HomeMy WebLinkAbout08/18/2015 05H West Yakima Irrigation System Ph 2 Improvements Project Completion; POW Contracting, Inc.'1111111 1,
nun 11,1:1141r10
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. S.H.
For Meeting of: August 18, 2015
ITEM TITLE: Project Completion and Contract Acceptance for POW Contracting,
Inc. - Project IR2323 West Yakima Irrigation System Ph 2
Improvements (Standard Motion V -B -Accept the project and approve
the final payment)
SUBMITTED BY: Debbie Cook - Director of Utilities and Engineering (509) 575-6120
Mike Shane - Water/Irrigation Engineer (509) 576-6480
SUMMARY EXPLANATION:
A final payment of $46,415.62 is recommended for POW Contracting, Inc. for Project IR2323. This project
is located in the neighborhoods between Summitview Avenue and Lincoln Avenue, from North 21st Avenue
to North 37th Avenue. The project installed approximately 5,130 LF of new 3" and 4" horizontal directional
drilled HDPE pipe; trenched approximately 7,390 LF of new 3" - 12" PVC pipe; and installed approximately
210 irrigation service connections. The project also included grind and overlay of a portion of Summitview
Avenue within the project area.
Final inspection for this project was made and the recommendation is that the project be accepted.
This Council action is to accept the project and approve the final construction costs.
Project Manager: Mike Shane
Contractor: POW Contracting, Inc.
Contract Award: 10/7/2014
Contract Cost: $1,004,434.00
Retainage Due: $46,415.62
The above total contract cost is for construction only an does not include engineering and other costs.
Resolution: Ordinance:
Other (Specify): Project Completion and Contract Acceptance
Contract: Contract Term:
Start Date: End Date:
Item Budgeted: Yes Amount:
Funding Source/Fiscal Impact:
Strategic Priority:
Insurance Required? No
Mail to:
Phone:
APPROVED FOR
SUBMITTAL:
RECOMMENDATION:
Accept Project
ATTACHMENTS:
Description
FINAL.
Irrigation Improvement fund
Improve the Built Environment
City Manager
Upload Date
7/15/2015
Type
G:';oveit Memo
City of Yakima
Water & Irrigation Division
2301 Fruitvale Blvd.
Yakima, WA 98902
TO: P.O.W. Contracting, Inc.
P,O. Box 4772
Pasco, WA 99302
WEST YAKIMA IRRIGATION SYSTEM PHASE 2 IMPROVEMENTS
City Project No.: 1R2323
HLA Project No.: 14055C
Progress Estimate No.: 7 AND FINAL
Date:
June 4, 2015
Item
No
1111
Most o
Mobilization
Project Temporary Traffic Control
Unit
LS
Contract
Quantic
1
Unit
Price
$41,000.00
Estimate 7
Quantic'
0%
Quantity
to Date
100%
Amount
$41,000.00
Contract
Quaruti
100%
LS
1
$25,000.00
0%
100%
$25,000.00
100%
Clearing and Grubbing
LS
1
$10,000.00
0%
100%
$10,000.00
100%
Asbestos Cement Pipe Removal and
LF
5,700
$2.65
0
3,799
$10,067.35
67%
Disposal
5
Abandon Irrigation Valve
EA
8
$1,000.00
0
10
$10,000.00
6
7
Shoring or Extra Excavation
LS
LF
1
5,110
$1,500.00
_
$37.00
0%
0
100%
5,146
$1,500.00
$190,402.00
100%
101%
rizontal Directional Drill 4 Inch HD
H opPE
H
PiIIII
e
Horizontal Directional Drill 2 -Inch HDPE
LF
20
$85.00
0
20
$1,700.00
100%
Pipe
9
Trench 12 -inch PVC Pipe
LF
2,290
$20.00
0
2,293
$45,860.00
100%
10
Trench 8 -Inch PVC Pipe
LF
1,730
$19.00
0
1.736
$32,984.00
100%
Trench 6 -Inch PVC Pipe
LF
2,400
$18.00
0
2,432
$43,776 00
101%
Trench 4 -Inch PVC Pipe
LF
220
$17.00
0
265
$4,505.00
120%
Trench 3 -Inch PVC Pipe
LF
750
$17.00
0
1 740
$12,580.00
99%
Trench 3 -Inch G.I. Pipe
LF
20
$75.00
0
$2,025.00
$2,500 00
0
$5,000.00 100%
16
-
$2,000.00
0
$8,000.00 133%
17
. -
$1,500.00
0
$6,000.00 100%
18
it
$1,000.00
0
19 $19,000.00 106%
19
-
EA
4
$1,000.00
0
fl $4,000.00 100%
20
2 -Inch Ball Valve
EA
3
$750.00
0
$2,250.00 100%
21
1 -Inch Service Connection
EA
111
$500.00
0
104 $52,000.00 94%
3/4 -Inch Service Connection
EA
100
$500.00
0
100 $50,000.00 100%
LF
940
$10.00
0
993 $9,930.00 106%
LF
9b0
$10.00
0
975 $9,750.00 103%
25
:
$175.00
0
104 $18,200.00
26
EA
100
$175.00
0
102 $17,850.00 102%
Type 1 Valve Box
EA
48
$175.00
0
$7,700.00'
28
Type 2 Valve Box
EA
200
$65.00
0
$12,805.00 • -
29
Cold Mix Asphalt
SY
3,750
$10.00
0
$23,230.00
30
HMA Trench Repair
SY
3,800
$29.50
0
$87,143.00
Gravel Surfacing Repair
SY
20
$100.00
0
20 $2,000.00
100%
Sodded Lawn Repair
SY
1,150
$20.00
0
280 $5,600.00
Cement Conc, Traffic Curb and Gutter
LF
330
$5.00
0
$235.00
Cement Conc. Sidewalk 6 -Inch Thick
SY
60
$100,00
0
$1,500.00
Mal
GtPROJECTSt2014t14055C YA W YA BRRIG SYS PH 2.. P O.VU CONTRACTING, INCtPROGRE S ESTIINATFSIPROG EST NO'7 FINALI2017-66715 REV FROG EST NO 7 FINAL xis
escriptton
Unit
35
Cement Conc. Sidewalk 4 -Inch Thick
SY
Contract
Quantity
55
Unit Estirnate 7
Price Quantity
$100.00 0
Quant
to Date
36
Crushed Surfacing Base Course
TON
1,750
$20.00 0.00
37
Select Backfill, as Directed
CY
180
38
Pavement Markings
LS
1
39
Minor Change
FA
EST„
$35.00
$5,000.00
$15,000.00
0
0%
0.00
2
1,063.00
184
100%
ontract
Amount Quan
$200.00 4%
$21,260.00 60.7%
$6,440.00, 102%
$5,000.00 100%
17,782.53
CHANGE ORDER NO„
$17,782.53 119%
$824,274.88
1-1
Provide a 2" grind and overlay (including
grinding, removal of grindings, sweeping,
tack coat, asphalt, compaction, testing,
valve box and manhole adjustments, extra
traffic control, lane striping, and all other
incidentals) in the north lane of Summitview
Avenue, at all locations abutting irrigation
trench, approximately 6'-9' wide from south
trench edge to lane line.
SY
5,310
$20.50
0
5,075
$104,037.50
96%
1-2
Reduction in Bid Item 30, HMA Trench
Repair
SY
-1,166
$29.50
Final quantities are reflected in the under run of
Bid Item 30.
CHANGE ORDER NO. 1, SUBTOTAL
$104,037.50
G;YPR6)70.L1fro42(k9 4d'IM615if: YAW YFA IRMO 57(;b N'di 2-P )W Cf7M'Y1dA. ING NOV FF tA'T NG7 IG INAI.42018, REV PROEST NO 71f01NAL Als
No,
Descriptior
Unit.
Contract Unit
Quantity Price
Estimate 7
Quantity
uan
SUBTOTAL, WORI< TO DATE
Amount
$928,312.38
P
US MATERIALS ON HAND
$0.00
SUBTOTAL AMOUNTS
8.2% STATE SALES TAX
$928,312.38
$76,121.62
TOTAL
$1,004,434.00
LESS TOTAL RETAINAGE
ACCEPTED:
Progress Estimate No. 1 $ 238.235.14
Progress Estimate No, 2 $ 219,160.95
Progress Estimate No. 3 $ 188,686.24
Progress Estimate No. 4 $ 94,003,06
Progress Estimate No. 5 $ 215,868.99
Progress Estimate No. 6 $ 2,064.00
Progress Estimate No. 7 AND FINAL $
0.00
LESS AMOUNTS PREVIOUSLY PAID'.
AMOUNT NOW DUE
$46,415.62
$958,018.38
$0.00
Retainage $ 11,542.40
Retainage $ 10,618.26
Retainage $ 9,141.78
Retainage $ 4,554.41
Retainage $ 10,458,77
Retainage $ 100,00
Retainage $ 0.00
I hereby certify that the foregoing is a true and correct statement of the work performed under this Contract.
I hereby accept the Final Progress Estimate and Final Contract Voucher Certification, in accordance with Section 1-09.9 of the
WSDOT Standard Specifications.
Contrac
Quantit
P.O,W. Contracting, Inc. Date:
G IPROJECTS\2014\14055C YA 77 YA IRRIG SYS PH 2 - P 0 W CONTRACTING, INCIPROGRESS ESTIMATESIPROG EST NO 7 FINAL\2015-06-15 REV PROG EST N0 7 FINAL Ns
City of Yakima
Water & Irrigation Division
2301 Fruitvale Blvd.
Yakima, WA 98902
TO: P.O.W. Contracting, Inc.
P.O. Box 4772
Pasco, WA 99302
MINOR CHANGES
WEST YAKIMA IRRIGATION SYSTEM PHASE 2 IMPROVEMENTS
City Project No.: IR2323
HLA Project No.: 14055C
Progress Estimate No.: 7 AND FINAL
Date:
June 4, 2015
DATE
DESCRIPTION
PAID
AS
SUB
AMOUNT
GC
AMOUNT
TOTAL
AMOUNT
SUB
NAME
TIME
EXTENSION
4/30/2015
SEE FORCE ACCT SUMMARY FOR DETAIL
39
$17,531.54
$17,531.54
2/26/2015
TRAFFIC CONTROL - SIDE SEWER REPAIR
39
$250.99
$250.99
STRIPE RITE
Subtotal
$17,782.53
cc: P.O.W. Contracting, Inc.
Ben Annen, PE
Steve Sziebert, HLA
Eric Stein, HLA