I T E M T IT L E :Miller P ark I mprovements P roject Update
S UB M IT T E D B Y:S cott S chafer, Director of Public Works
K en W ilkinson, P arks & Recreation Manager 509 576 6416
S UM M ARY E X P L ANAT I O N:
I n J uly of 2020, a fundraising effort was started by a group of Yakima northeast business owners,
parents, coaches, community leaders and basketball players to make much needed
improvements to Miller P ark.
The group reached out to City officials and an initial meeting was held at Miller P ark on Tuesday,
J uly 21, 2020 to identify their ideas for improving the park. A follow up meeting was then held on
J uly 28, 2020 at P ublic Works with the community members, Mayor B yers, Council Member
Macias and staff. A purpose statement was created by the attending group; “Revitalizing M iller
P ark as the Heart of the Community”. A list of improvements was then created by the group
and ranked by priority. T he improvements determined to be conducted at Miller P ark consisted
of:
• Resurface and restripe basketball courts 1-3
• Remove and replace basketball court 4
• L ights for basketball courts
• B asketball court perimeter fence replacement
• B asketball rims, backboards and poles for all four courts
• New restroom
• S econd picnic shelter
• New playground
• Added walkways
• Additional picnic tables and benches
• S hade structure performance area
Follow up meetings were held in which cost estimates were developed and shared with the
group. Three of the community members presented their ideas to the P arks & Recreation
Commission on Wednesday, A ugust 12, 2020. The Park & Recreation Commission was grateful
to the group and supported their efforts. Nicole Donegan from the F ield Group then donated her
time in creating an informational and fundraising brochure for the proposed park improvements.
1
Fundraising efforts were started with the City soon receiving both private donations as well as
grants from Walmart, Del Monte and G E S A Credit Union. I n addition, a Washington State
L egislative Capital B udget request was submitted and received by the City in the amount of
$625,000.
The progress that has been made to date on the project includes the City’s S treets Division
removing basketball court 4 and repaved it followed by crack sealing and re-coating courts 1-3.
A ll four courts were then restriped. I n addition, the basketball rims and backboards have been
replaced. T he picnic shelter project has begun. The prefabricated concrete restroom has been
ordered and the utility work is going out for bid soon. T he new playground has been installed and
has already been enjoyed by many children and families. T he shade structure for the
performance area has been ordered and the footers will be dug soon. T he lighting for the
basketball courts has also started and should be completed in late J une. W ith the improvements
being made to Miller P ark, the Millennium Foundation is funding a mosaic project to add beautiful
artwork throughout the park.
The Yakima P arks & Recreation Division is pleased to be working with a group of energetic and
motivated community members that want to make improvements to a Yakima Park.
I T E M B UD G E T E D:Yes
S T RAT E G I C P RI O RI T Y:Neighborhood and Community B uilding
AP P RO V E D F O R S UB M IT TAL B Y T HE C IT Y M ANAG E R
RE C O M M E ND AT I O N:
AT TAC HM E NT S :
Description Upload Date Type
Miller Park Improvement Project - fund raising brochure 5/31/2022 Backup Material
Miller Park presentation 6/2/2022 Cover Memo
2
3
4
Miller Park Improvements
Yakima City Council Study Session
June 14, 2022
Miller Park Established 1929
Miller Park Improvement Project 1
5
Miller Park Improvement Project Milestones
July 2020
Alicia Garza spoke with Mayor Byers regarding starting a fund raising effort to make improvements
to Miller Park. Meeting at Miller Park was held on Tuesday, July 21, 2020. A group of Northeast
business owners, parents, coaches, community leaders and basketball players met with staff at the
park to identify their ideas for improving the park. An initial meeting was held on July 28, 2020 with
the community members, Mayor Byers, Council Member Macias and staff.
August 2020
A purpose statement was created by the group. The statement is “Revitalizing Miller Park as the
Heart of the Community”.
A list of improvements was created by the group and ranked by priority.
•resurface and reline the basketball courts
•provide lights for safety and to allow play to continue later in the evening
•a new restroom
•a second picnic shelter
•a new playground
•added walkways
•additional picnic tables and benches.
Miller Park Improvement Project 2
6
Miller Park Improvement Project Milestones –(continued)
September 2020
SEPA Modification completed and submitted to City of Yakima Planning Division.
Fund raising brochure created by the Field Group.
October 2020
Funding request letter sent to the Washington State Department of Financial Management
Committee meeting was held on Monday, October 19, 2020.
November 2020
Basketball court removed and repaved by Yakima Streets Division
Funding request letter sent to Governor Inslee
December 2020
Project update given to Yakima Park & Recreation Commission
January 2021
Contract with Washington Department of Commerce approved by Yakima City Council
Miller Park Improvement Project 3
7
Miller Park Improvement Project Milestones –(continued)
April 2021
Washington State Legislative Capital Budget Request –Approved - $625,000
July 2021
Funding Documentation Submittal Begins
November 2021
Millennium Foundation approves funding Radiance Mosaic project
January 2022
Yakima City Council Approves Contract with Washington Department of Commerce
Playground Ordered, CXT Restroom Ordered, Basketball Backboards & Rims Ordered, etc.
Purchasing & Bidding Process Begins
March 2022
Basketball Backboards & Rims Installed
May 2022
Playground Completed, Picnic Shelter, Basketball Lighting Construction Begins
Miller Park Improvement Project 4
8
Projects
1. Resurface & Restripe Basketball Courts 1 –3
2. Remove and Replace Basketball Court 4
3. Lights for Basketball Courts
4. Four Benches –Memorial or Sponsorship
5. 24’ X 24’ Hexagon Picnic Shelter
6. Shade Structure Performance Area
7. Walkways
8. Picnic Tables
9. Restroom –CXT pre-fabricated building
10. Playground –ADA Accessible
11. Basketball Court perimeter fence replacement
12. Basketball Rims, Backboards & Poles – 4 courts
13. Fundraising & Information Brochure printing
Miller Park Improvement Project 5
9
Existing Rotary Picnic Shelter -2012
Gazebo Removed -2011
Miller Park Improvement Project 6
Old Bath House Removal -2016
Security Lighting Installed -2018
Previous Improvements
10
Spray Park -2007
Open Space
Miller Park Improvement Project 7
Spray Park Drain Field -2012
Previous Improvements -continued
11
Court #4 Removed & Repaved
November 2020
Miller Park Improvement Project 8
Current Improvements
12
Courts Recoated & Relined – March 2021
Miller Park Improvement Project 9
13
New Backboards and Rims Installed
14
Basketball Court Lighting
LED Fixtures
Miller Park Improvement Project 11
15
Old Playground and Tree Removed
Miller Park Improvement Project 12
16
Miller Park Improvement Project 13
17
Miller Park Improvement Project 14
Playground Construction –April 2022
Playground Installation
18
Miller Park Improvement Project 15
19
Miller Park Improvement Project 16
New 20’ X 20’ Picnic Shelter
20
CXT Concrete ADA Restroom
Miller Park Improvement Project 17
21
The Millennium Foundation
has committed to installing
mosaic pieces in the park
Estimated value of donation
$177,000
Miller Park Improvement Project 18
22
Mosaic Project
•5 Free Standing Mosaics
•1 Wall Mounted Mosaic
Miller Park Improvement Project 19
23
Porcelain Tile Entrance Mats
Miller Park Improvement Project 20
24
Miller Park Improvement Project 21
Performance Area
Shade Structure
25
Performance Area –Viva La MusicaConcerts
Miller Park Improvement Project 22
26
Miller Park Improvement Project 23
Questions?