HomeMy WebLinkAbout04/16/2013 05E Huibregtse, Louman Associates, Inc. (HLA) Agreement 2012-42 AddendumBUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No.
For Meeting of: April 16, 2013
ITEM TITLE: Resolution authorizing an Addendum to an agreement with
Huibregtse, Louman Associates, Inc (HLA) in an amount
not to exceed $37,640 to provide Engineering Services for
the Replacement of a Sanitary Sewer Pipe within Tieton
Drive between 38th and 40th Avenues
SUBMITTED BY: Debbie Cook, Director of Utilities and Engineering
Scott Schafer, Wastewater Division Manager
CONTACT Shelley Willson, Utility Engineer /575 -6077
PERSON /TELEPHONE:
SUMMARY EXPLANATION:
The City of Yakima (City) Wastewater Division completed inspection of existing sanitary
sewer pipes that lay under the 28 lane miles of streets identified in the 2013 Grind and
Overlay list. The sanitary sewer line under Tieton Drive between the intersections of 38th
Avenue and 40th Avenue has extensive cracks and is heavily corroded. The pipeline will be
removed and replaced prior to the Grind and Overlay Project. It is critical that the project be
designed, bid, awarded and constructed by June 28, 2013 to allow for the pavement work to
be completed this summer.
Using the Municipal Research and Services Center (MRSC) of Washington Roster, a
statewide small works and consultant's roster system, followed by a competitive selection
process, the City selected HLA. Their previous work with the City's IW project provided the
qualifications and expertise necessary to successfully complete this project within the
constricted timeline.
The Addendum (Addendum No. 3) to the existing Professional Services Agreement with
HLA, City Contract No. 2012 -42, is to provide all services, project administration,
formulation, field investigations, pre- engineering, environmental compliance, permitting, final
design, plans and specifications, including services during construction for the replacement
of 670 lineal feet of 8 -inch sanitary sewer pipe and associated system.
The terms of Addendum No. 3 would be in an amount not to exceed thirty -seven thousand,
four hundred sixty dollars ($37,460.00). See attached Agreement with Exhibit A and B.
Exhibit "A" of the Agreement describes the Scope of Work in more detail.
Exhibit "B" of the Agreement describes the Schedule of Rates.
STAFF RECOMMENDATION:
Staff respectfully requests City Council approve the Resolution authorizing the City Manager
to execute the accompanying contract.
BOARD/COMMISSION RECOMMENDATION:
ATTACHMENTS:
Click to download
L-1 Resolution HLA Sanitary Sewer Treton Dr. 2013
❑ HLA Agreement Addendum 3 Tieton Dr. 2013
RESOLUTION NO. R -2013-
A RESOLUTION authorizing the City Manager to execute an Addendum to existing
Professional Services Agreement 2012 -42 with Huibregtse, Louman
Associates, Inc. (HLA), in the amount not to exceed $37,460 for
Engineering Services for the replacement of 670 linear feet of 8-
inch sanitary sewer pipe.
WHEREAS, the City of Yakima (City) owns and operates wastewater collection
and treatment facilities in accordance with applicable Federal, State and Local
regulations; and
WHEREAS, the City maintains a roster of consultants whose statements of
qualifications represent that they have the expertise necessary to perform the services
required by the City; and
WHEREAS, the State of Washington requires these services to be performed by a
Professional Licensed Engineer; and
WHEREAS, the City already has an Agreement 2012 -42 with HLA Inc. for
Engineering Services related to the design and construction services on recent Industrial
Waste Line improvements for the City's wastewater system and are indentified to meet
regulatory requirements, community growth, replacement needs, and operational
efficiencies; and
WHEREAS, the City desires to retain HLA Inc. through an Addendum (Addendum
No.3) of the existing Agreement 2012 -42 to provide engineering services for design and
construction of the replacement of 670 linear feet of the City's 8 -inch sanitary sewer pipe
and related sewer system components on Tieton Drive, between 38th Avenue and 40th
Avenue; and
WHEREAS, the City desires to have this pipe replaced due to its poor condition by
June 28, 2013, prior to the Grind and Overlay Project to be completed; and
WHEREAS, the City Council has determined that it is in the best interest of the
City to enter into a Professional Services Agreement with a consultant selected from the
roster for such expertise; now , therefore;
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
The City Manager is hereby authorized to execute a Professional Services
Agreement in an amount not to exceed thirty -seven thousand, four hundred and sixty
dollars ($37,460) for Huibregtse Louman Associates, Inc. to provide the Professional
Engineering Services required to design the replacement of the City's 8 -inch sanitary
sewer pipe within Tieton Drive between 38th Avenue and 40th Avenue, a copy of the
Agreement (Addendum No.3) is attached hereto by reference and made a part hereof.
ADOPTED BY THE CITY COUNCIL this 16th day of April, 2013.
ATTEST:
Sonya Claar -Tee, City Clerk
Micah Cawley, Mayor
WIA-.n
Resolution R-2012-60
Project No. WW2327
F,1'1* I 1:4z] I I r-] 0 10 Gr4 VM151 I OEM I VALO I mg la [#I r� ffirL I gl� , I , Ili I IV Im I ML, I I ge 0 =IV I! P1 I U-9 MZ1111111111 EL01 F1 I I r� I A WAN-1q91*1 r� I kzNVE Ism
Profession Services first entered into on the 2nd day of May, 2012, Addendum No. 1 entered into on the
2 nd day of July 2012, and Addendum No. 2 in the process • being entered into, • the City of Yakima,
hereinafter called the "CITY," and Huibregtse, Louman Associates, Inc., hereinafter called the
"ENGWEEV."
• • it I I a SEMI 0
Other than the specific amendments identified herein, all other terms, conditions, and requirements of the
underlying contract, Addendum No. 1, and Addendum No. 2 shall remain in full force and effect
throughout the term of the Contract's performance.
WContracts & Task 0rdersXYakkna\YRWVVTP - 1W Unea=13-03-26 APS Addendum Nc3 - Tieton Replacement docx - 1 -
IN WITNESS WHEREOF the parties hereto duly enter into and execute this Addendum No. 3, as of this
day of 2013.
Signature
M
Date�
MMMMMMMw?_T =$_ , I
Date:
za
GIContracts &Task 0rderMYaklmMYRWVVTP - IW LlnaM2013-03-26 APS Addendum No3 -Tieton Replacement. docx
Q 114 Z I
CITY OF YAKIMA
wr_ P_Y! Aiwiiri 11 Or-
During the term of this AGREEMENT, the ENGINEER shall perform professional services in connection
with the following project:
This scope of work shall include the furnishing of all services, labor, materials, equipment, supplies, and
incidentals necessary to conduct and complete the work as indicated hereinafter. The work to bc
performed involves project administration, formulation, field investigations, pre-engineering,
environmental compliance, permitting, final design, plans and specifications, and services during
construction.
"',ROJECT: The City of Yakima Wastewater Department desires to replace an 8-inch diameter sanita
oth '7
sewer line along Tieton Drive from the intersection of 4 Avenue to the intersection of 38
Avenue (approximately 670 linear feet).
R, Perform topographic field survey required to complete the design, plans and
specifications for publicly bid improvements. Call for underground utility locates prior to
survey.
C. Prepare preliminary design plans and specifications.
D. Prepare easement documents and legal descriptions necessary for installation of the
facilities. CITY responsible to negotiate and pay all costs and fees associated with
obtaining utility easements.
E Prepare right of way documents and legal descriptions necessary for installation of the
facilities. CITY responsible to negotiate and pay all costs and fees associated with
obtaining right of way.
F� Review and discuss preliminary plans with CITY staff�
G. On the basis • approved preliminary plans, perform the final design, and prepare
complete plans and specifications for publicly-bid improvements, as authorized by the
CITY.
Furnish to the CITY engineering data for and assist in the preparation of the required
documents so the CITY may secure approval of such governmental authorities as hav,,-.
jurisdiction over design criteria applicable to the PROJECT.
J Furnish the CITY fifty (50) copies of the final plans and specifications for bidding and
construction. It is anticipated the ENGINEER will prepare one (1) complete set of plans
and specifications for one bid call; additional bid packages will be considered additional
services.
K, Send advertisement for bids to the Paper of Record and other papers selected by the
CITY. CITY shall pay all advertisement fees.
WContracts & Task Orders\Yakima\YRWVVTP - 1W Lines12013-03-26 APS Addendum No3 - Tieton Replacement.docx
PHASE 6 - SERVICES DURING CONSTRUCTION
A. Furnish the field survey crew necessary to set horizontal and vertical control for the
improvements authorized for construction.
W. Furnish a qualified resident engineer who shall make construction observations and i-
on the job at all times that significant work is in progress, whose duty shall be to provii
surveillance of project construction for substantial compliance with plans and specific
tions.
C. Prepare progress reports on the PROJECT for the days during which a resident engineer
is present and file same with the CITY.
D. Consult and advise the CITY during construction and make a final report of the
completed work.
WContracts & Task Orders%YakimakYRWWTP - 1W UnesQ013-03-26 APS Addendum No3 - Tieton Rep1scemenLdocx �4�
In conjunction with Section 7 of the AGREEMENT, following are anticipated completion times for Phases
• Wor�.
Plans, specifications, and estimates for all project elements shall be provided within 30 calendar days
after the date • authorization to proceed.
0 W
I I l loll
I] ril I 1� pi '1 1111 i III iiii� I ill I'll i I . • ,
-TIV"WT M-OR 15111 T-1. '0181
All work shall be performed on a time-spent basis at the hourly billing rates provided in EXAIBIT B plus
reimbursement for direct non-salary expenses as described in section 5.1.1 of the AGREEMENT. The
estimated maximum amount of this phase of work is $22,500.00.
WContracts & Task Orders\Yakima\YRVVvVTP - IW Lines\2013-03-26 APS Addendum No3 - Tieton Replacementdolox —5—
2010
Licensed Professional Land Surveyor $128.00 per hour
Project Engineer
$115.00 per hour
CAD Technician
$101.00 per hour
Resident Engineer/inspector
$96.00 per hour
Surveyor
$96.00 per hour
Senior Engineering Technician
$96.00 per hour
Engineering Technician
$67.00 per hour
Word Processing Technician
$67.00 per hour
Surveyor on Two Man Crew
$92.00 per hour
Surveyor on Three Man Crew
$80.00 per hour
Vehicle Mileage
$0.52 per mile
Global Positioning Survey System Fee
$88.00 per hour
GAContracts & Task Orders\Yakima\YRWWTP - IW LlnesTO13-03-26 APS Addendum No3 - Tieton Replacement cIccx
Licensed Principal Engineer
$176.00 per hour
Licensed Principal Land Surveyor
$18O.OD per hour
Licensed Professional Engineer
$145.00 per hour
Licensed Professional Land Surveyor
$132.OD per hour
Project Engineer
$11B.00 per hour
CAD Technician
$1O4.00 per hour
RemidentEngineer/|nmpeotor
$Bg.DO per hour
Surveyor
$&9.00 per hour
Senior Engineering Technician
$99.OU per hour
Engineering Technician
$7O.00 per hour
Word Processing Technician
$70.00 per hour
Surveyor on Two Man Crew
$95.00 per hour
Surveyor on Three Man Crew
$83.00 per hour
Vehicle Mileage
$O.55 per mile
Global Positioning Survey System Fee
$9O.0O per hour
GAContracts arask IW LinesM13-03-26 APS Addendum No3-rieto Revlacemmntdncx ~�-