RESOLUTION NO. R-2021-002
A RESOLUTION authorizing a contract with Insituform Technologies, LLC. for Project 2495
Cured -In -Place Pipe Rehabilitation of Sanitary Sewer Mains
WHEREAS, the City of Yakima maintains the Wastewater Collections System in
accordance with applicable Federal, State and Local regulations; and
WHEREAS, the City of Yakima Wastewater Division has identified pipeline segments that
require rehabilitation or replacement; and
WHEREAS, this and future projects will stabilize current conditions of the city's
wastewater pipe system and reduce infiltration of groundwater which will save treatment costs,
improve collection system reliability, and limit the need for upgrades to the Wastewater Treatment
Plant; and
WHEREAS, by resolution R-2020-034, the City entered into an agreement with HLA
Engineering and Surveying (HLA) to prepare the plans and contract documents for the
rehabilitation of City of Yakima sanitary sewer main lines in various locations in city, and
WHEREAS, the City of Yakima Wastewater Division requires construction services for the
rehabilitation of the deficient collections system pipes; and
WHEREAS, The City of Yakima used the procedure established by the State of
Washington for competitively bidding projects; and
WHEREAS, Insituform Technologies, LLC. submitted the low bid and has the ability to
perform the contact specified work; and
WHEREAS, the City Council finds that it is in the best interest of the City of Yakima and
its residents to enter into a contract with Insituform Technologies, LLC. to perform the work
detailed in the contract documents for the rehabilitation of approximately 15,550 LF of aging City
of Yakima sanitary sewer main lines by means of cured -in -place pipe; now, therefore
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
The City Manager is hereby authorized to execute the attached contract with Insituform
Technologies, LLC., in the amount of SIX HUNDRED SEVENTY-SIX THOUSAND AND
SEVENTY-SEVEN DOLLARS ($676,077)., for rehabilitation of approximately 15,550 LF of aging
City of Yakima sanitary sewer main lines by means of cured in place pipe in various locations in
city
ADOPTED BY THE CITY COUNCIL this 5th day of January, 2021.
/ZIT 11/71_:j
Patricia Byers, Mayor
CONTRACT
THIS AGREEMENT, made and entered in triplicate, this Lcday of 't't20 Z-1., by and between
the City of Yakima , hereinafter called the Owner, and Insituform Technologies, LLC a
Washington Corporation, hereinafter called the Contractor.
WITNESSETH:
That in consideration of the terms and conditions contained herein and attached and made a part of this
agreement, the parties hereto covenant and agree as follows:
I. The Contractor shall do all work and furnish all tools, materials, labor and equipment for THE
BID AMOUNT OF: $ 676,075.50 , for CIPP Rehabilitation - Priority 1, City of Yakima Project No.
2495, all in accordance with, and as described in the attached plans and specifications and the 2020
Standard Specifications for Road, Bridge, and Municipal Construction which are by this reference
incorporated herein and made a part hereof, and shall perform any alterations in or additions to the work
provided under this contract and every part thereof.
Work shall start within ten (10) days after the Notice to Proceed and shall be completed in Sixty-five (65)
working days. If work has not commenced within the ten (10) days after the notice to proceed, the first
chargeable working day shall be the eleventh (11th) working day after the date on which the City issues the
Notice to Proceed.
If said work is not completed within the time specified, the Contractor agrees to pay to the Owner the sum
specified in the Standard Specifications for each day said work remains uncompleted after expiration of the
specified time, as liquidated damages.
The Contractors shall provide and bear the expense of all equipment; work and labor of any sort whatsoever
that may be required for the transfer of materials and for constructing and completing the work provided for
in this contract and every part thereof, except such as are mentioned in the specifications to be furnished
by the City of Yakima .
II. The City of Yakima hereby promises and agrees with the Contractor to employ, and does
employ the Contractor to provide the materials and to do and cause to be done the above described work
and to complete and finish the same according to the attached plans and specifications and the terms and
conditions herein contained and hereby contracts to pay for the same according to the attached
specifications and the schedule of unit or itemized prices hereto attached, at the time and in the manner
and upon the conditions provided for in this contract.
III. INDEMNIFICATION. The Contractor shall defend, indemnify, and hold harmless the City, its
officers, elected officials, employees and agents from and against all claims, causes of action, damages,
losses, and expenses of any kind or nature whatsoever, including but not limited to, attorney's fees and
court costs, arising out of, relating to, or resulting from The Contractor's performance or non-performance
of the services, duties and obligations required of it under this Agreement.
IV. The Contractor for himself, and for his heirs, executors, administrators, successors, and
assigns, does hereby agree to the full performance of all the covenants herein contained upon the part of
the Contractor.
V. It is further provided that no liability shall attach to the City of Yakima by reason of entering into
this contract, except as expressly provided herein.
IN WITNESS, WHEREOF the parties hereto have caused this agreement to be executed the day and year
first herein above written.
Count signed: CITY OF YAKIMA
this i� day of Li CUP‘ 20'3 1.
CITY CONTRACT NO:
RESOLUTION NO
CONTRACTOR
Limited Liability Company
Insituform Technologies. LLC ,a DE rh/Vicir
Contractor
Schulte
(Print'Name)
Its: Contracting & Attesting Officer
(President, Owner, etc.)
Address: 17988 Edison Avenue
Chesterfield, MO 63005
G:\PROJECTS\2020\20079E\Spec\20079 Spec.docx
4-2
1
ITEM TITLE:
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 4.F.
For Meeting of: January 5, 2021
Resolution authorizing a contract with I nsituform Technologies,
LLC. for Cured -In -Place Pipe Rehabilitation of Sanitary Sewer
Mains
SUBMITTED BY: Scott Schafer, Director of Public Works
David Brown, Assistant Director of Public Works
Mike Price, Wastewater/Stormwater Manager, 249-6815
SUMMARY EXPLANATION:
City of Yakima (City) Project 2495 rehabilitates approximately 15,550 linear feet of aging and
deficient concrete and clay sewer pipe in the ten locations identified on the attached Project
Location Map.
Rehabilitating deficient sewer lines reduces groundwater infiltration, improves collection system
reliability, and decreases treatment costs at the Wastewater Treatment Plant. The Project will
utilize cured -in -place pipe technology to minimize surface disturbances.
The City previously entered into an Agreement with HLA Engineering and Land Surveying, Inc.
under City Contract 2020-047 to provide engineering design, bidding, and construction services
for the pipe rehabilitation. The City utilized the procedure established by the State of Washington
for competitively bidding projects. Three contractors submitted bids, with I nsituform
Technologies, LLC. submitting the lowest bid of $676,077.
The contract is attached for City Council review in an amount not to exceed $676,077. The
project is funded by Wastewater Capital Fund 476.
ITEM BUDGETED: Yes
STRATEGIC PRIORITY: Public Safety
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
RECOMMENDATION:
Adopt Resolution
2
ATTACHMENTS:
Description Upload Date Type
❑ Resolution 12/1/2020 Resolution
❑ Contract 12/4/2020 Contract
❑ Project Location Map 11/19/2020 Backup Material
March 12, 2021
OWNER:
PROJECT NAME.
CITY PROJECT NO
HLA PROJECT NO
CONTRACTOR:
CHANGE ORDER NO. 1
City of Yakima
CIPP REHABILITATION - PRIORITY 1
2495
20079C
Insituform Technologies, LLC
THE FOLLOWING CHANGES ARE HEREBY MADE TO THE CONTRACT DOCUMENT.
Original Contract Price (Including State Sales Tax):
$676,076.50
Current Contract Price Adjusted by Previous Change Order(s) (Including
State Sales Tax):
$676,076.50
Change in Contract Price Due to This Change Order (Including State Sales):
$129,882.59
Adjusted Contract Price Due to This Change Order (Including State Sales
Tax).
$805,959 09
Original Contract Completion Date:
April 26, 2021
Current Contract Completion Date Adjusted by Non -Working Days and/or
Previous Change Order
April 14, 2021
Change in Contract Completion Date Due to This Change Order
Two (2) Additional Working Days
Revised Contract Completion Date.
April 16, 2021
CONTRACTOR.
ENGINEER.
OWNER.
Insithform Technologies, LLC
Digitally signed by MichaelR
Date t2021.03.15 10:24:30
-07'00'
HLA Engineering and Land Surveying, Inc.
City of Yakima
CITY CONTRACT NO.
RESOLUTION NO'
oil Icail
-P0, _[) 0 o% -
G \PROJECTS \ 2020\20079C - YA CIPP REHAB- PRIORITY 1- INSITUFORM TECHICHANGE ORDERS12021-03-12 CHANGE ORDER 1
Date 03/15/2021
Date.
Date. 3 l g4 arDI
March 12, 2021
City of Yakima
CIPP REHABILITATION - PRIORITY 1
City Project No 2495
HLA Project No 20079C
CHANGE ORDER NO. 1
ITEM
NO.
DESCRIPTION
UNIT
QTY
UNIT
PRICE
AMOUNT
1-1
Increase quantity Bid Item 12 - Clean and
Video Inspect Existing Pipe - due to four
additional segments of pipe being added to the
project.
LF
1,198
$4 30
$5,151 40
1-2
Reduce quantity Bid Item 15 - Cured in Place
Pipe Rehabilitation 12 In. Diam. Reduction in
polyester resin quantity, replaced with epoxy
(non -styrene) resin included in Change Order
Bid Item No 1-4
LF
-956
$37 00
($35,372.00)
1 3
Increase quantity Bid Item 18 - Reinstate
Existing Side Service, Internal - due to four
additional segments of pipe being added to the
project.
EA
12
$136 00
$1,632.00
1-4
Epoxy (non -styrene) resin CIPP for footage
associated with the portion of 12" pipeline
running beneath Del Monte.
LF
956
$72.00
$68,832.00
1-5
Epoxy (non -styrene) resin CIPP for 15" pipeline
footage running beneath Del Monte.
LF
350
$120 00
$42,000 00
1-6
Epoxy resin CIPP for 6" pipeline footage
running through backyards at,Folsom Ave
LF
848
$44 44
$37,685.12
CHANGE ORDER NO 1 SUBTOTAL
$119,928.52
8 3% STATE SALES TAX
$9,954 07
CHANGE ORDER NO 1 TOTAL
$129,882.59
REASON:
An additional pipe segment was added to the project consisting of approximately 350 lineal feet of 15" diameter pipe
as shown on sheet Al through A3. The added pipe and pipe segements running from MH11 on sheet 41 through
MH13 on sheet 42 will use epoxy resin in place of the standard styrene resin Change in resin is due to the pipe being
inside the active Del Monte fruit handling warehouse The epoxy resin is nontoxic, meeting food grade safty
standards, and meets the structural requirements of styrene resin. Three additional pipe segments were added to the
project consisting of approximately 848 lineal feet of 6" diameter pipe as shown on sheet A4 through A6 The added
pipe and pipe segements run north and south from MH41 on sheet 53
G\PROJECTS12020120079C- YA CIPP REHAB - PRIORITY1- INSITUFORM TECH\CHANGE ORDERS2021-03-12 CHANGE ORDER 1 2