HomeMy WebLinkAbout03/01/2022 08. 2021 3rd & 4th Quarter Capital Improvement Projects Report 1 • Iv41 rr 11 i i�O enc u nrry 1 BUSINESS OF THE CITY COUNCIL YAKIMA, WASHINGTON AGENDA STATEMENT Item No. 8. For Meeting of: March 1, 2022 ITEM TITLE: 2021 3rd & 4th Quarter Capital Improvement Projects Report SUBMITTED BY: Scott Schafer, Director of Public Works Bill Preston, City Engineer- (509) 576-6754 SUMMARY EXPLANATION: Attached is the City of Yakima Engineering Division's 3rd and 4th Quarter 2021 Capital Improvement Projects presentation. The presentation highlights 3rd and 4th quarter 2021 projects, challenges still facing Engineering projects, and a quick look ahead at future projects. ITEM BUDGETED: NA STRATEGIC PRIORITY: Public Trust and Accountability APPROVED FOR SUBMITTAL BY THE CITY MANAGER RECOMMENDATION: Accept Presentation ATTACHMENTS: Description Upload Date Type 0 2/17/2022 Corer Memo CAPITAL IMPROVEMENT PROJEC ', 3rd and 4111 Quarter, 2021 Public Works Director: Scott Schafer City Engineer: Bill Preston 3rd & 4th Quarter 2021 Challenges What the future holds Completed Spring Creek Road Phase 2 - Wetland Mitigation /////;///// .. lam' .r 4.-+ n'Y,t �. j I 3alt: "fs r. Project Costs: $463,000 -' ,; !, �, • ' ; " �� Funding: REET P. ��,; ." .d!...,aii. is' :., i"1C? ' r, Completed I Northside Alley Paving ' , ��" , .,...oct. \.__ .. --i i - -,4., - i ik-, ., , ....... * ...olisi _ _ • e ■ . ki A I' - . '. i . ./.://///:/// r .r Imo`.: ,,{L; ._ ... - Project Costs: $530,000 Funding: Congestion Mitigation Air Quality (CMAQ) Completed North 1st Street Revitalization - Phase 2 `J' Street to `N' Street , 1 e . ifi'' -4Continuous or intermittent ,,„ +1 A ° tap lontinuous or intermittent planting strip #� Accent plants Airanting strip lir J. Cf i fly ! rr iS 1 IL 1 : -=- l 10 13' S' 11' 4, 11' / 11' 71' / t 1' f 5' / 13' Sidewalk Bike Lane Lane Median Lane Lane Bike Sidewalk 4' lane lane q' I Landscape/ •5.curb •5.curb Landscape) Amenity zone Amenity zone 100' 41'. Right of Way PROJECT COST: $2,586,000 FUNDING: TBD, STORMWATER, AND WATER Completed North 1st Street Revitalization - Phase 2 `J' Street to 'N' Street - �P /!* , - "- //A/ ., iql-Pt. ''‘ J R [r, om,n ' i fir. ' 1v t w.d = `!i� .... 'r f Fa :d:• =.fir I.: 6; \' J.. t n .,ti K fr 1 ....z_.._,..,-t.__ ....rol ri m i I.„,..,- if t. oh 0, in if 0 . ' J 1Pa '1 #' '� MEMEL f L _ .!..1c,.. i I' visor _ 2,/ ,.., ,---.. _\ i M. . / ,-3 ei. dig-T— I < • -, _ s \ - \ �, tit , r, : i, �'\ 8. I Under Construction Spring Creek Road Phase 2 - Soccer Complex Access ••7r' � 5. ICvo• MO .. NG #lrc �w 'fir � fir ' � � f. • 4,s ±fir• �a fir.-., . • `.. 4,N 4 t � • r !!' , I SOZO CAMPU', EXISTING j I PHASE 2 SOZO CAMPUS 1 R..t -A. t • EXPANSION PHASE 1 11:I";' 1 1 ;tom„ - _ _ y^=w, l r _fii . SPRt4G CREEK RQAD i • /t/I/ fi r : .` rr!+ a �i•! •'yY,+.' r11, a r.. ,' y Project Costs: $2,678,000 SIED Funds: $2,000,000 Signal Grant: $ 650,000 - Washington State Legislative Budget Under Construction Spring Creek Road Phase 2 - Soccer Complex Access ...t. \ . i_.,• _.. • f ••-.-----_,..\ • r',.,:,,.. • , -\ „- — . -— , _• L Jr. ctlirso ._. - -. . -. •INa• ..- ..• ' • . I • •• 1.. ••• ',. ...•.. 'V.. . . .. , '.- . •Ai• - • . •• i A. ,- — , U i ... .., -' . ' • .•:.-:-•---"A 1r,.,._.., ..L• ..., . I - ---•••••••••••n!.X1:••c,, -• •• . •_'e.14.-67../%:;!•aly d••-•7 ' •, V • . , ,.., . , ------- I ' . :1..7 v ' --'—............,........... -• _ •77'..- A . '' fdr7•-•'Ad•r•-'. ..,..'.:-"'t - A. .• - • d o. •• - • • 1 i •-• .. . ..%;•-•%VA:14-T,--•''.'...•-•d.... .d...., •- ,' , d *,.',.... • . Ar- ,.,•-- .... "-• ' - i•e 1 '-e—,./.A.re% A.V...o 1,'.dit I_ • ' •-..• ; - ''.d" ' 'd. A- • fi Nelson Dam Improvements •I. ' tea �r � - •r • li ;• •"1 .•"~ ��ti may'..., _ 1 ' "} �` ;, Via. ? #��,W.° ////// �. • ,*,1:1T-- y, .T ,.„ 04,1. ' I ,r •1.',•C • -.6.• i - ..s1 • Nelson Dam Improvements Project Cost: $18,100,000 Scheduled End Construction: 2023 (Phase 1) }� = 4. ;:. ''''..x. ^ .' }s ,.Ariti .,1f,..' 4:<• `^y.• }y:n;�, r.r."•.fir_ .TL .A: . . -. Y�.�;• � +t[y+_�'�'-". y4 h11,; i," '� to:. 2" 1�."" . Zen 5-C s. i ! _ _�� 4� ; •-r:: •mow ,I. .r{_.;�. -- _—_.:4:77 -e,14i.1tViik.u+ 4, — ---.1 . -*,-_:. / 1''� -ltr,, ''I �� .�+ ter- - - - '`1 :,.�i'r. # - 1 r z• Fund sources: • DOE • Community Cap Facili '-s • User Fees • Rivers Legacy Fund • Fish Barrier Removal Board Grant • BOR • Fund balance • Inter-Fund loan Nelson Dam Improvements . .. 7 , A .7.'i• 1'' • • "°- ......; '6--1 •- ' A',4 Z ept.-• -•,'''*1 ''' '- - • • • • .1,-,' '`.,„:q-•• '. •,?• ;''',.,;.c"4''t;i.'... \' •• -..; .;;'1 i 1....^s'•'.4 ' •,';•.''''=' .- :' '7;:.....' ' '•:•:''\ .•., .4::.:'pl..... ..:.'• . N. •-- '' '' _ .7 : v r.- - -.1wr / Other Capital Projects • Tiger Oil — N 15t • Development impacts • Tiger-Oil —W Nob Hill • Street breaks • HBJCC— HVAC • YPD building • PCI survey • City Hall Elevator • Capitol Theatre • Grant/Funding requests • ADA/Ped Plan • TIP • Top 10 Accident List • Traffic Calming Other Capital Projects EH iii..--IPF;i_ CITY OF YAKIMA ti 2021 ENGINEERING _ - ti� - - ,.„���' ." PROJECT MAP BY �. l._ •; • DISTRICT 'r • I• T . - " -,'-%.. rJ _ `1, L ;lH M1% -'5- - a *1 - �.::.�... -- = i ; }.._LI1• i s .1, a~� `/ it ' ^I . ,#_� -1 i' _!�. --; 3. �' ► i I It ..., ..». .. 1 r i I } Tit} I'II n �' 1 t L- -- . , / I :1 , i , ;1711 ;: 3 11i °`. rr I11 I .4' ; --% �w'4• _ .i �;tl - k ' R l ii ;I __ ki; I '�lki � aioa -ii rk for . I1- d 1 '1,1 i l 1 i .r _ r I I i 1 - i 1 ; �. ' . � , 1 — 1 - Challenges • June Inflation - AGE ,.; - lilt CU1i51VVCIlON = IO Materials costs ` ' ""'�„ CONSTRUCTION -' Labor issues INFLATION ALERT . -.-5:.,:..1 Number of bidders ......`Y:..4..•.0....4..4:.�:=- ri Covid special provisions / Response times (PE) Funding / Reimbursements What the future holds: 2022 • McClure Elementary Safety& 16th Ave Sidewalk - Construction $407k; Safe Routes to School, Federal Transit Authority, and City funds • Cowiche Canyon Trail-Construction $1 .2M; State Legislature funds • Summitview Ave Resurfacing - Construction $2.3M; Federal NHS funding • Spring Creek Road/48th Ave & Washington 11S • Robertson Elementary School Safety Improvements- Construction $500K; Safe Routes to School funds • Roosevelt, McKinley, Apple Valley RRFB's- Construction $40k; Washington State Commission Grant What the future holds: 2023 • Bravo Co Blvd- Phase 1 - Construction $6M; Bonds, City Utility, and LIFT funds • N 1st St Reconstruction - Phase 3- Construction $12M; City Utility, TBD, Bonds, Federal Freight, and TIB funds. (2 year project) • 72nd & Washington Ave Roundabout- Construction $1 .5M; State Legislature and City Arterial Streets funding 2024 //////> • 34th Ave & Fruitvale Blvd Roundabout- Construction $2M; Federal Safety, City Arterial Streets funding • What the future holds: Ilk Twaddngton State Six Year Transportation Improvement Program °ape°°°`°"`°° `•`1°° From 2022 to 2027 Agency:Yakima county:Yakima MPOYRTPO:YVCOC ..ade N Oubde _ _ - 1 — - I �AI C�np,el Pe We R 111rm3Qg i D ROM Name ce PAPAW 1• r •HY2 0b'112. 001•JI x Tly/gs a CLOPS O150 Ca YP1 1 1Y PAIN,1st Street Renaardl°e Phase 0 PICS]151 wax Mtn Boulevard to 2 Street Mq°w.Nanh 1YSN1°[°y hTAYI,J/C to 1.11143 .,MFaayt 011*0.;10 Urlla rl1Wecr 0d4P0IY100 ryreeplIC401 a�0+in10l ,,,==, ! =essrusnlenesennatut aaDaYlO ramura f Twang Satin Maw Plum 51MR Year(YYYYI FBONII FIm0 Coda Faeers]Fens SW Fal Cede Slam Fends LOCa1 Rinds TOW Fuca P CM 2022 0 TIB I sop WO 10 400 000 11 080.030 Tama e� _ 1.600A00 10.480.000 11.0110,000 I AIM14.1.7vlaalit1st2aIxa1an1svlaun DI11 aBO.000 0ilfl 0 o 0 Touts 1T.5B0A00 0 D111 0tl 0 Questions? /