Agreement Supplement
IAgency
City of Yakima
Federal Aid Project Number
STPUS-4591(002)
Supplement Number
2
Agreement Number
LA -7299
CFDA No. 20.205
(Catalog of Federal Domestic Assistance)
The Local Agency requests to supplement the agreement entered into and executed on
All provisions in the basic agreement remain in effect except as modified by this supplement.
The changes to the agreement are as follows.
Project Description
Name 64th Avenue Roadway Widening
Termini Nob Hill Boulevard to Tieton Drive
Description of Work ® No Change
Length 2,500 linear feet
Reason for Supplement
Move portion of remaining R/W funds to PE. Obligate construction funds.
Does this change require additional Right of Way or Easements? ❑ Yes ® No
Type of Work
Estimate of Funding
(1)
Previous
Agreement/Suppl.
(2)
Supplement
(3)
Estimated Total
Project Funds
(4)
Estimated Agency
Funds
(5)
Estimated
Federal Funds
PE .a. Agency
75,000 00
14,422.00
89,422.00
12,072.00
77,350.00
86.5 % b. Other
c. Other
Federal Aid d. State
Participation
Ratio for PE e. Total PE Cost Estimate (a+b+c+d)
75,000.00
14,422.00
89,422.00
12,072.00
77,350.00
Right of Way f Agency
83,422.00
-12,422.00
71,000 00
9,585 00
61,415 00
86.5 % q. Other Yakima County
15,000.00
-2,000.00
13,000.00
1,755.00
11,245.00
Federal Aid h. Other
Participation
Ratio for RW 1. State
1,000.00
1,000.00
135.00
865.00
j. Total R/W Cost Estimate (f+g+h+i)
99.422.00
-14.422.00
85.000.00
11.475,00
'73.525.00
Construction k. Contract
856,040.00
856,040.00
115,565 00
740,475 00
I. Other Non -participating
59,538.00
59,538.00
59,538.00
86.5 % m. Other
Federal Aid n. Other
Participation o Agency
Ratio for CN p State
10,000 00
10,000 00
1,350.00
8,650 00
q. Total CN Cost Estimate (k+l+m+n+o+p)
925,578.00
925,578.00
176,453.00
749,125.00
r. Total Project Cost Estimate (e+j+q)
174.422.00
925.578.00
1.100.000.00
200.000.00
900.000.00
The Local Agency further stipulates that pursuant to said Title 23, regulations and policies and procedures, and as a condition
to payment of the Federal funds obligated, it accepts and will comply with the applicable provisions.
Agenc Official
By Oa/
Title
City Mann fit
2-alo...`6
DOT Form 140-041 EF
Revised 03/2011
Washington St. e 'epartment
By
f Transportation
Director of Highways and
Date Executed
ocal Programs OCT 2 3 2013
Memorandum
October 2, 2013
To: Tony O'Rourke, City Manager
From: Debbie Cook, Director of Utilities and Engineering
Brett Sheffield, Chief Engineer
Subject: 64th Avenue Roadway Widening
Attached for your signature are two originals of the Local Agency
Agreement Supplement No. 2 for the 64th Avenue Roadway Widening
project. In July of 2010, the City was successful in securing an STP grant
of $900,000 for this project. The City's match for this project of $200,000
was received from the Wal-Mart Development Agreement, which gave
$200,000 for a pathway along 64th Avenue between Nob Hill Boulevard and
Tieton Drive. As part of the project, a 7 -foot wide sidewalk will be
constructed on the west side of the road, and the outside lanes will be 14 -
foot wide shared bicycle/vehicle lanes.
The Local Agency Agreement for this project was executed between the City
and WSDOT on November 23, 2010, at which time the preliminary
engineering funds were obligated. The Local Agency Agreement
Supplement No. 1 was executed on August 22, 2012, which obligated the
Right of Way funds. The required Right of Way for this project has been
acquired and the Right of Way file has been submitted to the FHWA for
certification.
This Local Agency Agreement Supplement No. 2 will obligate the
construction funds. Once these funds are obligated, the project can be
advertised. The project should begin construction in early spring.