HomeMy WebLinkAbout06/16/2015 10 2016-2021 Six-year Transportation Program (TIP) AmendmentITEM TITLE: SUBMITTED BY: SUMMARY EXPLANATION: BUSINESS OF THE CITY COUNCIL YAKIMA, WASHINGTON AGENDA STATEMENT Item No. 10. For Meeting of: June 16, 2015 Public Hearing to consider: A) Resolution adopting the Six-year Transportation Improvement Program for the years 2016 to 2021, and to amend the Metropolitan Transportation Plan; and B) Resolution amending the Yakima Urban Area Comprehensive Plan Capital Facilities Element Debbie Cook, Director of Utilities and Engineering Brett Sheffield, Chief Engineer Attached is the 2016 — 2021 Six-year Transportation Improvement Program (TIP), along with an explanation sheet that describes the information contained on the various columns of the Six-year TIP. No new projects have been added. Projects that that have been removed from the 2015 — 2020 TIP as they were completed or the funds were obligated include: • #3 Tieton Drive and 64th Avenue Intersection Improvements • #10 E. Lincoln Avenue and 10th Street Roundabout • #16 West Valley Middle School Safety Improvements Project #33, N. 1st Street and `I' Street Signal Upgrade, has been removed because this work is being included in the N. 1st Street Revitalization, MILK to 'N' Street project, renumbered #3. Council and the public are welcome to add other arterial system projects to the list. The six-year TIP project listing will be finalized at the June 18th hearing and sent to the Yakima Valley Conference of Governments (YVCOG) after approval. A) Each year the City is required by RCW 35.77.010 and RCW 36.81.121 to update its Six-year Transportation Improvement Program (TIP) for submittal to the Washington State Department of Transportation. This plan must include all transportation projects for which state gas tax revenue of federal revenue will be used. The current plan for 2016 — 2021 includes ten projects that are funded. Funding for the remainder of the projects will continue to be sought. The funded projects include: #1 — Yakima Railroad Grade Separations, Phase 4 #2 — North 1st Street Revitalization, 'N' Street to SR 12 #3 — North 1st Street Revitalization, MILK to 'N' Street #4 — East Nob Hill Boulevard and Fair Avenue Intersection Improvements #6 — Powerhouse Road Sidewalk #7 — Yakima Valley Transportation Company Preservation #44 — Northside Alley Pavers #45 — S. 80th Avenue Bridge #46 — Wide Hollow Bridge #47 — Lincoln Avenue Corridor Safety Improvements. Six-year Transportation Improvement Program (TIP) Background On August 10, 2005, the President signed into law the Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU). This act is the next authorization after the prior Transportation Equity Act of 1998 for the 21st Century (TEA -21) and previous Intermodal Surface Transportation Efficiency Act (ISTEA) of 1991. The current act again specifies the systems on which certain funds can be used and activities for which funds can be used and promotes the role of the Metropolitan Planning Organizations (MPO) in the planning and programming of projects. SAFETEA- LU requires each designated MPO to develop a Transportation Improvement Program (TIP), and the state to develop a Statewide Transportation Improvement Program (STIP) as a condition to securing federal funds for the transportation projects. Projects listed in the STIP are the only projects that can be approved by the Federal Highway Administration (FHWA) and the Federal Transit Administration (FTA) to utilize federal fund of by the State of Washington for approved State funding agencies. The STIP is a prioritized program of transportation projects, complied from local and regional plans, along with the Washington Transportation System Plan (WTP), which provides a backbone for developing projects for the intermodal transportation network in the State of Washington. The STIP contains federally funded projects plus state and local projects that are regionally significant. These projects have been identified through the planning process as the highest priority for the available funding to the state's transportation program. Planning activities of state and local governments are essential parts of integrated regional planning processes. Long range transportation planning is a part of the comprehensive land use planning carried out by local governments. Citizen participation is an integral part of the planning process at all levels. Local Agencies are required to develop and adopt a six-year transportation program. All local agencies are required to hold at least one public hearing during the development of the six-year transportation program. Project ranking has been performed utilizing data supplied by the Street and Traffic Division. The ranking will be integrated with other project needs and the total list will be reviewed and adjusted to the particular need of the City of Yakima. B) The City needs to amend the Yakima Urban Area Comprehensive Plan Capital Facilities Element to incorporate the adopted six-year TIP for 2014 to 2019. This will ensure that we are in compliance with the Growth Management Act and that we are consistent with the Comprehensive Plan as required. The amendment is limited to incorporate only those projects that adopted in the STIP and is not subject to the "once a year" change required under the laws of the Growth Management Act. Resolution: Ordinance: Other (Specify): Six -Year TIP Contract: Contract Term: Start Date: End Date: Item Budgeted: Amount: Funding Source/Fiscal Impact: Strategic Priority: Insurance Required? No Mail to: Phone: APPROVED FOR SUBMITTAL: RECOMMENDATION: City Manager Adopt the Six -Year TIP and amend the regional Metropolitan Transportation Plan and Comprehensive Plan Capital Facilities Element. ATTACHMENTS: Description Upload Date 1-11 Resolutions 6/8/2015 1-11 Six -Year Transportation Improvement Program 6/8/2015 1-11 Explanation Sheet 6/8/2015 Type fesollu.utiion E.iiixhii 15111 E.iiixhii 15111 RESOLUTION NO. R — 2015 - A RESOLUTION adopting the Six -Year Transportation Improvement Program for the period of 2016 through 2021 for the construction of streets and arterials streets in the City of Yakima and amending the Metropolitan Transportation Plan. WHEREAS, the City of Yakima annually prepares, reviews and adopts a Six Year Program for the construction of streets and arterial streets in the City of Yakima for the ensuing six year period, all as contemplated and required by State RCW 35.77.010 and applicable Federal law; and WHEREAS, the City of Yakima desires to amend the Metropolitan Transportation Plan to ensure compliance with the Growth Management Act and the regional transportation plan for the construction of streets and arterial streets in the City of Yakima, all as contemplated and required by State and Federal law, and WHEREAS, after public hearings on the matter, held at the regular meeting of the Yakima City Council on June 2, 2015 and June 16, 2015, with proper public notice as required by RCW 35.77.010, the City Council finds that the plan attached hereto should be adopted as the Six -Year Transportation Improvement Program for the period of 2016 through 2021 for the construction of streets and arterial streets in the City of Yakima, now, therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA: The Six -Year Construction Program for the period of 2016 through 2021, a copy of which is attached hereto and by this reference made a part hereof, is hereby adopted as the official Six -Year Transportation Improvement Program for the City of Yakima, including proposed amendments to the Metropolitan Transportation Plan along with Street Improvements, which are also approved. ADOPTED BY THE CITY COUNCIL this 16th day of June, 2015. Micah D. Cawley, Mayor ATTEST: City Clerk RESOLUTION NO. R — 2015 - A RESOLUTION to amend the Yakima Urban Area Comprehensive Plan Capital Facilities Element to incorporate the Six-year Transportation Improvement Program (TIP) for the period of 2016 through 2021. WHEREAS, the City of Yakima annually prepares, reviews and adopts a Six — Year Transportation Improvement Program for the construction of streets and arterial streets in the City of Yakima for the ensuing six year period, all as contemplated and required by State RCW 35.77.010 and applicable Federal law; and WHEREAS, the City of Yakima desires to amend the Yakima Urban Area Comprehensive Plan Capital Facilities Element to reflect the adoption of the Six-year TIP, as contemplated and required by RCW 36.70A.070(6) to ensure compliance with the Growth Management Act and consistency of the Comprehensive Plan and the Six-year TIP; and, WHEREAS, this amendment is limited to incorporation of the projects listed in the Six-year Transportation Improvement Plan for the period of 2016 to 2021 to the Capital Facilities Element of the Yakima Urban Area Comprehensive Plan, which is contemplated and provided under RCW 36.70A.130(2B) and RCW 35.77.010; and, WHEREAS, public hearings were held by the Yakima City Council on the Six-year TIP on June 2, 2015 and June 16, 2015, with proper public notice as required by RCW 35.77.010; now, therefore BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA: The adopted Six -Year Transportation Improvement Program for the period of 2016 through 2021 for the City of Yakima shall be incorporated as an amendment to the Capital facilities Element of the Yakima Urban Area Comprehensive Plan. ADOPTED BY THE CITY COUNCIL this 16th day of June, 2015. Micah D. Cawley, Mayor ATTEST: City Clerk Agency: Yakima Co. No.: 39 City No.: 1485 Co. Name: Yakima Co. MPO/RTPO: YVCOG Six Year Transportation Improvement Program From 2016 to 2021 Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015 Amend Date: Resolution No.: Functional Class Priority Number Project Identification A. PIN/Federal Aid No. B. Bridge No. C. Project Title D. Street/Road Name or Number E. Beginning MP or Road -Ending MP or Road F. Describe Work to Be Done Improvement Type(s) Status Total Length Utility Codes Project Costs in Thousands of Dollars Expenditure Schedule (Local Agency) Federal y Funded Projects Only j y Project Phase Phase Start Fund Source Information Federal Funding State Fund Code State Funds Local Funds Total Funds Envir. Type R/W Required Date (MM/YY) Federal Fund Code Federal Cost by Phase 1st 2nd 3rd 4th 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 14 1 Yakima Railroad Grade Separations - Phase 4 Lincoln Avenue from: N. 1st Street to: N. 1st Avenue Install art as project aesthetics for the railroad grade separations, and construct raised sidewalk on the south side of Lincoln Avenue 01 06 07 08 5 0.2 T P G 0 CN 1/1/2016 650 650 650 EA Yes 9/1/2009 Totals 0 0 650 650 650 0 14 2 North lst Street Revitalization North 1st Street from: 'N' Street to: SR 12 Improve North 1st Street by rehabilitating the pavement and lane markings, removing on -street parking, enhancing street and pedestrian lighting, constructing median islands and installing various pedestrian and decorative elements. 3 06 5 0.42 P T 0 C CN 11/1/2018 1 STP(U) I 2,7181 I 4241 3,1421 3,142 I CE No Totals 2,718 424 3,142 3,142 14 3 North lst Street Revitalization N. 1st Street from: MLK Blvd. to: 'N'Street Improve North 1st Street by rehabilitating the pavement and lane markings, removing on -street parking, enhancing street and pedestrian lighting, constructing median islands and installing various pedestrian and decorative elements. 06 12 P 0.98 P T G C CN 1/1/2016 TIGER 8,000 8,000 8,000 CE Yes 12/31/2015 Totals 8,000 0 8,000 0 0 14 4 E. Nob Hill Blvd. & Fair Ave. 1/5. Improvements Nob Hill Boulevard from: E. Nob Hill Blvd. to: Fair Ave. Widen Nob Hill Boulevard through the intersection, construct left -turn lane, curb, gutter, sidewalk, street lighting and drainage. Upgrade signal by installing mast arm structures. 03 04 31 5 N/A P T W C 0 RW CN 1/1/2016 6/1/2018 STP(U) STP(U) 187 1,457 I 29 227 216 1,684 216 1,684 I CE Yes 1/1/2018 Totals 1,644 256 1,900 0 1,684 Agency: Yakima Co. No.: 39 City No.: 1485 Co. Name: Yakima Co. MPO/RTPO: YVCOG Six Year Transportation Improvement Program From 2016 to 2021 Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015 Amend Date: Resolution No.: Functional Class Priority Number Project Identification A. PIN/Federal Aid No. B. Bridge No. C. Project Title D. Street/Road Name or Number E. Beginning MP or Road - Ending MP or Road F. Describe Work to Be Done Improvement Type(s) Status Total Length T, C u m Project Costs in Thousands of Dollars Expenditure Schedule (Local Agency) Federal y Funded Projects Only Project Phase Phase Start Fund Source Information Federal Funding State Fund Code State Funds Local Funds Total Funds Envir. Type R/W Required Date (MM/YY) Federal Fund Code Federal Cost by Phase 1st 2nd 3rd 4th 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 17 5 Powerhouse Road Sidewalk Powerhouse Road rom: Cowiche Canyon Rd to: Mobile Home Park Widen westbound lane to provide a 14 -foot wide shared bike lane and construct curb, gutter and sidewalk on the north side of the road. 05 12 5 0.6 0 CN 1/1/2016 TAP 245 245 245 CE No Totals 245 245 245 14 6 Yakima Valley Transportation Company Preservation Yakima Avenue rom: Yakima Avenue to: 6th Avenue Remove and replace a portion of the existing trolley rail in the vicinity of the intersection of 6th Avenue and Yakima Avenue. 03 5 0.02 0 CN 1/1/2016 STP(E) 521 521 52 CE No Totals 52 52 52 19 7 Adams Elem./Washington M.S. Sidewalk Improvements Various Streets rom: to: This project will make various pedestrian safety improvements in the vicinity of Adams Elementary School and Washington Middle School, such as, constructing sidewalks, improving roadway crossings and installing flashers 12 P N/A P T 0 PE RW CN 1/1/2016 1/1/2017 5/1/2017 SRTS SRTS SRTS 25 50 253 30 25 50 283 25 50 283 CE Yes 5/1/2017 Totals 328 30 358 25 333 19 8 Garfield Elementary Safety Improvements Various Streets rom: to: This project will make various pedestrian safety improvements in the vicinity of Garfield Elementary School, such as, constructing sidewalk, improving roadway crossings, installing flashers. 12 P N/A P T 0 PE 11/1/2016 RW 1/1/2017 CN 5/1/2017 SRTS SRTS SRTS 121 20 128 I 13 I 121 12 20 141 20 141 CE Yes 1/1/2017 Totals 160 13 173 12 161 Agency: Yakima Co. No.: 39 City No.: 1485 Co. Name: Yakima Co. MPO/RTPO: YVCOG Six Year Transportation Improvement Program From 2016 to 2021 Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015 Amend Date: Resolution No.: Functional Class Priority Number Project Identification A. PIN/Federal Aid No. B. Bridge No. C. Project Title D. Street/Road Name or Number E. Beginning MP or Road - Ending MP or Road F. Describe Work to Be Done Improvement Type(s) Status Total Length Utility Codes Project Costs in Thousands of Dollars Expenditure Schedule (Local Agency) Federal y Funded Projects Only Project Phase Phase Start Fund Source Information Federal Funding State Fund Code State Funds Local Funds Total Funds Envir. Type R/W Required Date (MM/YY) Federal Fund Code Federal Cost by Phase 1st 2nd 3rd 4th 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 12 9 SR 12 & 16th Avenue Interchange Westbound ramps of SR 12 rom: 16th Avneue to: SR 12 Construct a roundabout where the westbound ramps intersect with N. 16th Avenue. 03 06 P N/A 0 PE CN 1/1/2017 1/1/2018 STP(U) STP(U) 86 779 14 121 100 900 100 900 CE No Totals 865 135 1000 100 900 16 10 1-82 & Lincoln Avenue Interchange Lincoln Avenue rom: E. 'G' Street to: 1-82 Reconstruct/extend off -ramp from existing 1-82 off - ramp for Lincoln Avenue to E. 'G' Street. 01 P N/A 0 P G PE RW CN 1/1/2017 1/1/2018 6/1/2019 STP(U) STP(U) STP(U) 260 173 1,730 40 27 270 300 200 2,000 300 200 200 2,000 CE No Totals 2,163 337 2,500 0 500 200 2,000 14 11 Yakima Avenue& Fair Ave. Signalization E. Yakima Ave.rom: E. Yakima Ave. to: Fair Ave. Install traffic signal at the intersection of Yakima Avenue and Fair Avenue. 12 P N/A P T W 5 0 PE 1/1/20181 STP(U) CN 16/1/2019 STP(U) I 5191 1 I 81I 6001411 1001 600 CE No Totals 605 95 700 100 600 16 12 3rd Ave. Washington (o rd Avenue W. Washington Ave. Upgrade the traffic signalization system 12 P N/A P T PE CN 4/1/2017 9/1/2017 I I 0 20 I 2101 210 230 230 20 210 230 CE No Totals 230 230 230 Agency: Yakima Co. No.: 39 City No.: 1485 Co. Name: Yakima Co. MPO/RTPO: YVCOG Six Year Transportation Improvement Program From 2016 to 2021 Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015 Amend Date: Resolution No.: Functional Class Priority Number Project Identification A. PIN/Federal Aid No. B. Bridge No. c. Project Title D. Street/Road Name or Number E. Beginning MP or Road - Ending MP or Road F. Describe Work to Be Done Improvement Type(s) Status Total Length Utility Codes Project Costs in Thousands of Dollars Expenditure Schedule (Local Agency) Federal y Funded Projects Only Project Phase Phase Start Fund Source Information Federal Funding State Fund Code State Funds Local Funds Total Funds Envir. Type R/W Required Date (MM/YY) Federal Fund Code Federal Cost by Phase 1st 2nd 3rd 4th 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 14 13 S. 1st St. & E. Washington Ave. 1/5 Improvements 03 P N/A P PE 1/1/2017 STP(U) 260 40 300 300 CE Yes South 1st Street 06 W RW 1/1/2018 STP(U) 260 40 300 100 200 rom: S. 1st Street to: E. Washington Ave. 5 CN 1/1/2019 STP(U) 1,211 189 1,400 1,400 1/1/2019 Realign intersection, widen E. Washington Avenue to accommodate an additional lane, replace curb, gutter and sidewalk, and install a new traffic signalization system. T 0 Totals 1,731 269 2,000 400 200 1,400 17 14 S. 48th Avenue Reconstruction 03 P 1.00 P PE 1/1/2017 STP(U) 223 35 258 258 CE Yes South 48th Avenue 05 T RW 1/1/2018 STP(U) 519 81 600 600 rom: Summitview Ave. to: Nob Hill Blvd. W CN 1/1/2019 STP(U) 1,485 232 1,717 1,717 1/1/2019 5 Reconstruct and widen 48th Avenue, install curb, gutter, sidewalk, street lighting and drainage system. 0 Totals 2,227 348 2,575 0 258 600 16 15 Tieton Dr. & S. 5th Ave. 1/5 Improvements 12 P N/A P PE 1/1/2017 STP(U) 69I 11 80I 80 CE Yes Tieton Drive rom: Tieton Dr. to: 5. 5th Ave. W 5 RW CN 1/1/2018 6/1/2019 STP(U) STP(U) 104 I 865 16 I 135 120 1,000 120 1,000 5/1/2019 Remove existing traffic signal and construct a roundabout, remove and replace curb, gutter, sidewalk, street lighting and drainage T 0 Totals 1,038 162 1,200 80 1,120 16 16 E.' H' Street Extension, Ph. 1 01 P 1.10 P PE 1/1/2017 STP(U) 432 68 500 500 CE Yes E.'H'Street 08 T RW 1/1/2018 STP(U) 432 68 500 500 rom: 1st Street to: Yakima River W CN 1/1/2019 STP(U) 2,162 338 2,500 2,500 12/1/2018 Construct new roadway including water, sewer, curb, gutter, sidewalk, street lighting and storm drainage system. 5 0 Totals 3,026 474 3,500 500 500 Agency: Yakima Co. No.: 39 City No.: 1485 Co. Name: Yakima Co. MPO/RTPO: YVCOG Six Year Transportation Improvement Program From 2016 to 2021 Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015 Amend Date: Resolution No.: Functional Class Priority Number Project Identification A. PIN/Federal Aid No. B. Bridge No. c. Project Title D. Street/Road Name or Number E. Beginning MP or Road - Ending MP or Road F. Describe Work to Be Done Improvement Type(s) Status Total Length Utility Codes Project Costs in Thousands of Dollars Expenditure Schedule (Local Agency) Federal y Funded Projects Only Project Phase Phase Start Fund Source Information Federal Funding State Fund Code State Funds Local Funds Total Funds Envir. Type R/W Required Date (MM/YY) Federal Fund Code Federal Cost by Phase 1st 2nd 3rd 4th 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 17 17 Cascade Millsite Parkway North 10th Street rom: 'H' Street to: Lincoln Ave. Construct new roadway including water, sewer, curb, gutter, sidewalk, street lighting and storm drainage system. 01 06 P 1.3 P T W 5 0 PE RW CN 1/1/2016 1/1/2017 1/1/2018 STP(U) STP(U) STP(U) 350 2,746 3,837 54 429 599 404 3,175 4,436 404 3,175 4,436 CE Yes 1/1/2018 Totals 6,933 1,082 8,015 404 3,175 4,436 17 18 Yakima Downtown Future Initiatives, Phases rom: 1st Street to: 9th Street Install historic lighting, sidewalk modifications and other improvements. Exact improvement area(s) to be determined 06 12 P 0.15 P T C S PE CN 1/1/2017 4/1/2018 OTHER I (OTHER 500 5,500 I 5,500500 500 5,500 CE No Totals 6,000 500 5,500 19 19 75th Avenue Improvements 75th Avenue rom: Mead Ave. to: Nob Hill Blvd. Construct a new two-lane roadway and widen portions of existing roadway, install curb, gutter, sidewalk, street lighting and storm drainage system. 01 08 P 0.50 P W 5 T O PE RW CN 1/1/2018 1/1/2019 1/1/2020 STP(U) STP(U) STP(U) 87 173 1,038 13 27 162 100 200 1,200 100 200 1,200 CE Yes Totals 1,500 100 1,400 14 20 Washington Ave.&LongfiberRd.Intersection Washington Avenue rom: Washington Ave. to: Longfiber Rd. intersection by constructing an eastboung left -turn lane on Washington and a northbound left -turn lane on Longfiber, install or replace curb, gutter, sidewalk, 03 05 06 P N/A C T W 5 0 PE RW CN 1/1/2017 1/1/2018 1/1/2019 STP(U) STP(U) STP(U) 100 100 688 14 14 107 114 114 795 114 114 795 CE Yes 1/1/2019 Totals 888 135 1,023 114 114 795 Agency: Yakima Co. No.: 39 City No.: 1485 Co. Name: Yakima Co. MPO/RTPO: YVCOG Six Year Transportation Improvement Program From 2016 to 2021 Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015 Amend Date: Resolution No.: Functional Class Priority Number Project Identification A. PIN/Federal Aid No. B. Bridge No. c. Project Title D. Street/Road Name or Number E. Beginning MP or Road - Ending MP or Road F. Describe Work to Be Done Improvement Type(s) Status Total Length Utility Codes Project Costs in Thousands of Dollars Expenditure Schedule (Local Agency) Federal y Funded Projects Only Project Phase Phase Start Fund Source Information Federal Funding State Fund Code State Funds Local Funds Total Funds Envir. Type R/W Required Date (MM/YY) Federal Fund Code Federal Cost by Phase 1st 2nd 3rd 4th 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 14 21 E. Nob Hill Blvd. & S. 18th Street 1/S Improvements E. Nob Hill Boulevard rom: E. Nob Hill Blvd. to: S. 18th Street Widen south leg for double left turn from westbound Nob Hill, install curb, gutter, sidewalk, upgrade traffic signal system 01 04 P 0.10 C T W 5 PE RW CN 1/1/2017 1/1/2018 1/1/2019 STP(U) STP(U) STP(U) 50 50 346 8 8 54 58 58 400 58 58 400 CE Yes 1/1/2018 Totals 446 70516 58 58 400 17 22 Powerhouse Rd. & Englewood Ave. 1/5 Powerhouse Rd. rom: Powerhouse Rd. to: Englewood Ave. Realign intersection, install curb, gutter, sidewalk and safety flashing signal. Possibly construct a roundabout. 12 P N/A P T C 5 0 W PEI 1/1/2018 RW 1/1/2019 CN 1/1/2020 STP(S) STP(S) STP(S) 431 87 500 71 SOI 13 100 78 578 SOI 100 578 CE Yes 1/1/2019 Totals 630 98728 0 50 678 14 23 S. 48th Ave. & Summitview Ave. Signalization Summitview Avenue rom: Summitview Ave. to: 5. 48th Ave. Install traffic signal at the intersection of Summitview Avenue and 48th Avenue. 12 P N/A P T PE RW CN 1/1/2018 6/1/2018 1/1/2019 STP(S) STP(S) STP(S) 25 I 25 554 41 291 4 29 81 635 29 29 635 CE Yes 1/1/2019 Totals 604 89 693 58 635 14 24 W. Lincoln Ave. & MLKBIvd. Realignment W. Lincoln Avenue rom: N. 5th Ave. to: Custer St. Realign W. Lincoln Avenue, install curb, gutter, sidewalks, street lighting, drainage. 01 12 P 0.50 C T W 5 0 P G PE RW CN 1/1/2017 1/1/2018 1/1/2019 STP(E) STP(E) STP(E) 424 1,047 1,801163 1,210 I 671 491 281 2,082 491 1,210 I 2,082 CE Yes 1/1/2019 Totals 3,272 511 3,783 491 1,210 2,082 Agency: Yakima Co. No.: 39 City No.: 1485 Co. Name: Yakima Co. MPO/RTPO: YVCOG Six Year Transportation Improvement Program From 2016 to 2021 Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015 Amend Date: Resolution No.: Functional Class Priority Number Project Identification A. PIN/Federal Aid No. B. Bridge No. C. Project Title D. Street/Road Name or Number E. Beginning MP or Road - Ending MP or Road F. Describe Work to Be Done Improvement Type(s) Status Total Length T, C u m Project Costs in Thousands of Dollars Expenditure Schedule (Local Agency) Federal y Funded Projects Only Project Phase Phase Start Fund Source Information Federal Funding State Fund Code State Funds Local Funds Total Funds Envir. Type R/W Required Date (MM/YY) Federal Fund Code Federal Cost by Phase 1st 2nd 3rd 4th 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 14 25 E. Nob Hill Boulevard Reconstruction 03 P 0.85 C PE 1/1/2017 STP(U) 545 85 630 630 CE Yes E. Nob Hill Boulevard 04 T RW 1/1/2018 STP(U) 1,090 170 1,260 1,260 rom: S. 6th Street to: S. 18th Street 06 W CN 1/1/2019 STP(U) 6,532 1,020 7,552 7,552 1/1/2019 5 Reconstruct and widen roadway to 5 lanes with intersection improvements, curb, gutter, sidewalk, street lighting and drainage system 0 P G Totals 8,167 1,275 9,442 630 1,260 7,552 14 26 S. 72nd Ave. & W. Washington Ave. 1/5 12 P N/A P PE 1/1/2017 STP(C) 91 14 105 105 CE Yes 5. 72nd Avenue 06 T RW 1/1/2018 STP(C) 91 14 105 105 rom: s. 72nd Ave. to: W. Washington Ave. 0 CN 1/1/2019 STP(C) 544 86 630 630 1/1/2019 Improve intersection by installing a traffic signal system or roundabout. 5 W Totals 726 114 840 105 105 630 17 27 S. 66th Avenue Improvements 03 P 0.76 P PE 1/1/2017 STP(E) 86 14 100 100 CE Yes 66th Avenue 04 T RW 1/1/2018 STP(E) 173 27 200 200 rom: Summitview Ave. to: Scenic Dr. W CN 1/1/2019 STP(E) 1,096 164 1,260 1,260 1/1/2019 Reconstruct and widen roadway to three lanes, install curb, gutter, sidewalk, storm drainage system and utilities. 5 0 Totals 1,355 205 1,560 100 200 1,260 14 28 N. 40th Ave.&SummitviewAve.Intersection 12 P N/A P PE 1/1/2017 STP(U) 126 17 143 143 CE Yes N. 40th Avenue T RW 1/1/2018 STP(U) 130 20 150 150 rom: N. 40th Ave. to: Summitview Dr. W CN 1/1/2019 STP(U) 692 108 800 800 1/1/2019 Improve the intersection by constructing larger corner radii, lengthening the turn lanes, and upgrading the traffic signal system. 5 0 Totals 948 145 1,093 143 150 800 Agency: Yakima Co. No.: 39 City No.: 1485 Co. Name: Yakima Co. MPO/RTPO: YVCOG Six Year Transportation Improvement Program From 2016 to 2021 Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015 Amend Date: Resolution No.: Functional Class Priority Number Project Identification A. PIN/Federal Aid No. B. Bridge No. C. Project Title D. Street/Road Name or Number E. Beginning MP or Road - Ending MP or Road F. Describe Work to Be Done Improvement Type(s) Status Total Length Iv C tg •Code m Project Costs in Thousands of Dollars Expenditure Schedule (Local Agency) Federal y Funded Projects Only Project Phase Phase Start Fund Source Information Federal Funding State Fund Code State Funds Local Funds Total Funds Envir. Type R/W Required Date (MM/YY) Federal Fund Federal Cost by Phase 1st 2nd 3rd 4th 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 14 29 N. 40th Ave. & Englewood Ave. Intersection N. 40th Avenue rom: N. 40th Ave. to: Englewood Replace traffic signal poles and upgrade controller. 12 P N/A P T PE CN 1/1/2018 6/1/2018 STP(U) STP(U) 43 260 7 40 50 300 50 300 CE No Totals 303 47 350 350 14 30 N. 16th Avenue & Fruitvale Blvd. 1/5 N. 16th Avenue rom: N. 16th Ave. to: Fruitvale Blvd. Improve the intersection by constructing larger curb radii, installing ADA ramps, and upgrading the traffic signal system. 12 P N/A P T 0 5 W PE RW CN 1/1/2017 1/1/2018 1/1/2019 STP(U) STP(U) STP(U) 1261 173 400 I 18I 144 27 200 62 462 144 200 I 462 CE Yes 1/1/2019 Totals 699 107 806 144 200 462 17 31 Rudkin Road Reconstruction Rudkin Road rom: E. Viola Ave. to: Rainier PI. Reconstruct roadway, install curb, gutter, sidewalk and storm drainage. Partner with Union Gap to install additional sewer force main. 03 06 P 0.76 P T W 5 PE CN 1/1/2017 1/1/2018 STP(C) STP(C) 109 945 TPP 945 27 106 136 1,996 136 1,996 CE No Totals 1,054 133 2,132 136 1,996 0 16 32 E. Mead Avenue Reconstruction E. Mead Avenue rom: Rudkin Rd. to: Fair Ave. Partner with Union Gap to reconstruct E. Mead Avenue, install curb, gutter, sidewalk and storm drainage system. 03 06 P 0.76 P T S C G 0 PE CN 1/1/2018 1/1/2019 STP(S) STP(S) 122 1,730 TPP TPP 23 206 7 70 152 2,006 152 2,006 CE No Totals 1,852 229 77 2,158 152 2,006 Agency: Yakima Co. No.: 39 City No.: 1485 Co. Name: Yakima Co. MPO/RTPO: YVCOG Six Year Transportation Improvement Program From 2016 to 2021 Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015 Amend Date: Resolution No.: Functional Class Priority Number Project Identification A. PIN/Federal Aid No. B. Bridge No. C. Project Title D. Street/Road Name or Number E. Beginning MP or Road - Ending MP or Road F. Describe Work to Be Done Improvement Type(s) Status Total Length Iv C tg •Code m Project Costs in Thousands of Dollars Expenditure Schedule (Local Agency) Federal y Funded Projects Only Project Phase Phase Start Fund Source Information Federal Funding State Fund Code State Funds Local Funds Total Funds Envir. Type R/W Required Date (MM/YY) Federal Fund Federal Cost by Phase 1st 2nd 3rd 4th Thru 6th 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 17 33 S. 80th Avenue Improvements 04 P 1.30 P PE 1/1/2019 AIP 131 20 151 151 CE Yes S. 80th Avenue T RW 1/1/2020 AIP 382 59 441 441 rom: Tieton Drive to: Zier Road 0 CN 1/1/2021 AIP 1,667 260 1,927 1,927 1/1/2021 5 Widen roadway to three lanes, install curb, gutter, sidewalk, street lighting and storm drainage system. W C Totals 2,180 339 2,519 2,519 17 34 Englewood Avenue Improvements 05 P 1.00 P PE 1/1/2019 STP(C) 272 43 315 315 CE Yes Englewood Avenue 06 T RW 1/1/2020 STP(C) 349 55 404 404 rom: N. 40th Ave. to: N. 56th Ave. W CN 1/1/2021 STP(C) 2,352 340 2,692 2,692 1/1/2021 5 Widen roadway to three lanes, install curb, gutter, sidewalk, street lighting and storm drainage system. 0 C Totals 2,973 438 3,411 3,411 17 35 Englewood Avenue Improvements 05 P 0.50 P PE 1/1/2019 STP(U) 136 21 157 157 CE Yes Englewood Avenue 06 T RW 1/1/2020 STP(U) 173 27 200 200 rom: N. 16th Ave. to: N. 24th Ave. W CN 1/1/2021 STP(U) 1,164 182 1,346 1,346 1/1/2021 5 Widen roadway to three lanes, install curb, gutter, sidewalk, street lighting and storm drainage system. Totals 1,473 230 1,703 1,703 14 36 Nob Hill Boulevard Sidewalk Improvements 12 P 2.50 P PE 1/1/2019 STP(S) 55 8 63 63 CE Yes Nob Hill Boulevard T RW 1/1/2020 STP(S) 107 19 126 126 rom: S. 16th Ave. to: S. 6th Street 5 CN 1/1/2021 STP(S) 321 57 378 378 1/1/2021 Construct sidewalk in locations where it doesn't exist on the south side of Nob Hill W Totals 483 84 567 567 Agency: Yakima Co. No.: 39 City No.: 1485 Co. Name: Yakima Co. MPO/RTPO: YVCOG Six Year Transportation Improvement Program From 2016 to 2021 Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015 Amend Date: Resolution No.: Functional Class Priority Number Project Identification A. PIN/Federal Aid No. B. Bridge No. C. Project Title D. Street/Road Name or Number E. Beginning MP or Road - Ending MP or Road F. Describe Work to Be Done Improvement Type(s) Status Total Length Iv C u m Project Costs in Thousands of Dollars Expenditure Schedule (Local Agency) Federal y Funded Projects Only Project Phase Phase Start Fund Source Information Federal Funding State Fund Code State Funds Local Funds Total Funds Envir. Type R/W Required Date (MM/YY) Federal Fund Code Federal Cost by Phase 1st 2nd 3rd 4th Thru 6th 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 14 37 N. 34th Ave. & Fruitvale Blvd. 1/5 Improvements Fruitvale Boulevard rom: Fruitvale Blvd. to: N. 34th Ave. Improve intersection by installing a traffic signal system, curb, gutter and sidewalk. Widen leg south of Fruitvale to inlcude a left -turn lane 12 P N/A P T 0 5 W PE RW CN 1/1/2018 1/1/2019 1/1/2020 STP(U) STP(U) STP(U) 63 87 567 5 13 76 68 100 643 68 100 643 CE Yes 1/1/2020 Totals 717 94 811 68 743 17 38 Englewood Avenue Improvements Englewood Avenue rom: N. 24th Ave. to: N. 40th Ave. Reconstruct and widen roadway to three lanes, install curb, gutter, sidewalk, street lighting and storm drainage system. Install sewer and water lines. 03 05 06 P 1.00 P T W 5 0 PE RW CN 1/1/2019 1/1/2020 1/1/2021 STP(U) STP(U) STP(U) 218 327 2,980 34 51 244 252 378 3,224 252 378 3,224 CE Yes 1/1/2021 Totals 3,525 329 3,854 3,854 14 39 North/South Connector to West Valley Unknown Road rom: Ahtanum Rd. to: Summitview Ext. Corridor study to determine the best location for a north/south limited access route in West Valley. City and County joint project. 01 04 06 P 6.00 P T W 5 C G 0 PE 1/1/2018 STP(U) 1 4321 681 SOOT SOOT CE Yes Totals 432 68 500 500 14 40 Yakimareet Avenue Underpass rom: Yakima Ave. to: 18th Street Replace the bridge on E. Yakima Avenue that crosses over 18th Street. 12 P N/A P T 0 5 W PE CN 1/1/2017 1/1/2018 BRAC BRAC 240 2,288 1 5721 2,8606 300 300 2,860 CE No Totals 2,528 632 3,160 300 2,860 Agency: Yakima Co. No.: 39 City No.: 1485 Co. Name: Yakima Co. MPO/RTPO: YVCOG Six Year Transportation Improvement Program From 2016 to 2021 Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015 Amend Date: Resolution No.: Functional Class Priority Number Project Identification A. PIN/Federal Aid No. B. Bridge No. C. Project Title D. Street/Road Name or Number E. Beginning MP or Road - Ending MP or Road F. Describe Work to Be Done Improvement Type(s) Status Total Length T, C u m Project Costs in Thousands of Dollars Expenditure Schedule (Local Agency) Federal y Funded Projects Only Project Phase Phase Start Fund Source Information Federal Funding State Fund Code State Funds Local Funds Total Funds Envir. Type R/W Required Date (MM/YY) Federal Fund Code Federal Cost by Phase 1st 2nd 3rd 4th Thru 6th 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 17 41 88th Avenue Improvements 88th Avenue rom: Tieton Dr. to: SummitviewAve. Construct curb, gutter, sidewalk and storm drainage system on the east side of 88th Avenue. 06 12 P 0.48 P T C G PE RW CN 1/1/2018 1/1/2019 6/1/2019 STP(U) STP(U) STP(U) 43 52 285 7 8 45 50 60 330 50 60 330 CE Yes 6/1/2019 Totals 380 60 440 50 390 17 42 64th Avenue Improvements 64th Avenue rom: Washington Ave. to: Nob Hill Blvd. Widen roadway to three lanes, install curb, gutter, sidewalk, street lighting and storm drainage system. 03 04 06 P 1.00 P T W C G 0 PE CN 1/1/2018 1/1/2019 STP(U) STP(U) 2001 1,600 I 321 2321 249 1,849 2001 1,849 CE No Totals 1,800 281 2,081 200 1,849 14 43 North 1st Street N. Street M KtBlvdRevitaliz to: 'N' Improve North 1st Street by rehabilitating the pavement and lane markings, removing on -street parking, enhancing street and pedestrian lighting, constructing median islands and installing various pedestrian and decorative elements. 062 P 0 98 P G RW 6 CN 11/1/2017 TIGER I 8,0001 I 100 I 8,000 100 8,000 CE YesC 1/1/2017 Totals 8,100 0 8,100 100 8,000 19 44 Northside Alley Paver Alleys between Folsom Ave. and Fruitvale Blvd. rom: 16th Avenue to: 6th Avenue Improve the air quality throughout this section of the City by paving gravel alleys. 07 5 3.5 P T C 0 CN 1/1/2015 CMAQ I 3531 571 4101 410 I I CE No Totals 353 57 410 410 Agency: Yakima Co. No.: 39 City No.: 1485 Co. Name: Yakima Co. MPO/RTPO: YVCOG Six Year Transportation Improvement Program From 2016 to 2021 Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015 Amend Date: Resolution No.: Functional Class Priority Number Project Identification A. PIN/Federal Aid No. B. Bridge No. C. Project Title D. Street/Road Name or Number E. Beginning MP or Road - Ending MP or Road F. Describe Work to Be Done Improvement Type(s) Status Total Length v C u •Code m Project Costs in Thousands of Dollars Expenditure Schedule (Local Agency) Federal y Funded Projects Only Project Phase Phase Start Fund Source Information Federal Funding State Fund Code State Funds Local Funds Total Funds Envir. Type R/W Required Date (MM/YY) Federal Fund Federal Cost by Phase 1st 2nd 3rd 4th Thru 6th 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 17 45 S. 80th Avenue Bridge S. 80th Avenue rom: Wide Hollow Rd. to: Plath Ave. Replace existing two-lane bridge over Wide Hollow Creek with three -lane bridge. The City's involvement is only to pass through of an Ecology grant in conjunction with the County's flood plain management project. 09 5 0.05 P T 0 PE CN 1/1/2016 1/1/2017 DOE DOE 25 75 0 0 25 75 25 75 CE Totals 0 100 25 75 17 46 Wide Hollow Road Wide Hollow Road Bridge rom: 89th Avenue to: 88th Avenue Replace existing two-lane bridge over Wide Hollow Creek with three -lane bridge. The City's involvement is only to pass through of an Ecology grant in conjunction with the County's flood plain management project. 9 5 0.05 P T 0 PE CN 1/1/2016 1/1/2017DOE I I DOE 7525 1 I 725I 25 75 I CE No Totals 100 25 16 47 Lincoln Avenue Corridor Safety Improvements Lincoln Avenue rom: N. 32nd Ave. to: N. 5th Ave. Improve safety by installing larger signal lenses, installing ADA compliant ramps, repairing damaged sidewalk, installing new sidewalk, installing overhead school flashers, etc. 07 5 N/A P T 0 CN 1/1/2016 HSIP 3001 0 300 300 I CE Yes 1/1/2016 Totals 0 300 300 14 48 16th Avenue Corridor Improvement 16th Avenue rom: SR 12 to: Washington Ave. Study to determine strategies for improving the 16th Avenue corridor 04 P 3.50 P T W C G n PE 1/1/2018 STP(U) 1201 171 1371 1371 Totals 120 17 137 137 Agency: Yakima Co. No.: 39 City No.: 1485 Co. Name: Yakima Co. MPO/RTPO: YVCOG Six Year Transportation Improvement Program From 2016 to 2021 Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015 Amend Date: Resolution No.: Functional Class Priority Number Project Identification A. PIN/Federal Aid No. B. Bridge No. C. Project Title D. Street/Road Name or Number E. Beginning MP or Road - Ending MP or Road F. Describe Work to Be Done Improvement Type(s) Status Total Length Utility Codes Project Costs in Thousands of Dollars Expenditure Schedule (Local Agency) Federal y Funded Projects Only Project Phase Phase Start Fund Source Information Federal Funding State Fund Code State Funds Local Funds Total Funds Envir. Type R/W Required Date (MM/YY) Federal Fund Code Federal Cost by Phase 1st 2nd 3rd 4th Thru 6th 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 14 49 40th Avenue Corridor Improvements 40th Avenue rom: SR 12 to: Washington Ave. Study to determine strategies for improving the 40th Avenue corridor. 04 P 3.20 P T W C G 0 5 PE 1/1/2018 STP(U) 120 17 137 137 Totals 17 137 137 14 50 Nob Hill Boulevard Corridor Improvements Nob Hill Boulevard rom: 1-82 to: 16th Ave. Study to determine strategies for improving the Nob Hill Boulevard corridor. 03 04 P 2.70 P T 0 5 W C G PE 1/1/2018 STP(U) 1201 171 1371 1371 Totals 120 17 137 137 14 51 S. 1st Street/Main Street Corridor Improvements S. 1st Street/Main Street rom: Nob Hill Blvd. to: Barker Mill Bridge Joint project with Union Gap. Stucy to determine strategies for improving the 1st Street/Main Street corridor. 01 P 2.00 P T 0 5 W C PE 1/1/2018 STP(U) 1201 171 1371 1371 Totals 120 17 137 137 16 52 E.' H' Street Extension, Ph. 2 E.'H'Street rom: 10th Street to: 1-82 Construct new roadway including water, sewer, curb, gutter, sidewalk, street lighting and storm drainage system. 01 08 P 0.55 P T W 5 0 PE RW CN 1/1/2016 1/1/2017 1/1/2018 STP(U) STP(U) STP(U) 432 432 2,162 68 68 338 500 500 2,500 500 500 2,500 CE Yes 1/1/2018 474 3,500 500 500 2,500 0 9. Appendices A. Six Year Form Instructions Heading Agency County Number City Number MPO/RTPO Hearing Date Adoption Date Resolution Number Amendment Date Column Number Enter name of the sponsoring agency. Enter the OFM assigned number (see LAG Appendix 21.44). Enter the OFM assigned number (see LAG Appendix 21.45). Enter the name of the associated MPO (if located within urbanized area) or RTPO (if located in a rural area). Enter the date of the public hearing. Enter the date this program was adopted by council or commission. Enter Legislative Authority resolution number (if applicable.) Enter the date this program was amended by council or commission. 1. Functional Classification. Enter the appropriate 2 -digit code denoting the Federal Functional Classification. (Note: The Federal Functional Classification must be approved by FHWA.) Description 00- No Classification Rural (Under 5000 pop.) 01 - Interstate 02 - Principal Arterials 06 - Minor Arterials 07 - Major Collector 08 - Minor Collector 09 - Local Access Urban (Over 5000 pop.) 11- Interstate 12- Freeways & Expressways 14- Other Principal Arterials 16- Minor Arterial 17- Collector 19- Local Access 1. Priority Numbers. Enter local agency number identifying agency project priority (optional). 2. Project Identification. Enter (a) Federal Aid Number if previously assigned; (b) Bridge Number; (c) Project Title; (d) Street/Road Name or Number/Federal Route Number; (e) Beginning and Ending Termini (mile post or street names); and (f) Describe the Work to be Completed. 3. Improvement Type Codes. Enter the appropriate federal code number. Description 07 - Resurfacing 08 - New Bridge Construction 09- Bridge Replacement 01- New construction on new alignment 02- Relocation Project 03- Reconstruction 04- Major Widening 05- Minor Widening 06- Other Enhancements 10 - Bridge Rehabilitation 11 - Minor Bridge Rehabilitation 12 - Safety/Traffic Operation/TSM 13 - Environmentally Related 25 14 - Bridge Program -Special 21 - Transit Capital Project 22- Transit Operational 23 - Transit Planning 24 - Transit Training/Admin. 31- Non Capital Improvement 32 - Non Motor Vehicle Project 5. Funding Status. Enter the funding status for the entire project which describes the current status. S - Project is selected by the appropriate selection body and funding has been secured by the lead agency. P - Project is subject to selection by an agency other than the lead and is listed for planning purposes. (Funding has not been determined.) 6. Total Length. Enter project length to the nearest hundredth (or code "00" if not applicable). 7. Utility Code(s). Enter the appropriate code letter(s) for the utilities that would need to be relocated or are impacted by the construction project. C - Cable TV O - Other S - Sewer (other than agency -owned) W - Water G - Gas P - Power T - Telephone 8. Project Phase. Select the appropriate phase code of the project. PE - Preliminary Engineering only (or Planning) RW - Right of Way or land acquisition only (or equipment purchase) CN - Construction only (or transit operating) ALL - All Phases: from Preliminary Engineering through Construction 9. Phase Start Date. Enter the month/day/year in MM/DD/YY format that the selected phase of the project is actually expected to start. 10. Federal Fund Code. Enter the Federal Fund code from the table. BIA BR CDBG CMAQ DEMO Discretionary DOD IC IM NHS - Bureau of Indian Affairs - Bridge Replacement or Rehab. - Community Development Block Grant (HUD) - Congestion Mitigation Air Quality - ISTEA Demo Project (Selected) - Ferry Boat Discretionary, Public Lands Highways, or Scenic Byways - Dept. of Defense - Interstate Construction - Interstate Maintenance - National Highway System FTA Discretionary for Capital Expenditures 5307 - FTA Urban Areas 5309(Bus)- Bus 5309(FG) - Fixed Guideways 5309(NS) - New Starts 5310 - FTA Elderly/Disabled 5311 - FTA Rural Areas REV - Rural Economic Vitality Program STP(C) - STP Statewide Competitive Program STP(E) - STP Transportation Enhancements STP(S) - STP Safety Including Hazard and RR STP(R) - STP Rural Regionally Selected STP(U) - STP Urban Regionally Selected STP - WSDOT use only 11. Federal Funds. Enter the total federal cost (in thousands) of the phase regardless of when the funds will be spent. 12. State Fund Code. Enter the appropriate code for any of the listed state funds to be used on this project. 26 CAPP - County Arterial Preservation Program PWTF - Public Works Trust CHAP - City Hardship Assistance Program RAP - Rural Arterial Program TPP - Transportation Partnershis Program SCP - Small City Program AIP - Arterial Improvement Program WSDOT - WSDOT funding PSMP - Pedestrian Safety & Mobility Program OTHER - All other unidentified state funding PTST - Public Transportation Systems Progra 13. State Funds. Enter all funds from the State Agencies (in thousands) of the phase regardless of when the funds will be spent. 14. Local Funds. Enter all the funds from Local Agencies (in thousands) of the phase regardless of when the funds will be spent. 15. Total Funds. Enter the sum of columns 10, 12, and 14. (Auto -calculation in the "STIP Too" program.) 16-19. Expenditure Schedule - (1st, 2nd, 3rd, 4th thru 6th years). Enter the estimated expenditures (in thousands) of dollars by year. (This data is for Local Agency use.) 20. Environmental Data Type. Enter the type of environmental assessment that will be required for this project. (This is "required" for Federally funded projects, but may be filled in for state or locally funded projects.) EIS - Environmental Impact Statement EA - Environmental Assessment CE - Categorical Exclusion 21. R/W Certification. Click Y if Right of Way acquisition is required. If yes, Enter R/W Certification Date, if known. (This is "required" for Federally funded projects only.) 27