HomeMy WebLinkAbout09/30/2014 05 Drinking Water Connection Fee UpdateITEM TITLE:
SUBMITTED BY:
SUMMARY EXPLANATION:
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 5.
For Meeting of: September 30, 2014
Drinking Water Connection Fee Update
David Brown, Water/Irrigation Manager
Debbie Cook, Utilities and Engineering Director
Connection charges are a unit cost of the City's investment in the fixed plant needed to serve its customers
with drinking water and to provide fire suppression. The water connection charge study is attached. The City
has three components to the drinking water connection charges:
Domestic water connection charge – Recovers a proportionate share of the cost of general facilities—
those that provide water treatment, transmission, storage, and pumping capacity. Applies to all new
connections to the domestic water system.
Distribution plant connection charge – Recovers a proportionate share of the cost of local facilities—
distribution lines, hydrants, services, and meters—that have not been already paid for through LIDs or
developer extensions.
Base irrigation charge – Recovers a proportionate share of treatment, transmission, storage, and
pumping capacity costs as they apply to customers who use domestic water for irrigation purposes.
These charges were first established using the same method as this study used. However in the 17 years
since the connection charges were first implemented the costs have increased due to inflation and the
numerous capital improvements that have completed in the system, which results in the need to increase fees.
The capital improvement program was adopted by Council through the six-year Water System Plan and was
incorporated in this study.
The method used to calculate the fees is based on the customer's impact to the water system. The larger the
service the more demand or the more impact the customer has on the system which results in the customer
using more of the system capacity. The study uses three basic components to calculate the fee:
Cost Basis for Existing Facilities including supply, treatment, transmission and distribution which
includes metering.
Cost Basis for Future Facilities including supply, treatment, transmission and distribution which includes
metering. This study was completed in November 2012 so two major projects were included in this section,
Recycle Lagoons at the Water Treatment Plant and the Automated Meter Reading System (both complete).
This study included the projected cost of the Automated Meter Reading as $8,000,000 the project was
completed for just over $5,000,000. This component of the fee has been recalculated to reflect the reduction
in cost from $1,329 to $1,269 per equivalent residential unit, reflected in a reduced distribution connection
charge.
Capacity which includes the total capacity of the system to meet demand in million gallons per day, both
existing and future. This factor divides into the cost for facilities resulting in the connection fee per equivalent
residential unit.
Resolution: Ordinance:
Other (Specify): Study
Contract: Contract Term:
Start Date: End Date:
Item Budgeted: Yes Amount:
Funding
Source/Fiscal
Impact:
Schedule of Charges
Strategic Priority:
Insurance Required? No
Mail to:
Phone: 509-575-6204
APPROVED FOR
SUBMITTAL:
RECOMMENDATION:
Improve the Built Environment
City Manager
Accept study and direct preparation of ordinance
ATTACHMENTS:
Description
Strategic Initiative
Connection Charge Study
Upload Date
9/26/2014
9/25/2014
Type
fi::x htiiibliit
Backup IMlateiriiall
STRATEGIC INITIATIVE (POLICY ISSUE) CONNECTION CHARGE
UPDATE
BUDGETED
PROPOSAL
Connection charges are a unit cost of the City's investment in the fixed plant needed to serve its
customers with drinking water and to provide fire suppression. The water connection charge
study is attached. The City has three components to the drinking water connection charges:
• Domestic water connection charge – Recovers a proportionate share of the cost of general
facilities—those that provide water treatment, transmission, storage, and pumping capacity.
Applies to all new connections to the domestic water system.
• Distribution plant connection charge – Recovers a proportionate share of the cost of local
facilities—distribution lines, hydrants, services, and meters—that have not been already paid
for through LIDS or developer extensions.
• Base irrigation charge – Recovers a proportionate share of treatment, transmission, storage,
and pumping capacity costs as they apply to customers who use domestic water for irrigation
purposes.
These charges were first established using the same method as this study used. However in the
17 years since the connection charges were first implemented the costs have increased due to
inflation and the numerous capital improvements that have completed in the system, which
results in the need to increase fees. The capital improvement program was adopted by Council
through the six-year Water System Plan and was incorporated in this study.
The method used to calculate the fees is based on the customer's impact to the water system.
The larger the service the more demand or the more impact the customer has on the system
which results in the customer using more of the system capacity. The study uses three basic
components to calculate the fee:
• Cost Basis for Existing Facilities including supply, treatment, transmission and
distribution which includes metering.
• Cost Basis for Future Facilities including supply, treatment, transmission and
distribution which includes metering. This study was completed in November 2012 so
two major projects were included in this section, Recycle Lagoons at the Water
Treatment Plant and the Automated Meter Reading System (both complete). This study
included the projected cost of the Automated Meter Reading as $8,000,000 the project
was completed for just over $5,000,000. This component of the fee has been recalculated
to reflect the reduction in cost from $1,329 to $1,269 per equivalent residential unit,
reflected in a reduced distribution connection charge.
• Capacity which includes the total capacity of the system to meet demand in million
gallons per day, both existing and future. This factor divides into the cost for facilities
resulting in the connection fee per equivalent residential unit.
IMPACTS
1. Fiscal Impact —
Schedule of Charges
Meter
Domestic Charge
Distribution Charge
Meter Size
Equivalence
Factors
Existing
New Fee
Existing
New Fee
3/4 -inch
1.00
$ 474
$ 683
$ 120
$ 585
1 -inch
1.67
$ 790
$ 1,139
$ 199
$ 976
1 1/2 -inch
3.33
$ 1,580
$ 2,278
$ 398
$1,951
2 -inch
5.33
$ 2,528
$ 3,644
$ 638
$3,122
3 -inch
10.67
$ 4,740
$ 7,289
$1,195
$6,244
4 -inch
16.67
$ 7,900
$11,388
$1,992
$9,756
Services over 4 inches are to be calculated using the equivalent residential units the
new service will use.
Base Irrigation Fee. This fee is calculated separately as many customers have an
alternate source of irrigation water and will not be using drinking water to irrigate.
The new fee for single family or duplexes in $0.073 per total square foot of lot (this
assumes only 60% of the lot is permeable surface). For multiple family, commercial
and industrial the fee is $0.1220 per square foot of permeable surface. Please note
there is a reduction in the fee from the current fee some $0.017 and $.028
respectively.
2. Proposed Funding Source — Fee increase
New water customers
3. Public Impact — Increased cost of new water service
4. Personnel Impact — None
5. Required Changes in City Regulations or Policies — will require an ordinance and
public hearing to change rates
6. Legal Constraints, if applicable —
7. Viable Alternatives — Leave fees at current level, rates will continue to subsidize
new customers. Raise fees to something less than the calculated need,
Redmond Town Center
7525 166's Ave NE, Suite D-215
Redmond, Washington 98052
T: 425.867.1802 F: 425.867.1937
v
225 Bush St.
Suite 1825
San Francisco, CA 94104
T: 415.445.8947 F: 415.398.1601
4380 SW Macadam Avenue
Suite 220
Portland, OR 97239
T: 503.841.6543 F: 503.841.6573
Technical Memorandum
Date: November 6, 2012
To: Dave Brown, Water/Irrigation Division Manager
From: Karyn Johnson, Principal
Subject: City of Yakima Connection Charges
At the City's request, we reviewed the connection charges used by the City of Yakima water
system and updated them to reflect current costs and system capacity.
Pt I IIY""I11
The City's water system has three types of connection charges:
• Domestic water connection charge — Recovers a proportionate share of the cost of
general facilities—those that provide water treatment, transmission, storage, and
pumping capacity. Applies to all new connections to the domestic water system.
• Distribution plant connection charge — Recovers a proportionate share of the cost of
local facilities—distribution lines, hydrants, services, and meters—that have not been
already paid for through LIDs or developer extensions.
• Base irrigation charge — Recovers a proportionate share of treatment, transmission,
storage, and pumping capacity costs as they apply to customers who use domestic water
for irrigation purposes.
Calculating the first two types of charges requires that water system capacity costs, net of
contributed capital, be allocated between general facilities and local facilities. Calculating the
base irrigation charge requires that the domestic water connection charge be converted from a
"per ERU" basis to a "per square foot" basis.
Any connection charge is the unit cost of the City's investment in the fixed plant needed to serve
its customers. The numerator is the applicable cost of the system's fixed plant, minus contributed
capital, plus accrued interest. The denominator is either the number of units served by that plant
(demand) or able to be served by that plant (capacity). In this study we continue the City's past
practice of using capacity as the denominator rather than demand.
��Y dPm19P III �C , � ✓�.�P 1Pl �
(:) oIP°Ilii ° IV is 11(:)1. ort e c:tlII m ), Ir1 , ,M
We will explain first the basic components of the connection charge calculation: existing costs,
future costs, and existing and future capacity. Except for the allocation between general and local
facilities, these components are the same for all three types of connection charges, so we will
discuss them together.
Technical Memorandum
City of Yakima Connection Charges
°.�Pvt Basis Ili,sI' 4.'.N II'vV�III II ;� N�..nll
Hies
IVU"'s
The cost basis is the starting point in calculating a connection charge, and it has two components:
the cost of existing facilities and the cost of future facilities. The cost basis for existing facilities
is discussed first.
The following page contains three exhibits that together show different elements of the cost basis
for existing facilities.
Exhibit 1 summarizes the cost of existing facilities by the year the assets were placed in service.
The age of existing assets is important because state law allows the connection charge to include
in its cost basis up to ten years of accrued interest, using for each asset the interest rate prevailing
at the date it was placed in service. The total asset cost for the Yakima water system is $54.1
million.
Exhibit 2 allocates the $54.1 million cost between general and local facilities, then subtracts
contributed capital and adds the accrued interest. Contributed capital totals $22.1 million; it is
assumed to apply 100% to the distribution system, or local facilities, because most contributed
capital results from the extension of local distribution lines by either developers or Local
Improvement District projects. (Contributed capital is also referred to as "Contributions in Aid of
Construction," abbreviated as "CIAC.")
Exhibit 3 adds construction work in progress (CWIP) as of the end of 2011, allocating it between
general and local facilities in proportion to the total original cost net of CIAC.
FCS GROUP 425-867-1802
Page 2 November 6, 2012
Technical Memorandum
City of Yakima Connection Charges
Exhibit 1: Summary of Existing Plant in Service by Year
Account
Asset Description
2003 and
Prior
2004 2005 2006 2007 2008 2009 2010 2011 Total
900 Intangible Plant -Water $ 221,830 $ $ - $
901 Source of Supply - Water 2,242,541 - -
902 Storage 1,899,066 - -
903 Pumping Plant -Water 1,280,515 - -
904 Water Treatment Plant 2,931,970 1,838,431 39,054 4,768,805
905 Transmission Plant -Water 2,804,147 - - -
906 Distribution Plant -Water 25,238,726 1,240,137 540,272 831,099
907 General Water Plant 2,528,630 14,526 5,323
$ $ - $ - $ $ - $ 221,830
- - - - 2,242,541
- - 1,464,474 - - 3,363,540
- - - - 1,280,515
37,511 33,058 - 5,170 9,653,999
- - - - 2,804,147
1,010,954 764,044 667,721 705,855 950,770 31, 949, 579
6,070 - 14,950 - 11,703 2,581,202
$39,147,424 $ 3,093,095 $ 584,649 $ 5,599,904 $ 1,054,535 $ 797,103 $ 2,147,144 $ 705,855 $ 967,643 $54,097,352
Note: Reservoirs and standpipes reclassified from 906 -Distribution Plant to 902 -Storage.
Exhibit 2: Existing Plant in Service minus Contributions plus Interest, Allocated between General and Local Facilities
Exhibit 3: 2011 Construction Work in Progress — Allocation between General and Local Facilities
Construction Work in Progress
2011 Total
Balance
General
Facilities
Local
Facilities
Water Construction Work In Progress $ 3,346,876 $ 1,941,495 $ 1,405,381 Allocate to Local Facilities in proportion to Original Cost net of Contributed Capital.
FCS GROUP 425-867-1802
Page 3
November 6, 2012
Total
General Facilities
Local Facilities
Account
Asset Description
Original
Cost
Contributed
Capital
Allocable
Interest Cost
Original
Cost
Contributed
Capital
Allocable
Interest Cost
Original
Cost
Contributed
Capital
Allocable
Interest Cost
900 Intangible Plant -Water
$ 221,830 $ - $ 137,091
$ 221,830 $ - $ 137,091
$ - $ - $ -
901 Source of Supply - Water
2,242,541 - 1,332,779
2,242,541 - 1,332,779
- - -
902 Storage
3,363,540 - 1,373,889
3,363,540 - 1,373,889
- - -
903 Pumping Plant -Water
1,280,515 - 720,233
1,280,515 - 720,233
- - -
904 Water Treatment Plant
9,653,999 - 3,724,432
9,653,999 - 3,724,432
- - -
905 Transmission Plant -Water
2,804,147 - 1,732,813
2,804,147 - 1,732,813
- - -
906 Distribution Plant -Water
31,949,579 15,917,567 9,934,403
- - -
31,949,579 15,917,567 9,934,403
907 General Water Plant
2,581,202 - 1,598,670
2,581,202 - 1,598,670
- - -
Total Fixed Assets
$54,097,352 $15,917,567 $20,554,311
$22,147,773 $ - $10,619,908
$31,949,579 $15,917,567 $ 9,934,403
Original Cost less Contributed Capital
$38,179,785
$22,147,773
$16,032,012
100.0%
58.0%
42.0%
Exhibit 3: 2011 Construction Work in Progress — Allocation between General and Local Facilities
Construction Work in Progress
2011 Total
Balance
General
Facilities
Local
Facilities
Water Construction Work In Progress $ 3,346,876 $ 1,941,495 $ 1,405,381 Allocate to Local Facilities in proportion to Original Cost net of Contributed Capital.
FCS GROUP 425-867-1802
Page 3
November 6, 2012
Technical Memorandum
City of Yakima Connection Charges
Exhibit 4 shows the final component of the existing cost basis: the Water Fund cash and debt.
Outstanding debt principal is subtracted from the cost basis because when there is outstanding
debt that was used for pay for certain assets, today's ratepayers haven't paid for those assets yet,
even though the assets are in service. A newly connecting customer becomes a ratepayer and
therefore will help pay for those assets through future rates.
However, today's ratepayers have helped accumulate cash in the Water Fund. This cash offsets
the amount that future ratepayers will have to pay to retire outstanding debt. For that reason, the
calculation of the existing cost basis subtracts "net debt principal," which is the outstanding debt
principal minus fund cash. (If cash is greater than outstanding debt, net debt principal is zero.)
EXHIBIT 4: 2011 Cash and Debt Summaries
2011 Year-end Outstanding Debt
Revenue Bonds
PWTF Loans
SIED Loans
Total Outstanding Debt
Total Water
General Local Allocation Basis
Facilities Facilities
58.0% 42.0%
$ 1,385,000
$ 4,212,816
$ 10,400
$ 5,608,216
Source: Debt -to -Maturity schedule as of 12/31/11
2011 Year-end Cash Balances
Operating Fund Cash
Revenue Bond Reserve Account Cash
Revenue Bond Redemption Account Cash
Total
$ 3,253,279 $ 2,354,937 In proportion to Assets net of CIAC
58.0% 42.0%
$ 1,214,008 $ 704,236 $ 509, 772
$ 347,968 $ 201,853 $ 146,115
$ 14,281 $ 8,284 $ 5,997
$ 1,576,257 $ 914,373 $ 661,884
Source: 2011 Financial Statements - Comparative Statements of Cash Flows
In proportion to Assets net of CIAC
In proportion to outstanding debt
In proportion to outstanding debt
Exhibit 5 shows how the existing cost basis is calculated, using all the above components. For
general facilities, the total is $32.4 million; for local facilities, the total is $25.7 million.
Exhibit 5: Calculation of Cost Basis for Existing Facilities
Existing Cost Basis
Total
General
Facilities
Local
Facilities
PLANT -IN-SERVICE
Utility Capital Assets
plus: Construction Work in Progress
less: Contributed Capital
plus: Interest on Non -Contributed Plant
Existing Cash Balances $ 1,576,257
less: Debt Principal Outstanding (5,608,216)
less: Net Debt Principal Outstanding $ (4,031,959)
$ 54,097,352 $ 22,147,773
3,346,876
(15, 917, 567)
20, 554, 311
1,941,495
10, 619, 908
914,373
(3,253,279)
$ (2,338,906)
$ 31,949,579
1,405,381
(15, 917, 567)
9,934,403
661,884
(2,354,937)
$ (1,693,053)
TOTAL EXISTING COST BASIS
$ 58,049,013 $ 32,370,270
$ 25,678,743
yg PglJ i 11 s for HAAT V' 9 t l T ga 11
II V' IVn
Exhibit 6 on the following page shows the water utility's 2012-16 Capital Improvement Plan
(CIP), which is the source for the future cost basis.
FCS GROUP 425-867-1802 Page 4
November 6, 2012
Technical Memorandum
City of Yakima Connection Charges
Exhibit 6: Capital Improvement Plan 2012-2016
FCS GROUP 425-867-1802 Page 5
2012 Dollars (including Inflation)
R&R
Upgrade
Expansion
2010 Dollars
Description
2012
2013
2014
2015
2016
Total Costs
2012-2016
General
Facilities
Local
Facilities
Source of Supply
3,719,797
1,058,324
--
1,058,324
-
-
-
Leak Detection
132,290
20,000
20,000
132,290
20,000
60,000
60,000
-
Water Treatment Plant
--
6,349,943
20,981,058
-
-
-
WTP PLC Replacement
250,000
250,000
250,000
-
WTP Lagoons / electrical service
400,000
3,114,800
3,514,800
3,514,800
-
Intake Flood Repair
1,000,000
1,000,000
1,000,000
-
Distribution
-
-
-
Automated Metering Infrastructure
1,500,000
6,500,000
8,000,000
-
8,000,000
Open Gear Vale Replacement
25,000
25,000
25,000
25,000
25,000
125,000
-
125,000
Private Water Main Replacement
175,000
175,000
175,000
175,000
175,000
875,000
-
875,000
Lead -Oakum Joint Line Replacement
2,000,000
2,000,000
2,000,000
6,000,000
-
6,000,000
Total Capital Projects in 2010 Dollars
2,100,000
11,084,800
2,220,000
2,200,000
2,220,000
19,824,800
4,824,800
15,000,000
Total Projects in 2012 Dollars
2,222,480
11,731,308
2,349,479
2,328,312
2,349,479
20,981,058
5,106,201
15,874,858
Repair & Replacement Project Costs
211,665
1,534,570
2,328,312
2,328,312
2,328,312
8,731,172
1,322,905
7,408,267
Upgrade Project Costs
2,010,815
10,196,739
21,166-
21,166
12,249,887
3,783,296
8,466,591
Expansion Project Costs
-
-
-
-
-
-
-
-
FCS GROUP 425-867-1802 Page 5
2012 Dollars (including Inflation)
R&R
Upgrade
Expansion
Total Costs
2012-2016
63,499
-
63,499
264,581
--
264,581
-
3,719,797-
3,719,797
1,058,324
--
1,058,324
-
8,466,591-
8,466,591
132,290
--
132,290
926,033
--
926,033
6,349,943
--
6,349,943
20,981,058
8,731,172
8,731,172
12, 249, 887
12, 249, 887
November 6, 2012
Technical Memorandum
City of Yakima Connection Charges
The 2011 Water Master Plan expressed its project cost estimates in 2010 dollars, so Exhibit 6
uses the ENR Construction Cost Index to convert the estimates into 2012 dollars. It also
separates the projects between those that improve general facilities versus those that improve
local facilities. Finally, Exhibit 6 classifies the projects into one of three categories: repair &
replacement (R&R) projects, upgrade projects, and expansion projects. This classification
determines whether a particular project can be included in the future cost basis for the connection
charge. Expansion projects are always eligible to be included; R&R projects are generally
ineligible. For upgrade projects, it depends on the particular methodology used for the
connection charge.
Exhibit 7 summarizes the future cost basis for the connection charges, assuming the "integrated
methodology" that we are recommending for the connection charges. With this methodology,
upgrade projects can be included in the future cost basis.
Exhibit 7: Summary of Cost Basis for Future Facilities
Future Cost Basis
Total
General
Facilities
Local
Facilities
CAPITAL IMPROVEMENT PLAN
Total Future Projects (2012 CIP net of CIAC)
less: Repair & Replacement Portion of Projects
$ 20,981,058 $ 5,106,201
(8,731,172) (1,322,905)
$ 15,874,858
(7,408,267)
TOTAL FUTURE COST BASIS $ 12,249,887 $ 3,783,296
$ 8,466,591
may
4 II /
After the existing and future costs are determined, the final component of the connection charge
calculation is the denominator—the system capacity, expressed in equivalent residential units
(ERUs).
Exhibit 8 shows the 2010 and projected 2020 total water system capacity in million gallons per
day (mgd), according to the 2011 Water Master Plan. Because the CIP goes out only to 2016, we
interpolated on a straight-line basis to estimate 2016 figures. Exhibit 8 shows that in 2010,
maximum day demand (MDD) was at 90% of total system capacity.
Exhibit 8: Capacity and 2010-2016 Projected Demand (million gallons per day)
Capacity and Projected Demand (mgd)
Source: 2011 Water Master Plan, Table 3-22.
Total System Capacity - Non -Drought Year (mgd)
Maximum Daily Demand (MDD) (mgd)
Unused Capacity (mgd)
% Unused Capacity
Interpolation
2010 2020 2016
25.00
22.40
2.60
10%
25.00
24.70
0.30
1%
25.00
23.78
1.22
5%
Exhibit 9 shows the conversion of the system capacity figure from mgd to ERUs. According to
City staff, the average water consumption per ERU is 270 gallons per day. Assuming a peaking
factor of 1.75 (from Table 2-33 of the 2011 Water Master Plan), the maximum -day water
consumption per ERU is 473 gpd, which implies a total capacity of 52,910 ERUs. Since the CIP
does not contain any capacity -enhancing projects through 2016, this capacity figure applies to
2016 as well as the present.
FCS GROUP 425-867-1802
Page 6 November 6, 2012
Technical Memorandum
City of Yakima Connection Charges
Exhibit 9: Capacity and 2010-2016 Projected Demand (ERUs)
Capacity and Projected Demand iim ERUs
Total System Capacity - Non -Drought. Year (i d)
Interpolation
2010 2020 2015
Equivalent Residential Unit (ERU')::
Average Usage per ERU (gpd')
Peaking Factor
Peak Usage per ER.0 (gpd)
Sources: Dave Brown & 2011 Water Master Plan,, able 2-33
Total System Capacity - Non -Drought Year (ERUs)
Maximum Daily Demand (MM) (ERUs)
25.00 25.00 25.00
270 270 270
1..75 1..75 1..75
473 473 473
52,910, 52,910, 52,910,
47,.407 52,,.275 50,,328
This capacity figure is an overall system constraint, so we are treating it as applicable to both
general facilities and local facilities.
CU
� nr lltiltuinllc: arid
:Agri
tintition 1G
,uirllruo c:•(wlll III �� ��:III III c.
it a
Exhibit 10 shows the calculation of both the domestic water connection charge and the
distribution plant connection charge, assuming an "integrated" methodology, in which the total
existing plus future cost basis is divided by the total projected capacity. This approach provides a
simple, easily replicated methodology that takes into account a broad range of existing and future
costs and still tends to be stable over time. It yields a domestic connection charge of $683 per
ERU, which is an increase over today's $474 per ERU. For the distribution plant connection
charge, the increase is greater: $645 per ERU, compared with the current charge of $120 per
ERU.
Exhibit 10: Connection Charge Calculation
Connection Charge Calculation Total
Domestic
Charge
Distribution
Charge
Existing Cost Basis
Future Cost Basis (including upgrade projects)
Total Cost Basis
Total Projected Capacity (ERUs)
Total Charge per ERU
$ 58,049,013
12,249,887
$ 70,298,900
52,910
$ 1,329
$ 32,370,270
3,783,296
$ 36,153,566
52,910
$ 683
$ 25,678,743
8,466,591
$ 34,145,334
52,910
$ 645
Assumes integrated methodology - total existing plus future costs divided by total projected capacity.
Includes Upgrade projects from CIP.
Exhibit 11 provides a schedule of charges for various meter sizes, based on the "per ERU"
amounts shown in Exhibit 10. For meters larger than 4", we recommend that the connection
charges be determined on a case-by-case basis, based on the projected water demand of the
particular building in relation to the "per ERU" charges shown in Exhibit 10.
FCS GROUP 425-867-1802 Page 7
November 6, 2012
Technical Memorandum
City of Yakima Connection Charges
Exhibit 11: Domestic and Distribution Plant Connection Charges by Meter Size
Schedule of Charges
Meter
Domestic Charge
Distribution Charge
Meter Size
Equivalence
Existing
Calculated
Existing
Calculated
Factors
3/4 -inch
1.00
$ 474
$ 683
$ 120
$ 645
1 -inch
1.67
$ 790
$ 1,139
$ 199
$ 1,076
1 1/2 -inch
3.33
$ 1,580
$ 2,278
$ 398
$ 2,151
2 -inch
5.33
$ 2,528
$ 3,644
$ 638
$ 3,442
3 -inch
10.67
$ 4,740
$ 7,289
$ 1,195
$ 6,884
4 -inch
16.67
$ 7,900
$ 11,388
$ 1,992
$ 10,756
va V.;'ii:".."i iV'tion IIV"ge
The base irrigation charge applies to properties that will be relying on the domestic water system
for irrigation purposes, either because they are newly connecting to domestic service (but not
irrigation service) or because their irrigation service has been discontinued. This charge is based
on the cost of the domestic system, not the irrigation system. In effect, it is an additional
increment of domestic system capacity that must be committed because a particular property
uses domestic water for both purposes.
In the 2008 update to the connection charges, the amount of the base irrigation charge for one
ERU was equivalent to the amount of the domestic connection charge. In other words, someone
connecting a property to the domestic water system for both domestic and irrigation purposes
was assumed to be requiring, on average, twice as much water during the peak season as
someone who connects only for domestic purposes.
However, according to the 2011 Water Master Plan, the relationship between the maximum daily
demand and average daily demand is 1.75, which implies that the additional requirement created
by using a domestic water connection for irrigation purposes is equivalent to only .75 times the
requirement for domestic purposes. Given the recommended domestic connection charge of $683
per ERU, the assumed equivalent amount for irrigation purposes alone is $683 multiplied by .75,
or $512 per ERU.
The base irrigation charge is expressed in "per square foot" terms rather than "per ERU" terms,
reflecting the relationship between irrigation demands and lot size. For single-family and duplex
lots, the charge is based on total square feet. For other lots, the charge is calculated (at the
owner's option) based on either total square feet or permeable square feet, with permeable square
feet assumed to average 60% of total square feet.
We continued the assumption from the prior study that a typical single-family lot would be 7,000
total square feet. For a 7,000 square foot lot, $512 per ERU is equivalent to $.073 per square
foot. Assuming an average of 60% coverage with permeable surface, $512 per ERU is equivalent
to $.122 per permeable square foot. These results are summarized in Exhibit 12.
FCS GROUP 425-867-1802
Page 8 November 6, 2012
Technical Memorandum
City of Yakima Connection Charges
Exhibit 12: Calculation of Irrigation Base Charges
Domestic System Unit Cost ($/ERU) $ 683
Peaking factor 1.75
Incremental requirement due to irrigation service $ 512
Assumed square footage 7,000
Irrigation Connection Charge ($/square foot) $ 0.073
Assumed % permiable square feet per lot 60%
Irrigation Connection Charge ($/permiable s.f.) $ 0.1220
FCS GROUP 425-867-1802
Page 9 November 6, 2012