HomeMy WebLinkAbout05/05/2009 14 Cowiche Canyon Sanitary Sewer Lines and Pedestrian Bridge Interlocal Agreement with Yakima County • BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. r` 1
For Meeting of May 5, 2009
ITEM TITLE: A resolution authorizing the City Manager to execute an Interlocal Agreement
between the City of Yakima and Yakima County for the design and construction
of sanitary sewer lines and pedestrian bridge in Cowiche Canyon.
SUI- MITTED BY: Doug Mayo, City Engineer
CONTACT PERSON/TELEPHONE: Doug Mayo, City Engineer, (509) 576 -6678
SUMMARY EXPLANATION:
Staff respectfully requests City Council consideration of a resolution authorizing the City
Manager to execute an Interlocal Agreement with Yakima County for the design and
construction of sanitary sewer lines and a pedestrian bridge in Cowiche Canyon. Yakima
County is planning road improvements from Power House Road on the Cowiche Canyon road
for approximately 1,100 feet. Installing the sewer with the County project would eliminate the
need and added cost to restore the road if the sewer were installed after the County's project
411) was completed. The pedestrian bridge is an integral piece of the William O. Douglas Trail
(See attached Agreement).
Resolution X Ordinance Contract X Other (Specify
Contract Mail to (name and address):
Funding Source: Sewer. Fund 476 Sewer Construction project #2276
Bridge: Fund 142 Arterial Street Capital project #2167
APPROVED FOR SUBMITTAL:
CITY MANAGER
STAFF RECOM n,'EN D ATION: Staff respectfully requests the City Council adopt the enclosed
resolution authorizing the City Manager to execute an Interlocal Agreement between the City
of Yakima and Yakima County for the design and construction of 1,100 feet of sanitary sewer
lines and a pedestrian bridge in Cowiche Canyon.
BOARD /COMMISSION RECOMMENDATION:
COUNCIL ACTION:
• •
i
RESOLUTION NO. R -2008-
A RESOLUTION authorizing the City Manager to execute an Interlocal Agreement between
the City of Yakima and Yakima County for the design and construction of
sanitary sewer lines and a pedestrian bridge in Cowiche Canyon.
WHEREAS, the County intends to construct a road improvement project known as the
C3051, Cowiche Canyon Road Improvements, From Powerhouse Road South 1,100 feet
(hereinafter the "Road Project"); and
WHEREAS, the construction of sanitary sewer and side sewer lines (hereinafter the
"Sewer & Pedestrian Bridge Project") within the limits of the Road Project are consistent with
the long range plans of the City; and
WHEREAS, the William O. Douglas Trail project requires the construction of a
pedestrian bridge immediately adjacent to the County road project; and
WHEREAS, the County and the City agree that combining the Sewer & Pedestrian
Bridge Project with the Road Project will serve to reduce overall costs, minimize disruption to
• the natural environment and impacts to transportation systems users; and
WHEREAS, the City has determined that it is in its best interest to provide funding for
• the Sewer & Pedestrian Bridge Project and to allow Yakima County to oversee the
construction; and
WHEREAS, the Yakima County Engineer has determined that it is in the best interest of
the County that the Yakima County Public Works Department contract for the design and
construction of the Sewer & Pedestrian Bridge Project within the same construction contract as
the Road Project; now, therefore: .
E IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
The City Manager is hereby authorized to execute an Interlocal Agreement with Yakima
County for the design and construction of 1,100 feet of sanitary sewer and a pedestrian bridge
in Cowiche Canyon as well as funding for the improvements.
ADOPTED :,Y THE CITY COUNCIL this 5th day of May, 2009.
David Edler, Mayor
ATTEST:
City Clerk
III
•
INTERLOCAL AGREEMENT BETWEEN THE CITY OF YAKIMA AND YAKIMA COUNTY
FOR SANITARY SEWER IMPROVEMENTS AND CONSTRUCTION OF A PEDESTRIAN
BRIDGE AND FUNDING
THIS INTERLOCAL AGREEMENT is entered into between Yakima County, Washington
(hereinafter the "County"), whose address is 128 North 2 Street, Yakima, Washington 98901,
and the City of Yakima (hereinafter the "City "), whose address is 129 North 2 Street, Yakima,
Washington 98901, pursuant to RCW 39.34.
WHEREAS, the County intends to construct a road improvement project known as the
C3051, Cowiche Canyon Road Improvements, From Powerhouse Road South 1,100 feet
(hereinafter the "Road Project"); and,
WHEREAS, the City wants to have sanitary sewer, side sewer lines and a pedestrian
bridge for the William O. Douglas Foot Trail (hereinafter "the Sewer & Pedestrian Bridge
Project ") constructed at certain locations within the limits of the Road Project. The location of the
Sewer & Pedestrian Bridge Project is shown on Exhibit 'A'; and,
WHEREAS, the County and City agree that having the Sewer & Pedestrian Bridge
Project constructed in combination with the Road Project is mutually beneficial; and,
WHEREAS, the City has determined that it is in its best interest to provide funding for
the Sewer & Pedestrian Bridge Project and to allow Yakima County to oversee the design and
construction; and,
WHEREAS, the City of Yakima Engineer has determined that it is in the best interest of
the City to have Yakima County Public Services design the Sewer & Pedestrian Bridge Project
for inclusion in the contract; and,
WHEREAS, the Yakima County Engineer and City of Yakima Engineer have determined
that it is in the best interest of the County and the City to have Yakima County Public Services
Department contract for the construction of the Sewer & Pedestrian Bridge Project within the
same construction contract as the Road Project
NOW, THEREFORE, IT IS HEREBY AGREED as follows:
1. Purpose. The purpose of this Agreement is to define the scope of services contracted
between the City and the County and enumerated other related provisions that contribute to the
mutual benefit of the parties to this Agreement.
2. Duration of Agreement. This Agreement shall become effective on the date of signing
by the City and the County and,shall continue until terminated by either party in accordance with
Section 13 of this Agreement.
411
Interlocal Agreement Between City of Yakima and Yakima County Page 1 of 6
Sanitary Sewer Improvements and Pedestrian Bridge Construction
3. Obligations of the Parties.
THE CITY SHALL:
1. Provide funding to the County for design, environmental documentation and
construction management for the Sewer & Pedestrian Bridge project.
2. Review the County's final contract plans and specifications and provide written
approval of the Sewer & Pedestrian Bridge Project plans and specifications to the
County before the advertisement of the project.
3. Review construction bids provided by the County and provide written notice of
approval or disapproval of the Sewer & Pedestrian Bridge Project bids to the
County before the award of a construction contract. Written notice will be
provided to the County no later than five working days following opening of bids.
4. Review and approve all Source of Materials submittals regarding the Sewer &
Pedestrian Bridge Project.
5. Provide all on -site field inspection for the construction of the sanitary sewer
portion of the Sewer & Pedestrian Bridge Project except those services provided
by the County identified in County Section 5 and County Section 6 of this
Agreement The City shall provide 24 -hour prior notice for testing services
identified in County Section 6 of this Agreement. The field inspection will be
consistent with the Washington State Departrnent of Transportation's 2008
Standard Specifications for Road, Bridge, and Municipal Construction and
Washington State Department of Transportation's Construction Manual. The City
shall prepare Daily Inspector Reports consistent with the standard of the industry.
The Daily Inspector Reports shall clearly identify all bid items and quantities to be
paid and list any agreed to change order work or any work paid under the bid
item Minor Changes. The City shall provide copies of the Inspector Daily Reports
to the County at least once a week.
6. Prepare a monthly progress estimate of quantities used on the Sewer &
Pedestrian Bridge Project using the bid item schedule for the construction
contract. The progress estimate shall be provided to the County no later than the
5th day of each month. The progress estimate shall include all work completed
through the last day of the previous month.
7. Upon review and approval by the City of the amounts charged, provide monthly
progress payments to the County for work performed on the Sewer & Pedestrian
Bridge Project by the contractor. Progress payments shall be made to the County
no later than the 20th day of each month. The progress payment shall be based
on the progress estimate provided for in City Section 6 of this agreement.
8. Upon review and approval by the City of the amounts charged, provide a final
payment to the County for all costs reasonably incurred by the County that are
directly related to the Sewer & Pedestrian Bridge Project. These costs shall
include actual sewer construction costs made to the contractor, County
personnel labor costs for time reasonably spent on the Sewer & Pedestrian
Interlocal Agreement Between City of Yakima and Yakima County Page 2 of 6
Sanitary Sewer Improvements and Pedestrian Bridge Construction
•
• Bridge Project work and material testing expenses. Final payment shall be made
to the County no later than 30 days after the City receives the report of final costs
from the County.
9. Upon completion of the Sewer & Pedestrian Bridge Project by the Contractor and
final inspection by the City, the City shall provide the County with written
acceptance of the sewer work prior to paving of the roadway.
THE COUNTY SHALL:
1. Prepare all required environmental documentation and Biological Assessment.
2. Prepare the design, details, specifications and estimate for the Sewer &
Pedestrian Bridge Project and incorporate the Sewer & Pedestrian Bridge Project
design, details and specifications into the County's Road Project. The Sewer &
Pedestrian Bridge Project construction bid items shall be listed under separate
pay schedules within the contract documents.
3. Provide a copy of the final plans and specifications for the construction project to
the City Engineer for his review and approval before the advertisement of the
project.
4. Provide a copy of the bid results to the City Engineer for his review and approval
0 before the award of a construction contract.
5. Provide copies of all Source of Materials submittals for the Sewer & Pedestrian
Bridge Project to the City Engineer for his review and approval before use of the
materials on the project.
6. Provide field inspection and material testing of trench excavation, trench
backfilling and pavement repair and bridge inspection required for the Sewer &
Pedestrian Bridge Project. _
7. Provide construction control surveying for the Sewer & Pedestrian Bridge Project.
8. Make progress payments to the contractor.
9. Provide a monthly statement of progress payments made to the Contractor for
the Sewer Project and a bill requesting reimbursement for those costs.
10. Provide a statement of County personnel labor costs for time spent on the Sewer
& Pedestrian Bridge Project, including material testing costs and a bill requesting
reimbursement for those costs.
11. Provide a report of final costs for the Sewer & Pedestrian Bridge Project to the
City following completion of the construction contract. The report shall include a
breakdown of costs incurred by the County.
0 4. Administration m
Department Manager and This the County ent Public shall Servi be Director administered by the City's Engineering
Interlocal Agreement Between City of Yakima and Yakima County Page 3 of 6
Sanitary Sewer Improvements and Pedestrian Bridge Construction
5. No Third Party Rights. This Agreement is entered into for the sole benefit of the City and
the County. It shall confer no benefits or rights, direct or indirect, on any third parties. No
person or entity other than the City and the County may rely upon or enforce any provision of
this Agreement.
6. Indemnification and Hold Harmless.
a. Each party hereto agrees to be responsible and assume liability in the
performance of this Agreement for its own wrongful and/or negligent acts or omissions, and
those of its officers, agents, or employees to the fullest extent allowed by law.
b. The provisions of this Section shall survive the termination or expiration of this
Agreement.
c. Nothing contained in this Section or this Agreement shall create a liability or a
right of indemnification in any third party.
7. Dispute Resolution.
a. , The City and the County shall confer in good faith to resolve disputes by
negotiation that arise under this Agreement as requested by either party.
b. The following shall serve as the designated representatives for the purpose of
resolving disputes that arise under this Agreement:
City Engineer, City of Yakima
County Engineer, Yakima County
c. In the event the designated representatives are unable to resolve the dispute, the
following shall confer and resolve the dispute:
City Manager, City of Yakima
Public Services Director, Yakima County
The City and County agree that they shall have no right to seek relief in a court of law until and
unless the Dispute Resolution process is exhausted first.
8. Integration. This Agreement contains all of the terms and conditions agreed on by the
parties. No other understandings, oral or otherwise, regarding the subject matter of this
Agreement, are deemed to exist or to bind either of the parties.
9. Modifications. The parties may modify this Agreement but no proposed changes or
modifications shall have validity or become binding on either party unless such changes or
modifications are in writing and executed by both parties.
10. Nondiscrimination. The parties agree that they shall not discriminate against any
person on the grounds of race, creed, color, religion, national origin, sex, sexual orientation,
age, marital status, political affiliation or belief, or the presence of any sensory, mental or
physical handicap in violation of the Washington State Law Against Discrimination (RCW
chapter 49.60) or the Americans with Disabilities Act (42 U.S.C. 12101 et seq.) or any other
applicable state, federal or local law, rule or regulation.
11. Severability. •
Interlocal Agreement Between City of Yakima and Yakima County Page 4 of 6
Sanitary Sewer Improvements and Pedestrian Bridge Construction
i a. If a court of competent jurisdiction holds any part, term or provision of this
Agreement illegal, or invalid in whole or in part, the validity of the remaining provisions shall not
be affected, and the parties' rights and obligations shall be construed and enforced as if the
Agreement did not contain the particular provision held invalid.
b. If any provision of this Agreement is in direct conflict with any statutory provision
of the State of Washington, that provision which may conflict shall be deemed inoperative and
null and void insofar as it may conflict, and shall be deemed modified to conform to such
statutory provision.
12. Waiver. The waiver by either party of any term or condition of this Agreement shall not
operate in any way as a waiver of any other condition, obligation or term or prevent either party
from enforcing such provision.
13. Termination. The parties may terminate this Agreement, with or without cause, by
written notice from either party to the other party sixty (60) days in advance of the termination.
In the event of termination, the amount of compensation shall be for services rendered through
the termination date.
14. Survival. Any provision of this Agreement which imposes an obligation after expiration
or termination of this Agreement shall survive the expiration or termination and shall bind the
parties.
0 15. Notices. Unless otherwise stated herein, all notices and demands are required in written
form and sent to the parties at their addresses as follows:
TO CITY OF YAKIMA:
R. A. Zais, Jr., City Manager
City of Yakima
129 North Second Street
Yakima, WA 98901
•
TO YAKIMA COUNTY:
Vem M. Redifer, PE
Public Services Director
128 North Second Street
Yakima, WA 98901
16. Governing Law. This Agreement shall be govemed by and construed in accordance
with the laws of the State of Washington.
17. Compliance with Law. All Parties to this Agreement shall comply with all applicable
federal, state and local laws, rules and regulations in carrying out the terms and conditions of
this Agreement.
18. Filing. Copies of this Agreement shall be filed with the Yakima County Auditor, pursuant
to RCW 39.34.040, and with the City Clerk of Yakima.
•
Interlocal Agreement Between City of Yakima and Yakima County Page 5 of 6
Sanitary Sewer Improvements and Pedestrian Bridge Construction
CITY OF YAKIMA BOARD OF YAKIMA COUNTY
COMMISSIONERS
R.A. Zais, Jr., City Manager Rand Elliott, Chairman
Date Signed Date Signed
Kevin J. Bouchey, Commissioner
Attest: Deborah Moore
Date Signed
City Clerk
Michael D. Leita, Commissioner
Date Signed
Approved as to form:
Deputy Prosecuting Attorney
Interlocal Agreement Between City of Yakima and Yakima County Page 6 of 6
Sanitary Sewer Improvements and Pedestrian Bridge Construction
• : ° .14:41
• L.' , / T 4 '5 o I 1 L
. c. T.13 R.IB W.M .-"` a j t '1 * j � �ac ___ •
NORTH RR S ON C p d ' STA 97 +20 1 p a+a• ----- _t[ , m ` { \ µ
a m eND 1[Y�•TP.AIL T• a- n" J n,
{ '� ' I« ' r � r 1 S �. 4 ' eAPE STRIP 1...-; i , , "► ��[ I� t
GOAIZ ti no A.. ,Ll �I,.bH ;1r-fa.'
t \ f WUIV! QF .•• ..�t.� � • 1 O� n 8 f m c (18730942008) m • /� - _,
AKIMA ,, _v r � ' YAKIM ca P.W.D. an
CANAL C. ��� // 111
• / ' ' Pl1 O 1 _ircm.. ` ~ —' "`' , w ' / COIMICHE CANYON RD. •
` - -
• - 1 ,, ..7 ...,,,... .....--.1 _ ` �y�,a�+ - ±!' ^ ` � � � �7N� �.�.. m • IMPROVVfMENTS
4 •
g+ P
' ► %��� *41 .. 1V ,,,, c3051
ef` . -:: ; - f - W 1 4 " iX1 � $ h C ,�4�vl�:. ' . m 1� 1 _� /` SIPH 2039 (031)
L' •r 0 $ ✓• s % ,yr1 a r�� � (18130942000 ` r,, , ,� tr `
q ® (1813084y017) • ; -.;464- ,� p l y YAKIMA CO, P.W,D" � ( ~ I T EARTH TECH IAEODM
11" YAKIMA VALLEY \ `, r ; 1*4'14 to ; ' EARTH
CroasU4TION Nona CANAL CO, � 1 4.44Z - '. `i 18,5' - r 1 M J' ms•
' O 67A,99x70 TO STA 97+00, LT., INSTALL 0 StA 95.85 TO STA 96 +15, LT., CONSTRUCT r 0 0 69 L e i ' • -
CNA 41NIC FE7.1ce TYPE k Is' BEYOND CEMENT CONCRETE RETAINING WALL 7' BEHEAD *��``• �1�ir MP CONS c _
SIDEWALK PER WSDOT STD PLAN WAIL. BEE DETAILS SHEET . 4 , \,- ° /�,/� STA. 99 +63.6A -
470.10-00. ' ® REMOVE AND REPLACE 48' SIPHON. SEE '•1 `u 5 0IJU DER m ER W A5 Y n T r t
•
♦ ♦ i• ' j H 0 , .
70 STA 95.70 TO STA 97+51, LT. INSTALL SIPHON PLANS AND DETAILS SHEETS _"
BEYO . 4 P 4 !. MARSHA (1813 0942009 ) SHOUL / 1310 0P RADIU RETURNS P` yVABy
SILT FENCE 2' ND CATCH Lin DMZ > _ I ' A: OF 4 . - 'C . k:
OP WALL PER WSDOT STD PLAN 1- 90.10.00. 19 STA 9E470 TO STA 9855, RT. REMOVE 0 INSrAu. MONUEIPNT t, �� STA 45(08,43 s .004E. oil 111>E Q• Q•
Q. STA 96.15 TO STA 91•00, LT, CONSTRUCT EXISTING PAVEMENT AID SCARIFY. YA BM 57D PLAN 5•I I. NOT6 �` �� STA 99+99,68 E coWICNe E ANYOA! A 4 59% T • J27 .. • • p -, •s I ; •
Buc WANING WALL 2' BEHIND TRAIL. ' ® STA 9861.7, 362 LT. TO 96■93.2. 0.5' Lt, ALL DIMENSIONS ARE TV PACE OF CURB. ...
BEE DETAILS SHEET 15. RE110YE 76 LF OF GUARDRAIL AND P0676. 'gip
q
•••• ..... . �: •J: 1:. . +" CO.' " ' 7 •;: r d - ."—." — -•- ......_
1i 7�7+"i`_WIl iF li5RVI'_ IL� = W 1 A d ' .. ... . .::::.:::.::.::...::......:.:_ .. ` R Ai18T£7�
� :4L; f+
� A ............... . . - am
6 �i�9 ro
. ..... �i�iii.: , :: A • .... -: .......... - -� ::: : 77: __J1
::: .:... ... . ....: .
?tip: :: •. ,r• a iy i . ....... n ...
11 - - ' ' e , r;; 1L :.c PROJECT &MEER: ■
1 k m", , ..... 4.: - - - 4. :+:- .. -Hal a. NUSCRKA
> ... FL : M .d: ... • • OqA CHECKED bY:
Ir.:
Jet- -....
L "i
_ 1 -1 -tl9
- - JrN 1,
lx
R ,
tTa_.
r
• .,,,. arc. . I J'
• z EO
• : :: ::: , , _ , ::: ;:::: ::: : : :: : : ::::::: r.:::.. I ...... ......... . , 8 • ° .... MAN AND PROFILE
: . : ..: :' :: : : : . : : :: ; :: : = ::: ..._.._ . , _ ...:.�_. _:. ,... ,_ .. . . . __ STA 95+20 To
1 :'.Pi. : � . 1 T7.":"::. I . .
- -- ..... . _ - •
-- STA 99120
.. .......:.:::.::.. :iTiON 'A L::::::: u ri 110N1.T . i Li4 . r.C'_ _. ipl I
y .. •RR�tT: i j 78 yg g
„f,
:7% ::::::: .. . ° I�. . :: . 4 :R m 1
y �
. SHEET 7 OF 013
i
•