HomeMy WebLinkAbout07/15/2008 07 Six-year TIP for 2009-2014; Metropolitan Transportation Plan Amendement; Yakima UACP Amendment BUSINESS OF THE CITY COUNCIL
• YAKIMA, WASHINGTON
CORRECTED
AGENDA STATEMENT 7
Item No.
a
For Meeting of July 15, 2008
ITEM TITLE: Public Hearing to consider:
A) Adoption of the Six -year Transportation Improvement Program (TIP) for
years 2009 to 2014, and to amend the Metropolitan Transportation Plan;
and
B) Amend the Yakima Urban Area Comprehensive Plan Capital Facilities
Element to incorporate the adopted Six -year Transportation Improvement
Program (STIP).
SUBMITTED BY: Department of Community and Economic Development -
William Cook, Director
411 CONTACT PERSON/TELEPHONE: Brett Sheffield, P.E., Chief Engineer, 576 -6797
SUMMARY EXPLANATION:
See Attached.
Resolutions X Ordinance Contract Other (Specify) STIP and STIP Form Instructions
Funding Source
APPROVED FOR SUBMITTAL: 1
City Manager
ag er
STAFF RECOMMENDATION:
1) Hold the Public Hearing to consider adoption of Resolution approving the Six -year TIP
and amending the regional Metropolitan Transportation Plan and the Comprehensive Plan
Capital Facilities Element.
2) Adopt the plan.
BOARD /COMMISSION RECOMMENDATION:
IP COUNCIL ACTION:
Six -year Transportation Improvement Program (continued)
SUMMARY EXPLANATION: Attached is the 2009 -2014 Six -Year TIP. Three projects have been added to
• the six -year TIP following the July 1, 2008 meeting. These projects are:
• #74. SR12 and 16 Avenue Interchange Improvements
• #75. I -82 and `G' Street Interchange
• #76. Fair Avenue and Yakima Avenue Intersection Signal
Project rankings are determined by reviewing data supplied by the City's Street and Traffic Division and
integrating particular needs of the City.
Projects that were deleted from the 2008 -2013 TIP as they were completed or funds were obligated include:
• Downtown Yakima Futures Initiative, Phase 3
• Tieton Pedestrian Safety Improvements
Council and the public are welcome to add other arterial system projects to this list. The Six -Year TIP listing
will be finalized at today's hearing and sent to Yakima Valley Conference of Governments, (YVCOG) after
approval.
City and County staff, together with the Council Intergovernmental Committee, are working toward common
standards and coordinated planning for public projects that impact both the city and surrounding county areas.
• Agreement on these issues will be the first step toward the goal of a seamless transportation planning process
between the City and County.
A) Each year the City is required by RCW 35.77.010 and RCW 36.81.121 to update its Six -Year
Transportation Improvement Program (TIP) for submittal to the Washington State Department of
Transportation. This plan must include all transportation projects for which state gas tax revenue or
federal revenue will be used.
The plan for 2009 — 2014 includes sixteen (16) funded projects and locally identified activities. Funding for
the remainder of the projects will continue to be sought.
On August 10, 2005, the President signed into law the Safe, Accountable, Flexible, Efficient Transportation
Equity Act: A Legacy for Users (SAFETEA -LU). This act is the next authorization after the prior
Transportation Equity Act of 1998 for the 21 Century (TEA -21) and previous Intermodal Surface
Transportation Efficiency Act (ISTEA) of 1991. The current act again specifies the systems on which certain
funds can be used, and activities for which funds can be used and promotes the role of the Metropolitan Planning
Organizations (MPO) in the planning and programming of projects. SAFETEA -LU requires each designated
MPO to develop a Transportation Improvement Program (TIP), and the state to develop a Statewide
Transportation Improvement Program (STIP) as a condition to securing federal funds for the transportation
projects.
Projects listed in the STIP that are on an identified federal route are the only projects that will be eligible for .
approval by the Federal Highway Administration (FHWA) and the Federal Transit Administration (FTA) to
• utili7 federal funds or by the State of Washington for approved State - funding agencies. The STIP is a
prioritized program of transportation projects, compiled from local and regional plans, along with the
2 - July 14, 2008
Washington Transportation System Plan (WTP), which provides a backbone for developing projects for the ,
intermodal transportation network in the State of Washington.
The STIP contains federally funded projects plus state and local projects that are regionally significant. These
projects have been identified through the planning process as the highest priority for the available funding to
the state's transportation program.
Planning activities of state and local governments are essential parts of integrated regional planning processes.
Long range transportation planning is a part of the comprehensive land use planning carried out by local
governments. Citizen participation is an integral part of the planning process at all levels. Local Agencies are
required to develop and adopt a six -year transportation program. All local agencies are required to hold at
least one public hearing during the development of the six -year transportation program. All Transaction
Committee projects within the city limits are listed in the TIP with at least preliminary engineering needs
identified.
B) The City needs to amend the Yakima. Urban Area Comprehensive Plan Capital Facilities Element to
incorporate the adopted Six -year Transportation Plan for 2009 to 2014. This will ensure that we are in
compliance with the Growth Management Act and that we are consistent with the Comprehensive Plan as
required. This amendment is limited to incorporate only those projects that are adopted in the STIP and is
not subject to the "once a year" change required under the laws of the Growth Management Act.
•
•
RESOLUTION NO. R — 2008 -
A RESOLUTION adopting a Six -Year Transportation Improvement Program for the period of
2009 through 2014 for the construction of streets and arterials streets in the
City of Yakima and amending the Metropolitan Transportation Plan.
WHEREAS, the City of Yakima annually prepares, reviews and adopts a Six Year Program
for the construction of streets and arterial streets in the City of Yakima for the' ensuing six year
period, all as contemplated and required by State RCW 35.77.010 and applicable Federal law; and
WHEREAS, the City of Yakima desires to amend the Metropolitan Transportation Plan to
ensure compliance with the Growth Management Act and the regional transportation plan for the
construction of streets and arterial streets in the City of Yakima, all as contemplated and required by
State and Federal law, and •
WHEREAS, after public hearings on the matter, held at regular meetings of the Yakima City
Council on July 1, 2008, and on July 15, 2008, with proper public notice as required by RCW
35.77.010, the City Council finds that the plan attached hereto should be adopted as the Six -Year
Transportation Improvement Program for the period of 2009 through 2014 for the construction of
streets and arterial streets in the City of Yakima, now, therefore,
411 BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
The Six -Year Construction Program for the period of 2009 through 2014, a copy of which is
attached hereto and by this reference made a part hereof, is hereby adopted as the official Six -Year
Transportation Improvement Program for the City of Yakima, including proposed amendments to the
Metropolitan Transportation Plan along with Street Improvements, which are also approved.
ADOPTED BY THE CITY COUNCIL this 15th day of July, 2008.
David Edler, Mayor
ATTEST:
•
City Clerk
•
• RESOLUTION NO. R — 2008 -
•
A RESOLUTION to amend the Yakima Urban Area Comprehensive Plan Capital Facilities
Element to incorporate the Six -year Transportation Improvement Program
(TIP) for the period of 2009 through 2014
WHEREAS, the City of Yakima annually prepares, reviews and adopts a Six Year
Transportation Improvement Program for the construction or repair of streets and arterial streets in
the City of Yakima for the ensuing six year period, all as contemplated and required by State RCW
35.77.010 and applicable Federal law; and
WHEREAS, the City of Yakima desires to amend the Yakima Urban Area Comprehensive
Plan Capital Facilities Element to reflect the adoption of the 6 -Year TIP, as contemplated and
required by RCW 36.70A.070(6) to ensure compliance with the Growth Management Act and
' consistency of the Comprehensive Plan and the 6 -Year TIP; and,
WHEREAS, this amendment is limited to incorporation of the projects listed in the 6 -Year
Transportation Improvement Plan for the period of 2009 to 2014 to the Capital Facilities Element of •
the Yakima Urban Area Comprehensive Plan, which is contemplated and provided under RCW
36.70A.130(2B) and RCW 35.77.010; and,
WHEREAS, public hearings have been held by the Yakima City Council on the 6 -Year TIP
on July 1, 2008 and again on July 15, 2008, with proper public notice as required by RCW 35.77.010;
now, therefore
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
The adopted 6 -Year Transportation Improvement Program for the period of 2009 through 2014 for
the City of Yakima shall be incorporated as an amendment to the Capital Facilities Element of the
Yakima Urban Area Comprehensive Plan.
ADOPTED BY THE CITY COUNCIL this 15th day of July, 2008.
• David Edler, Mayor
•
ATTEST:
City Clerk
•
•
•
•
9. Appendices
A. Six Year Form Instructions
Heading
• Agency Enter name of the sponsoring agency.
County Number Enter .the OFM assigned number (see LAG Appendix 21.44).
City Number Enter the OFM assigned number (see LAG Appendix 21.45).
MPO /RTPO Enter the name of the associated MPO (if located within urbanized area) or
RTPO (if located in a rural area).
Hearing Date Enter the date of the public hearing.
Adoption Date Enter the date this program was adopted by council or commission.
Resolution Number Enter Legislative Authority resolution number (if applicable.)
Amendment Date Enter the date this program was amended by council or commissio n.
Column Number
•
1. Functional Classification. Enter the appropriate 2- digit code denoting the Federal
Functional Classification. (Note: The Federal Functional Classification must be
approved by FHWA.)
Description .
00- No Classification
Rural (Under 5000 pop.) Urban (Over 5000 pop.)
01 - Interstate 11- Interstate
02 - Principal Arterials 12- Freeways & Expressways
06 - Minor Arterials .. 14- Other Principal Arterials
07 - Major Collector 16- Minor Arterial
08 - Minor Collector • 17- Collector
. 09 - Local Access 19- Local Access
1. Priority Numbers. Enter local agency number identifying agency project priority
(optional).
2. Project Identification. Enter (a) Federal Aid Number if previously assigned; (b)
Bridge Number; (c) Project Title; (d) Street/Road Name or Number /Federal Route
Number; (e) Beginning and Ending Termini (mile post or street names); and (f)
Describe the Work to be Completed.
•
3. Improvement Type Codes. Enter the appropriate federal code number.
Description
01- New construction on 07 - Resurfacing 14 - Bridge Program - Special
new alignment 08 - New Bridge Construction 21 - Transit Capital Project
02- Relocation 09- Bridge Replacement 22- Transit Operational
Project
03- Reconstruction 10 - Bridge Rehabilitation 23 - Transit Planning
• 04- Major Widening • 11 - Minor Bridge Rehabilitation 24 - Transit Training /Admin.
05 Minor Widening 12 - Safety /Traffic Operation /TSM 31- Non Capital Improvement
06- Other Enhancements 13 - Environmentally Related 32 - Non Motor Vehicle Project
•
25
•
O
• 5. Funding Status. Enter the funding status for the entire project which describes the
current status.
S - Project is selected by the appropriate selection body and funding has
been secured by the lead agency.
P - Project is subject to selection by an agency other than the lead and is
listed for planning purposes. (Funding has not been determined.)
6. Total Length. Enter project length to the nearest hundredth (or code "00" if not
applicable)..
7. Utility Code(s). Enter the appropriate code letter(s) for the utilities that would
need to be relocated or are impacted by the construction project.
C -Cable TV G -Gas
O - Other P Power
S - Sewer (other than agency- owned) T - Telephone
W - Water
8. Project Phase. Select the appropriate phase code of the project.
PE - Preliminary Engineering only (or Planning) 411
RW - Right of Way or land acquisition only (or equipment purchase)
CN - Construction only (or transit operating)
ALL - AM Phases: from Preliminary Engineering through Construction
9. Phase Start Date. Enter the month /day /year in MM /DD/YY format that the
selected phase of the project is actually expected to start.
10. Federal Fund Code. Enter the Federal Fund code from the table.
FTA Discretionary for Capital Expenditures
BIA - Bureau of Indian Affairs 5307 - FTA Urban Areas
BR - Bridge Replacement or Rehab. 5309(Bus)- Bus
CDBG - Community Development 5309(FG) - Fixed Guideways .
Block Grant (HUD) 5309(NS) - New Starts
CMAQ - Congestion Mitigation Air Quality • 5310 - FTA Elderly /Disabled
DEMO - ISTEA Demo Project (Selected) 5311 - FTA Rural Areas
Discretionary - Ferry Boat Discretionary, Public REV - Rural Economic Vitality Program
Lands Highways, or Scenic Byways STP(C) - STP Statewide Competitive Program
DOD - Dept. of Defense STP(E) - STP Transportation Enhancements
IC - Interstate Construction STP(S) - STP Safety Including Hazard and RR
IM' - Interstate Maintenance STP(R) - STP Rural Regionally Selected
NHS - National Highway System STP(U) - STP Urban Regionally Selected
STP - WSDOT use only
11. Federal Funds. Enter the total federal cost (in thousands) of the phase
regardless of when the funds will be spent.
• 12. State Fund Code. Enter the appropriate code for any of the listed state funds 111
to be used on this project.
26
•
•
CAPP - County Arterial Preservation Program PWTF - Public Works Trust
CHAP - City Hardship Assistance Program RAP - Rural Arterial Program
• TPP - Transportation Partnershis Program SCP - Small City Program
• AIP - Arterial Improvement Program WSDOT - WSDOT funding
PSMP - Pedestrian Safety & Mobility Program OTHER - All other unidentified state funding
PTST - Public Transportation Systems Progra
13. State Funds. Enter all funds from the State Agencies (in thousands) of the phase
regardless of when the funds will be spent.
14. Local Funds. Enter all the funds from Local Agencies (in thousands) of the phase
regardless of when the funds will be spent.
15. Total Funds. Enter the sum of columns 10, 12, and 14. (Auto - calculation in the "STIP
Too" program.)
16 -19. Expenditure Schedule - (lst, 2nd, 3rd, 4th thru 6th years).. Enter the estimated
expenditures (in thousands) of dollars by year. (This data is for Local Agency use.)
20. Environmental Data Type. Enter the type of environmental assessment that will be
S required for this project. (This is "required" for Federally funded projects, but may be
filled in for state or locally funded projects.)
• EIS - Environmental Impact Statement
EA - Environmental Assessment
CE - Categorical Exclusion
21. RAN Certification. Click Yif Right of Way acquisition is required._ If yes, Enter R/W
Certification Date, if known. (This is "required" for Federally funded projects only.)
•
•
•
27
AM. '
Si Y ear T Im provement Program
T Washington State Department o Transportation
- Agg en ncy: Yakima • From 2009 to 2014
Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -1 -2008 Adoption Date: •
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
(a
A. PIN /Federal Aid No. B. Bridge No. c 6 m N Fund Source Information Expenditure
A e Schedule Projects Only
.T+ � E OI 9 ( 9 Y)
g m : o C. Project Title a 3 c ii Federal Funding R/W
c r > D. Street/Road Name or Number o rn Phase Federal Federal State 4th Required
t` o Z E. Beginning MP or Roa - Ending MP or Road E I - o - o Start Fund Cost by Fund State Local Total 1st • ' 2nd 3rd Thru Envir. Date
F. Describe Work to be Done
a (mm/dd/j yyy) Code Phase Code Funds Funds Funds 6th T ype (MM/YY)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
CN 1/1/2009 FMSIB 4500 1000 5500
14 1 01 S 0.2 T CN 1/1/2009 • OTHER 2250 . 2250 EA
Yakima Railroad Grade Separations - Phase 2 06 G CN 4/1/2009 STP(U) 20600 AIP 4650 25250 15000 18000 Yes
Lincoln Ave. 8 Martin Luther King J. Blvd. 07 0
from: N 1st St to: N 1st Ave - 08 w 3/01/07
Construct Grade Separations and adjacent roadway reconstructon, S
including realignment of Front Street. .
Totals 20,600 11400 1000 33000 15000 18000
14 2 01 S 1.0 P CN 4/1/2009 3840 38401 3840 EA
16TH AVENUE REALIGNMENT 08 0 Yes
16TH AVENUE REALIGNMENT T
from: AHTANUM ROAD to: WASHINGTON AVENUE W
S 11/2007
Realign 16th Avenue out of the runway safety area of the Yakima Air
Terminal. Includes FAA funds.
Totals 3840 3840 3840
PE 1/1/2009 STP(E) 18 32 50 50
00 3 03 P N/A G CN 6/1/2009 STP(E) - 1900 285 2185 2185 EA
YVT Railway Rehabilitation & Museum .0 No
3rd Ave S
from: 3rd Ave to: Pine St T
W
Car Bam, Museum Restoration and Pathway P
Totals • 1,918 317 2235 2235
N/A CN 1/1/2009 5307 1655 1655 33101 3310
00 4 12 S CE
Transit Operating Expenditures 22 No
Various Funding Areas 23
from: N/A to: N/A 24
Supplemental Funding far Transit Service Operating Expenses 31
Totals 1,655 1655 3310 3310
v. 5.7 - Supersedes previous editions
Report Date: July 10, 2008 . Page 1
40/ 0 0
•
. 0 .
• .
•
•
P
�' Washington State Department of Transportation Six Year Transportation Improvement Program
Agency: Yakima From 2009 to 2014
Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -1 -2008 Adoption Date:
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
m T ._ A. PIN /Federal Aid No. B. Bridge No. m t . d a) Fund. Source Information Expenditure Schedule Projects Only
a m o C. Project Title d d J .. Federal Funding (Local Agenc}� •
R/W
c� eL Z D. StreeURoad Name or Number .. S i Phase Federal Federal State 4th Required
LL E. Beginning MP or Road - Ending MP or Road E B ° Start Fund Cost b Fund State Local Total Envir. Date
° y Funds Funds Funds 1st 2nd 3rd 6 h Type (MM/YY)
F. Describe Work to be Done a. (mm/dd/yyyy) Code Phase Code
1 2 3 4 5 6 7 8 9 • 10 11 12 13 14 15 16 17 18 19 20 21
00 5 03 S N/A C PE 1/1/2009 STP(E) 36 36 36
RW 1/1/2009 STP(E) 205 205 205 CE
YVT Trolley Barn/Powerhouse Rehabilitation G CN 1/1/2009 STP(E) 255 255 255 Yes
S 3rd Ave O
from: to: P
Minor car barn and powerhouse restoration including property purchase S 06/01/07
T
W Totals 496 496 496
00 6 22 S N/A ALL 1/1/2009 ' . WSDOT 50 50I 50 CE
Street Asset Amenities (Transit) 31 No
Route Maintenance, Repair and Improvements
from: to:
Maintenance of Shelters, Benches and Signage throughout our Transit
Route System
Totals . 50 50 50
00 7 32 S 1.0 o CN 4/1/2009 STP(E) 525 5251 525
CE
William 0 Douglas Trail 08 P N
6th Ave Pathway & Bridge Decking 06 S
from: to: • W
Build pathway and install pathway decking an Neches River bridge with T
partner William 0. Douglas Trail Fundation
. Totals . 525 525 525
00 8 32 S N/A G PE 1/1/2009 STP(E) 65 - 65 65
RW 1/1/2009 STP(E) 150 150 150 CE
. William 0. Douglas Heritage Trails 13 P CN 1/1/2009 STP(E) 285 285 285 . Yes
Bridge Restoration & Trailhead 10
S
from: to: T 01/01/07
Trailhead restoration, right of way acquisition partner with the Wiliam 0. W -
Douglas Foundation, including restoration of bridge , cleaning, rust removal •
and painting Totals 500 • 500 500
v. 5.7 - Supersedes previous editions
Report Date: July 10, 2008 Page 2 p ersees P
•
Ilk
Washington State Department of Transportation
Six Year Transportation Improvement Program
- Agge en ncy: Yakima From 2009 to • 2014
Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -1 -2008 Adoption Date:
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
A. PIN /Federal Aid No. B. Bridge No. c E e y Fund Source Information Expenditure Schedule Projects Only
To w m d m o N (Local Agency)
0 m ; C. Project Title m n .9 3 c .c Federal Funding R/W
L U D. Street/Road Name or Number oo -r u 1: o Phase Federal Federal State 4th Required
LL E I ; Start Fu Cost b Fund State Local Total Thru Envir. Date
MP
E. Beginning or Road - Ending MP or Road o y Funds Funds Funds 1st 2nd 3rd T M/
ype (MY10
F. Describe Work to be Done a (mm/ddyyyy) Code Phase Code 6th
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
ALL 1/1/2009 WSDOT 51 9 60 60
00 9 22 S N/A
Transit Service to Terrace Heights No
New University & Retail Links
from: to:
Provide Transit service to this growing area of Yakima County to include the •
new University & Retail Shops.
Totals 51 9 60 60
PE 1/1/2009 TPP 200 300 500 500 EA
14 10 04 P .77 P RW 1/1/2009 200 200 200
Nob Hill Blvd C CN 1/1/2009 STP(U) 1000 TPP 1300 2000 4300 4300 Yes
Nob Hill Blvd O
from: S 52nd Ave to: S 68th Ave S 01/01/07
Widen, curb, gutter, sidewalk, lighting, drainage T
W Totals 1,000 1500 2500 5000 5000
PE 1/1/2009 STIP (S) 60 60 120 120 CE
00 11 . 01 P N/A CN 4/1/2009 STP(S) 180 AIP 240 420 420
Annual Signal Upgrades CN 4/1/2009 STIP (S) 360 360 360 No
Local Selection
from: N/A . to: N/A
Upgrade signals .
Totals 600 240 60 900 120 780
00 12
07 P N/A w CN 6/1/2009 STP(U) 228 32 2601 260 EA
Various Overiav ProlectsfSelected on Local Priority S No
N/A
from: N/A to: N/A
•
Totals 228 32 260 260
v. 5.7 - Supersedes previous editions
Report Date: July 10, 2008 Page 3
110 0 . II
• • • •
•
Washington State Department of Transportation Six Year Transportation Improvement Program
Agency: Yakima From 2009 to 2014
Co. No:: 39 Co. Name: Yakima Co: Hearing Date: 7/1/2008 Adoption Date:
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
m D at A. PIN/Federal Aid No. B. Bridge No. m o d w Fund Source Information Expenditure Schedule Projects Only
4 m . o E C Project T i t le d d J L Federal Funding (Lo Agency)
c U P D. Street/Road Name or Number o r Z' 0-
R/W
7 a Z a1- rn 9 Phase Federal Federal State 4th Required
LL E. Beginning MP or Road - Ending MP or Road E 1- S tart Fund Cost b Fund State Local Total Envi Date
(17.; mm/dd/ y Funds Funds Funds 1st 2nd 3rd Thru Type (MWy
F. Describe Work to be Done a ( yYYY) Code Phase Code 6th
1 2 3 4 5 6 7 8 • 9 10 11 12 . 13 14 15 16 17 18 19 20 21
00 13 32 P N/A PE 1/1/2009 100 100 100
Storm Drains/Vegetation CN 1/1/2009 900 900 900 EA
No
Local Selection
from: City Wide to:
City Vide
Totals 1000 1000 1000
17 14 • 03 P 76 W PE 1/1/2010 STP(C) 109 27 136 136
CN 1/1/2011 STP(C) 945 TPP 945 106 1996 1996 CE
Reconstruction Rudkin Rd , 06 T No
Rudkin Rd P
from: E Viola Ave to: Rainier Place S
Reconstruct, excavate ballast, top course, curb, gutter, sidewalk
Partner with City of Union Gap, additional sewer force main •
Totals 1,054 - 945 133 2132 136 1996
16 15 03 P .76 C PE 9/1/2010 STP(S) 122 TPP 23 7 152 152
CN 4/1/2010 STP 1730 TPP 206 70 2006 2006 CE
E Mead Ave Reconstruction 06 G No
E Mead Ave 0
•
from: Rudkin Rd to: Fair Ave P .
•
. Partner with City of Union Gap, reconstruct, excavate ballast, top course, T
curb, gutter, storm. acp
. Totals 1,852 229 77 2158 152 2006
19 16 03 P N/A p PE 1/1/2010 STP(U) 100 14 114 114
CN 1/1/2011 STP(U) 700 95 7951 . 795 CE
Longfiber Rd & Washington Ave 05 S Yes
Intersection 06 W
T
from: to: 0 7/1/2009
New intersection construction and reconstruction, 3 -lane and 5 -lane wtum,
curb, gutter, sidewalks.
Totals 800 109 909 114 795
•
v. 5.7 - Supersedes previous editions
Report Date: July 10, 2008 Page 4 P p
•
•
•
WashingtonStateDepartmentofTransportation Six Year Transportation Improvement Program
Agency: Yakima From 2009 to 2014 .
Co. No.: 39 Co. Name: Yakima Co. .
Hearing Date: 7/1/2008 Adoption Date:
City No.: 1485 MPO /RTPO: YVCOG • Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
To 65
A. PIN /Federal Aid No. B Bridge No. m y F und Source Information
I') o xpenditure Schedule Projects Only
°1 — O
o . C. Project Title d J t (Local Agency) Federal Funding R/W
c U a D D. Street/Road Name or Number ° y Cl- Phase Federal Federal State 4th Required
� _ Z E o State Local Total Envir. Date
E. B MP or Road - Ending MP or Road g 5 . Start Fund Cost by Fund Funds Funds Funds 1st 2nd 3rd Thru Type (M»
• F. Describe Work to be Done a (mm/dd/yyyy) Code Phase Code 6th
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
04 P
.1 C CN 1/1/2009 STP(U) 240 42 282 282
14 17 CE .
E Nob Hill Blvd 8 S 18th St 0 1 S Yes
E Nob Hill Blvd W
from: S 18th St to: E Nob Hill Blvd T
01/01/07
Wden south leg for double LT from west bound Nob Hill: (Tie to WSDOT
Project) possible curb, gutter and sidewalk Totals 240 42 282 282
PE 4/1/2009 CMAQ 24 3 27 27
16 18 01 P N/A S CN 7/1/2009 CMAQ 480 65 5451 545 CE
Roadway City l4ffde Shoulder Improvements No
City Wide .
from: to:
City Wide shoulder improvements, PM10 abatement. •
Totals 504 68 572 572
14 19 31 S N/A O PE 1/1/2009 STP(U) 1 72 11 831 83 CE
E Nob Hill Blvd 8 Fair Ave 03 C Yes
E Nob Hill Blvd 04 P
from: E Nob Hill Blvd to: Fair Ave • T
W 10/01/2009
Intersection widening 8 new signal, curb, gutter and sidewalk, street
lighting, stormwater
Totals 72 11 83 83
17 20 04 P 1.3 0 PE 1/1/2009 AIP 131 20 151 151
RW 1/1/2010 AIP 382 59 441 441 EA
S 80th Ave - Tieton Dr to Zier Rd P CN 6/1/2010 AIP 1667 260 1927 1927 Yes
S 80th Ave
•
from: Tieton Dr • to: Zier Rd T
•S ._ 01/01/09
Major widening, curb, gutter, sidewalk •S
Totals 2180 339 2519 151 2368
Report Date: July 10, 2008 Page 5 v. 5.7 - Supersedes previous editions
e O
O
• • 0
Washington State Department of Transportation Six Year Transportation Improvement Program
•
Agency: Yakima From 2009 to 2014
Co. No.: 39 Co. Name: Yakima Co. Hearing Date: .7/1/2008 Adoption Date:
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
• Project Identification Project Costs in Thousands of Dollars Federally Funded
m T A. PIN /Federal Aid No. B. Bridge No. d -2.. d d Fund Source Information Expenditure Schedule Projects Only
C N =' C. Project Title E m d r Federal Funding (Coca/ Agency)
. -3 al o f > 3 3 _ 9 R/W
n U li Z D. Street/Road Name or Number a1 rn 3 8 u Phase Federal Federal State 4th Required
E. Beginning MP or Road - Ending MP or Road E t °� Start Fund Cost by Fund State Local Total Envir. Date
y Funds Funds Funds 1st 2nd 3rd Thru Type F. Describe Work to be Done a (mm/dd yyyy) Code Phase Code 6th yP (M h
1 2 3 4 5 6 7 8 9 10 11 12 13 . 14 15 16 17 18 19 20 21
PE 1/1/2009 STP(E) 22 7 29 29
17 21 05 . S .15 C CN 6/1/2009 STP(E) 75 20 95 95 CE
• Zier Rd - S 75th Ave to S 72nd Ave 06 S Yes
Zier Rd T
from: S 75th Ave to: S 72nd Ave P
Minor widening, curb, gutter and sidewalk 03/01/09
Totals 97 27 124 124
17 22 05 P 1.0 W PE 1/1/2012 STP(C) 272 43 315 315
RW • 6/1/2012 STP(C) 349 55 404 404 EA
Englewood Ave - N 40th Ave to N 56th Ave 06 S CN 1/1/2013 STP(C) 2352 340 2692 2692 • Yes
Englewood Ave T
from: N 40th Ave to: N 56th Ave P
• Widen roadway. curb, gutter, sidewalk - 04/01/11
' C
Totals 2,973 438 3411 3411
17 23 05 P 2 0 PE 1/1/2010 STP(U) 219 34 253 253
RW 1/1/2011 STP(U) 327 51 378 378 EA
Englewood Ave - N 24th Ave to N 16th Ave 06 S CN 6/1/2012 STP(U) . 2980 244 3224 3224 Yes
Englewood Ave
from: N 16th Ave to N 24th Ave
Widen, curb, gutter and sidewalk, water and sewer lines 01/01/10
Totals 3,526 329 3855 253 378 3224
PE 1/1/2011 STP(E) 252 34 286 1 • 286
00 24 14 P .25 T CN 3/1/2012 STP(E) • 3150 412 3562 3562 CE
Pedestrian Bridge 32 P No
Pedestrian Bridge • 0
from: N 10th St to: Yakima Greenway
Construct pedestrian bridge from Gateway area to Yakima Greenway, .
power, handicap accessible, lights
Totals 3,402 446 ' 3848 • 286 3562
•
•
Report Date: July 10, 2008 Page v. 5.7 - Supersedes previous editions
•
.
Washington State Department of Transportation Six Year Transportation Improvement Program
Agency: Yakima From 2009 to 2014
Co. No.: 39 Co. Name: Yakima Co. Hearing 'Date: 7/1/2008 Adoption Date: .
City No.: 1485 MPO /RTPO: . YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
A. PIN /Federal Aid No. B. Bridge No. m E d a , Fund Source Information ' Expenditure Schedule Projects Only
a, (Local Agency)
o m : E C. Project Title o a m c 0 . Federal Funding R/W
n v — Z D. Street/Road Name or Number $. o) . u Phase Federal Federa State 4th Required
o _E 2 State Local Total Envir, Date •
tL E. Beginning MP or Road - Endin MP or Road E 2 D Start Fund Cost by Fund 1st 2nd 3rd Thru
9 9 Ending o Funds Funds Funds Type (MM/vr)
F. Describe Work to be Done • ti (mailddtyyyy) Code Phase Code 6th
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
' PE 4/1/2009 252 252 100 70 82
00 25 07 P N/A S CN 6/1/2009 CMAQ 195 38 233 233 CE
Gravel Road B.S.T. No
Various Areas
from: City Wide to:
Totals 195 290 485 100 70 315
CN 10/1/2010 STP(S) 504 74 5781 578
16 26 12 P N/A T CE
Powerhouse Rd & Englewood Ave P - Yes
Powerhouse Rd 0
from: Powerhouse Rd to: Englewood Ave S
C 09/01/2009
Intersection, realignment, curb, gutter, sidewalk, Safety Flashing Signal, w
possible roundabout
Totals 504 74 578 578
PE 1/1/2012 STP(S) 25 4 29 29
14 27 12 P N/A P RW 6/1/2012 STP(S) 25 4 29 29 CE
S 48th Ave & Summitview Ave Signalizafion T CN 8/1/2013 STP(S) 554 81 635 635 Yes
S 48th Ave
from: S 48th Ave to: SummitviewAve 06/01/12
Signalization
Totals 604 89 693 693
PE 4/1/2009 13 131 13
16 28 12 P N/A P CN 6/1/2009 214 214 214 CE
S 3rd Ave & W Washington Ave Signal T No
S3rdAve
from: S 3rd Ave to: W Washington Ave
Signal Upgrades ,
Totals 227 227 227
•
v. 5.7 - Supersedes previous editions
Report Date: July 10, 2008 Page 7
O
e 0
•
0 • 0 .
•
Washington State Department of Transportation Six Year Transportation Improvement Program
Agency: Yakima From 2009 to 2014 .
Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7/1/2008 Adoption Date:
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
• Project Identification Project Costs in Thousands of Dollars Federally Funded
A. PIN /Federal Aid No. • B. Bridge No. 5 • d m Fund Source Information Expenditure Schedule Projects Only
o m - ° C. Project Title d d . m L Fede Funding (Local Agency
m n -J 9 R/W
7 U I- Z D. Street/Road Name or Number al- 0 A w a Phase Federal Federal State • 4th Required
LL E. Beginning MP or Road - Ending MP or Road E
O D o Start Fund Cost by Fund State Local Total 1st 2nd 3rd Thru Envir. Date
F. Describe Work to be Done
a (mm/dd/yyyy) Code Phase Code Funds Funds Funds 6th Type (MYY)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
• PE 1/1/2009 AIP 120 52 172 100 72
14 29 • 12 S N/A P RW 6/1/2009 AIP 84 36 120 40 80 CE
S 16th Ave & W Washington Ave Signal & Intersection. 05 T CN 6/1/2009 AIP 880 383 1263 1263 ' • Yes
S 16th Ave 03 .
from: S 16th Ave to: W Washington Ave
Included in Union Gap's Valley Mall Blvd. project 3/1/2009
Totals 1084 471 1555 1403 152
PE 1/1/2010 STP(S) 55 8 63 63
14 30 12 P 2.5 P RW 6/1/2010 STP(S) 107 19 126 126 CE
WNob Hill Blvd Sidewalks T CN 3/1/2011 STP(S) 321 57 378 378 Yes
W Nob Hill Blvd W
from: S 16th Ave to: S. 6th St. S
Install missing sidewalks on southside of Nob Hill. 09/01/08
Totals 483 84 567 189 378
PE 1/1/2011 STP(S) 57 . 7 64 • 64
00 31 06 P 1.0 P RW 6/1/2011 STP(S) 189 25 214 214 CE
Beech St Pedestrian Connection 32 T CN 1/1/2012 STP(S) 504 • 68 572 572 Yes
Beech St
from: Fair Ave to: Chalmers/Riverside
Construct pedestrian pathway under SR82 to Greenway 09/01/10
Totals 750 100 850 64 786
16 32 12 P 2 0 P PE 1/1/2011 STP(S) 43 7 50 • 50
RW 6/1/2011 STP(S) 86 • 15 101 101 CE
WLincoln Ave Sidewalks T CN 1/1/2012 STP(S) 572 88 660 660 Yes
W Lincoln Ave S
from: N 56th Ave to: N 29th Ave W
Sidewalks. meters and fire hydrants replacement or relocation 09/01/11
Totals 701 110 811 811
V. 5.7 - Supersedes previous editions
Report Date: July 10, 2008 Page 8
•
•
Aft
Washington State Department of Transportation Six Year Transportation Improvement Program
Agency: Yakima From 2009 to 2014
Co. No.: 39 Co. Name: Yakima Co. .
Hearing Date: 7/1/2008 Adoption Date:
City No.: 1485 • MPO /RTPO: YVCOG • Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
To >, .6 A. PIN /Federal Aid No. B. Bridge No. d ^ o , 9 m Fund Source Information Expenditure Schedule Projects Only
w N c , e (Local Agency)
o m :o E C. Project Title i d m U r Federal Funding R/W
c 3 ti m D. Street/Road Name or Number c � in a Phase Federal Federal State 4th Required
LL Z E. Beginning MP or R oad - Ending MP or Road o Start Fund Cost by Fund State Local Total 1st 2nd 3rd Thru Envir. Date mi
F. Describe Work to be Done
a (mm/dd/yyyy) Code Phase Code Funds Funds Funds 6th Type (Myy)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
PE 1/1/2010 STP(E) 424 • 67 491 491
14 33 01 P .5 W RW 1/1/2011 STP(E) 1047 163 1210 1210 CE
WLincoln Ave & 'B' St Realignment 12 T CN 1/1/2012 STP(E) 1801 281 2082 2082 Yes
W Lincoln Ave
from: W 5th Ave to: Custer SI P
• p 09/01/11
Realignment of W Lincoln Ave, sidewalks, curb, gutter, lights G
C Totals 3,272 511 3783 491 3292
PE 1/1/2009 PSMP 13 2 15 15
16 34 12 P N/A W CN 1/1/2009 PSMP 239 • 48 2871 287 CE
School Safety Projects - No
Various Locations - Citywide
from: to:
Crossing flashers, sidewalks, signing, other features
Totals 252 50 302 302 .
PE 1/1/2010 STP(C) 546 84 630 630
14 35 03 P .85 C RW 1/1/2011 STP(C) 1090 170 1260 1260 EA
E Nob Hill Blvd. Reconstruction 04 0 CN 1/1/2012 STP(C) 6539 1013 7552 7552 Yes
E Nob Hill Blvd. 06
from: S 6th Street to: S 18th Street P
S 1/1/2010
Major roadway widening and reconstruction to 5 lanes with intersection T
improvements, curb, gutter, sidewalks, replacement or relocation of meters
an hydrants W Totals 8,175 1267 9442 9442
• PE 1/1 /2010 STP(C) 91 14 105 105
N / A y/
17 36 • 01 P RW 1/1/2011 STP(C) 91 14 105 105 CE
S72nd Avenue & W Washington Avenue 12 T CN 1/1/2012 STP(C) 544 86 630 630 Yes
S 72nd Ave 06
from: S 72nd Ave to: W Washington Ave P
p 1/1/2011
Intersection improvement, possible roundabout
Totals 726 114 840 840
Report Date: July 10, 2008 Page 9 v. 5.7 - Supersedes previous editions
•
0
e 0
• •
• .
Am. • •
iv , Washington State DepartmentofTransportation Six Year Transportation Improvement Program
Agency: Yakima From 2009 to 2014 '
Co. No.: 39 Co. Name: Yakima Co. • Hearing Date: 7/1/2008 • Adoption Date:
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
m >.. a`_ A. PIN /Federal Aid No. B. Bridge No. m rn m e , Fund Source Information Expenditure Schedule Projects Only
` s N . _ 9 C. Pro ect Title E c c to (Local Agency) '
m o E I t Federal Funding R/W
c c 1 0-Z D. Street/Road Name or Number Q.1- v0 a Phase Federal Federal State 4th Required
t ` E. Beginning MP or Road - Ending MP or Road E O. at Start Fund Cost by Fund State Local Total Thru Envir. Date
F. Describe Work to be Done a ` (mnvddJyyYY) ' Code Phase Code Funds Funds Funds 1st 2nd 3rd 6th Type (MM/Yt�
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
14 37 4579 12 P N/A P PE 6/1/2009 STP 252 38 290 290
EA •
S 1st St. - E. Washington Ave. Intersection Improvement W Yes
S 1st St, S
from: S 1st St. to: E Washington Ave. T o Realign intersection. upgrade traffic signal 01/01/11
- Totals 252 38 290 290
4562 ALL 4/4/2010 STP(U) 378 WSDOT 378 7561 756
16 38 12 P N/A P CE
. Tieton Dr- S 5th Ave. Intersection Project • W No
• Tieton Drive T
from: 5th Ave. Intersection to: 0
Replace traffic signal with roundabout � $ •
Totals 378 378 756 756
17 39 4587 03 P 1 P ALL 4/1/2009 STP 2268 307 25751 525 2050 '
EA
S 48th Ave. Reconstruction T
S 48th Avenue W No
from: Summitview Ave. to: Nob Hill Blvd. S
Wden, curb, gutter, sidewalk, lighting, drainage 0
w •
' Totals 2,268 307 • 2575 525 2050
14 40 03 P N/A 0 PE 1/1/2009 STP(U) 51 8 59 59
CN 6/1/2009 STP(U) 383 61 - 444 444 CE
South 72nd Ave & Mead Ave Intersection 12 P No
South 72nd Ave S -
from: South 72nd Ave to: Mead Ave T
W
New intersection, signals, curb, gutter and sidewalk
Totals 434 69 503 503
•
Report Date: July 10, 2008 Page 1 o v. 5.7 - Supersedes previous editions
•
Washington State Department of Transportation Six Year Transportation Improvement Program
-en Aggncy: Yakima From 2009 to 2014
Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7/1/2008 Adoption Date:
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
A. PIN /Federal Aid No. B. Bridge No. m 3 m e Fund Source Information Expenditure Schedule Projects Only
1 on c ca (Local Agency)
o m E C. Project Title m d « d . Federal Funding R/W
c v • D. Street/Road Name or Number P_ ° m - P a Required
ti. li E ,- v) o a t Phase Federal Federal State State Local Total 4th Envir. Date
E. Beginning MP or Road - Ending MP or Road . Start F und Cost b Fund Funds Funds Funds 1st 2nd 3rd Thru Type
F. Describe Work to be Done a (mm/dd/yyyy) Code Phase Code 6th (My)
1 2 3 . 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
PE 1/1/2009 STP(E) 10 2 12 12
00 41 14 p N/A 0 CN 7/1/2009 STP(E) 109 17 126 126 CE
William 0. Douglas Pathway 32 S No
P
from: Pine St to: Cowiche Canyon W
Pathway improvements, connections, and signage to Cowiche Canyon
Trail.
Totals 119 19 138 138
PE 1/1/2009 STP(E) 23 5 28 28
17 42 04 P ,76 W CN 7/1/2009 STP(E) 1096 164 1260 1260 Yes
S 66th Avenue 03 S
S 66th Ave •
from: Scenic Drive to: Summitview P
0 1/1/2009
Widen roadway. curb, gutter, sidewalk and utilities
Totals 1,119 169 1288 1288
PE 1/1/2010 STP(S) 164 25 189 • 189
16 43 05 P .20 G RW 6/1/2010 STP(S) 382 60 442 442 CE
66th Ave. 8 Summitview Intersection 12 P CN 7/1/2011 STP(S) 1090 170 1260 1260 Yes
N. 66th Avenue & Summitview
from: N. 66th Ave. to: Summitview Ave. S
T 1/1/2010
Widen for left tum lanes, intersection improvements, curb, gutter, handicap
W
ramps and lighting
C Totals 1,636 255 1891 189 442 1260
PE 1/1/2010 STP(U) 126 17 143 143
N /A W 14 44 12 P RW 1/1/2010 STP 63 • 8 71 • 71 CE
40th Avenue and Summitview Signal Upgrade T CN 6/6/2010 STP(U) . 544 86 630 630 Yes
40th Avenue
from: 40th Avenue to: Summitview P
0 1/1/2010
Signal upgrade, radius improvements, tum lane extension
Totals 733 111 844 844
v. 5.7 - Supersedes previous editions
Report Date: July 10, 2008 Page 11
e e..olio
•
II IP .
III
Washington State Department of Transportation Six Year Transportation Improvement Program
Agency: Yakima From 2009 to 2014
Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -1 -2008 Adoption Date:
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded '
A) A. PIN/Federal Aid No. B. Bridge No m o, iv d • Fund Source Information Expenditure Schedule Projects Only
o N � C. Project Title E " N c o m (Local Agency)
U m o f I ; n «' - t Federal Funding R �
U a Z D. Street/Road Name or Number o `a � u Phase Federal Federal State Envir. Date
4th Required
t` E. Beginning MP or Road - Ending MP or Road E 12 . o Start Fund Cost by Fund State Local Total
Funds Funds .Funds 1st 2nd 3rd Thru T
F. Describe Work to be Done a _ (mm/dd/YYYY) Code Phase Code 6th Type lM >7
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
14 45 12 P N/A W PE 1/1/2010 STP 95 13 108 108
RW 40th.Avenue and Englewood T CN 1/1/2011 1/1/201 STP 63 8 71 71 CE
CN STP 145 20 165 165 Yes
40th Avenue S
from: 40th Avenue to: Englewood P
Replace traffic signal poles. upgrade controller 1/1/2010
Totals 303 41 344 344
00 46 12 P N/A W PE 1/1/2010 STP 126 18 144 144
RW 6/1/2010 STP 63 8 71 71 CE
16th Avenue and Fruitvale Blvd T CN 1/1/2011 STP 315 43 358 358 Yes
16th Avenue S
•
from: 16th Avenue to: Fruitvale Blvd P
Replace traffic signal poles, radius improvements, ADA ramps 6/1/2010
Totals 504 69 573 573
PE 1/1/2010 STP 32 5 37 37
14 47 12 P N/A W
1st Street and IStreet T CN 1/1/2011. STP 126 17 143 143 CE
1st Street S No
from: 1st Street to: I Street P •
0
Replace and upgrade traffic signal equipment
Totals 158 22 180 180
14 48 01 P 25 W PE 6/1/2011 STP(U) 820 189 1009 1009
RW 1/1/2012 STP(U) 3150 630 3780 3780 CE
Mead Ave. Railroad Grade Separation T CN 1/1/2013 STP(U) 6552 1008 7560 7560 Yes
Mead Ave. S
from: Presson Place to: Maryland P
Construct railroad overpass including all utilities 1/1/2012
. Totals 10,522 1827 12349 4789 7560
r
v. 5.7 - Supersedes previous editions
Report Date: July 10, 2008 Page 12 P p •
•
Washington State Department of Transportation Six Year Transportation Improvement Program
-en
Agency: Yakima From 2009 to 2014
Co. NO.: 39 Co. Name: Yakima Co. Hearing Date: 7 -1 -2008 Adoption Date:
City No.: 1485 MPO /RTPO: YVCOG • Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
A. PIN /Federal Aid No. B . Bridge No. c a Fund Source Information Expenditure Schedule . Projects Only
c ,T, ° — v a (Local Agency)
o m . E C. Project Title d d a J u t Federal Funding R/W
1 ,
a Z D. Street/Road Name or Number a� fn g ;� a Phase Federal Federal State 4th Required
LL E o m State Local Total Envir. Date
E. Beginning MP or Road - Ending MP or Road 1- 5 o Start Fund Cost by Fund Funds Funds Funds 1st 2nd 3rd Thru Type (mew)
F. Describe Work to be Done a (mm/dd/yyyy) Code Phase Code 6th
1 2 3 4 5 6 7 8 9 10 . 11 12 13 14 15 16 17 18 19 20 21
PE 6/1/2011 STP(U) 820 189 1009 1009
16 49 01 p .25 0 RW 1/1/2012 STP(U) 3150 630 3780 3780 CE
. Washington Ave. Railroad Grade Separation S CN 1/1/2013 STP(U) 6552 1008 7560 7560 Yes
Washington Ave.
from: Longfibre Road to: T W 1/1/2012
Railroad grade overpass including all utilities
Totals 10,522 1827 12349 12349
PE 6/1/2011 STP(U) 252 38 290 290
16 50 01 P 4.0 0 RW 1/1/2012 STP(U) 756 88 844 844 CE
Citywide Pathway Connections S CN 1/1/2013 STP(U) 1890 315 2205 2205 Yes
Yakima •
from: to: T
W 1/1/2012
Cowiche Canyon Trail, Powerhouse Rd pathway, east side canal paths,
WOD Trail, Greenway including Neches Rail Spur, signage and amenities
Totals 2,898 441 3339 290 3049
PE 1/1/2011 STP(U) 2180 340 2520 2520
16 51 01 P 1.1 0 RW 1/1/2013 STP(U) 2180 340 2520 2520 CE
E. 'H" St. Extension 08 S CN 6/1/2014 STP(U) 1199 - 1871 3070 3070 Yes
E. "H" St.
from: 1st St. to: Yakima River T
W
Construct road including water, sewer, curb, gutter and sidewalk for future 1/1/2013
development. •
Totals 5,559 2551 8110 8110
PE 1/1/2012 STP(C) 700 108 808 808
17 52 01 P 1.3 0 RW 1/1/2013 STP(U) 5500 850 6350 6350 CE
N. 10th St. Extension 06 S CN 6/1/2013 STP(U) 7900 972 8872 8872 Yes
N. 10th St.
. from: R St. to 10th Street - Lincoln Ave. T
W 1/1/2013
Construct road including water, sewer, curb, gutter, sidewalk for future
•
development.
Totals 14,100 1930 16030 16030
• v. 5.7 - 'Supersedes previous editions
Report Date: July 10, 2008 • Page 13
•
.o
0 0
•
•
•
• .
. 0 .
•
Washington State Department of Transportation Six Year Transportation Improvement Program
Agency: Yakima From 2009 to 2014
Co. No.: 3g Co. Name: Yakima Co. Hearing Date: 7 -1 -2008 Adoption Date:
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No::
Project Identification Project Costs in Thousands of Dollars • Federally Funded
T A. PIN /Federal Aid No. B. Bridge No. d .- $ in 5 , Fund Source Information Expenditure Schedule Projects Only
C N = n E a N c o • (Local Agency)
U m : o E C. Project Title > n J o , Federal Funding R/W
D v 0-Z D. Street/Road Name or Number to.'" rn 3 D u Phase Federal • Federal State 4th Required
u. E. Beginning MP or Road - Ending MP or Road 1.- z .o Start Fund Cost by Fund State Local Total 1st 2nd 3rd Thru Envir. Date
F. Describe Work to be Done t (mm/dd/yyyy) Code Phase Code Funds Funds Funds 6th Type (MM/YY)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
PE 1/1/2012 STP(U) 315 38 353 353
00 ' 53 03 P N/A 0 CN 6/1/2012 STP(U) 945 126 1071 1071 CE
)4/7 32 S No
• YVT Railway Corridor.
from: to: T
Development pathway in West Valley area including 53rd Ave, Wide W .
Hollow, 64th Ave, Ahtanum including all utilities and signage
Totals 1,260 164 1424 1424
PE 1/1/2011 STP(U) 63 5 _ 68 1 68 •
17 54 01 P N/A 0 CN 6/1/2011 STP(U) 567 76 643 643 CE
34th Ave & River Rd Improvements 12 S No
Fruitvale Blvd.
from: 34th Ave. to: River Rd. T
Intersection improvements including lumination, sewer, water, curb, vale( W
and sidewalks •
Totals 630 81 711 711
17 55 01 P 1.0 0 PE 1/1/2010 STP(U) 218 34 252 252
RW 6/1/2011 STP(U) 327 51 378 378 CE
Englewood Ave 05 S CN 1/1/2012 STP(U) 2980 244 3224 3224 Yes
Englewood Ave • 12 •
from: 24th Ave to: 40th Ave T
Reconstruct roadway, widen, curb, gutter and sidewalks. Sewer, water W 6/1/2011
lines and street lights.
. . Totals 3,525 329 3854 ' 630 3224
16 56 01 P 1.3 C PE 1/1/2010 STP(U) 272 43 315 . 315
RW 6/1/2010 STP(U) 349 55 404 404 CE
Frontage Road & "H" St. Loop O CN 1/1/2011 STP(U) 2352 340 2692 2692 Yes
N. 8th St.
from: "H" St. to: 1 -82 S 6/1/2010
Construct new roadway, water, sewer, cutb, gutter, sidewalk and lighting for T
future development and Terrace Heights connection. W -
. Totals 2,973 43 3411 719. 2692
•
•
•
v. 5.7 - Supersedes previous editions
Report Date: July 10, 2008 - Page 14
Washington State Department of Transportation Six Year Transportation Improvement Program
Agency: Yakima From 2009 to 2014 •
Co. No.: 39 Co. Name: • Yakima Co. Hearing Date: 7 - - 2008 Adoption Date: •
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
A. PIN /Federal Aid No. B. Bridge No. c 6 m w Fund Source Information Expenditure Schedule Projects Only
m m ° — a o N (Local Agency)
o N ' — E C. Project Title d d B m ` r.) L Federal Funding R/W
c v a D. Street/Road Name or Number c to I - Phase Federal Federal State 4th Required
u_ o 5 State Local Total Envir. Date
E. Beginning MP or Road - Ending MP or Road I- D • Start Fund Cost by Fund Funds Funds Funds 1st 2nd 3rd Thru Type (MM/Y)�
F. Describe Work to be Done o - (mm /ddyyyy) Code Phase Code 6th
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
00 57 07 P
.5 G CN 6/1/2009 75 75 25 25 25 CE
Citywide Alleys P No
S
from: to: W .
T
Pave alleys throughout the city. -
Totals 75 75 25 25 25
2.7 C PE 1/1/2010 STP(U) 120 17 1371 137
14 58 03 P CE
Nob Hill Corridor 04 • G
Nob Hill O
from: 1 -82 to: S. 16th Ave. P
Widen roadway, sidewalk. curb, gutter, lighting T •
W Totals 120 17 137 137
• PE 1/1/2011 STP(U) 120 17 137 1 137
14 59 04 P 3.2 C CE
40th Ave. Corridor 0
40th Ave. G
from: SR -12 to: Washington Ave. P •
S
Widen roadway, curb, gutter, sidewalks, lighting. W
T Totals 120 17 137 137
3.5 C PE 1/1/2012 STP(U) 120 17 137 1 137
14 60 04 P CE
16th Ave. Corridor • G
16th Ave.
0
from: SR -12 to: alhington Ave.Nalley Mall P
Widen roadway, curb, gutter, sidewalk', lighting. T
. W Totals 120 - 17 137 137
•
Report Date: July 10, 2008 Page 15 • v. 5.7 - Supersedes previous editions
e e . 0
0 .
• 0
Ilk
Washington State Department of Transportation Six Year Transportation Improvement Program
Agency: Yakima From 2009 to 2014
Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -1 -2008 Adoption Date:
City No.: 1485 MPO!RTPO: YVCOG . Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
7, >, ,_ A. PIN/Federal Aid No. B. Bridge No. c t 2 N Fund Source Information Expenditure Schedule Projects Only
c N ; i c e, (Local Agency)
o m $ E C. Project Title ; o . F e d eral F R/W
U a` Z D. Street/Road Name or Number a in
a Phase Federal Federal State 4th Required 2 l E. Beginning MP or Road - Ending MP or Road 1- o Start Fund Cost by Fund State Local Total 1st 2nd 3rd Thru Envir. Date
F. Describe Work to be Done ti (mm/dd/yyyy) Code Phase Code Funds Funds Funds 6th Type (MM��
1 2 3 4 5 6 7 8 • 9 10 11 12 13 14 15 16 17 18 19 20 21
PE 1/1/2012 STP(U) 120 17 137 137
14 61 04 P 2.0 C CE
• S. 1st St/Main St. Corridor G
S. 1st St. /Main St. O •
from: Nob Hill Blvd. to: Barker Mill Bridge P
' Joint project with Union Gap to siden roadway, curb. gutter, sidewalk, T
lighting. W
Totals 120 17 137 137
14 62 01 P PE 1/1/2012 STP(U) 120 17 1371 137 CE
6.0 C
W Yakima North/South Connector to West Valley 04 G
Unknown road 06 O
from: North - South to: in West Valley P
S
City 8 County joint project to build/extend roadways.
T .
W Totals 120 17 137 137
00 63 23 S
N/A PE 1/15/2009 OTHER 100 1001 100
West Side Transit Center Placement Study
Acquire Property to Expand Operations
. from: to:
, Recent Annexations Mandate Transit Expansion to These Areas '
Totals 100 100 100
16 64 04 p 73 C CN 6/1/2009 ' 432 68 5001 500
W Nob Hill Blvd -S 68th Ave to S. 72nd Ave. 03 W
W Nob Hill Blvd 0
from: S. 68th Ave. to: 72th P
•
Reconstruct to minor arterial standards s
Totals 432 68 500 500
. Report Date: July 10, 2008 Page 16
v. 5.7 - Supersedes previous editions
•
Washington State Department of Transportation Six Year Transportation Improvement Program
Agency: Yakima From 2009 to 2014
Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7/1/2008 Adoption Date:
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
H Expenditure Schedule Projects Only
A. PIN /Federal Aid No. B. Bridge No. c m � Fund Source Information
c `GI d... a v y r -
4 m o E C. Project Title > d 3 0 .e Federal Funding (Local Agency)
R/W
c U 6: D. Street/Road Name or Number ° 1- in - - Phase Federal Federal State 4th Required
u_ E. Beginning MP or Road - Ending MP or Road E � n .o Start Fund Cost by Fund State Local Total 1st 2nd 3rd Thru Envir. Date
F. Describe Work to be Done a (mm/dd/yyyy) Code Phase Code Funds Funds Funds 6th Type (MM/YY)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
PE 5/1/2009 OTHER 400 400 400
17 65 06 S .60 P CN 4/1/2010 OTHER 2600 2600 2600 CE •
Yakima Downtown Future Initiatives, Phase 4 12 S No
from: 1st Street to: 9th Street T
•
Install Historic Lighting, Sidewalk Modification & Other Improvements. O
Exact improvement area(s) to be determined.
Totals 3000 3000 3000
00 66 03 S .50 S CN 1/1/2009 CMAQ 440 214 6541 654 CE
Coolidge Road Widening and Paving. 05 W No
06 T
from: 80th AVE. to: 88TH AVE. T
Wden roadway and pave with curb and gutter.
Totals 440 214 654 654
16 67 01 P .38 S PE 1/1/2012 100 1001 100
Occidental Road Construction. W
P
from: 58th Ave. to: 64th Ave. T
Construct roadway
Totals 100 100 100
00 68 01 P 27 PE 1/1/2012 100 1001 100
86th Ave. Road Construction
from: Occidental to: Coolidge
Construct roadway •
Totals 100 100 100
Report Date: July 10, 2008 Page 17 V. 5.7 - Supersedes previous editions
• • 111 ill .
o •
•
•
•
-en Washington State Department of Transportation Six Year Transportation Improvement Program
Agency: Yakima From 2009 to 20.14
Co. No.: 39 Co. Name: Yakima Co. -
Hearing Date: 7 -1 -2008 Adoption Date:
•
City No.: 1485 . MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
Ta >.. ..... A. PIN /Federal Aid No.. B . Bridge No. c 5 d Expenditure Schedule
a „ a d Fund Source Informatio P Projects Only
m :o E C. Project Title Eta ? e c .) L Federal Funding (Local Agency)
c U D. StreetiRoad Name or Number o r ;r a R/W
m a Z al- ( - • Phase Federal Federal State Start Fund Cost by Fund State Local Total Required
LL E. Beginning MP or Road - Ending MP or Road E 2 D .o 4th Envir. Date
Funds Funds Funds 1st 2nd 3rd Thru T e
F. Describe Work to be Done o. (mm/dd/YYYY) Code Phase Code 6th yp (M �
1 2 3 • 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
16 69 04 P 1.5 w PE 1/1/2012 STP(U) 120 17 137 137 EA
64th Ave. Roadway INfden/nq. 06 G
P YES
from: Washington Avenue. to: Tieton Drive. T
Wide Roadway,Curb, Gutter, Sidewalks, Lighting, Drainage. C O • 7/4/2012
Totals 120 17 137 137
ALL 1/1/2009 5309(Bus) 1540 15401 1540 CE
00 70 21 S N/A • Purchase four new transit buses (replacements) No
On -going vehide replacement program
from: to: •
Seek RFP's to acquire four new transit buses that will replace units that are
18 years of age. (six years past federal standards)
Totals 1540 1540 1540
ALL 6/1/2009 85 30 1151 115
00 71 21 S N/A CE
Acquisition of new Dial -A -Ride paratransit vehicles No
Replace several older vehicles
from: to:
Upgrade Dial -A -Ride service by replacing several older vehicles with new
models.
• Totals - 85 30 115 115
CN 4/1/2009 BR 700 360 10601 1060
14 72 11 P 0.2 CE
Nob Hill Overpass Repair • No
from: 1st Street to: Ledvrich Ave •
Make necessary repairs to Railroad Overpass (Bodge)
. Totals 700 • 360 1060 1060
Report Date: July 10, 2008 Page 18 v. 5.7 - Supersedes previous editions
Washington State Department of Transportation Six Year Transportation Improvement Program
Agency: Yakima From 2009 to 2014
Co. No.: 39 Co. Name: Yakima Co. .
Hearing Date: 7 -1 -2008 Adoption Date:
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
A. PIN /Federal Aid No. B. Bridge No. c E m a, Fund Source Information Expenditure Schedule Projects Only
a� d— m 9 . (Local Agency)
g m ; C. Project Title d a Z 3 c L Federal Funding R/W
c o p ` - Z D. Street/Road Name or Number a� i n A Phase Federal Federal State 4th Required
LL E o State Local Total Envir. Date M/ •
E. Beginning MP or Road - End M P or Road t- D • Start Fund Cost by Fund 1st 2nd 3rd Thru
F. D Work to be Done a (mm/dd/yyyy) Code Phase Code Funds Funds Funds 6th Type (MY1)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
PE 1/1/2009 STP(U) 173 27 200 200
14 73 03 P N/A RW 1/1/2010 STP(U) 433 67 500 500
E. Lincoln & 10th Street Roundabout 05 CN 6/1/2010 STP(U) 1125 175 1300 1300 Yes
•
06
from: E. Lincoln to: E. MLK Jr. Blvd.
• 4/1/2010
Roundabout construction at intersection curb, gutter, sidewalk, & street
lighting
Totals 1,731 269 2000 200 1800
N/A O ALL 1/1/2009 STP(U) 865 135 10001 1000
12 74 03 P CE
S.R.12 & 16th Avenue Interchange 06 • No
Interchange
from: 16th Avenue to: S.R. 12
Upgrade Interchange by constructing a Roundabout
Totals 865 135 1000 1000 .
11 75 01 P N/A 0 I I I I I I I I I I I EA
1 -82 & Lincoln Avenue Interchange P • Yes
1 -82 Interchange G
from: E. "G" Street to: 1 -82 6/2011
Reconstruct / extend off -ramp from existing 1-82 off -ramp for Lincoln
Avenue to E'G' Street,
Totals
14 76 l2 P N/A P ALL 1/1/2010 STP(U) 865 135 10001 1000 CE
E . Yakima Avenue & Fair Avenue Signalization W • No
T
•
from: E. Yakima Avenue to: Fair Avenue S
0
Construct Traffic Signal
Totals 865 135 1000 1000
• Grand Totals for Yakima 123,098 21,344 29,785 174,227 40,215 33404 30,005 70,603
Report Date: July 10, 2008 Page 19 v. 5.7 - Supersedes previous editions
410 0 .
0