HomeMy WebLinkAbout06/15/2010 06 Yakima Urban Area Comprehensive Plan Amendment Incorporating the 2011-2016 Six-Year Transportation Improvement Program BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No.
For Meeting of June 15, 2010
ITEM TITLE: Public Hearing to consider:
A) Adoption of the Six -year Transportation Improvement Program (TIP)
for the years 2011 to 2016, and to amend the Metropolitan
Transportation Plan; and
B) Amend the Yakima Urban Area Comprehensive Plan Capital
Facilities Element to incorporate the adopted Six -year TIP.
SUBMITTED BY: Michael Morales, Director of Community and Economic Development -
CONTACT PERSON/TELEPHONE: Doug Mayo, City Engineer, 576 -6797.
SUMMARY EXPLANATION:
Attached is the 2011 — 2016 Six -year TIP, along with an explanation sheet that describes the
information contained on the various columns of the Six -year TIP. Four transit projects have been
added to the six -year TIP. These projects are:
• #78 Transit Operating Hours Expansion
• #79 Terrace Heights /Moxee Route Expansion •
• #80 Kittitas — Yakima Commuter Bus
• #81 Sunday Bus Service
Continued on Page Two
Resolution X Ordinance Contract Other (Specify) Six -Year TIP
Funding Source
APPROVED FOR SUBMITTAL: C
City Manager
STAFF RECOMMENDATION:
1. Hold the Public Hearing to consider adoption of Resolution approving the Six -year TIP and
amending the regional Metropolitan Transportation Plan and the Comprehensive Plan
Capital Facilities Element.
2. Adopt the Six -year TIP and amend the Metropolitan Transportation Plan and Yakima Urban
Area Comprehensive Plan Capital Facilities Element.
411) BOARD /COMMISSION /COMMITTEE RECOMMENDATION:
COUNCIL ACTION:
Page Two
Projects that that have been deleted from the 2010 — 2015 TIP as they were completed or the
funds were :obligated include:
• #1 Yakima Railroad'Grade Separations — Phase 2
• #4 " YVT Trolley Barn /Powerhouse Rehabilitation
• #5 ''' William O. Douglas Trail
• #28 Yakima Downtown Future Initiatives, Phase 4
Council and the public are welcome to add other arterial system projects to the list. The six -year
TIP project''listing will be finalized at today's hearing and sent to the Yakima Valley Conference of
Governments (YVCOG) after approval.
City and County staff, together with the Council Intergovernmental Committee, are working toward
common standards and coordinated planning for public projects that impact both the city and
surrounding county areas. Agreement on these issues will be the first step toward the goal of a
seamless transportation planning process between the City and County. •
A) Each year the City is required by RCW 35.77.010 and RCW 36.81.121 to update its Six -year
Transportation Improvement Program (TIP) for submittal to the Washington State Department of
Transportation. This plan must include all transportation projects for which state gas tax revenue
of federal revenue will be used.
The current plan for 2011 — 2016 includes nine projects that are funded. Funding for the
remainder of the projects will continue to be sought.
Six -year Transportation Improvement Program (TIP) Background .
On August 10, 2005, the President signed into law the Safe, Accountable, Flexible, Efficient
Transportation Equity Act: A Legacy for Users (SAFETEA -LU). This act is the next authorization
after the prior Transportation Equity Act of 1998 for the 21 Century (TEA - 21) and previous
Intermodal Surface Transportation Efficiency Act (ISTEA) of 1991. The current act again specifies
the systems on which certain funds can be used, and activities for which funds can be used and
promotes the role of the Metropolitan Planning Organizations (MPO) in the planning and
programming of projects. SAFETEA -LU requires each designated MPO to develop a Transportation
Improvement Program (TIP), and the state to develop a Statewide Transportation Improvement
Program (STIP) as a condition to securing federal funds for the transportation projects.
Projects listed in the STIP are the only projects that can be approved by the Federal Highway
Administration (FHWA) and the Federal Transit Administration (FTA) to utilize federal fund of by
the State of, Washington for approved State funding agencies. The STIP is a prioritized program
of transportation projects, complied from local and regional plans, along with the Washington
Transportation System Plan (WTP), which provides a backbone for developing projects for the
intermodal transportation network in the State of Washington.
The STIP contains federally funded projects plus state and local projects that are regionally
significant. h These projects have been identified through the planning process as the highest
priority for the available funding to the state's transportation program.
,I�
•
Page Three
Planning activities of state and local governments are essential parts of integrated regional
planning processes. Long range transportation planning is a part of the comprehensive land use
planning carried out by local governments. Citizen participation is an integral part of the planning
process at all levels. Local Agencies are required to develop and adopt a six -year transportation
program. All local agencies are required to hold at least one public . hearing during the
development of the six -year transportation program.
Project ranking has been performed utilizing data supplied by the Street and Traffic Division. The
ranking will be integrated with other project needs and the total list will be reviewed and adjusted to
the particular need of the City of Yakima.
B) The City needs to amend the Yakima Urban Area Comprehensive Plan Capital Facilities
Element to incorporate the adopted six -year TIP for 2011 to 2016. This will ensure that we are in
compliance with the Growth Management Act and that we are consistent with the Comprehensive
Plan as required. The amendment is limited to incorporate only those projects that adopted in the
STIP and is not subject to the "once a year" change required under the laws of the Growth
Management Act.
•
•
110
• RESOLUTION NO. R -2010-
A RESOLUTION to adopt the Six -Year Transportation Improvement Program for the period
of 2011 through 2016 for the construction of streets and arterials streets in
the City of Yakima and amending the Metropolitan Transportation Plan.
WHEREAS, the City of Yakima annually prepares, reviews and adopts a Six Year
Program for the construction of streets and arterial streets in the City of Yakima for the ensuing
six year period, all as contemplated and required by State RCW 35.77.010 and applicable
Federal law; and
WHEREAS, the City of Yakima desires to amend the Metropolitan Transportation Plan
to ensure compliance with the Growth Management Act and the regional transportation plan for
the construction of streets and arterial streets in the City of Yakima, all as contemplated and
required by State and Federal law, and
WHEREAS, after public hearings on the matter, held at the regular meeting of the
Yakima City Council on June 1, 2010 and June 15, 2010, with proper public notice as required
by RCW 35.77.010, the City Council finds that the plan attached hereto should be adopted as
the Six -Year Transportation Improvement Program for the period of 2011 through 2016 for the
construction of streets and arterial streets in the City of Yakima, now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
• The Six -Year Construction Program for the period of 2011 through 201
9 p g 2016, a copy of which
is attached hereto and by this reference made a part hereof, is hereby adopted as the official
Six -Year Transportation Improvement Program for the City of Yakima, including proposed
amendments to the Metropolitan Transportation Plan along with Street Improvements, which are
also approved.
ADOPTED BY THE CITY COUNCIL this 15 day of June, 2010.
•
Micah Cawley, Mayor
ATTEST:
City Clerk
• RESOLUTION NO. R -2010-
A RESOLUTION to amend the Yakima Urban Area Comprehensive Plan Capital Facilities
Element to incorporate the Six -year Transportation Improvement Program
(TIP) for the period of 2011 through 2016.
WHEREAS, the City of Yakima annually prepares, reviews and adopts a Six — Year
Transportation Improvement Program for the construction of streets and arterial streets in the
City of Yakima for the ensuing six year period, all as contemplated and required by State RCW
35.77.010 and applicable Federal law; and
WHEREAS, the City of Yakima desires to amend the Yakima Urban Area
Comprehensive Plan Capital Facilities Element to reflect the adoption of the Six -year TIP, as
contemplated and required by RCW 36.70A.070(6) to ensure compliance with the Growth
Management Act and consistency of the Comprehensive Plan and the Six -year TIP; and,
WHEREAS, this amendment is limited to incorporation of the projects listed in the Six -
year Transportation Improvement Plan for the period of 2011 to 2016 to the Capital Facilities
Element of the Yakima Urban Area Comprehensive Plan, which is contemplated and provided
under RCW 36.70A.130(2B) and RCW 35.77.010; and,
WHEREAS, public hearings were held by the Yakima City Council on the Six -year TIP
on June 1, 2010 and June 15, 2010, with proper public notice as required by RCW 35.77.010;
411 now, therefore
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
The adopted Six -Year Transportation Improvement . Program for the period of 2011
through 2016 for the City of Yakima shall be incorporated as an amendment to the Capital
facilities Element of the Yakima Urban Area Comprehensive Plan.
ADOPTED BY THE CITY COUNCIL this 15 day of June, 2010.
Micah Cawley, Mayor
ATTEST:
City Clerk
•
•
•
•
• W ashin g Sate Department of Transportation Si x Year Transportation Improvement ra
T P P
Agency: Yakima From 2011 to 2016
Co. No.: 39 Co. Name: Yakima Co. •
Hearing Date: 7 -15 -2010 Adoption Date: 7 -15 -2010 .
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars . • Federally Funded
m >, m A . PIN /Federal Aid No. B. Bridge No. *C" m , a , Fund Source Information Expenditure Schedule Projects Only
9 = ° C. Project Title E W c o (Local Agency) '
m o E ro i e > v m U a Federal Funding • � R/W •
c U ec z D. Street /Road Name or Number a - rn a Phase Federal Federal State 4th Required
E. Beginning MP or Road - Ending MP or Road a r ° Envir. Date
Sta Fund Cost b by. F und State Local Total Thru.
mm /dd/ y Funds Funds Funds 1st 2nd . 3rd Type (MM/YY)
F. • Describe Work to be Done a ( yyyy) Code Phase Code 6th .
•
• 1 2 • • 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
14 1 • 01 P 0.2 T CN 4/1/2011 STP(U) 1700 FMSIB 2000 4530 8230 3000 5230 EA
CN 4/1/2011 DEMO 3281 AIP 1500 4781 3000 1781 •
Yakima Railroad Grade Separations- Phase 3 06 P Yes •
Martin Luther King, Jr. Blvd • 07 G • from: N. 1st Sreet - to: N. 1st Ave 0 '
08
' Construct Grade Separation and adjacent roadway reconstruction including 9/1/2009
Front Street
. Totals 4,981 3500 4530 13011 6000 7011 •
•
• ALL 1/1/2011 5307 1601 1601 32021 3202
00 2 12 S N/A CE
T ransit Operating Expenditures 22 No
Various fixed rates and locations 23 .
from: N/A to: N/A 24 •
Annual operating assistance from the FTA in support of our transit system; 31
• fixed conte, paratransit Dial -A -Ride and vanpool program
• Totals 1,601 1601 3202 3202
00 3 32 S N/A G RW 1/1/2011 STP(E) 150 150 150
CN 1/1/2011 STP(E) 285 285 285 CE
• William O. Douglas Heritage Trails .13 O Yes
Bridge Restoration & Trailhead • 10 P
from: to: S
T 6/01 /09
Trailhead restoration, right of way acquisition partner with the William O. W
Douglas Foundation, including restoration of bridge , cleaning, rust removal
and painting Totals 435 435 435
ALL 1/1/2011 5309(Bus) 280 50 3301 50 100 100 80 CE
00 4 22 S N/A
Street Asset Amenities (Transit) 31 • No
Route Maintenance, Repair and Improvements •
from: N/A . _ to: N/A
On going improvements to bus benches, shelters and signage infrastructure - .
• Totals 280 50 330 50 100 100 80
•
Report Date: May 25, 2010 Page •1 v. 5.7 - Supersedes previous editions
•
•
•
•
•
• Was ton State Department of Six Year Transportation Improveme rogram
Agency: Yakima From 2011 to 2016
Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -15 -2010 Adoption Date: 7 -15 -2010
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
` m A. , PIN/Federal No. B. Bridge No. rn N Fund Source Information Expenditure Schedule Projects Only •
(Local Agency)
C m . o E C Project Title o a 8 i ii Federal F R/W
U i Z D. Street /Road Name or Number al- fn 1g " = Phase Federal Federal State 4th Required
o
LL E. Beginning MP or Road - Ending MP or Road E l- o . State Local Total Envir. Date Start Fund, Cost by Fund Funds Funds Funds 1st 2nd 3rd Thru
• Type (MMn YI
F. Describe Work to be Done • a (mm /dd/yyyy) Code Phase Code 6th
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 6 17 18 19 20 21 •
ALL 1/1/2011 CMAQ 71 11 82 82
00 5 • 22 S N/A .
Continue Transit Service to Terrace Heights No
New University & Retail Links
from: N/A to: N/A
Extension of fixed route bus service only into the Terrace Heights area of ' •
Yakima County Totals 71 11 82 • 82
.71 C CN 1/1/2011 JOBS 925 9251 925 CE
14 6 03 P .
Nob Hill Blvd and 64th Ave Improvements • • 05 P . No
Nob Hill Blvd 07 T • •
from: 53rd Ave to: 64th Ave 12 . •
Widen and re- construct 64th Ave. to 33 -foot width with curb, gutter and 13
sidewalk from Nob Hill Blvd. to 400 feet north. Construct curb, gutter
sidewalk and storrnwater runoff treatment on the north side of Nab Hill. Totals 925 925 925
CN 1/1/2011 AIP 880 383 1263 1263
14 7 12 S N/A T CN 7/1/2011 AIP 1000 214 1214 1214 CE •
S 16th Ave & W Washington Ave Signal & Intersection. 05 Yes
S 16th Ave 03
from: S 16th Ave to: W Washington Ave
4/1/2010
Included in Union Gap's Valley Mall Blvd. project .
• Totals 1880 597 • 2477 2477
16 8 05 S 20 G CN 1/1/2011 600 6001 600 CE
66th Ave. & Summitview Intersection . 0 Yes
N. 66th Avenue & Summitview P ,
S
from: N. 66th Ave. to: Summitview Ave. T 4/1/2010 •
Widen for left turn lanes, intersection improvements, curb, gutter, handicap W
ramps and lighting C
Totals 600 600 600
Report Date: May 25, 2010 Page 2 v. 5.7 - Supersedes previous editions
•
•
0 .. •
- Washing ate Department of Transportation S ix Year Trans Transportation Im Improvement Illitram
P p
Agency: Yakima From 2011 to 2016
•
Co. No.: 39 Co. Name: Yakima Co.
City No.: 1485 MPO/RTPO: YVCOG Hearing Date: 7 -15 2010 Adoption Date: 7 -15 2010 ,
Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded .
.. v T m A . PIN /Federal Aid No. ' B. Bridge No m 5 v 5, Fund Source Information Expenditure Schedule Projects Only
4 N = C. Project Title g v o (Local Agency)
', m o E m o .E.• Federal Funding R/VV
• • g n a Z D. Street/R Name or Number ° a o °- Required z.
a1-- rn 5 _ Phase Federal Federal State 4th State Local Total . Envir. Date
E. Beginning MP or Road - Ending MP or Road E . Date
* °' S tart Fund Cost by Fund
F. Describe Work to be Done a (mm/dd /yyyy) Code Phase Code Funds Funds . Funds 1st 2nd 3rd Thru Type (MM/VYI
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 • 19 20 21
00 9 03 S .50 S CN 1/1/2011 CMAQ 540 214 754 754 CE
Coolidge Road Widening and Paving. 05 W Yes
P
. 06 T
from: 80th AVE. to: 88TH AVE. T
•
Widen roadway and pave with curb and gutter. 9/1/2009
Totals 540 214• 754 754
ALL 1/15/2013 5309(NS) 96 84 • 1801 180 ,
CE
00 10 21 S N/A
Acquisition of new Dial -A -Ride paratransit vehicles No
from: N/A to: N/A
Purchase new vehicles to replace older, less reliable units ,
Totals 96 84 180 180
PE 1/1/2011 STP(U) 173 27 200 200
14 11 03 P N/A RW 1/1/2012 STP(U) 433 67 500 500 CE
E. Lincoln & 10th Street Roundabout 05 CN 6/1/2012 STP(U) 1125 175 1300 1300 Yes
•
•
06
•
from: E. Lincoln • to: E. MLK Jr. Blvd.
Roundabout construction at intersection curb, gutter, sidewalk, 8 street 6/1/2011
lighting
Totals 1,731 27 242 2000 200 1800
ALL 1/1/2011 STP(U) 865 135 10001 1000 CE
12 12 03 P N/A O
S.R. r2 & 16th Avenue Interchange 06 No
Interchange
from: 16th Avenue to: S.R. 12 .
Upgrade Interchange by constructing a Roundabout
Totals 865 135 1000 1000
•
Report Date: May 25, 2010 Page 3 v. 5.7 - Supersedes previous editions
•
•
•
•
•
•
•
•
•
•
•
'1111■
• 0
7 Wa ton State Department of Transportation Six Year Transportation Improveme rogram
Agency: Yakima From 2011 to 201 6
Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -15 -2010 Adoption Date: 7 -15 -2010
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
• To. w A .PIN/Federal Aid No. B. Bridge No. d._ t cs v d Fund Source Information Expenditure Schedule Projects Only
t Iv o E C. Project Title E d v r Federal Funding (Local Agency) Rl1N
c U eL Z D . Street/Road Name or Number a co o Phase Federal Federal State 4th Required
LL E. Beginning MP or Road - Ending MP or Road E r 5 o St Fund Cost by Fund State Local Total 1st 2nd 3rd Thru Envir. Date
F. Describe Work to be Done n
(mm /dd /yyyy� Code Phase Code Funds Funds Funds 6th Type (MM/Y1')
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 . 17 18 19 20 21
ALL 1/1/2012 STP(U) 865 135 1000 1000
• 11 13 01 P N/A 0 EA
1 -82 & Lincoln Avenue Interchange • P Yes
1 -82 Interchange G •
from: E. "G° Street to: 1 -82 '
Reconstruct / extend off -ramp from existing 1 -82 off -ramp for Lincoln Avenue 6/2011
to E. "G" Street.
Totals 865 135 1000 1000
14 14 12 P N/A P ALL 1/1/2012 STP(U) 865 135 10001 1000
CE
E. Yakima Avenue & Fair Avenue Signalization W No
T • i. from: E. Yakima Avenue . to: Fair Avenue S
Construct Traffic Signal O
Totals 865 135 1000 1000
00 15 22 S ALL 1/2/2011 5316 131 131 2621 131 . 131 CE •
Fixed route Bus Services to Moxee along SR 24 Corridor No
SR 24 Hwy Corridor /Park & Ride Lots
from: • • lo:
JARC funded demonstration project to determine ridership potential to and
from the Moxee area including stops at two Park & Rlde lots along SR 24.
• Totals 131 131 262 131 131
RW 1/1/2012 STP(U) 173 27 200 200
14 16 31 P N/A
E Nob Hill Blvd & Fair Ave 03 C CN 4/1/2012 STP(U) 865 135 1000 1000 CE
Yes
E Nob Hill Blvd P
04 T
from: E Nob Hill Blvd to: Fair Ave W 4/1/2001
Intersection widening & new signal, curb, gutter and sidewalk, street lighting,
stormwater
Totals 1,038 162 1200 1200
•
Report Date: May 25, 2010 Page 4 v. 5.7 - Supersedes previous editions
•
•
•
AM.
Washing tate Department of Transportation • Six Year Transportation Improvemen flOgram
Agency: Yakima From 2011 to 2016
Co. No.: 39 Co. Name: Yakima Co.
• Hearing Date: • • 7 -15 -2010 Adoption pate: 7 -15 -2010
City No.: 1485 MPO /RTPO: Y\/COG Amend Date: Resolution No.:
•
Project Identification Project Costs in Thousands of Dollars Federally Funded
a A. PIN / Federal AId No. B. Brid No. Z' m Expenditure Schedule Projects Only
� „ o , �, Fund Source Information E p 1 y
4 n ' — .n C . P roject Ti , v ' v o m (Local Agency)
.0 cn o E > J 0 L Federal Funding R/VV
c U ti Z D. Street/Road Name or Number o .l' -- in T a Phase Federal Federal State 4th Required
LL E • o — a • State Local Total Envir. Date
E. Beginning MP or Road - Ending MP or Road F o Start Fund Cost by Fund F un d s F un d s F unds 1st 2 nd 3rd sin Type M
_ a . (mm/dd/yyyy) Code Phase Code ( tf
•
F. Describe Work to be Done
1' 2 3 4 5 6 7 8 9 10 11 12 13. 14 15 16 17 . 18 • 19 20 • 21
PE 4/1/2011 13 13 13
16 17 12 P N/A P CN 6/1/2011 - 214 214 214 CE
• S 3rd Ave & W Washington Ave Signal T No •
S 3rd Ave •
from: S 3rd Ave to: W Washington Ave •
Signal Upgrades '
•
•
• Totals 227 227 227.
4579 PE 6/1/2011 STP(U) 1 252 38 2901 290
14 18 • 12 P N/A P EA
S 1st St. - E. Washington Ave. Intersection Improvement W Yes •
S 1st St. S .
from: S 1st St. to: E Washington Ave. T .
Realign intersection, upgrade traffic signal 01/01/11
' Totals 252 38 . 290 290
17 19 4587 • 03 P 1.00 P ALL 4/1/2012 STP 2268 307 25751 525 2050 EA
S 48th Ave. Reconstruction T Yes
S 48th Avenue W
from: Summitview Ave. to: Nob Hill Blvd. S
• Widen, curb, gutter, sidewalk, lighting, drainage 4/1/2014 •
Totals 2,268 307 2575 525 2050
PE 1/1/2012 STP(U) 51 8 59 59
14 20 03 P N/A 0 CN 6/1/2012 STP(U) 383 61 444 444 CE
South 72nd Ave & Mead Ave Intersection 12 P - Yes
South 72nd Ave S
' from: South 72nd Ave to: Mead Ave T
W 6
New intersection, signals, curb, gullet and sidewalk
•
•
Totals. 434 69 503 503
•
Report Date: May 25, 2010 Page 5 v. 5.7 - Supersedes previous editions
•
•
•
•
•
r •
0 .
Wash on State Department of Transportation De P Six Year Transportation Improvemerogram
• Agency: Yakima . From 2011 to 2016
Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -15 -2010 Adoption Date: 7 -15 -2010
.. City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
• Project Identification Project Costs In Thousands of Dollars Federally Funded
A. PIN /Federal Aid No. B. Bridge No. -.E. v e , Fund Source Information Expenditure Schedule Projects Only
a) e H rn C c u (Local Agency)
0 m o C. Project Title > ;, 5 f, c.) t Federal Funding R/W
-.0 ct D. StreeVRoad Name or Number 5 in S a Phase Federal Federal State 4th Required
o - State Local Total Envir. Date
E. Beginning MP or R - Ending MP o r Road E o Start Fund Cost by Fund Funds Funds Funds 1st 2nd 3rd Thru Type (MMn y) •
F. Describe Work to be Done n. (mm /dd /yyyy) Code Phase Code 6th
1 2 • 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
4562 N/A P ALL 4/4/2012 STP(U) 378 WSDOT 378 756 756 CE
16• 21 12 P
Tieton Dr - S 5th Ave. Intersection Project W • Yes
Tieton Drive T
0
from: 5th Ave. Intersection to: S 4/1/2014
Replace traffic signal with roundabout
- Totals 378 378 756 756
PE 1/1/2012 STP(U) 2180 340 2520 2520
16 22 - 01 P 1.1 0 RW 1/1/2014 STP(U) 2180 340 2520 2520 CE
E. 1-1° St. Extension. 08 P CN 6/1/2014 STP(U) 1199 1871 3070 3070 Yes •
• E. "H" St.
from: 1st St. to: Yakima River T
W
Construct road including water, sewer, curb, gutter and sidewalk for future • 111 /2014
development. Totals 5,559 2551 8110 2520 • 5590
' PE 1/1/2012 STP(C) 700 108. 808 808
17' 23 01 P 1.3 0 RW 1/1/2013 STP(U) 5500 850 6350 6350 CE
N. 10th St. Extension 06 P CN 6/1/2013 STP(U) 7900 972 8872 8872 Yes
N. 10th St.
•
from: R St. to: 10th Street - Lincoln Ave. T
W 1/1/2013
Construct road including water, sewer, curb, gutter, sidewalk for future •
development.
Totals 14,100 1930 16030 808 15222
•
00 24 23 P N/A PE 1/1/2011 5309(NS) 400 OTHER 100 5001 500 CE
West Side Transit Center No
Acquire Property to Expand Operations
from: N/A to: N/A • -
Locate and acquire property for the placement of a West Side Transit
Center Operation -
Totals 400 100 500 500
Report Date: May 25, 2010 Page 6 v. 5.7 - Supersedes previous editions
•
•
•
. Washingt•ate Department of Transportation •• Six Year Transportation Improvement Ieram
Agency: Yakima From 2011 to 2016
Co. No.: 39 Co. Name: Yakima Co. .
Hearing Date: 7 -15 -2010 Adoption Date: 7 -15 -2010
City No.: 1485 MPO /RTPO: • YVCOG Amend Date: Resolution No.:
•
Project Identification Project Costs in Thousands of Dollars Federally Funded .
ro , T A. PIN /Federal Aid No. B. Bridge No. v rn 2 e , Fund Source Information Expenditure Schedule Projects Only
s n C. Project Title v v o m (Local Agency)
i t — E a o ri Federal Funding R/W 72 U i Z D. Street/Road Name or Numbe o.� in := = a ' P hase Federal Federal State 4th Required
• . E. Beginning MP or Road - Ending MP or Road E 5 ° Start Fund Cost b Fund State Lo T Thru
F. Describe Work to be Done Envir. Date
° mm /dd/ y Funds Funds Funds 1st 2nd 3rd 6th Type (MM/YY)
a ( YYY Y) Code Phase Code
1 2 ' 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 •21
17 25 06 P 60 P PE 4/1/2011 OTHER , 6000 6000 6000 .
CE
' Yakima Downtown Future Initiatives, Phase 5 12 W No
S
from: 1st Street to: 9th Street T •
I
0 nstall Historic Lighting, Sidewalk Modification & Other Improvements.
Exact improvement area(s) to be determined. '
Totals 6000 6000 6000
• PE 1/1/2011 STIP (S) 60 60 120 120
• 00 26 - 01 P N/A CN 4/1/2012 STP(S) 180 AIP 240 420 420 CE
• Annual Signal Upgrades CN 4/1/2012 STIP (S) 360 360 360 No
Local Selection
from: N/A to: N/A '
Upgrade signals •
Totals soo 240 60 900 120 780
00 27 07 P N/A w CN 6/1/2011 - STP(U) 228 32 - 2601 260 '
EA
Various Overlay Projects /Selected on Local Priority S No
N/A
from: N/A to: N/A
Totals 228 32 260 260
PE 1/1/2011 STP(U) 100 14 114 114
19 28 03 P N/A P CN 3/1/2012 STP(U) 700 • 95 795 795 CE
Longliber Rd 8 Washington Ave • 05 S Yes
Intersection - 06 T
from: to: T
New intersection construction and reconstruction, 3 - lane and 5 - lane w /tum,
O 3/1 /2012
curb, gutter, sidewalks.
Totals • 800 109 909 114 795
•
•
Report Date: May 25, 2010 Page 7 • v. 5.7 - Supersedes previous editions
•
•
•
• Transportation Im rovemeero ram
Was7lRlgton State Department of'Transportation Six Year p p g •
6
Agency: Yakima From 2011 to 2016
Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -15 -2010 Adoption Date: 7 -15 -2010
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
Y `
A. PIN /Federal Aid No. B . Bridge No, rn v N Fund Source Information Expenditure Schedule Projects Only
o _ o E C . Project Title E a m ` c i r (Local Agency) Federal Funding R/W
a Z
c U D. Street /Road Name or Number 2 >, in - 4' a Phase Federal Federal State • 4th Required
..1- State Local Total Envir. Date
E. Beginning MP or Road - Ending MP or Road E o - o Start Fund Cost by Fund Funds Funds Funds 1st 2nd 3rd Thru Type (Amyy)
F. Describe Work to be Done a (mm /yyyy) C ode Phase Code 6th .
1 2 • 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 -
•
14 29 04 P .1 c CN 4/1/2011 STP(U) 240 42 282 282 CE
E Nob Hill Blvd & S 18th St • 01 S Yes
E Nob Hill Blvd . W .
from: S 18th St to: E Nob Hill Blvd T
01/01/07
' Widen south leg for double LT from west bound Nob Hill; (Tie to WSDOT
Project) possible curb, gutter and sidewalk
Totals 240 42 282 282
PE 1/1/2011 . STP(E) 22 7 29 1 29
' 17 30 - 05 P .15 s CN 6/1/2011 STP(E) 75 • 20 95 95 CE Yes
Zier Rd - S 75th Ave to S 72nd Ave 06 ,
Zier Rd T
from: S 75th Ave to: S 72nd Ave P
6/1/2011
Minor widening, curb, gutter and sidewalk
•
Totals 97 27 124 124
PE 1/1/2011 50 501 50
00 31 07 P N/A S CE
CN 6/1/2011 240 240 240
Gravel Road B.S.T. ' No
Various Areas
• from: City Wide to:
Totals 290 290 290
16 32 12 P N/A T CN 10/1/2013 STP(S) . 504 74 5781 578 CE
Powerhouse Rd & Englewood Ave P Yes
Powerhouse Rd o •
from: Powerhouse Rd to: Englewood Ave 10/1/2013
Intersection, realignment, curb, gutter, sidewalk, Safety Flashing Signal, w
possible roundabout Totals 504 74 578 578
Report Date: May 25, 2010 Page 8 v. 5.7 - Supersedes previous editions .
•
•
•
Washing ate Department of Transportation • • SIX Year Trans ortation Im rovement ra m
Agency: Yakima From 2011 to 201 6
Co. No.: 39 Co. Name: Yakima Co.
Hearing Date: 7 -15 -2010 Adoption Date: 7 -15 -2010
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars • Federally Funded
2 Phase Federal Federal S
A. PIN /Federal Aid No. B B No. c .c w Expenditure Schedule Pro'
, , o a Fund Source Information P Projects Only •
_ 9 (Lo cal Age ncy)
o n .n C. Project Title d o m o m RNV
m o E > " L Federal Funding Required
ti 15 L- 2 D. Street/Road Name or Number a r a
aF- V) eeraeeratate 4th Date
E. Beginning MP ' or Road - Ending MP or Road E 1 2 5 ° Start Fund Cost by Fund State Local Total • Envir.
F. Describe Work to be Done a- (mm/dd /yyyy) Code Phase Code Funds Funds Funds 1st 2nd 3rd 6th Type (mm/yy) •
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
14 33 12 p N/A P PE 1/1/2013 STP(S) 25 4 29 29
S 48th Ave & Summitview Ave Signalization T RW 6/1/2013 STP(S) 25 4 29 29. CE
CN 8/1/2014 STP(S) 554 • 81 635 635 Yes •
S 48th Ave
•
from: S 48th Ave to: Summitview Ave '
Signalization 8/1/2013
Totals 604 89 693 58 . 635
14 34 01 P .5 y, P E 1/1/2012 STP(E) 424 67 491 491
W LincolnAve &'8'StRealignment T RW 1/1/2013 STP(E) 1047 163 1210 1210 CE •
W Lincoln Ave 12 S CN 1/1/2014 STP(E) 1801 281 2082 2082 Yes
from: W 5th Ave to: Custer St P
0 Realignment of W Lincoln Ave, sidewalks, curb, gutter, lights G
1/1/2014
C Totals 3,272 511 3783 . 491 1210 2082
16 35 12 P N/A w I. I I I I I I I I I I CE
School Safety Projects No
Various Locations - Citywide
from: to:
Crossing flashers, sidewalks, signing, other features
Totals
14 36 03 P .85 C PE 1/1/2012 STP(C) 546 84 630 630
RW 1/1/2013 STP(C) 1090 170 1260 1260 EA
ENob Hill Blvd. Reconstruction 04 G CN 1/1/2014 STP(C) 6539 1013 7552 7552 Yes
E Nob Hill Blvd. 06 o
•
from: S 6th Street to: S 18th Street P
S 1/1/2014
Major roadway widening and reconstruction to 5 lanes with intersection T
improvements, curb, gutter, sidewalks, replacement or relocation of meters W
an hydrants Totals • 8,175 1267 9442 630 1260 7552 .
•
Report Date: May 25, 2010 Pages v. 5.7 - Supersedes previous editions
•
•
•
•
•
•
•
i■■
0
Was on State Department'ofTransportation Six Year Transportation Improvemeerogram
Agency: Yakima From 2011 to 2016
Co. No.: 39 Co- Name: Yakima Co. • Hearing Date: 7 -15 -2010 Adoption Date: 7 -15 -2010
City No.: 1485 'MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
A. PIN /Federal Aid No. • B. Bridge No. a rn a 0 Fund Source Information Expenditure Schedule Projects Only
g. :o E C. Project Title • o a W a 0 a Federal Funding (Local AgenC»
= v D. Street/Road Name or Number '' r = Ph ase Federal Federal State 4 th Required •
Z ° ~ o - State Local Total Envir. Date
LL E. Beginning MP or Road - Ending MP or Road . E 1- S o Start Fund Cost by Fund Funds Funds Funds 1 2nd 3rd Thru Type (Mtl/yy)
F. Describe Work to be Done Z (mm /dd /yyyy) Code Phase Code 6th
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
PE 1/1/2012 STP(C) 91 14 105 105
17 37 01 P N/A W RW 1/1/2013 STP(C) 91 14 105 105 CE
S 72nd Avenue & W Washington Avenue 12 T CN 1/1/2014 STP(C) 544 86 630 630 Yes
S 72nd Ave 06
from: S 72nd Ave to: W Washington Ave P
P 1/1/2013
Intersection improvement, possible roundabout
Totals 726 114 840 105 105 630
PE 1/1/2012 - STP(E) 23 5 28 28
17 . 38 04 P .76 • W CN 7/1/2013 STP(E) 1096 . 164 1260) 1260 Yes
S 66th Avenue 03
S 66th Ave S
from: Scenic Drive to: Summitview P 7/1/2012
Widen roadway, curb, gutter, sidewalk and utilities
Totals 1,119 169 1288 28 1260
PE 1/1/2013 STP(U) 126 17 143 143
14 39 12 P N/A W RW 1/1/2013 STP 63 8 71 71 CE
40th Avenue. and Summitview Signal Upgrade • T CN 6/6/2013 STP(U) 544 86 630 630 Yes
40th Avenue P
from: 40th Avenue to: SummiNiew O 6/1/2012
Signal upgrade, radius improvements, turn lane extension ,
Totals 733 111 844 844
14 40 12 P PE 1/1/2013 STP 95 13 108 108
N/A W RW 1/1/2014 STP . 63 8 71 71 CE
40th Avenue and Englewood T CN 1/1/2014 STP 145 20 165 165 Yes •
40th Avenue S
from: 40th Avenue to: Englewood PO - 1/1/2013
Replace traffic signal poles, upgrade controller .
Totals 303 41 344 179 165
Report Date: May 25, 2010 Page 10 v. 5.7 - Supersedes previous editions •
•
•
•
•
._'
Washingtate Department of Transportation • Six Year Transportation Improvement Iram
v 7
Agency: Yakima From 2011 tO 2016
Co. No.: . 39 Co. Name: Yakima Co.
Hearing Date: . 7 -15 -2010 Adoption Date: 7 -15 -2010
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification , Project Costs in Thousands of Dollars Federally Funded
• y PIN /Federal Aid No. B. Bridge c Expenditure Schedule Projects Only
„ d �, Fund Source Information
rn •— a . � 9 a No. E ;- N C o N (Local Agency)
g y C. Project Title v J o _. Federal Funding R/W
a- Z D. St Name or Number Q F in m Phase Federal Federal State 4th Required
r LL E. Beginning MP or Road - Ending MP or Road E 1 d Start Fund Cost by Fund State Local Total Thru Envir. Date
—
° mm /dd/ y Funds Funds Funds 1st 2nd 3r .Type (MM/YY)
F. Describe Work to be Done o. ( YYYY) Code Phase Code . 6th
1 2 3 i 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
0 41 12 P N /A W PE 1/1/2013 STP 126 18 144 144
16th Avenue and Fruitvale Blvd T RW W 6/1/2013 /2013 STP 63 8 71 71 CE
CN 1/1/2014 STP 315 43 358 358 Yes
16th Avenue S
•
from: 16th Avenue to: Fruitvale Blvd P
Replace traffic signal poles, radius improvements, ADA ramps O 1/1/2013
Totals • 504 69 573 215 358
•
14 42 12 P N/A W PE 1/1/2011 STP 32 • 5 37 37
CN 1/1/2012 STP 126 17 1431 143 CE
1st Street and !Street T No
1st Street S '
from: 1st Street • to: I Street P
Replace and upgrade traffic signal equipment O
Totals 158 22 180 37 143
16 43 01 P .25 p PE 6/1/2014 STP(U) 820 189 1009 1009
RW 1/1/2015 STP(U) 3150 E
630 3780 3780 C
Washington Ave. 'Railroad Grade Separation P CN 1/1/2016 STP(U) 6552 1008 7560 7560 Yes '
Washington Ave. S
from: Longfibre Road to: T
W 1/1/2016
Railroad grade overpass including all utilities
Totals 10,522 1827 12349 12349
16 44 01 P 1.3 C PE 1/1/2013 STP(U) 272 43 315 315
RW 6/1/2014 STP(U) 349 55 404 404 CE
. Frontage Road & "M' St. Loop G CN 1/1/2016 STP(U) 2352 340 2692 • 2692 Yes
N. 8th St. O
from: "H" St. to: 1 -82 P
Construct new roadway, water, sewer, cutb, gutter, sidewalk and lighting for T 1/1/2015
T •
future development and Terrace Heights connection. • .
W Totals 2,973 ' 438 3411 315 3096 '
•
Report Date: May 25, 2010 Page 11 v. 5.7 - Supersedes previous editions .
•
•
•
• •
• Transportation Im
Was on State Department of Transportation Six Year Transpo p roveme ro g ram
Agency: Yakima From 2011 to 2016
•
Co. No.: 39 Co. Name: Yakima Co- Hearing Date: 7 -15 -2010 Adoption Date: 7 -15 -2010
City No.: 1485 MPO /RTPO: YVCOG • • Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
or T ._ A. PIN /Federal Aid No. B. Bridge No- t rn v 3 Fund Source Information Expenditure Schedule Projects Only
o y -D C . Pro ect Title E ; ; o y (Local Agency)
o f j > o m J 0 L F ederal Funding R/W
c U t i Z D. Street /Road Name or Number o i n Phase Federal Federal State 4th
Required
— , Envir. Date
t ' - . E. Beginning MP or Road - Ending MP or Road E o State Local Total
o Start Fund Cost by Fund Funds Funds Funds 1st 2nd 3 r d Thru Type (MM/1)7
F. Describe Work to be Done a (mm/dd /yyyy) Code Phase Code 6th
1 2 3. . • 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
14 45 04 P 3.5 G PE 1/1/2014 STP(U) 120 17 137 • 137 CE
16th Ave. Corridor
16th Ave. 0 •
•
• from: SR -12 to: Wahington Ave.Nalley Mall P •
Widen roadway, curb, gutter, sidewalk, lighting. S T
W Totals 120 17 137 137
14 46 04 P 3.2 C PE 1/1/2013 STP(U) 120 17 . 1371 137 CE
40th Ave. Corridor 0
40th Ave. - G
' from: SR -12 to: Washington Ave. • P
Widen roadway, curb, gutter, sidewalks, lighting. S
W •
T Totals 120 17 137 137
PE 1/1/2012 STP(U) 120 17 137 • 137
14 47 • 03 P 2.7 G 1 C
Nob Hill Corridor 04
Nob Hill - 0
from: 1 -82 to: S. 16th Ave. P
T
Widen roadway, sidewalk, curb, gutter, lighting
T
W Totals 120 17 137 137
14 48 04 P 2.0 G PE 1/1/2014 STP(U) 120 17 1371 137 CE
S. 1st St/Main St. Corridor
S. 1st St. /Main St.
from: Nob Hill Blvd. • to: Barker Mill Bridge P '
Joint project with Union Gap to widen roadway, curb, gutter, sidewalk, • 3
lighting. T
W Totals 120 17 137 137
•
• Report Date: May 25, 2010 Page 12 v. 5.7 - Supersedes previous editions
•
•
Washingt ate Department of Transportation ID Six Year Transportation Improvement ram .
P P
Agency: Yakima From 2011 to .2016
Co. No.: 39 Co. Name: Yakima Co.
Hearing Date: 7 -15 -2010 Adoption Date: 7 -15 -2010
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.: .
Project Identification Project Costs in Thousands of Dollars Federally Funded
H Expenditure Schedule Projects Only
Y A. PIN /Federal Aid No. B. Bridge No. c., a Fund Source Information
y N C a N (Local Agency)
o t-? C. Project Title > a 3 J Li r Federal Funding R/W
M U a z D. Street/Road Name or Number 2 i :° n Ph ase • Federal Federal State 4th Required
u` E. Beginning MP or Road - Ending MP or Road t ° Start Fund C os t by Fund State Local Total 1st 2nd . 3rd Thru Envir. Date
F. Describe Work to be Done ate. (mm /dd /yyyy) Code Phase Code Funds • Funds Funds 6th Type '(MM/Vl�
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 •
00 49 32 P N/A PE 1/1/2011 100 100 100 EA •
CN 1/1/2011 900 900 900
Storm Drains/Vegetation No
Local Selection • '
from: City Wide to:
• City Wide
. Totals 1000 1000 1000
17 50 03 P •76 W PE 1/1/2012 STP(C) 109 27 136 136 CE
CN 1/1/2013 STP(C) 945 TPP 945 . 106 1996 1996
Reconstruction Rudkin Rd 06 T No
Rudkin Rd P
. from: E Viola Ave to: Rainier Place S -
Reconstruct, excavate ballast, top course, curb, gutter, sidewalk '
• Partner with City of Union Gap, additional sewer force main
Totals 1,054 945 133 2132 136 1996
16 51 03 P 76 C PE 9/1/2012 STP(S) 122 TPP 23 7 152 152
CN 4/1/2013 STP • 1730 TPP 206 70 2006 2006 ' CE
E Mead Ave Reconstruction 06 G No
E Mead Ave C
from: Rudkin Rd to: Fair Ave P
Partner with City of Union Gap, reconstruct, excavate ballast, top course, T •
curb, gutter, storm, acp T
Totals 1,652 229 77 2158 152 2006
•
PE 1/1/2012 'AIP 131 20 151 151
17 52 - 04 P 1 . 3 0 RW 1/1/2013 AIP 382 59 441 441 EA
S 80th Ave - Tieton Dr to Zier Rd C CN 4/1/2013 AIP 1667 260 1927 1927 Yes
S 80th Ave P
T• .
from: Tieton Dr -to: Zier Rd W 4/1/2012
Major widening, curb, gutter, sidewalk s -
Totals 2180 339. 2519 151 2368
•
•
Report Date: May 25, 2010 Page 13 v. 5.7 - Supersedes previous editions
•
•
• S ix Year Transportation Im ro •
p p
*71F Was•on State Department of Transportation
•
Agency: Yakima From 2011 to 2016
•
Co. No.: 39 Co. Name: Yakima Co. Hear Date: 7 15 -2010 A doption Date: 7 -15 -2010
• City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
A. PIN /Federal Ald No. B. Bridge No. m Fund Source Information Expenditure Schedule Projects Only a c 'Eli E H d ° " Federal Fundin (Local Agency) RNV
a $ C C. Project Ti c T m ,� r a g Required
C Z D. Street /Road Name or Number a� i ; 4 =_ Phase Federal . Federal State • 4th Envir.
u- E r ° - °' Start by Fund Cost b Fund State Local Total 1st 2nd 3rd Thru Type Date
E. Beginning MP or Road - Ending MP or R o Funds Funds Funds 6th yp e (MM/YY)
F. Describe Work to be Done a. (mm /dd/yyyy) Code Phase � Code
1 2 3 4 5 6 7 8 9 10 , 11 12 13 14 15 16 17 18 19 20 21
PE 1/1/2014 STP(C) 272 43 315 315 •
17 53 05 P 1 . 0 W RW 6/1/2014 STP(C) 349 55 404 ' 404 EA
Englewood Ave - N 40th Ave to N 56th Ave 06 S CN 1/1/2015 STP(C) 2352 340 2692 - 2692 Yes
Englewood Ave T
P
from: N 40th Ave to: N 56th Ave
1/1/2013
Widen roadway, curb, gutter, sidewalk C
Totals 2,973 438 3411 3411 •
• 17 54 05 PE 1/1/2013 STP(U) 219 34 253 • 253 - EA
P 2 o . RW 6/1/2013 STP(U) 327 51 378 378
Englewood Ave - N 24th Ave to N 16th Ave 06 3 CN 6/1/2014 STP(U) 2980 244 3224 3224 Yes
Englewood Ave
from: N 16th Ave to: N 24th Ave : 6/1/2013
• • W iden, curb, gutter and sidewalk, water and sewer lines '
Totals 3,526 329 3855 631 3224
PE 1/1/2013 STP(S) 55 8 63 63 • CE
14 55 • 12 P 2.5 P RW 6/1/2013 STP(S) 107 19 126 126 •
W Nob Hill Blvd Sidewalks W CN 3/1/2014 STP(S) 321 57 378 - 378 Yes
W Nob Hill Blvd
• from: S 16th Ave to: S. 6th St. S
3/1/2013
Install missing sidewalks on southside of Nob Hill. .
Totals 483 84 567 189 378
PE 1/1/2013 STP(S) 57 7 64 64 CE
00 56 06 P 1.0 P RW 6/1/2013 STP(S) 189 25 214 214
Beech St Pedestrian.Connection 32 T CN 1/1/2014 STP(S) 504 • 68 572 572 Yes
Beech St '
from Fair Ave to: Chalmers /Riverside - 1/1/2013
Construct pedestrian pathway under SR82 to Greenway .
Totals 750 100 850 . . 278 572
•
Report Date:' May 25, 2010 Page 14 • v. 5.7 - Supersedes previous editions •
Washing ate Department of Transportation
111 Six Year Transportation Improvement
' Agency: Yakima From 2011 to 2016 •
:Co. No.: 39 Co. Name: Yakima Co.
City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 7 -15 -2010 Adoption Date: 7 -15 -2010
Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
T T L - A. PIN /Federal Aid No. B. Bridge No. c t
l w EX enditure Schedule Pro
y - d m Fund Source Information P jects Only
0 N ' - C. Project Title v " o (Local Agency)
. '0 m .2 v _ o L Federal Funding • g U n`. D. Street /Road Name or Number 2 r
to m IL Dat
a - 5 _ - Phase Federal Federal State • 4th R
•
E. Beginning MP or Road - Ending MP or Road E I ° Start Fund Cost by Fund State Local Total . Envir. Date
F. Describe Work to be Done a (mm /dd /yyyy) Code Phase Code Funds Funds Funds 1st 2nd 3rd 6th Type (MMN11
1 2 , , 3 4 5 6 7 8 9 10 11 12 13 14 15 , 16 17 18r, 19' 20 21
16 57. 12 P 2.0 P PE 1/1/2013 STP(S) 43 ' 7 50 50 •
RW 6/1/2013 STP(S) 86 15 101 101 CE
•
W Lincoln Ave Sidewalks T
W Lincoln Ave S CN 1/1/2014 STP(S) 572 88 660 660 Yes
w
from: N 56th Ave to: N 29th Ave • •
. Sidewalks, meters and lire hydrants replacement or relocation 1/1/2014
Totals 701 110 811 151 660 .
14 58 01 P .25 W PE 6/1/2013 STP(U) 820 189 1009 1009
Mead Ave. Railroad Grade Separation T RW 1/1/2014 STP(U) 3150 630 3780 3780 CE • .
Mead Ave. S CN 1/1/2015 STP(U) 6552 1008 7560 7560 • Yes
•
. from: Presson Place . to: Maryland P
Construct railroad overpass including all utilities 1/1/2014 •
Totals 10,522 1827 12349 1009 11340
16 59 01 P 4.0 0 PE 6/1/2012 STP(U) 252 38 290 290 •
City wide Pathway Connections P RW 1/1/2013 STP(U) 756 . 88 844 844 CE .
Yakima ' S CN 1/1/2014 STP(U) 1890 315 2205 .2205 Yes
• from: to: T
Cowiche Canyon Trail, Powerhouse Rd pathway, east side canal paths, W 1/1/2013
•
WOD Trail, Greenway including Naches Rail Spur, signage and amenities .
Totals 2,898. 441 3339 290 844 2205
•
17 60 01 P N/A 0 PE 1/1/2013 STP(U) 63 5 68 [ 68
34th Ave & River Rd Improvements 12 P CN 6/1/2013 STP(U) 567 76 643 643 CE .
• Fruitvale Blvd. S • • No •
•
from: 34th Ave. to: River Rd. T
Intersection improvements including lumination, sewer, water, curb, water W
•
and sidewalks
Totals 630 81 711 711
•
•
Report Date: May 25, 2010
Page 15
v. 5.7 - Supersedes previous editions •
•
•
•
•
•
Wash Department of Transportation III Six Year Transportation Improvemerogram
C
• Agency: Yakima From 2011 to 2016 •
Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -15 -2010 Adoption Date: 7 -15 -2010
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification , Project Costs in Thousands of Dollars Federally Funded
ctl m go m
A. PIN /Federal Ald No. B. Bridge No. a Fund Source Information Expenditure
Agency)
Projects Only
s . ' — fl C. Project Title d d ` w c ° � N L Federal Funding (Local 9 » R/W .
t MI c 0 a Z D. Street/Road Name or Number a in n Phase Federal Federal State • 4th Required
o State Local Total Envir. Date
E. Beginn M P or Road - Ending MP or Road 1 . . Start Fund Cost by Fund Funds Funds Funds 1st 2nd 3rd Thru Type (MM/Y1�
F. Describe Work to be Done a (m m/dd /yyyy) Co de Phase Code 6th
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 ' .21
PE 1/1/2013 STP(U) 218 34 252 252
17 61 01 P 1.0 0 RW 6/1/2014 STP(U) 327 51 378 378 CE
Englewood Ave 05 8 CN 1/1/2015 STP(U) 2980 244 3224 3224 Yes
Englewood Ave 12
from: 24th Ave to: 40th Ave T
W 1/1/2015
Reconstruct roadway, widen, curb, gutter and sidewalks. Sewer, water lines
and street lights. Totals 3,525 329 3854 252 3602
PE 1 1/1/2014 STP(U) 120 17 1371 137 CE
14 62 01 P 6.0 c
W. Yakima North /South Connector to West Valley 04 G
Unknown road 06 O
•
from: North - South to: in West Valley s
S •
City & County joint project to build/extend roadways. T
W Totals 120 17 137 137
16 63 01 P .38 S PE 1/1/2014 100 1001 100
Occidental Road Construction. W
P
from: 58th Ave. to: 64th Ave. T .
Construct roadway
Totals 100 100 100
2 7 PE 1/1/2014 100 1001 100
00 64 01 P -
86th Ave. Road Construction
from: Occidental to: Coolidge
Construct roadway
•
• Totals loo 100 100
Report Date: May 25, 2010 Page 16 • v. 5.7 - Supersedes previous editions
•
•
•
•
•
WashingtDl�tate Department of Transportation • Six Year Transportation Improvement jram
vI/
Agency: Yakima From 2011 to 2016
Co. No.: 39 Co. Name: Yakima Co.
Hearing Date: 7 -15 -2010 Adoption Date: 7 -15 -2010
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
m T A. PIN /Federal Aid No. B. Bridge No. 6 rn iii d Fund Source Information Expenditure Schedule Projects Only
C v, .. E w m c o e, (Local Agency)
o m . E C. Project Title d O J O L Federal Funding R/W
U i Z D. Street /Road Name or Number • o in 5 w a Phase Federal Federal State 4th Required
t` E. Beginning MP or Road - Ending MP or Road E i2 ° Start Fund Cost b Fd State Local Total Thru Envir. Date
° mm/dd by Fund Funds Funds Funds 1st 2nd 3rd Type (MM/YY)
F. Describe Work to be Done a / ( YYYY) Code Phase Code 6th
1 • 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
16 65 04 P 1.5 w PE 1/1/2014 STP(U) 120 • 17 ' 137 137
EA
64th Ave. Roadway Widening. 06 G YES
P
from: Washington Avenue. to: Tieton Drive. T
C 7/4/2014
Wide Roadway,Curb, Gutter, Sidewalks, Lighting, Drainage.
O
. Totals 120 17 137 137
00 66 • 03 P N/A G PE 1/1/2014 STP(E) 18 " 32 50 50
CN • 6/1/2014 STP(E) 1900 285 2185 - • 2185 EA
YVT Railway Rehabilitation & Museum C No
3rd Ave S
•
from: 3rd Ave to: Pine St T
Car Bam, Museum Restoration and Pathway W -
P •
Totals 1,918 317 2235 . 2235
16. 67 01 P N/A S PE 4/1/2012 CMAQ 24 3 27 • 27
CN 7/1/2012 CMAQ 480 65 545 545 CE
Roadway City Wide Shoulder Improvements No
City Wide
from: to: .
City Wide shoulder improvements, PM10 abatement.
Totals 504 68 • 572 572 '
PE 1/1/2013 STP(E) 252 34 286 1 286
00 68 14 P .25 T CN 3/1/2014 STP(E) 3150 412 3562 - 3562 CE
Pedestrian Bridge 32 P O • - No
. Pedestrian Bridge
from: N 10th St to: Yakima Greenway
Construct pedestrian bridge from Gateway area to Yakima Greenway,
power, handicap accessible, lights
•
Totals 3,402 446 3848 286 3562
•
Report Date: May 25, 2010 Page 17 • v. 5.7 - Supersedes previous editions
•
•
•
•
•
•
•
•
Alb. • S Y ear T Imt
Wa•onStateDepartrnefltOfTraflSPOrtatiofl M M
v71
Agency: Yakima From 2011 to 2016
•
• Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -15 -2010 Adoption Date: 7 -15 -2010
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.: .
Project Identification Project Costs in Thousands of Dollars Federally Funded
A. PIN /Federal Aid No. B. Bridge No. o v �, • Fund Source Information • Expenditure Schedule Projects Only
`.v E N N c o N (Local Agency)
g y a C. Project Title v d t Federal Funding R/W
• •
c U a Z D. Street/Road Name or Number a i n a Phase Fe deral Federal State 4th Required
LL E t ° Start F und C ost b Fund State Local Total Thru Envir. Date
E. Beginning MP or Road - Ending MP or Road o y Funds Funds Funds 1st 2nd 3rd Type (MM/YY)
F. Describe Work to be Done o- (mm/ddyyyy) Code Phase Code 6th
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
PE 1/1/2011 STP(E) 10 2 12 12
00 69 14 P N/A 0 CN 7/1/2011 STP(E) 109 17 126 126 'CE No
William O. Douglas Pathway 32 P .
•
from: Pine St to: Cowiche Canyon ,
Pathway improvements, connections, and signage to Cowiche Canyon Trail.
Totals 119 19 138 138
•
PE 1/1/2014 STP(U) 315 38 353 1 353
00 70 03 P N/A 0 CN 6/1/2014 STP(U) 945 126 1071 1071 CE
YVT Pathway 82 P No •
YVT Railway Corridor. S
•
• T
from: to: V/
Development pathway in West Valley area including 53rd Ave, Wide Hollow,
64th Ave, Ahtanum including all utilities and signage
,Totals 1,260 164 1424 1424
• CN 6/1/2011 75 75 I 25 25 25
00 71 07 P .5 G CE
City wide Alleys P No
S .
W
• from: to: . T
Pave alleys throughout the city.
Totals 75 75 25 .25 25
PE 1/1/2011 ARRA - 50 50 50
14 72 06 p 2.64 CN 6/1/2011 ARRA - 1950 1950 I 1950 CE
Summitview Ave: Grind 8 Overlay 07 No
from: 14th Ave • to: 56th Ave
Grind 0.20' of ACP & replace with 0.20' of HMA, and install required ADA
ramps Totals 2,000 2000 2000
v. 5.7 - Supersedes previous editions
Report Date: May 25, 2010 . P age 18
•
•
• Washing ate Department of Transportation Six Year Transportation Improvement illtrarn
c
Agency: .Yakima From 2011 to 2016
Co. No.: 39 Co. Name: Yakima Co. •
Hearing Date: 7 -15 -2010 Adoption Date: 7 -15 -2010
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
ii " S
a 8 A. PIN /Federal Aid No. B. Bridge No. c :c d E enditure Schedule projects
rn � , Fund Source Information • P ) is Only
IS. N ._ -2 C. Project Title E" N 5 o y (Local Agency)
m o E ) d ' L Federal Funding R/N/
•
c U a Z D. Street /Road Name or Numbe ° r 9 Required
° Re
at - i n ° _ o Phase Federal Federal State 4th q
r ` E. Beginning MP or Road - Ending MP or Road E t ° - 5 , - Start Fund. Cost b Fund State Local Total Envir. Date
° m y Funds Funds Funds 1st 2nd 3rd Thru Type MM
F. Describe Work to be Done a ( m/dd /YYYY) Code Phase Code 6th
•
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
17 _ 73 03 P 0.50 W ALL 1/1/2014 STP(U) 1298 • 202 1500 1500
CE •
River Road Improvements 05 G Yes
06 P
T
from: 6th Ave to: 16th Ave
Reconstruct roadway, w 07 T 6/1/2015 widen, curb, gutter, sidewalk, lighting and drainage
Totals 1,298 202 1500 1500
74 • 05 P 0.97 C CN 7/1/2012 STP(U) 2700 421 31211 • 312
Nob Hill Blvd 06 P ' CE No
07 T
G
from: 49th Avenue to: 64th Avenue
Widen, curb, gutter, sidewalk, lighting, drainage, grind and overlay.' ull width 12 O
13
Totals 2,700 421 3121 3121
75. 10 P O1 P PE 4/1/2011 BRAG 50 501 50 N/A
18th Street Underpass 11 T No
• C
from: Yakima Ave to: 18th Street
Repair or replace 18th Street Underpass
Totals 50 • 50 • 50
76 06 P 0.48 C PE 1/1/2012 WSDOT 50 50 • 50
• 88th Avenue C RW 2/1/2012 WSDOT 25 25 25 CE
12 T CN 6/1/2012 WSDOT 320 10 330 330 Yes .
13 G
•
from: Tieton Drive to: Summitview Ave •
Construct curb, gutter, sidewalk and stormwater runoff treatment on the east
' side of 88th.
Totals 395 10 405 405 •
Report Date: May 25, 2010 Page 19 • V. 5.7 - Supersedes previous editions
•
•
•
•
•
•
. S Was on state Department of Transportation Six Year Transportation Improvemelarogram
•
Agency: Yakima From • 2011 t0 2016
Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -15 -2010 Adoption Date: 7 -15 -2010
City No.: 1485 MPO /RTPO: YVCOG Amend Date: ' Resolution No.:
Project Identification Project Costs in Thousands of Dollars Federally Funded
To >sjr, A. PIN /Federal Ald No. B . Bridge No. 9 Fund Source Information Expenditure Schedule Projects Only
(Local Agency)
_ C. Project Title c a T i i Federal Funding R/W -J
c v a z D. Street/Road Name or Number a� fn 2 = Phase Federal Federal State 4th Required •
o - State Local Total Envir. • Date
E. Beginning MP or Road - Ending M o r Road E o ° Start Fund Cost by Fund 1st 2nd 3rd Thru
g g g a (mm /dd /yyyy) Code Phase Code Funds Funds Funds • 6th Type (MM/YYI
F. Describe Work to be Done
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
77 23 P N/A S PE 4/1/2013 5309(Bus) 15000 1000 16000 2000 14000
Westside Transit Center (Transit) Yes
from: N/A to: N/A
Construct a West Side Transit Center (Park & Ride Facility)
Totals 15,000 1000 16000 2000 14000
78 23 P ALL 3/1/2011 5307 ' 428 428 I 428 CE
• Transit Operating Hours Expansion •
from: to:
Expand Transit Operating Hours an hour later into the evening except for
one route that will be expanded an hour earlier
Totals 428 428 428
79 23 P ALL 1/1/2011 5307 288 2881 288 CE
Terrace Heights Moxee Route Expansion
from: 10:
Expand route service to Terrace Heights and Moxee
Totals 288 288 288
80 23 P ALL 1/1/2011 5307 602 602I 602 CE
Kiftitas- Yakima Commuter Bus
•
from: to:
Expand Route Service to Kittilas County
Totals 602 • 602 602
Report Date: May 25,2010 • Page 20 . v. 5.7 - Supersedes previous editions
•
•
•
Washingt te Department of Transportation
• Six Year Transportation Improvement mram
Agency: Yakima • From 2011 to 2016
Co. No.: 39 Co. Name: Yakima Co.
Hearing Date: 7 -15 -2010 Adoption Date: 7 -15 -2010
City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.: •
Project Identification Project Costs in Thousands of Dollars • Federally Funded
T A. PIN /Federal Aid No. B. Bridge No. Fund Source Information Expenditure Schedule Projects Only
s C. Project Title E N W c o (Local Agency)
o E I v L Federal Funding R/W
z D. Street/Road Name or Number o =° o Required
a� u1 f : — i Phase Federal Federal State 4th Date
E. Beginning MP or Road - Ending MP or Road E • 1 5 o Start Fund Cost by Fund State Local Total Thru Envir.
F. Describe Work to be Done n (mm/dd /yyyy) Code Phase Code Funds Funds Funds 1st 2nd 3rd 6th Type (MM/Yy)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
81 23 S N/A ALL 1/1/2011 CMAQ 200 200 200
CE
Sunday Bus Service - No
from: to:
Expand existing bus service to operate every two hours lour times per route
on Sunday
Totals 200 200 200
Grand Totals for Yakima • 129,171 15,463 27,369 172,003 28,721 25605 36,279 81,398
•
•
•
•
•
•
•
•
•
•
•
Report Date: May 25, 2010 Page 21 V. 5.7 - Supersedes previous editions
•
•
•
•