HomeMy WebLinkAboutR-2023-093 Resolution amending the Yakima Urban Area Comprehensive Plan Capital Facilities Element RESOLUTION NO. R-2023-093
A RESOLUTION to amend the Yakima Urban Area Comprehensive Plan Capital Facilities
Element to incorporate the Six-year Transportation Improvement Program
(TIP) for the period of 2024 through 2029.
WHEREAS, the City of Yakima annually prepares, reviews and adopts a six-year
Transportation Improvement Program for transportation improvements to arterial streets in the
City of Yakima for the ensuing six-year period, all as contemplated and required by the State
RCW 35.77.010 and applicable Federal law; and
WHEREAS, the City of Yakima desires to amend the Yakima Urban Area
Comprehensive Plan Capital Facilities Element to reflect the adoption of the Six-year TIP, as
contemplated and required by RCW 36.70A.070(6) to ensure compliance with the Growth
Management Act and consistency of the Comprehensive Plan and the Six-year TIP; and,
WHEREAS, this amendment is limited to incorporation of the projects listed in the Six-
Year Transportation Improvement Plan for the period of 2024 to 2029 to the Capital Facilities
Element of the Yakima Urban Area Comprehensive Plan, which is required under RCW
36.70A.130(2B) and RCW 35.77.010; and,
WHEREAS, a public hearing was held by the Yakima City Council on the Six-year TIP
on June 20, 2023 with the proper public notice as required by RCW 35.77.010; and
WHEREAS, the City Council of the City of Yakima, after reviewing the information and
holding the public hearing, finds that amending the Yakima Area Comprehensive Plan Capital
Facilities Element is in the best interest of the City and its residents; now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
The adopted Six-year Transportation Improvement Program for the period of 2024
through 2029 for the City of Yakima shall be incorporated as an amendment to the Capital
Facilities Element of the Yakima Urban Area Comprehensive Plan.
ADOPTED BY THE CITY COUNCIL this 20th day of June, 2023.
ATTEST: �PK,nnq```����11 Janice Deccio, Mayor
* i
Rosalinda Ibarra, City Cler'�� ��} --to"
i 1 �oz i
1
s F` ,1„11„4\
4..
igikiiiiii),....
\L):.... )
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 9.
For Meeting of: June 20, 2023
ITEM TITLE: Public hearing to consider: A) Resolution adopting the Six-Year
Transportation I mprovement Program for the period of 2024
through 2029, and to amend the Transportation Systems Plan
2040; and B) Resolution amending the Yakima Urban Area
Comprehensive Plan Capital Facilities Element
SUBMITTED BY: Scott Schafer, Public Works Director
* Bill Preston, PE, City Engineer(509) 575-6754
SUMMARY EXPLANATION:
A) Each year the City of Yakima (City) is required by state statute to update its Six-year
Transportation Improvement Program (TIP) for submittal to the Washington State Department of
Transportation. This plan must include all transportation projects for which state gas tax revenue
or federal revenue will be used.
The current plan for 2024 —2029 contains a list of two(2) projects that have not previously been
on our six year TI P. The two projects include:
1. 40th Ave & Fruitvale Blvd Roundabout
2. Prasch Avenue Sidewalk Improvements
Attached is the complete 2024 — 2029 Six-Year TIP, which describes all projects currently on the
list. The City will continue to seek funding for projects that do not currently have secured funding.
City Council and the public are welcome to add other arterial system projects to the TIP. The
Six-Year TI P project listing will be finalized at this hearing and sent to the Yakima Valley
Conference of Governments (YVCOG) after approval.
In order to utilize federal funds, such as those administered by the Federal Highway
Administration (FHWA) and the Federal Transit Authority (FTA), projects must be included in the
Statewide Transportation Improvement Program (STI P). The STI P is a prioritized program of
transportation projects, compiled from local and regional plans, along with the Washington
Transportation System Plan (WTP), which provides a backbone for developing projects for the
inter-modal transportation network in the State of Washington.
The STI P contains federally funded projects plus state and local projects that are regionally
significant. These projects have been identified through the planning process as the highest
2
priority for the available funding to the state's Transportation Program. Planning activities of state
and local governments are essential parts of integrated regional planning processes. Long range
transportation planning is a part of the comprehensive land use planning carried out by local
governments. Public participation is an integral part of the planning process at all levels. Local
agencies are required to develop and adopt a Six-year Transportation Program; holding at least
one public hearing during its development.
B) The City is required to amend the Yakima Urban Area Comprehensive Plan Capital Facilities
Element by incorporating the adopted Six-Year TI P for 2024 to 2029. This will ensure that we
are in compliance with the Growth Management Act and that we are consistent with the
Comprehensive Plan as required. The amendment is limited to incorporating only those projects
that are adopted in the Six-Year TIP and is not subject to the "once a year" change required under
the laws of the Growth Management Act.
The Public Hearing notice has been provided to all Yakima-area media, including to Decides',
KDNA Radio, El Sol de Yakima, Hispanavision, Bustos Media, and El Mundo.
ITEM BUDGETED: NA
STRATEGIC PRIORITY: Public Trust and Accountability
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
RECOMMENDATION:
Adopt Resolutions
ATTACHMENTS:
Description Upload Date Type
❑ Resolution a 5/16/2023 Resolution
❑ Resolution b 5/16/2023 Resolution
D 11P Update 5/18/2023 Backup Material
alk
-/a WashiDeparngto
to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakirra
Courty: Yakirra
MPO/RTPO: Yb1CDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x a `m = A
5 C. Project Tille n o G, w k u 3 z
a c D. Road Name cc Number m a a 5 7
d c E.Begin &End Termiri M 1 m o M a
H d M F. Project Descripticn G.Structure ID a a a p >• a
03 1 YAK92 0807122 08.07/22 R-2022.089 04 COOPS 0.750 CE Yes
TW
With 1st Street ReVtalization,Phase3
Math 1st Street
tdL K Boulevard to%I'Street
Ficonstruct and widen roadway,bike lanes.curb and gutter.sidewalks,curb ramps.
illumination.and signals.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
S CN 2023 NHFP 2090 p00 0 0 2.090 p00
S CN 2023 NHPP 2.910000 0 0 2.910.000
S CN 2023 0 TIB 1,500 p00 0 1,500 p00
S CN 2023 0 0 3,411900 3.411.900
P CN 2023 NHPP 3.473000 0 0 3.473000
Totals 8,473 A00 1.500 000 3,411.900 13.384.900
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
CN 7,000000 8,384900 0 0 0
Tdals 7.000 000 6,384500 0 0 0
Page 1
alk
-/a WashiDeparngto
to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: YVCDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x a `m = A
5 C. Project Title x. o G, m k u 3 z
3 D. Road Name K Number m a a 5 7 °' iO
a . E.Begin &End Termini M 1 m oz 5� a 5�
tvn w F. Project Descripticn G.Structure ID a a R. p M m M a
04 2 YAK11 0807122 06.07722 R-2022.089 01 0 P S T W 0.280 EA No
Bravo Company Boulevard.Phase 1
Bravo Company Blvd
Railroad Tracks to Tr Street
Construct four-lane roadwaysection with median,bike lanes and roundabouts.install
curb,gutter,sidewalk,sheet lighting and storm drainage system,along with water
and sewersystems.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
S CN 2023 0 0 8.000000 0000 000
Totals 0 0 6000,000 6,000000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
CN 3000 000 3.000 000 0 0 0
Tdals 3,000000 3,000000 0 0 0
Page 2
�_ Washington State Six Year Transportation Improvement Program
-/' Department of Transportation
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: Yb1CDG Y hside N Outside
m
3 c
a
a
3. A. PIN/Project No. B.STIP 10 x a ` a
ti k C. Project Tille x m G m k d 3 z
cO. Road Name a Number = a a o a °' iO
. E.Begin &End Termini M ' m i 5-1 a 5�
F. Project Description G.Structure ID a a 2 p M m M a
DD 3 11485(024) YAK 80 06.7/22 06.7/22 R-2022-069 28 1.000 CE Yes
Cowiche Canyon Trail-Phase 1
Cowiche Canyon Trail
Powerhouse Road to Cow iche Canyon Lane
Construct a pathway,including pedesbian bridge over Cowiche Creek
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
S CN 2023 0 CWA 2,316,700 0 2,316,700
Totals 0 2,316,700 ft 2,316,700
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
CN 600000 1,716700 0 0 0
Tdals 600000 1,716700 0 0 0
Page S
alk
-/a UWashing opartme to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: YVCDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x a `m = A
5 C. Project Tille n o G, m k u 3 z
a c D. Road Name cc Number m a a 5 7 °' iO
a . E.Begin &End Termini M 1 m oz 5� a 5�
tvn d F. Project Description G.Structure ID a a R. p M >• M a
14 4 /9939(028) YAK98 0807122 08.07/22 R-2022.089 21 0 P S T W 0.050 CE Yes
S.72nd Atenue and W.Washington Pomnue Improtements
S.72nd Atenue
S.72nd Atenue to W.Washington Ale.
Improve intersection by constructing a roundabout.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Furds Total Finds
S CN 2023 0 OTHER 800000 0 800.000
Totals 0 800000 0 800.000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
CN 800 A00 0 0 0 0
Tdals 800A00 0 0 0 0
Page 4
alk
-/a UWashing opartme to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: Yb1CDG Y hside N Outside
m
3 c
a
m A. PIN/Project No. B.STIP ID x a ` = A
5 C. Project Tille n W. c. e k u 3 z
a c O. Road Name cc Number m a a 5 7
d . E.Begin &End Termini M 1 m oz 5� a 5�
H d M F. Project Descripticn G.Structure 10 a a R. p M >• M a
03 5 /000S(473) YAK44 0807/22 08.07122 R-2022.089 21 0 P S T W 0.200 CE Yes
34th Avenue&Fruitvale Boulevard,and 341h Po.enue and River Road Roundabouts
34th Avenue
Rver Road to Fruilvale Boulevard
Improve the intersedions of River Road&Fruilvale Boulevard,and N.34th Avenue
and River Road by installing roundabouts.
Fundng
Status PIese Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
S CM 2023 HSIP 788,308 0 87,590 875,898
S CM 2023 0 OTHER 1,000 A00 0 1,000A00
P CM 2023 NHPP 1,228 p00 0 0 1,228 A00
Totals 2,016$08 1,000 900 87,590 3,103$98
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
CN 300 900 2,803$98 0 0 0
Tdals 300900 2,803$98 0 0 0
Page 5
alk
-/a UWashing opartme to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakirra
Courty: Yakirra
MPO/RTPO: Yb1CDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x a `m = A
5 C. Project Tille n o G, m k u 3 z
2 D. Road Name cc Number m a a 5 7 °' iO
d m E.Begin &End Termini M 1 m oz 5� a 5�
H d F. Project Description G.Structure ID a a R. p M >• M a
19 6 YAK88 0607122 06.07/22 R-2022.089 28 C 0 P T 0.300 CE No
Robertson Elementary School Safety Improvements
various streets
various locations to various locations
This project will make various pedestrian safety improvements in the vicinityof
Robertson Elementary School,pith as new sidewalk and constructing ADAramps.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fur4 Code Federal Funds State Find Code State Finds Local Funds Total Finds
S CN 2023 0 SRTS 410,560 0 440,560
Totals 0 440,580 0 440,560
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
CN 440560 0 0 0 0
Toals 440560 0 0 0 0
Page 6
alk
-/a WashiDeparngto
to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: Yb1CDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x a `m = A
5 C. Project Tille n o G, w k u 3 z
a c D. Road Name cc Number m a a 5 7
d . E.Begin &End Termini M 1 m oz 5� a 5�
H d M F. Project Descripticn G.Structure ID a a R. p M >• M a
03 7 YAK115 12.08/22 12.08/22 R-2022-089 04 0.100 CE No
2023 City Safety-Systemic Pedestrian Safety Improvements,Signal Upgrades;
Curb Exensions at 5th Ale.and'D'St.US
N.51h Avenue
Lincoln Ave to Cherry Ave
Upgrade signal controllers at 10 intersecionsto allow for leading pedestrian
intenels. hstall curb extensions Mille intersection of 5th Avenue and'D'St.to
improve pedestrian safety.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
S PE 2023 HSIP 45,000 0 0 45,000
S CN 2023 HSIP 272,000 0 0 272,000
Totals 317,000 0 0 317,000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &Sth
PE 45000 0 0 0 0
CN 272 A00 0 0 0 0
Toals 317000 0 0 0 0
Page 7
alk
-/a UWashing opartme to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: Yb1CDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x a `m = A
5 C. Project Title n o G, m k u 3 z
a c O. Road Name cc Number ro a a 5 7
d . E.Begin &End Termiri M 1 m oz 5-1 a 5�
H d F. Project Description G.Structure 10 a a a p M >• M a
17 8 YAK70 0607122 06.07/22 R-2022.089 10 0.050 CE No
Box Culvert Installations
S.80th Avenue and Wide Hollow Road
Wile Hollow Road to 801h Avenue
hstall box culvert(s)adjacent to the 80th Avenue Bridge and Wde Hollow Bridgeto
reduce feeding issues. Joint project with Yakima County.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
P CN 2023 0 OTHER 176,000 0 176.000
Totals 0 176,000 0 176.000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
CN 176.000 0 0 0 0
Tdals 176000 0 0 0 0
Page 8
alk
-/a UWashing opartme to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: Yb1CDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x a `m = A
5 C. Project Title n o G, m k u 3 z
a c D. Road Name K Number m a a 5 7
d . E.Begin &End Termini M 1 m o � a 5�
H d M F. Project Description G.Structure ID a a R. p M m M a
16 9 YAK10 0607122 08.07/22 R-2022.089 01 0 P S T W 0.550 EA Yes
E."H"Street Edension, Phase 1
E."H"Street
1st Streetto 7th Street
Construct new roadway inlcuding water,sewer,cult.gutter.sidewalk,sheet lighting
and storm drainage system.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
P PE 2024 BUILD 566.500 0 0 566.500
P CN 2025 BUILD 5.438,400 TIB 1,320 A00 0 6,758,400
Totals 6.004900 1,320 000 0 7.324.900
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
PE 0 566500 0 0 0
CN 0 0 6.758,400 0 0
Tdals 0 566500 6.758 A00 0 0
Page 9
alk
-/a UWashing opartme to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: YVCDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x a `m = A
5 C. Project Title x. o G, a, k u 3 z
3 D. Road Name cc Number m a a 5 7 °' iO
a . E.Begin &End Termini M 1 m oz 5� a 5�
tvn w F. Project Descripticn G.Structure ID a a 2 p M >• M a
04 10 W4.13520 0807122 08.07/22 R-2022.089 01 S W 0.280 EA No
Bravo Company Boulevard.Phase 2
Bravo Comp any Boulevard
"H"Streetto Railroad Tracks
Construct four-lane roadwaysection with median,bike lanes and roundabouts.install
curb,gutter,sidewalk,street lighting and storm drainage system,along with water
and sewersystems.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
P CN 2025 0 OTHER 8.500 p00 0 8500 p00
Totals 0 6,500 A00 0 6500 A00
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
CN 0 0 8500 A00 0 0
Tdals 0 0 6500A00 0 0
Page 10
alk
-/a UWashing opartme to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakirra
Courty: Yakirra
MPO/RTPO: YVCDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x a `m = A
5 C. Project Tille n o G, a k u 3 z
a c D. Road Name cc Number a a a 5 7
d . E.Begin &End Termini M 1 m oz 5� a 5�
H d M F. Project Description G.Structure ID a a R. p M >• M a
07 11 YAK103 0607122 08.07722 R-2022.089 28 co P T 0.500 CE No
Nob Hill Bementary School Safety tnprovements
various streets
various locations to various locations
This project will make various pedestrian safety improvements in tie vicinityof Nob
HII Bemenbry School,such as new sidewalk and constructing ADAramps.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Furds State Find Code State Finds Local Funds Total Finds
P PE 2028 0 SRTS 101,200 0 101,200
P CN 2027 0 SRTS 642,400 0 642.400
Totals 0 743,600 0 743.600
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
PE 0 0 0 101200 0
CN 0 0 0 0 642,400
Tdals 0 0 0 101200 642A00
Page 11
alk
-/a UWashing opartme to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakirra
Courty: Yakirra
MPO/RTPO: Yb1CDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x Cr. `m = A
5 C. Project Tille n o G, m k u 3 z
a c D. Road Name cc Number ro a a 5 7
d c E.Begin &End Termiri M 1 m o M a
H d M F. Project Descripticn G.Structure ID a a R. p >• a
07 12 Vt/A-13522 0807122 08.07/22 R-2022.089 28 CGPST 0.530 CE No
W
Browne Po,enue Sidewalk
Browne Posenue
7th Po,enueto 18th Poenue
Replace damaged sidewalk panels.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fur4 Code Federal Funds State Find Code State Finds Local Funds Total Finds
P ALL 2025 0 0 378,170 378,170
Totals 0 0 378,170 378,170
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &8th
ALL 0 0 378,170 0 0
Toals 0 0 378,170 0 0
Page 12
alk
-/a UWashing opartme to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakirra
Courty: Yakirra
MPO/RTPO: YVCDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x a `m = A
5 C. Project Tine n o G, a k u 3 z
a c D. Road Name cc Number ro a a 5 7
d c E.Begin &End Termiri M 1 m o M a
H d M F. Project Descripticn G.Structure ID a a R. p >• a
07 13 Vt/A-13523 08.07122 08.07/22 R-2022.089 28 CGPST 0.200 CE No
W
Pacifc Pomnue Sidewalk
Pacifc Pomnue
Fair Entrance to.mil Property
Construct sidewalk on south side of roadway.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
S ALL 2023 0 TIB 250.000 0 250.000
Totals 0 250.000 0 250.000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &Sth
ALL 250 p00 0 0 0 0
Toals 250A00 0 0 0 0
Page 13
alk
-/a Washi gte to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: Yb1CDG Y hside N Outside
m
3 c
I
m k A. PIN/Project No. B.STIP ID x a ` A
5 C. Project Tille n G, m k °' 3 z
a c D. Road Name cc Number w a a 5 7
d 3 . E.Begin &End Termiri M ' m i 5-1 a 5�
H d M F. Project Descripticn G.Structure ID a a R. p M i M a
03 14 /4566(007) 2143 06.07/22 06.07/22 R-2022.089 03 C 0 P T W CE Yes
E Nob Hill Blvd&Fair Pole VS Improvements
Nob Hill Blvd
E Nob Hill Blvd to Fair Poe
W den Nob Hill Boulevard through the intersection,construct left.tum lane,cult,
gutter,sidewalk,street lighting and drainage. Upgrade signal.including mast ann
structures.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
S CN 2024 STP(US) 1,175,110 0 189,831 1,364941
Totals 1,175,110 0 189,831 1,364,941
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
CN 0 1,364,941 0 0 0
Toals 0 1,364941 0 0 0
Page 14
alk
-/a UWashing opartme to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: YVCDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x a `m = A
5 C. Project Tille n W. G, m k u 3 z
a c D. Road Name a Number ro a a 5 7 °' iO
d c E.Begin &End Termiri M 1 m o M a
d F. Project Descripticn G.Structure ID a a R. p m >• a
04 15 YAK104 0807122 08.07/22 R-2022.089 05 COOPS 1.530 CE No
TW
Tieton Drive Resurfacing
Tieton Drive
S.48th Po.e.to S.72nd Ate.
Grind and overlay,and AOAcurb ramp replacement.
Fundng
Status Phase Phase Start Year(YYYY) Federal Furd Code Federal Funds State Find Code State Finds Local Funds Total Finds
P PE 2025 0 TIB 97,000 24,280 121,280
P CN 2025 0 TIB 1,108$00 277,200 1,388 000
Totals 0 1,205$00 301,460 1,507260
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
PE 0 0 121280 0 0
CN 0 0 1,388 A00 0 0
Tdals 0 0 1,507260 0 0
Page 15
alk
-/a UWashing opartme to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: Yb1CDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x a `m = A
5 C. Project Tille n W. G, m k u 3 z
a c D. Road Name K Number m a n 5 g
d . E.Begin &End Termini M 1 m o 5-1 a 5�
H 0, el F. Project Descripticn G.Structure ID 43 a R. p M m M .
17 16 YAK93 0607122 05.07/22 R-2022.089 38 C 0 T 0.600 CE Yes
Powerhouse Road Multi-Use Path
Powerhouse Road
Mobile Home Parkto Cow iche Canyon Rd.
Construct 10-bot wide mild-use path tom40th Pomnue/US 12 intersection to
Powerhouse Road.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
P PE 2028 0 Ped/Bike Program 44,500 5,500 50,000
P CN 2028 0 Ped/Bike Program 341,835 42,250 384,085
Totals 0 386,335 47,750 434,085
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
PE 0 0 0 50A00 0
CN 0 0 0 0 384,085
Tdals 0 0 0 50000 384085
Page 16
alk
-/a UWashing opartme to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: YVCDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x a `m = A
5 C. Project Tille n W. G, m k u 3 z
a c D. Road Name cc Number ro a a 5 7
d c E.Begin &End Termiri M 1 m o M a
H d M F. Project Descripticn G.Structure ID a a R. p >• a
07 17 YAK 107 0807122 08.07/22 R-2022.089 28 COPST 0.450 CE No
W
88th Avenue Sidewalk
88th Avenue
Tieton Drive to Summhview Avenue
Construct sidewalk on east sde of roadway.
Fundng
Status Phase Phase Start Year(YYYY) Federal Furd Code Federal Funds State Find Code State Finds Local Funds Total Finds
P PE 2023 0 SRTS 89.090 0 89.090
P CN 2024 0 SRTS 588.150 0 588.150
Totals 0 657.240 0 657.240
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
PE 89A90 0 0 0 0
CN 0 588.150 0 0 0
Tdals 89 090 568.150 0 0 0
Page 17
alk
-/a WashiDeparngto
to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: Yb1CDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x a `m = A
5 C. Project Tille n o G, m k u 3 z
a c D. Road Name cc Number ro a a 5 7
d . E.Begin &End Termiri M 1 m oz 5� a 5�
H d M F. Project Description G.Structure ID a a R. p M >• M a
16 18 YAK102 0607122 06,07722 R-2022.089 21 P T 0.030 CE No
N 1st St&R St Signal
N. 1st St.
R Street to R Street
hstall traffic signal at the intersection.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
P PE 2027 STP 66,990 0 10,395 77,385
P CN 2028 STP 401,709 0 62,722 484,431
Totals 468.699 0 73,117 541,816
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
PE 0 0 0 0 77,385
CN 0 0 0 0 484,431
Tdals 0 0 0 0 541 2316
Page 18
alk
-/a UWashing opartme to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: Yb1CDG Y hside N Outside
m
3 c
a
m A. PIN/Project No. B.STIP ID x a ` g A
5 C. Project Tille n c. m k u 3 z
c O. Road Name K Number ro n a 5 7 d iO
a 3 . E.Begin &End Termiri M ' m i -i a 5�
tvn d F. Project Description G.Structure 10 a a R. p M m M a
14 19 YAK57 0807122 08.07/22 R-2022.089 11 C P T 0.010 CE No
18th Street Underpass
Yakima Aienue
Yakima Aienue to 18th Street
Replacethe bridge on E.Yakima Avenue that crosses over 18th Street.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
P PE 2028 BR 311,970 0 77,970 389.940
P CN 2027 BR 2.974.380 0 743,590 3.717.950
Totals 3,286.330 0 821,560 4,107$90
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
PE 0 0 0 354,490 0
CN 0 0 0 0 3,379950
Tdals 0 0 0 354490 3,379 S50
Page 19
alk
-/a UWashing opartme to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: YVCDG Y hside N Outside
m
3 c
a
m A. PIN/Project No. B.STIP ID x a cD g A
5 C. Project Title n a.. e k u 3 z
a c D. Road Name cc Number ro a a 5 7 °' iO
d 3 c E.Begin &End Termini 0.1 .1.1.
m i M a
w F. Project Descripticn G.Structure ID a a R. p m >• a
04 20 YAK 108 0807122 08.07/22 R-2022.089 03 CGPST 0.030 CE No
W
S.1st Street and E.Washington Avenue Intersedion Improvements
1st Street
Washington Aenue to Washington Avenue
Realign intersection,widen E.Washington Ave.for additional lane,replace curb,
gutter,sidewalk.and construct new signal.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
P ALL 2027 0 0 2,705,725 2,705,725
Totals 0 0 2,705,725 2,705,725
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
ALL 0 0 0 0 2,705,725
Toals 0 0 0 0 2,705,725
Page 20
alk
-/a WashiDeparngto
to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: Yb1CDG Y hside N Outside
m
3 c
a
m A. PIN/Project No. B.STIP ID x a 'cD g A 3
5 C. Project Tille n G, m k °' 3 z
a c D. Road Name cc Number ro a a 5 g °' iO
d 3 c E.Begin &End Termiri M .1.1.
m i a
tvn d F. Project Descripticn G.Structure ID a a a p m >• a
14 21 YAK14 0807122 08.07/22 R-2022.089 21 COPST CE Yes
W
Washington laenue&Longfiber Road Intersection htprovements
Washington Aaenue
Washington Po.enue to Longiber Road
hiprove the tftfashington Atenue/Longfiber Road intersection byconstruction of
channelizanon.a signal,or a roundabout.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
S PE 2023 0 0 100,000 100,000
P RW 2024 0 0 150,000 150,000
P CN 2025 0 0 1000,000 1000 000
Totals 0 0 1250,000 1,250000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
PE 100000 0 0 0 0
RW 0 150.000 0 0 0
CN 0 0 1,000 p00 0 0
Tdals 100000 150,000 1,000000 0 0
Page 21
alk
-/a UWashing opartme to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: YVCDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x a `m = A
5 C. Project Tille n o G, w k u 3 z
a c D. Road Name cc Number ro a a 5 7 °' iO
d c E.Begin &End Termiri M 1 m oz a
w F. Project Descripticn G.Structure ID a a R. p m >• a
14 22 YAK84 0807122 08.07/22 R-2022.089 04 COOPS 0.400 CE Yes
TW
18th Avenue and Tieton Drive htersecfion Improvements
18th Avenue
18th Avenue to Tieton Dive
Reconstruct and widen 16th Avenue and Tieton Drive by adding let-ttm lanes for all
movements atthe intersection. Upgradethe traffic signal.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
P PE 2028 STP(UL) 358512 0 53592 412,104
P RW 2028 STP(UL) 1.498 507 0 233.893 1,732500
P CN 2028 STP(UL) 1,840583 0 252,483 1,893,188
Totals 3497$02 0 539,968 4,037,770
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
PE 0 0 0 0 412.104
RW 0 0 0 0 1,732500
CN 0 0 0 0 1,893,188
Toals 0 0 0 0 4,037,770
Page 22
�_ Washington State Six Year Transportation Improvement Program
-/' Department of Transportation
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: Yb1CDG Y hside N Outside
m
3 c
a
a
3. A. PIN/Project No. B.STIP 10 x a c g a
ti k C. Project Tille x m G m k d 3 z
cO. Road Name cc Number = sa a o a "' iO
i c E.Begin &End Termiri Ma y q i < a
F. Project Description G.Structure ID a a 2 P w il a
04 23 YAK 109 08.07122 06A7Q2 R-2022-069 28 CGPST 0.500 CE Yes
W
FairAtenue Sidewalk
FairAtenue
Pacifc Pomnue to Nob Hill Boulevard
Construct sidewalk on west side of roadway.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fird Code Federal Ford: State Enid Code State Ends Local Funds Total Finds
P ALL 2024 0 0 500 560 500 560
Totals ii II 500580 500580
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
ALL 0 500560 0 0 0
Totals 0 500 560 ii ii 0
Page 23
�_ Washington State Six Year Transportation Improvement Program
-/' Department of Transportation
From 2024 to 2029
Agency: Yakirra
Courty: Yakirra
MPO/RTPO: Yb1CDG Y hside N Outside
m
3 c
a
a
3. A. PIN/Project No. B.STIP 10 x a 'c0 a
ti k C. Project Tille x m G w k d 3 z
cO. Road Name cc Number = sa a o a "' iO
i c E.Begin &End Termiri Ma y q i a
F. Project Description G.Structure ID a a 2 p m 7 i a
04 24 YAK 110 06.7/22 06.07t22 R-2022-069 28 CGPST 1.500 CE Yes
W
Nob Hill Boulevard Sidewalk
Nob Hill Boulevard
12th St en 14th Street
Construct sidewalk on south side of roadway.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fird Code Federal Ford: State Prid Code State Finds Local Funds Total Frds
P ALL 2028 0 0 175.868 175.i:B:
Totals 0 0 175.868 175.%:E.%:
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
ALL 0 0 0 0 175$68
Totals 0 0 .. .. 175$68
Page 24
�_ Washington State Six Year Transportation Improvement Program
-/' Department of Transportation
From 2024 to 2029
Agency: Yakirra
Courty: Yakirra
MPO/RTPO: YVCDG Y hside N Outside
m
3 c
a
a
3. A. PIN/Project No. B.STIP 10 x a `m a
ti k C. Project Tille x m G m k 0 3 z
cO. Road Name cc Number = sa n o 7 "' iO
i c E.Begin &End Termiri Ma y q i a
F. Project Descripticn G.Structure ID a a 2 p w 7 il a
04 75I YAK 111 08.7/22 08.07t22 R-2022-089 04 CGPST 1.500 CE No
W
6th Avenue Roadway Irrproierrents
81h Abmnue
Walnut Steetto River Road
Reconstruct roadwayincluding trolleyprovisions.
Fundng
Status Ph se Prase Start Year(YYYY) Federal Fus Code Federal Eurd= State Find Code State Ftrids Local Fuss Total Finds
S PE 2023 0 0 300.000 300,000
P PE 2023 0 0 700.000 700,000
P UN 2025 0 0 8.58080 8.584$80
Totals .. .. 7564.880 7.564$80
E.perditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
PE 300 A00 ?SDpDo 0 0 0
PLL 0 0 8.584$80 0 0
L3als 300900 7oo,o0 6,564$80 0 0
Page 25
alk
-/a UWashing opartme to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: YVCDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x a `m = A
5 C. Project Tille x o G, m k u 3 z
a c D. Road Name cc Number ro asa 5 7
d c E.Begin &End Termini M x q z —1 a
H d M F. Project Descripticn G.Structure ID a a R. p >• a
05 28 YAK 112 08.07/22 08.07/22 R-2022.089 04 CGPST 0.030 CE No
W
Powerhouse Road and Englewood Avenue Intersedion Improvements
Powerhouse Road
Englewood Aienue to Englewood Avenue
hstall traffic signal at the intersection.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
P ALL 2028 0 0 1.014.431 1,014,431
Totals 0 0 1114.431 1.014431
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &Sth
ALL 0 0 0 0 1.014.431
Toals 0 0 0 0 1.014431
Page 26
alk
-/a WashiDeparngto
to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakirra
Courty: Yakirra
MPO/RTPO: YVCDG Y hside N Outside
m
3 c
I
m 2 A. PIN/Project No. B.STIP ID x Cr.
` A
5 C. Project Tille x m G, m k °' 3 z
a c D. Road Name cc Number ro la
a 5 a °' iO
d 3 c E.Begin &End Termiri M x q i —1 a
d F. Project Descripticn G.Structure ID a a R. p ,. i a
04 27 YAK 113 08.07122 08.07122 R-2022-089 28 COPST 0.010 CE No
W
Mead fhenue Pedestrian Signal
Mead Aaenue
10th Atenue to 10th Po.enue
hstall pedestrian signal atthe east leg of the intersection.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
P ALL 2028 0 0 418,030 418,030
Totals 0 0 418,030 418,030
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &61h
ALL 0 0 0 0 418,030
Tdals 0 0 0 0 41800
Page 27
�_ Washington State Six Year Transportation Improvement Program
-/' Department of Transportation
From 2024 to 2029
Agency: Yakirra
Courty: Yakirra
MPO/RTPO: Yb1COG Y hside N Outside
m
3 c
a
a
3. A. PIN/Project No. B.STIP 10 x a c0 g a
ti k C. Project Tille x m G a k d 3 z
cO. Road Name cc Number = sa a o a "' iO
c E.Begin &End Termiri Ma y q i 'C a
F. Project Descripticn G.Structure ID a a 2 p w a
04 ?x YAK 119 06.7/22 0607/22 R-2022-069 28 CGPST 0.120 CE Yes
W
N. 16th Aienue Sidewalk
N. 16th Awnue
Rver Road to%I'Street
Construct sidewalk on west side of roadway.
Fundng
Status Phase Phase Start Year(YYYY) Federal Ford Code Federal Ford: Mite End Code State Finds Local Funds Total Finds
P ALL 2028 0 0 209.022 209.022
Totals it 0 209.022 209.022
Expenditure Schedule
Phase 1st 2nd ,rd 4th 5th &Sth
ALL 0 0 0 0 209 D22
Tdals 0 0 ii ii 209.022
Page 28
alk
-/a UWashing opartme to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: YVCDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x a `m = A
5 C. Project Tille n o G, m k u 3 z
a c D. Road Name cc Number m a a 5 7
d . E.Begin &End Termini M 1 m oz 5� a 5�
H d F. Project Description G.Structure ID a a a p M >• M a
00 29 Vt/A-143210807122 08.07/22 R-2022.089 28 0.100 No
Ul@st Valley Schools Pedestrian Bridge
S.75th Po,enue
S.75th Po,enue to Wu/Community Park
Construct new pedestrian bridge mertiflAde Hollow creek connecting S.75th Avenue
to WV Park and schools
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
P CN 2023 0 SRTS 2000 A00 0 2.000 p00
Totals 0 2,000000 0 2,000000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
CN 2000 A00 0 0 0 0
Tdals 2000A00 0 0 0 0
Page 29
alk
-/a UWashing opartme to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: Yb1CDG Y hside N Outside
m
3 c
a
m 2 A. PIN/Project No. B.STIP ID x a ` g A
5 C. Project Tille n G, m k °' 3 z
a c D. Road Name cc Number iv a a 5 7
d 3 . E.Begin &End Termini M .1.1.
m i � a 5�
H d M F. Project Descripticn G.Structure ID a a a p M >• M a
00 30 Ir1W-14324 1208122 12.08/22 R-2022.089 21 CE No
2023 City Safety-Systemic Pedestrian and Bicycle Data Collection
to
Collect pedestrian and bicycle counts at citystreet intersectionsto develop Lore
local road nfetyplans.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
S PE 2023 HSIP 280.000 0 0 280.000
Totals 260000 0 0 260000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
PE 280 A00 0 0 0 0
Tctals 260A00 0 0 0 0
Federal Funds State Finds Local Funds Total Finds
Grand Totals for Yakima 577,000 0 1500.000 2077 A00
Page 30
alk
-/a UWashing opartme to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: Yb1CDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x a `m = A
5 C. Project Title x s G, m k u 3 z
a c D. Road Name a Number m a a 5 7
d . E.Begin &End Termini M ' m i � a 5�
H w F. Project Descripticn G.Structure ID a a a p M >• M a
05 31 Vt/A.14955 1208/22 R-2022-NNN 04 0.750 CE Yes
Coolidge Road from 72nd P e to 89h Ate- Roadway Improvements
Coolidge Road
72nd Aenue to 89h Avenue
Rehabilitate Busting pavement and update roadwayto current citystandards.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Finds
P PE 2024 0 0 200.000 200.000
P RW 2024 0 0 200.000 200.000
P CN 2025 0 0 1.100.000 1.100 A00
Totals 0 0 1.500.000 1.500000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &6th
PE 0 200 p00 0 0 0
RW 0 200 p00 0 0 0
CN 0 0 1.100900 0 0
Tdals 0 400000 1,100A00 0 0
Page 31
alk
-/a WashiDeparngto
to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: YVCDG Y hside N Outside
m
3 c
'o. 0 c J
' A. PIN/Project No. B.STIP ID 3 0 3 a m
ii 'C C. Project Tille x m S. m ,k d a z
a D. Road Name cc Number m s- i 3 y u y c.
—0 o- E.Begin &End Termiri M $
H w M F. Project Descripticn G.Structure ID n a 7 & ri n
00 WA15080 04.04/23 04/18/23 R-2023.N1N 05 co P T 0.850 CE No
2024 Nonhside Aley Paling
Various Aleys
N nth Po.enue to Wilco Street
The city of Yakima will paw approximately4500 LF of noMhouth alleys between N
nth Avenue and N 3rd Avenue,tom W D'Streetto IMllow Street.
Fundng
Status Phase Phase Start Year(YYYY) Federal Fund Code Federal Funds State Find Code State Finds Local Funds Total Funds
S PE 2023 CMAQ 50.000 0 0 50.000
S CN 2024 CMAQ 450.000 0 0 450.000
Totals 500.000 0 0 500.000
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &Sth
PE 50A00 0 0 0 0
CN 0 450A00 0 0 0
Totals 50A00 450A00 0 0 0
Federal Funds State Finds Local Funds Total Funds
Grand Totals fcr Yakima 500.000 0 0 500.000
Page 32
alk
-/a WashiDeparngto
to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: YVCDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x Cr. `m = A
5 C. Project Tine x o G, w k u 3 z
a c D. Road Name cc Number m a n 5 g
d„ . E.Begin &End Termiri m i � a 5�
H d M F. Project Descripticn G.Structure ID a a a p M >• M a
03 WA15117 15 P S W No
40th Ate and Fruitvale Blvd Roundabout
to
Roundabout, Rectangular Rapid Flashing Beacons(RRFB),New Marked Crosswalk,
Green Patement/BicwIe Intersection Crossing Markings,ADA Curb Ramps,Pudible
Pedestrian Signal,Bicyde Wayfnding Signs/Markings,Shared•use Path/Trail
Error Subreport could not be shown.
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th &Bth
0 0 0 0 0
Tctals 0 0 0 0 0
Page 33
alk
-/a WashiDeparngto
to Tre ansportation Six Year Transportation Improvement Program
From 2024 to 2029
Agency: Yakima
Courty: Yakima
MPO/RTPO: Yb1CDG Y hside N Outside
m
3 c
I
m A. PIN/Project No. B.STIP ID x a `m = A
5 C. Project Tine x s G, w k u 3 z
2 D. Road Name cc Number w a n 5 a °' iO
d . E.Begin &End Termini m 3z � a 5�
H w M F. Project Descripticn G.Structure ID a a a p M >• M a
07 WA15118 28 P T No
Prasch Aienue Sidewalk Improvements
to
Construct sidewalks against existing curbing on Prasch Avenue from S.16th/benue
to S.20111 Avenue
Error Subreport could not be shown.
Expenditure Schedule
Phase 1st 2nd 3rd dth 5th f.0th
0 0 0 0 0
Tctals 0 0 0 0 0
Page 34