HomeMy WebLinkAboutR-2024-014 Resolution accepting Change Order No. 1 to City Contract 2023-161 with Industrial Construction of Washington LLC for Project SW2661 DID #29 Stormwater Improvements and Spot Repairs RESOLUTION NO. R-2024-014
A RESOLUTION accepting Change Order No. 1 to City Contract 2023-161 with Industrial
Construction of Washington LLC for Project SW2661 DID #29 Stormwater
Improvements and Spot Repairs.
WHEREAS, Industrial Construction of Washington LLC was selected as the contractor
and the City of Yakima (City) entered into an Agreement for the realignment and spot repairs of
stormwater conveyance pipe in the amount of $243,955.22; and
WHEREAS, shallow groundwater depth during construction required additional labor,
equipment, materials and the addition of ten (10) contract working days to protect existing utility
infrastructure and worker and traffic safety; and
WHEREAS, the total cost is $116,715.30 for the labor, equipment, materials, and the
addition of 10 working days associated with Change Order No. 1; and
WHEREAS, the City Council finds that it is the best interest of the City of Yakima and its
residents to proceed with approval of Change Order No. 1; now, therefore
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
The City Manager is hereby authorized to execute Change Order No. 1 between the City
of Yakima and Industrial Construction of Washington LLC in the amount of One Hundred Sixteen
Thousand Seven Hundred-Fifteen Dollars ($116,715) for additional working days and labor and
materials required for Project No. SW2661 DID#29 Stormwater Improvements and Spot Repairs.
ADOPTED BY THE CITY COUNCIL this 16th day of January, 2024.
ATTEST: `_ �<rMyyIlAi 1' Patricia Byers, Mayor
i
SEAL ; *$
Rosalinda Ibarra, City Cler' % `/1lr�cIO
Change Order
=' City of Yakima
Change Order Number 01
DID#29 Stormwater Improvements and Spot Repai Change Order Date November 29, 2023
Project: (Name) P P P 9
(Number) City No SW2661, HLA No 22175C Contract Number SW2661
To: (Contractor) Contract Date September 20, 2023
Industrial Construction of Washington
84609 N Yakima River Drive
West Richland, WA 9353
L J
You are directed to make the following changes in this Contract:
This Change Order consists of adding 1050 CY of Unclassified Excavation Inc' Haul, 2000 TN of Select Backfill, 135 LF of
Cement Conc.Traffic Curb and Gutter, drain rock and fabric for Infiltration round Manhole#6, and 10 additional days of
Project Temporary Traffic Control
The Contractor encountered differing site conditions during the construction of the DID#29 improvement project at the Lincoln
Avenue and 35th Avenue intersection. The discovery of shallow ground water depth during excavation for the new pipe was
not anticipated based on the initial design that relied on information from surrounding ground water monitoring wells.
The presence of shallow ground water led to unsuitable soil conditions during construction, causing significant trench
collapsing throughout the project site To mitigate this issue,the unsuitable material was removed from the trench, and select
backfill(crushed rock)was used as backfill
Given these unforeseen circumstances and the additional work required to address them,the City has requested the
preparation of a change order Factors such as increased labor, materials, and equipment needed to address the trench
collapsing was included in this change order This also included temporarily cutting and capping of a water main to avoid any
disasters if it had collapsed into the trench, this was in everyone's interest and was directed by the City.
The contractor has managed to continue with all the additional work necessitated by the change order within the timeframe
required for paving before the asphalt plants close down for the winter Adding ten working days to the contract for the extra
work is necessary given the scope of what needed to be addressed.
The breakdown of the change order items-such as ten days of traffic control, unclassified excavation, select backfill, curb
and gutter replacement, and the installation of infiltration material around manhole#6-demonstrates the various aspects
affected by the unforeseen site conditions and the measures taken to address them This change order is all encompassing
of the change in conditions and includes full compensation for work completed and the additional work anticipated to install
the storm sewer pipe from STA 20+18 to STA 21+05 Any new change of conditions that may arise in order to complete the
project will be reviewed on a separate change request submitted by the contractor.
Not valid until signed by both the Approving Authority and Contractor.
Signature of the Contractor indicated agreement herewith,including any adjustment on the Contract Sum or Contract Time.
The original Contract Sum was $ 243,955 22
Net change by previous Change Orders $ 0 00
The Contract Sum prior to this Change Order $ 243,955 22
The Contract Sum will be: I@ Increased ❑ Decreased ❑ Unchanged by this Change Order $ 116,715 30
The New Contract Sum including this Change Order will be $ 360,670.52
The Contract Time will be: B Increased ❑ Decreased 0 Unchanged by 10 working days
The New Contract Time will be 30 working days
Contractor Approval Recommended • •roval •e•`•mmended
Stephen S.Hazzard,PE,Project Engineer :• hate,• • lire •�
By Andy Peters p� PE
President By— �
��• .- ;�� ��•�°�°xa �� � By
Title pz.,za„<O,��
Date Date /Aff)
Marc Cawley, Wastewater Operations Supenntendent Approved n .
Date 12/6/2023
By
Y 1
Date /2.. 2 3
Date
Based on Original to• 0 Contractor Copies to: 0 Region 0 Construction Administrator
DOT Form
o m 70 0 i EF ❑OSC Accounting 0 City Engineering ^� �,y�
CITY CONTRACT NO:���"ag-1�l (�S�'i' I
RESOLUTION NO: ac-I—O' /
1
0*
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 7.E.
For Meeting of: January 16, 2024
ITEM TITLE: Resolution accepting Change Order No. 1 to City Contract 2023-
161 with Industrial Construction of Washington LLC for Project
SW2661 DID #29 Stormwater Improvements and Spot Repairs
SUBMITTED BY: Scott Schafer, Director of Public Works
* Mike Price Wastewater/Stormwater Manager 509-249-6815
SUMMARY EXPLANATION:
The City of Yakima (City) entered into Contract 2023-161 with Industrial Construction of
Washington LLC for the replacement and realignment of a segment of deteriorated stormwater
drainage pipe in the vicinity of West Lincoln and North 35th Avenues. Prior to bidding the
construction project, the engineering consultant's review of groundwater levels in nearby
monitoring wells indicated that groundwater elevations should not interfere with the construction as
designed. However, the construction contractor encountered shallow groundwater depth during
the excavation that required an increase in the trench footprint, traffic control, fill material, paving
area, and an additional ten (10)working days for safe project completion.
The attached Change Order No. 1 provides for the addition of 10 working days and the required
materials, equipment, and labor at a total cost of $116,715.30.
ITEM BUDGETED: Yes
STRATEGIC PRIORITY: Public Safety
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
RECOMMENDATION:
Adopt Resolution.