HomeMy WebLinkAbout09/01/2009 11 Gardner Park Well Final Contract Payment - City Project No. WA2132 BUSINESS OF THE CITY COUNCIL
0 , YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 4 J 1
For Meeting of 9/1/09
ITEM TITLE: Final Contract Payment for Gardner Park Well — City Project No.: WA2132
SUBMITTED BY: Dave Brown - Water /Irrigation Division Manager
CONTACT PERSON /TELEPHONE: Dave Brown — 509 - 576 -6480
SUMMARY EXPLANATION: .
This project was to install a municipal drinking water supply well. The well is located in the
northwest corner of Gardner Park at Cornell Ave. and W. Pierce. The well was completed to
about 900 feet below ground surface. Test pumping concluded the well will produce about 3,000
gallons per minute, well within design.
Final inspection for this project was made and the recommendation is that the project be
accepted.
Construction of the pumping facility will continue in 2010 under separate design and contract.
This Council action is to accept the project and approve the final construction costs.
•
Contractor: Layne Christensen Company
Contract Award: 12/1/08
Contract Cost: $1,420,666.00
Final Contract Cost: $1,382,847.40
Amt. This Payment: -0-
The above total contract cost is for construction of the well only and does not include
engineering, pumping facility and other costs.
Resolution Ordinance X Other (Specify) Final Contract Payment
Contract _ Mail to (name and address):
Funding Source Water Improvement Fund - 477
APPROVED FOR SUBMITTAL: J City Manager
STAFF RECOMMENDATION: Accept the project and approve final estimate.
COUNCIL ACTION:
•
0 Gardner Park Well Project #2132
Final 8/14/2009
$1,278,047.50 Subtotal, Work to Date
$104,799.90 Sales Tax 8.2%
$1,382,847.40 Total
$69,142.37 Less 5% Retainage
$1,313,705.03 Less Amounts Previously Paid