370.00 $370.00
thickness found.
Overflow Hood Screen Covers Item 19 $727.64 $727.64
Labor to replace the standard Air Release Valve with a low Item 19 $118.00 $118.00
pressure model
Repair the rusted out lower portion of the Reservoir 2 overflow Item 19 $1,563.46 $1,563.46
pipe
TOTAL $7,030.87
cc: .
TTC Construction, LLC
Gene Soules
Steve Sziebert
0 Vic DeBlasio
G:\PROJECTS12006 \060288 -C TTC \PROGRESS ESTIMATES \050708 PROGRESS ESTIMATE 5 AND FINAL
Huibregtse,. Lowman Associates, Inc.