HomeMy WebLinkAbout04/05/2022 16.B. Yakima River Basin Integrated Water Resource Management Plan February 2022 Quarterly Project Activity Update 4L25:
1114'+
7—rei
•6
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 16.B.
For Meeting of:April 5, 2022
ITEM TITLE: Yakima River Basin Integrated Water Resource Management Plan
February 2022 Quarterly Project Activity Update
SUBMITTED BY: David Brown,Assistant Director of Public Works 509-575-6204
Scott Schafer, Director of Public Works
SUMMARY EXPLANATION:
The February 2022 Quarterly Project Activity Update provides information on technical aspects
of ongoing planning studies for the Yakima River Basin Integrated Water Resource Management
Plan (Integrated Plan).
ITEM BUDGETED: NA
STRATEGIC PRIORITY: Partnership Development
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
RECOMMENDATION:
I nformation only
ATTACHMENTS:
Description Upload Date Type
ID February 2022 Yakima Riper Basin Quarterly Report 3/17/2022 Backup Material
Yakima River Basin Integrated Water Resource Management Plan
YBIP Project Activity Update
February 2022
Purpose: Update on ongoing technical planning studies and project implementation
activities for the Yakima River Basin Integrated Water Resource Management Plan
(Integrated Plan)
Fish Passage Element
Cle Elum Darn Fish Passage Facilities and Reintroduction Project
The juvenile fish passage facility will use an innovative helix design to transport juvenile fish
downstream. It will allow fish to leave the reservoir as the water surface fluctuates over the top 63 feet
in elevation. This will provide downstream passage from April 1 through the beginning of June in most
years. The upstream adult fish passage facility will be a trap-and-haul facility where fish are trapped at
the base of the spillway, loaded into a truck, and then hauled for release into Cle Elum Reservoir or to
upstream tributaries.
Construction Update: The access road and spillway bridge and the secant pile and vault contracts are
complete. Construction for the tunnel contract was completed in March 2021. Reclamation anticipates
close-out of the tunnel contract in 2022. The last downstream section of the tunnel will be constructed as
part of the Adult Collection Facility(ACF). We expect to award the ACF contract in 2022 and it will be
the last construction contract needed to complete the Cle Elum Dam Fish Passage project.
The Intake, Gate, and Helix(IGH) contractor mobilized in April 2019. After completing intake six in
the fall of 2020, the contractor continued intake construction in 2021 and completed intakes 5 and 4 last
fall. Also installed last fall,were the crest gates for intake six and five. In 2020, the contractor placed
and sealed in concrete the majority of the precast conduits that provide the connections from the
reservoir intakes to the secant vault leaving 40 feet for the final connection into the Secant. The final 40
feet of conduit boxes will be placed following the penetration of the secant vault at each level. Last fall
and into January 2022,the contractor tunneled through the last 40 feet to the secant piles, sawed through
and removed the cut secant pile sections, and placed the final conduits at level six and five (reminder
that work needs completed from the lowest level up). The contractor has also been working inside the
Secant completing the helix/gate chamber separation wall and the access structure walls. The access
structure will house an elevator and stair system. More recent work inside the secant has included the
installation of two guard gates at level six and five. These gates will control water flow between the
intake conduits and the helix system. Videos: https://vimeo.com/508632343 (winter 2021) &
https://vimeo.com/579619438 (summer 2021)
Sockeye Study Update: In 2018, Reclamation and the Yakama Nation worked with the U.S. Geological
Survey to conduct an adult sockeye tracking test to understand their migration between Roza and Cle
Elum dams. The study found that 20 of the 20 tagged fish migrated successfully to the base of Cle Elum
Dam. In 2019,these same partners, along with Washington Department of Fish and Wildlife (WDFW),
began a sockeye tracking study in the lower Yakima River. The study reach runs from the mouth of the
Yakima River up to the Roza Dam and is evaluating potential passage issues at diversion dams,possible
false attraction,microclimate use, and Columbia River Stranding. We expect to conduct this study over
three years depending on the study findings.
WASHINGTON STATE
- BUREAU OF - DEPARTMENT OF
1114 IIIRECLAMATIONE C O L O G Y
3
Results from the first year of the study (2019)found very low migration success rates for tagged
Sockeye primarily due to high river temperatures. Findings from 2020 continued to show that high river
temperatures limit access upstream for much of the summer, Sockeye migration can be slowed down at
diversion darns, and false attraction and predation may also be impacting upstream migration. The final
report for 2020's study is complete: Evaluation of factors affecting migration success of adult sockeye
salmon(Oncorhynchus nerka) in the Yakima River, Washington, 2020 (usgs.gov). The study for 2021
was postponed due to extreme air and river temperatures in the lower Yakima River. Reclamation,
Yakama Nation, WDFW, Ecology and other partners plan to resume this study this summer in 2022.
Box Canyon Creek Fish Passage
In 2018, WDFW, with input from Reclamation, Ecology, and other passage restoration experts, has
completed a conceptual design for the Box Canyon Creek Fish Passage Enhancement Project. Following
the completion of the conceptual design, Reclamation contracted with HDR to prepare a 60% project
design. HDR completed the 60%design and cost estimate late Fall 2021.
Clear Creek Darn Fish Passage
Reclamation and Ecology completed an appraisal level design for fish passage in September 2018. The
design consists of a traditional pool-and-weir-style fishway with a steel bulkhead at the upstream end
that will draw cool water from deeper in the reservoir. Situated along the left abutment of the dam,fish
would enter the fishway in the stilling basin and exit in the reservoir pool. The bulkhead will be deep
enough to maintain suitable water temperature in the fishway for Bull Trout.
Reclamation is coordinating with Ecology,U.S. Fish and Wildlife Service (USFWS), Yakama Nation,
WDFW, USFS, NMFS, and others to complete the final ladder design. The partners met with basin
biologists to define the range of species targeted for passage and provide input for designers regarding
ladder geometry. Reclamation conducted geotechnical investigations in October 2020 and completed
30% designs on November 2, 2020. Comments from the Yakima Storage Dams Fish Passage Core Team
were reviewed on January 21, 2021 and have been sent to the technical workgroup for review and
comment. A Value Engineering Study was completed the week of February 8, 2021. The 60%design
was completed in June 2021. Ninety percent design was completed and provided for comment in
December 2021. The 90%design comments were discussed at a technical meeting on February 10,
2022. Final design is anticipated in April 2022.
Until passage improvements are accomplished, USFWS, Reclamation, and WDFW will continue
capturing Bull Trout from below Clear Creek Dam and transporting genetically identified North Fork
Tieton River fish around the dam so they can reach spawning habitat in the North Fork Tieton
River. Fish capture and transport has been conducted 2016 through 2021. To date, 107 adult Bull Trout
have been transported above the dam.
Structural and Operational Changes Element
Cle Elum Pool Raise
The purpose of the Cle Elum Pool Raise Project is to increase the Cle Elum reservoir's capacity for
improved aquatic resources for fish habitat, rearing, and migration in the Cle Elum and upper Yakima
River,thereby fulfilling the intent of the congressional authorization, Title XII of Public Law 103-434.
Completed: Radial Gate construction was completed in April 2017. Reclamation completed
modifications to three saddle dikes as of 2018. The USFS Cle Elum River Campground recreation area
2
4
was completed in November 2017. The USFS Speelyi Day Use Area recreation area was completed in
May 2019. Shoreline protection along Salmon La Sac Road was completed in 2021.
Construction Update: Reclamation and Ecology are currently implementing shoreline protection actions
for private and public lands and facilities. Construction of shoreline protection at Wish Poosh
Campground& Boat Launch began in April 2021 and will be completed by the end of May 2022. The
Sandelin Lane shoreline protection area contract was awarded in July 2021. Remaining shoreline
protection will be implemented as funding becomes available. Landowners and the public will be
updated periodically on the project via mail and website postings during project implementation.
Reclamation and Ecology continue working with landowners along the shoreline to acquire easements as
appropriate for the project and released a video to inform our partners and public on the project. Video:
https://youtu.be/9G3-CgBMQsE.
In addition, Reclamation sends out a quarterly update postcard to landowners to continue outreach
around Cle Elum Reservoir.
Chandler Pumping Plant Electrification
Kennewick Irrigation District(KID) continues to evaluate an electrical pumping plant at Chandler. As of
March 2022, Reclamation continues to work with KID. KID is preparing updated design drawings and
operational diversion plans for review of Chandler Electrical Pumping Plant by Reclamation.
Reclamation has extended an existing Memorandum of Agreement through 2022 with KID for this
work. Reclamation and KID have regular meetings to address KID water supply issues. Reclamation is
part of the Lower River Leadership team along with Ecology, Yakama Nation, and KID to discuss a
multitude of options to meet lower river flow needs for KID. An electrical pumping plant may still be
considered by KID, however, recently KID has been reviewing other options which may include an
onsite storage reservoir.
Lower Yakima River Smolt Survival Study
The survival of juvenile salmon(smolts) migrating to the ocean can influence the abundance of
returning adults and the availability of fish for harvest years later. Smolt survival is affected by passage
at darns, predators, and environmental conditions such as river flow and water quality. Factors affecting
smolt survival are being identified by the Lower Yakima River Smolt Survival Study with the goal of
developing recommendations for improvement projects. The study area includes the mainstem Yakima
River from the City of Yakima to the Columbia River confluence. Project funding comes from Yakama
Nation (YN), Reclamation, irrigation districts, Ecology, and the US Geological Survey(USGS), with
YN and USGS leading the field work and data analysis. During each year of the study(2018-2022)
about 1,000 juvenile salmon and steelhead are collected,tagged, and released in the Yakima River to
monitor their behavior and survival as they migrated downstream. Monitoring stations are set up at
major diversion darns and key river reaches. Data on predator populations such as pelicans and bass,
river flows, and water temperatures are also being collected so they can be related to fish survival.
Preliminary results over three years (2018-2020) indicated smolt survival was highest in early spring and
lowest in June when the Yakima River warmed, flows declined, and predator abundance was high.
In response to the study findings, the Sunnyside Division Board of Control (SBDOC) initiated a project
to install a(1)fish and debris guidance boom and(2) sluice gate modification at Sunnyside Dam. The
project is intended to reduce the numbers of fish diverted into Sunnyside canal without affecting
irrigation. The guidance boom was manufactured by Pacific Netting Products and installed by SVID in
March 2021. The floating guidance boom was made from HDPE pipe and marine-grade hardware which
3
5
suspends a 4-foot deep stainless-steel fish screen below the water surface. Data collected in 2021
showed that fewer fish were diverted into the Sunnyside Canal with the guidance boom in place, thus
reducing smolt mortality associated with the diversion. Sluice gate improvements installed in October
2021 should further reduce smolt mortality. Survival at the facility will again be monitored in 2022.
Surface Water Storage Element
Kachess Drought Relief Pumping Plant(KDRPP)
The KDRPP is proposed to access 200,000 (out of 585,000) acre-feet of inactive storage in the Kachess
Reservoir that is below the current outlet works for use in severe drought.
On April 26, 2019, Reclamation signed the Record ofDecision (ROD), which does not approve
implementation of any alternatives but carries forward Alternative 4 - KDRPP Floating Pumping Plant
(FPP) for further analysis. Consistent with this decision, the remaining alternatives in the FEIS,
including the Kachess to Keechelus Conveyance, are unlikely to be carried forward. Reclamation and
Ecology will use a phased approach for further site-specific analysis in a Tier 2 NEPA process to narrow
the range of feasible alternatives for KDRPP.
The Project Proponent,the Roza Irrigation District, in coordination with Reclamation and Ecology, is
currently developing a new Proposed Action and clarifying the FPP alternative for the KDRPP Tier 2
NEPA process. This final and complete Proposed Action and Reclamation's subsequent Notice of Intent
(NOI)for the Tier 2 EIS are currently projected for 2022. Roza and possibly other pro-ratable waters
users (KRD, Wapato Irrigation Project(WIP) and KID)would fund, design, construct, and operate the
KDRPP.
Wymer Reservoir
Consideration of site requirements is ongoing.
Bumping Reservoir Enlargement Project
Consideration of site requirements is ongoing.
Groundwater Storage Element
Groundwater Storage—Basin-wide Analysis
The Groundwater Storage Subcommittee is progressing forward with identifying groundwater storage
opportunities in the basin. In the upper basin, KRD continues work on high-priority MAR sites and City
of Ellensburg completed an ASR pre-feasibility study. In the lower basin,the Yakama Nation is
advancing MAR projects on the Toppenish Fan and CWU is studying the hydrogeology of the Badger-
Coulee area.
The Groundwater Storage Subcommittee discussed projects for the 2021-2023 biennium and made
funding recommendations in August/September. Projects recommended for funding are:
• City of Moxee ASR Feasibility Study,
• CWU Evaluation of MAR in Basalts of the Rattle Snake Ridge Area,
• CWU Evapotranspiration and Floodplain Aquifer Storage Capacity Study,
• City of Ellensburg ASR Feasibility Study,
• KRD Taneum Creek MAR Pilot Testing,
4
6
• KRD Continue and Expand On-going Monitoring Efforts at High Priority MAR Sites,
• KRD Basalt ASR Assessment, and
• KRD Central Data Repository/GIS Clearinghouse.
Aquifer Storage and Recovery(ASR)
The City of Yakima is planning full build-out for its permitted ASR program and intends to drill two
ASR devoted wells:the first well is estimated for 2022-2023, and the second is estimated for 2025-2026.
The City has requested funds for future projects with Reclamation.
Habitat Protection and Enhancement Element
Targeted Watershed Protection and Enhancement
The Watershed Lands Conservation Subcommittee finalized its new 10-year lands plan(the Phase 2
Plan). The plan describes the Subcommittee's focus elements —acquisitions, designations, and forest
health and management- for continued implementation of the Targeted Watershed Protection and
Enhancement component of the Habitat Element of the Integrated Plan.
Subgroups of the Lands Subcommittee are working on first steps on the acquisitions and designations
elements of the Phase 2 Plan.
Mainstem Floodplain and Tributaries Fish Habitat Enhancement Program
The Habitat Subcommittee has developed its 2021-2023 biennial budget proposal for Ecology under the
Habitat Element. The Subcommittee will continuously monitor implementation status of the projects.
The Subcommittee has focused the next biennial budget formulation on lower river priority actions
related to high juvenile salmon and steelhead mortality as well as lower river temperature barriers to
adult salmon migration. Lower river projects funded include ongoing support for Bateman Island
Causeway Removal and Thermal Refuge and Aquifer Recharge studies, as well as several habitat
restoration projects on the Yakama Nation reservation in the Wapato Reach and Toppenish Creek. The
Subcommittee recognizes the criticality of resolving lower river passage issues if upper-watershed
habitat protection and enhancement projects are to be successful in the long-term.
The Subcommittee allocated funds to the South Fork Tieton Bridge restoration project, which will be
cost shared with the bull trout working group and Reclamation. Several restoration and stewardship
projects were funding in the upper Yakima River watersheds as well.
The Subcommittee reviewed and approved the funding proposal from the bull trout working group. This
project list included matching funds for the South Fork Tieton Bridge replacement project. It continues
providing funds for ongoing projects including Gold Creek and Kachess Habitat restoration, Yakama
Nation Bull Trout restoration and monitoring, the bull trout task force, bull trout working group, and the
WDFW bull trout senior biologist.
The Subcommittee is closely monitoring the SBDOC fish boom and sluice gate project. The project is a
key milestone for lower river habitat enhancements, and the Habitat Subcommittee is interested in how
implementation of the project will affect smolt outmigration season in 2021. The Habitat Subcommittee
will use the data gathered from the study in 2021 to further refine its lower river strategy.
5
7
The Subcommittee is updating it's 10-year strategic plan throughout the fall and winter of 2021.
Subcommittee members are discussing proposed capital plans from project sponsors for priority reaches
to determine funding strategies that stretch across several biennia.
The Subcommittee has reviewed the projects proposed for the Integrated Plan as part of the adaptive
management process and will provide feedback to the Executive Committee.
Enhanced Water Conservation Element
Upon passage of the Dingell Act in March 2019, the Reclamation, Ecology, Yakama Nation and
YRBWEP Workgroup Partners have a goal to conserve 85,000 acre-feet of water by 2029. The overall
conservation savings goal upon full Integrated Plan implementation is 170,000 acre-feet. Reclamation
and Ecology are conducting an inventory of water conservation accomplishments associated with the
Integrated Plan. Projects that count towards this goal must adhere to three parameters:
• Begin in 2013 or later
• Be an agricultural or municipal improvement project resulting in conserved water, and
• Not be part of the Title XII, Section 1203 Basin Conservation Plan
To date, there have been 123 conservation projects implemented. Approximately $119 million invested
has resulted in approximately 56,000 acre-feet conserved ($2,100 per acre-foot). A technical
memorandum explaining the history, accounting, and future framework planning for the Enhanced
Water Conservation element projects was released to the Water Use Subcommittee in April 2021.
Within this memorandum, Reclamation and Ecology have developed a project prioritization proposal for
achieving the remaining portion of the initial development phase goal.
The Water Use Subcommittee will begin planning for the 2023 —2025 funding request in spring 2022.
Market Reallocation Element
The Kittitas Reclamation District (KRD)and Trout Unlimited (TU) continued water market research and
development as part of the Market Reallocation element of YBIP. Ongoing research in the last quarter
focused on evaluating changes to water supply, data preprocessing for smart market modeling, and
instream flow analysis. Additionally,the project team developed a scope of work and preliminary
structure for a Water Transfer Working Group transfers database to capture past market activity.
Outreach continued with COVID-19 restrictions in place and a revised outreach approach was
developed.
More information about the project can be found at https://www.yakimabasinwatermarketing.org/
Proposed Projects for Consideration
During implementation of the Integrated Plan, an adaptive approach is being used periodically to assess
progress towards meeting the identified instream flow objectives,the 70 percent proratable supply goal
for irrigation, and goals for other out-of-stream needs. The need for additional water supply
enhancements would depend on the effectiveness of projects that are implemented as part of the
Integrated Plan, how the Yakima basin economy develops over time, and the timing of and manner in
which climate changes affect water supply availability. From time-to-time, new projects may be
identified(and proposed)for consideration under the Integrated Plan. Reclamation, Ecology, Yakama
Nation, and the Executive Committee have developed a formalized process to consider new projects. In
6
8
December 2021, Reclamation, Ecology, Yakama Nation agreed to include YTID's proposal for change in
point of diversion to Wapatox and removal of the Tieton Diversion Dam as part of the Integrated Plan. In
addition, Upper Yakima System Storage was also included as part of the Integrated Plan.
Contacts for Information on the Integrated Plan:
Wendy Christensen, U.S. Department of the Interior, Bureau of Reclamation, Columbia-Cascades Area
Office, (509) 573-8050
Thomas Tebb, Washington State Department of Ecology, Office of Columbia River, (509) 574-3989
Project website: http://www.usbr.gov/pn/programs/yrbwep/index.html
7