HomeMy WebLinkAbout06/05/2012 07 2013 thru 2018 Six-Year Transportation Improvement Program Adoption - Public Hearing X , BUSINESS OF THE CITY COUNCIL YAKIMA, WASHINGTON AGENDA STATEMENT Item No. For Meeting of: June 5, 2012 • ITEM TITLE: Public Hearing to consider: A) Adoption of the Six -year Transportation Improvement Program (TIP) for the years 2013 to 2018, and to amend the Metropolitan Transportation Plan; and B)Amend the Yakima Urban Area Comprehensive Plan Capital Facilities Element SUBMITTED BY: Joan Davenport, Acting Director of Community and Economic Development CONTACT Doug Mayo, City Engineer, 576 -6678 PERSON /TELEPHONE: SUMMARY EXPLANATION: Attached is the 2013 - 2018 Six -year TIP, along with an explanation sheet that describes the information contained on the various columns of the Six -year TIP. Two projects have been added to the six -year TIP. The projects are: • #18 S. 75 Avenue - Mead Ave. to Nob Hill Blvd. • #46 S. 80 Avenue Bridge (over Wide Hollow Creek) Projects that that have been removed from the 2012 - 2017 TIP as they were completed or the funds were obligated include: • Powerhouse/William O. Douglas Trail Connector • Nob Hill Blvd. - 49 Avenue to 64 Avenue Many Yakima Transit projects have also been removed from the City's TIP as they have elected to create their own six -year TIP. Their six -year TIP is no due until December. Council and the public are welcome to add other arterial system projects to the list. The six - year TIP project listing will be finalized at the June 19 hearing and sent to the Yakima Valley Conference of Governments (YVCOG) after approval. City and County staff, together with the Council Intergovernmental Committee, are working toward common standards and coordinated planning for public projects that impact both the city and surrounding county areas. Agreement on these issues will be the first step toward the goal of a seamless transportation planning process between the City and County. A)Each year the City is required by RCW 35.77.010 and RCW 36.81.121 to update its Six - year Transportation Improvement Program (TIP) for submittal to the Washington State Department of Transportation. This plan must include all transportation projects for which state gas tax revenue of federal revenue will be used. The current plan for 2013 - 2018 includes two projects that are funded. Funding for the remainder of the projects will continue to be sought. We have grant applications in for six more projects. Six -year Transportation Improvement Program (TIP) Background On August 10, 2005, the President signed into law the Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA -LU). This act is the next authorization after the prior Transportation Equity Act of 1998 for the 21 Century (TEA -21) and previous Intermodal Surface Transportation Efficiency Act (ISTEA) of 1991. The current act again specifies the systems on which certain funds can be used and activities for which funds can be used and promotes the role of the Metropolitan Planning Organizations (MPO) in the planning and programming of projects. SAFETEA -LU requires each designated MPO to develop a Transportation Improvement Program (TIP), and the state to develop a Statewide Transportation Improvement Program (STIP) as a condition to securing federal funds for the transportation projects. Projects listed in the STIP are the only projects that can be approved by the Federal Highway Administration (FHWA) and the Federal Transit Administration (FTA) to utilize federal fund of by the State of Washington for approved. State funding agencies. The STIP is a prioritized program of transportation projects, complied from local and regional plans, along with the Washington Transportation System Plan (WTP), which provides a backbone for developing projects for the intermodal transportation network in the State of Washington. The STIP contains federally funded projects plus state and local projects that are regionally significant. These projects have been identified through the planning process as the highest priority for the available funding to the state's transportation program. Planning activities of state and local governments are essential parts of integrated regional planning processes. Long range transportation planning is a part of the comprehensive land use planning carried out by local governments. Citizen participation is an integral part of the planning process at all levels. Local Agencies are required to develop and adopt a six -year transportation program. All local agencies are required to hold at least one public hearing during the development of the six -year transportation program. Project ranking has been performed utilizing data supplied by the Street and Traffic Division. The ranking will be integrated with other project needs and the total list will be reviewed and adjusted to the particular need of the City of Yakima. B) The City needs to amend the Yakima Urban Area Comprehensive Plan Capital Facilities Element to incorporate the adopted six -year TIP for 2013 to 2018. This will ensure that we are in compliance with the Growth Management Act and that we are consistent with. the Comprehensive Plan as required. The amendment is limited to incorporate only those projects that adopted in the STIP and is not subject to the "once a year" change required under the laws of the Growth Management Act. Resolution Ordinance Other Six -Year TIP (specify) Contract: Mail to: Contract Term: Amount: Expiration Date: Insurance Required? No Funding Source: Phone: APPROVED FOR SUBMITTAL: City Manager STAFF RECOMMENDATION: 1. Hold the Public Hearing to consider adoption of Resolution approving the Six -Year TIP amending the regional Metropolitan Transportation Plan and the Comprenhensive Plan Capital Facilities Element. 2. Continue Public Hearing to the June 19, 2012 Council Meeting for second Public Hearing and possible adoption of plan. BOARD /COMMISSION RECOMMENDATION: ATTACHMENTS: Click to download ❑ TIP Explanation Sheet ❑ 2013 - 2018 Transportation Improvement Program 9. Appendices A. Six Year Form Instructions Heading Agency Enter name of the sponsoring agency. County Number Enter the OFM assigned number (see LAG Appendix 21 44). City Number Enter the OFM assigned number (see LAG Appendix 21 45). MPO /RTPO Enter the name of the associated MPO (if located within urbanized area) or RTPO (if located in a rural area). Hearing Date Enter the date of the public hearing Adoption Date Enter the date this program was adopted by council or commission Resolution Number Enter Legislative Authority resolution number (if applicable ) Amendment Date Enter the date this program was amended by council or commission. Column Number 1. Functional Classification. Enter the appropriate 2 -digit code denoting the Federal Functional Classification. (Note: The Federal Functional Classification must be approved by FHWA.) Description 00- No Classification Rural (Under 5000 pop.) Urban (Over 5000 pop.) 01 - Interstate 11- Interstate 02 - Principal Arterials 12- Freeways & Expressways 06 - Minor Arterials 14- Other Principal Arterials 07 - Major Collector 16- Minor Arterial 08 - Minor Collector 17- Collector 09 - Local Access 19- Local Access 1. Priority Numbers. Enter local agency number identifying agency project priority (optional). 2. Project Identification. Enter (a) Federal Aid Number if previously assigned; (b) Bridge Number; (c) Project Title; (d) Street/Road Name or Number /Federal Route Number; (e) Beginning and Ending Termini (mile post or street and (f) Describe the Work to be Completed. 3. Improvement Type Codes. Enter the appropriate federal code number. Description 01- New construction on 07 - Resurfacing 14 - Bridge Program - Special new alignment 08 - New Bridge Construction 21 - Transit Capital Project 02- Relocation 09- Bridge Replacement 22- Transit Operational Project 03- Reconstruction 10 - Bridge Rehabilitation 23 - Transit Planning 04- Major Widening 11 - Minor Bridge Rehabilitation 24 - Transit Training /Admin. 05- Minor Widening 12 - Safety /Traffic Operation /TSM 31- Non Capital Improvement 06- Other Enhancements 13 - Environmentally Related 32 - Non Motor Vehicle Project 25 5. Funding Status. Enter the funding status for the entire project which describes the current status. S - Project is selected by the appropriate selection body and funding has been secured by the lead agency. P - Project is subject to selection by an agency other than the lead and is listed for planning purposes. (Funding has not been determined.) 6. Total Length. Enter project length to the nearest hundredth (or code "00" if not applicable). 7. Utility Code(s). Enter the appropriate code letter(s) for the utilities that would need to be relocated or are impacted by the construction project. C - Cable TV G - Gas 0 - Other P - Power S - Sewer (other than agency- owned) T - Telephone W - Water 8. Project Phase. Select the appropriate phase code of the project. PE - Preliminary Engineering only (or Planning) RW - Right of Way or land acquisition only (or equipment purchase) CN - Construction only (or transit operating) ALL - All Phases: from Preliminary Engineering through Construction 9. Phase Start Date. Enter the month /day /year in MM /DD/YY format that the selected phase of the project is actually expected to start. 10. Federal Fund Code. Enter the Federal Fund code from the table. FTA Discretionary for Capital Expenditures BIA - Bureau of Indian Affairs 5307 - FTA Urban Areas BR - Bridge Replacement or Rehab 5309(Bus)- Bus CDBG - Community Development 5309(FG) - Fixed Guideways Block Grant (HUD) 5309(NS) - New Starts CMAQ - Congestion Mitigation Air Quality 5310 - FTA Elderly /Disabled DEMO - ISTEA Demo Project (Selected) 5311 - FTA Rural Areas Discretionary - Ferry Boat Discretionary, Public REV - Rural Economic Vitality Program Lands Highways, or Scenic Byways STP(C) - STP Statewide Competitive Program DOD - Dept. of Defense STP(E) - STP Transportation Enhancements IC - Interstate Construction STP(S) - STP Safety Including Hazard and RR IM - Interstate Maintenance STP(R) - STP Rural Regionally Selected NHS - National Highway System STP(U) - STP Urban Regionally Selected STP - WSDOT use only 11. Federal Funds. Enter the total federal cost (in thousands) of the phase regardless of when the funds will be spent. 12. State Fund Code. Enter the appropriate code for any of the listed state funds to be used on this project. 26 CAPP - County Arterial Preservation Program PWTF - Public Works Trust CHAP - City Hardship Assistance Program RAP - Rural Arterial Program TPP - Transportation Partnershis Program SCP - Small City Program AIP - Arterial Improvement Program WSDOT - WSDOT funding PSMP - Pedestrian Safety & Mobility Program OTHER - All other unidentified state funding PTST - Public Transportation Systems Progra 13. State Funds. Enter all funds from the State Agencies (in thousands) of the phase regardless of when the funds will be spent. 14. Local Funds. Enter all the funds from Local Agencies (in thousands) of the phase regardless of when the funds will be spent. 15. Total Funds. Enter the sum of columns 10, 12, and 14. (Auto - calculation in the "STIP Too" program.) 16 -19. Expenditure Schedule - (1st, 2nd, 3rd, 4th thru 6th years). Enter the estimated expenditures (in thousands) of dollars by year. (This data is for Local Agency use.) 20. Environmental Data Type. Enter the type of environmental assessment that will be _ required for this project. (This is "required" for Federally funded projects, but may be filled in for state or locally funded projects.) EIS - Environmental Impact Statement EA - Environmental Assessment CE - Categorical Exclusion 21. RNV Certification. Click Y if Right of Way acquisition is required. If yes, Enter R/W Certification Date, if known. (This is "required" for Federally funded projects only.) 27 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co. From 2013 to 2018 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: Adoption Date: Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded Expenditure Schedule m w Project Identification 'Fund Source Information . Only a m (Local Agency) u E / A. PIN /Federal Aid No. B. Bridge No. c t Federal Funding R W G Project Title m 't, v t - Phase 4 Z D. stre /Rood Name or Number N °3 ` ° Federal State State Local Total Envir Required Start Federal Fund c`o E. Beginning MP or Road - Ending MP or Road o. a ' 1p "g. o Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date ,: a F Describe work to Be Done _ E Ft ∎if la 5 a Phase (MM/YY) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 14 1 Yakima Railroad Grade Separations - Phase 3 01 P 0.2 T CN 1/1/2013 STP(U) 798 FMSIB 3,500 2,200 6,498 3,000 3,498 EA Yes Martin Luther King, Jr. Boulevard 06 P CN 1/1/2013 DEMO 2,582 AIP 6,000 8,582 3,000 5,582 from: N. 1st Street to: N. 1st Avenue 07 G 9/1/2009 Grade separate the rail and vehicle traffic at the 08 O Martin Luther King, Jr Boulevard rail crossing. Construct a Front Street Bridge over Martin Luther King, Jr. Boulevard. Totals 3,380 9,500 2,200 15,080 6,000 ,9,080 16 2 64th Avenue Roadway Widening 04 5 0.5 W CN I1 /1/20131 STP(U) 1 7491 I l 1761 925 9251 I I CE Yes 64th Avenue 06 G from: Nob Hill Boulevard to: Tieton Drive 03 P 10/31/2011 T Widen roadway, install curb, gutter, sidewalk, lighting C and drainage. 0 Totals 749 176 925 925 14 3 North 1st Street Revitalization P 0.42 P CN 1 1/1/20141 STP(U) I 2,6631 1 1 4161 3,0791 I 3,0791 I CE No North 1st Street T from: 'N' Street to: SR 12 0 C - Improve North 1st Street by rehabilitating the pavement and lane markings, removing on- street parking, enhancing street and pedestrian lighting, constructing median islands and installing various pedestrian and decorative elements. Totals 2,663 416 3,079 3,079 14 4 E. Nob Hill Blvd. & Fair Ave. l/5 Improvements 03 P N/A P RW 1/1/2015 STP(U) 173 27 200 200 CE Yes Nob Hill Boulevard 04 T CN 6/1/2016 STP(U) 865 135 1,000 1,000 from: E. Nob Hill Blvd. to: Fair Ave. 31 W 1 1 1 t 4/1/2015 • C Widen Nob Hill Boulevard through the intersection, 0 construct left-turn lane, curb, gutter, sidewalk, street • lighting and drainage. Upgrade signal by installing i mast arm structures. Totals 1,038 162 1,200 200 1,000 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co. From 2013 to 2018 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: Adoption Date: Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded Project Identification Fund Source Information — Expenditure Schedule Projects Only n (Local Agency) 1 10 j A. PIN /Federal Aid No. B. Bridge No. w L b m Federal Funding R/W Z C. Project Title E ti v t Phase ° D. Street/Road or u ° « Federal State State Local Total Envir Required L c Start Federal Fund .o E. Beginning MP or Road - Ending MP or Road o. > m c L o Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date E.- F Describe Work to Be Done E r vi 2 j o Phase (MM/YY) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19, 20 21 14 5 E. Lincoln Avenue & 10th Street Roundabout 03 P N/A P PE 1/1/2014 STP(U) 173 27 200 200 CE ' Yes Martin Luther King, Jr Boulevard 05 RW 1/1/2015 STP(U) 433 67 500 500 from: E. Lincoln Ave. to: N. 10th Street 06 CN 1/1/2016 STP(U) 1,125 , 175 1,300 1,300 10/31/2015 Construct a roundabout at the intersection of Lincoln Avenue, 10th Street and MLK, Jr Boulevard. Install curb, gutter, sidewalk, street lighting and drainage. Totals 1,731 269 2,000 200 500 1,300 12 6 SR 12 & 16th Avenue Interchange 03 P N/A 0 PE 1 1/1/20151 STP(U) 1 861 1 1 141 1001 1 1 1001 CE No Westbound ramps of SR 12 06 CN 1/1/2016 STP(U) 779 121 900 900 from: 16th Avneue to: SR 12 Construct a roundabout where the westbound ramps intersect with N. 16th Avenue. Totals 865 135 1000 100 900 1.1 7 1 -82 & Lincoln Avenue Interchange 01 P N/A 0 PE 1/1/2013 STP(U) 260 40 300 300 CE No Lincoln Avenue P RW 1/1/2014 STP(U) 173 27 200 200 from: E. 'G' Street to: 1 -82 G CN 6/1/2014 STP(U) 1,730 270 2,000 500 1,500 Reconstruct /extend off -ramp from existing 1 -82 off- ramp for Lincoln Avenue to E. '0' Street. Totals 2,163 337 2,500 300 ' 700 1,500 14 8 E. Yakima Ave. & Fair Ave. Signalization 12 P N/A P PE 1 1/1/20151 STP(U) 1 861 1 1 141 1001 1 1 1001 CE No Yakima Avenue T CN 6/1/2016 STP(U) 519 81 600 600 from: E. Yakima Ave. to: Fair Ave. W 5 Install traffic signal, 0 Totals 605 95 700 100 600 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co. From 2013 to 2018 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: Adoption Date: Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded m `w Project Identification Fund Source Information Expenditure Schedule a Projects Only V E A. PIN /Federal Aid No. B. Bridge No. c Federal Funding Local Agency) / 2 z' C• Project Title E E'o - 5 t Phase g R W o D.street/RoadNameorNumher N J d a Federal State State Local Total Envir Required Start Federal Fund c o E. Beginning MP or Road - Ending MP or Road a a 3 m 'o Cast by Fund Co Funds Funds Funds 1st 2nd 3rd 4th Type Date 2 a F Describe Work to Be Done E F N = a Code Phase (MM /YY) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 16 9 S. 3rd Avenue & W Washington Ave. Signal 12 P N/A P PE 4/1/2013 20 20 20 CE No S. 3rd Avenue - T CN 9/1/2013 210 210 210 from: S. 3rd Ave. to: W Washington Ave. Upgrade the traffic signalization system Totals 230 230 230 14 10 S. 1st St. & E. Washington Ave. l/S Improvements 03 P N/A P PE 1/1/2014 STP(U) 260 40 300 300 . CE Yes South 1st Street 06 W RW 9/1/2014 STP(U) 260 40 300 100 200 from: S. lstStreet to: E. Washington Ave. 5 CN 9/1/2015 STP(U) 1,211 189 1,400 200 1,200 8/1/2015 Realign intersection, widen E. Washington Avenue to T accommodate an additional lane, replace curb, gutter 0 and sidewalk, and install a new traffic signalization system. Totals 1,731 269 2,000 400 400 1,200 ' 17 11 S. 48th Avenue Reconstruction 03 P 1.00 P PE 1/1/2014 STP(U) 223 35 258 200 - 58 CE Yes South 48th Avenue 05 T RW 1/1/2015 STP(U) 519 81 600 600 from: Sumrnitview Ave. to: Nob Hill Blvd. W CN 1/1/2016 STP(U) 1,485 232 1,717 1,485 12/1/2015 5 Reconstruct and widen 48th Avenue, install curb, O gutter, sidewalk, street lighting and drainage system. Totals 2,227 348 2,575 200 658 1,485 14 12 S. 72nd Ave. & Mead Ave. 1/S Signalization 12 P N/A P PE 1 1/1/20131 SRTS 1 251 I 1 5 301 301 1 1 CE No S. 72nd Avenue T CN 6/1/2013 SRTS 258 25 283 283 from S. 72nd Ave. to: Mead Ave. W S Install traffic signal system. 0 Totals 283 30 313 313 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co. From 2013 to 2018 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: Adoption Date: Amend Date: Resolution No.: Project Costs In Thousands of Dollars Federally Funded • m to Project Identification , r Fund Source Information Expenditure Schedule Projects Only U E A. PIN /Federal AId No. B. Bridge No. c (Local Agency) a F e d era l Funding R/W o Z C. Project Title u a Phase Federal State State Local Total Envir Required D Street /Road Name or Number > Start Federal Fund c . E. Beginning MPar Road - Ending MP or Road a — o. ,,, ^ L o Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date , d F Describe Work toBeDone E F .n r 5 a Phase (MM /YY) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 17 13 Zier RoadImprovements 06 P 0.15 P PE 1/1/2013 SRTS 25 5 30 30 CE No Zier Road T CN 6/1/2013 SRTS 236 25 261 261 from: 75th Ave. to: 72nd Ave. C Install curb, gutter and sidewalk on the south side of S Zier Road. Totals 261 30 291 291 16 14 Tieton Dr & 5. 5th Ave. 1/5 Improvements 12 P N/A P PE 1/1/2015 STP(U) 69 11 80 80 CE Yes Tieton Drive W RW 1/1/2016 STP(U) 104 16 120 120 from: Tieton Dr. to: 5. 5th Ave. S CN 6/1/2016 STP(U) 865 135 1,000 1,000 5/1/2016 Remove existing traffic signal and construct a T roundabout, remove and replace curb, gutter, 0 sidewalk, street lighting and drainage Totals 1,038 162 1,200 80 1,120 16 15 E. 'H' Street Extension 01 P 1.10 P PE 1/1/2013 STP(U) 303 47' 350 250 100' CE Yes E. 'H' Street 08 T RW 6/1/2014 STP(U) 303 47 350 150 200 from: lst Street to: Yakima River W CN 1/1/2016 STP(U) 1,730 270 2,000 2,000 12/1/2015 Construct new roadway including water, sewer, curb, S gutter, sidewalk, street lighting and storm drainage 0 system. Totals 2,336 364 2,700 250 250 2,200 17 16 N. 10th Street Extension 01 P 1.3 P PE 1/1/2013 STP(U) 700 108 808 700 108 CE Yes North 10th Street 06 T RW 6/1/2014 STP(U) 5,500 850 6,350 300 6,050 from: 'R' Street to: Lincoln Ave. W CN 1/1/2016 STP(U) 7,900 972 8,872 8,872 12/1/2015 Construct new roadway including water, sewer, curb, S gutter, sidewalk, street lighting and storm drainage 0 system. Totals 14,100 1,930 16,030 700 408 6,050 8,872 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co. From 2013 to 2018 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: Adoption Date: Amend Date: Resolution No.: • Project Costs in Thousands of Dollars Federally Funded Expenditure Schedule `v projects Only Project Identification Fund Source Information (Local Agency) E A. PIN /Federal Aid No. B. Bridge No. w .c ' w '^ Federal Funding R/W c z C. Project Title E s v -c Phase D. Street /Road Name or Number N u a- Federal State State Local Total Envir Required c _ Start Federal Fund c E. Beginning MP or Road - Ending MP or Road o, n ' m o Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date Li.. F. Describe Work to Be Done E F N 2 5 a Phase . (MM /YY) 1 2 3 4 5 6 7 8 9 10 11 . 12 13 14 15 16 17 18 19 20 21 ' 17 17 Yakima Downtown Future Initiatives, Phase 5 06 P 0.15 P PE 1/1/2014 OTHER 500 500 500 CE No 12 T CN 4/1/2015 OTHER 5,500 5,500 5,500 from: 1st Street to: 9th Street C Install historic lighting, sidewalk modifications and 5 other improvements. Exact improvement area(s) to be determined Totals 6,000 500 5,500 17 18 75th Avenue Improvements 01 P 0.50 P PE 1/1/2016 STP(U) 87 13 100 100 CE No 75th Avenue 08 W RW 1/1/2017 STP(U) 173 27 200 200 from: Mead Ave. to: Nob Hill Blvd. 5 CN 1/1/2018 STP(U) 1,038 162 1,200 1,200 Construct portions of and widen roadway, install T - curb, gutter, sidewalk, street lighting and storm 0 drainage system. t Totals 1,500 1,500 14 19 Washington Ave. & Longfiber Rd. Intersection 03 P N/A C PE 1/1/2014 STP(U) 100 14 114 114 CE Yes Washington Avenue 05 T RW 6/1/2014 STP(U) 100 .14 114 114 from: Washington Ave. to: Longfiber Rd. 06 W CN 1/1/2015 STP(U) 700 95 795 795 12/1/2015 Widen Washington Avenue to 5 lanes and widen 5 Longfiber Road to 3 lanes, install or replace curb, 0 gutter, sidewalk, street lighting and Safety Flashing Signal. Totals 900 123 1,023 228 795 14 20 E. Nob Hill Blvd. & S. 18th Street 1/5 lmprovements ,01 P 0.10 C PE 1/1/2014 STP(U) 50 8 58 58 CE No E. Nob Hill Boulevard 04 T CN 6/1/2014 STP(U) 346 54 400 400 from: E. Nob Hill Blvd. to: S. 18th Street W Widen south leg for double left turn from westbound 5 Nob Hill, install curb, gutter, sidewalk, upgrade traffic signal system Totals 396 62 458 458 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co. From 2013 to 2018 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: Adoption Date: Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded m Zr, Project Identification N Fund Source Information Expenditure Schedule Projects Only V E g A. PIN /Federal Aid No. 8. Brid a No. c Federal Funding R/W (Local Agency) - r ;, o z' . StreectTitie a ` i u 11 Phase Federal State State Local Total Envir Required D. Street /Road Name or Number : •,-,-; _ r Start Federal Fund c . ."8 D E. Beginning MP or Road - Ending MP or Road a E ' T. o Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date Li n F Describe Work to Be Done E m � �, 12 a Phase (MM /YY) 1 2 3 4 . 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 16 21 Powerhouse Rd. & Englewood Ave. I/5 12 P N/A ' P PE 1/1/2014 STP(S) 43 7 50 50 CE Yes Powerhouse Rd. T RW 1/1/2015 STP(S) 87 13 100 100 from: Powerhouse Rd. to: Englewood Ave. C CN 6/1/2015 STP(S) 504 74 578 578 5/1/2015 5 Intersection realignment, install curb, gutter, 0 sidewalk, Safety Flashing Signal. W Totals ' 634 94 728 50 678 14 22 S. 48th Ave. & Summitview Ave. Signolization 12 P N/A P PE 1/1/2015 STP(S) 25 4 29 29 CE Yes Summitview Avenue T RW 6/1/2015 STP(S) 25 4 29 29 from: Summitview Ave. to: S. 48th Ave. CN 1/1/2016 STP(S) 554 81 635 635 12/1/2015 Install traffic signalization system Totals 604 89 693 58 635 14 23 W Lincoln Ave. & MLK Blvd. Realignment 01 P 0.50 C PE 1/1/2014 STP(E) 424 67 491 491 CE Yes W Lincoln Avenue 12 T RW 1/1/2015 STP(E) 1,047 163 1,210 1,210 from. W 5th Ave. to: Custer St. W CN 1/1/2016 STP(E) 1,801 281 2,082 2,082 12/1/2015 S , 0 Realign W Lincoln Avenue. Install curb, gutter, P sidewalks, street lighting, drainage. G Totals 3,272 511 3,783 491 1,210 2,082 14 24 E. Nob Hill Boulevard Reconstruction 03 P 0.85 C PE 1/1/2014 STP(C) 546 84 630 630 CE Yes E. Nob Hill Boulevard 04 T RW 1/1/2015 STP(C) 1,090 170 1,260 1,260 from: S. 6th Street to: 5. 18th Street 06 W CN 1/1/2016 STP(C) 6,539 1,013 7,552 7,552 12/1/2015 5 Reconstruct and widen roadway to 5 lanes with 0 intersection improvements, curb, gutter, sidewalk, P street lighting and drainage system G Totals 8,175 1,267 9,442 630 1,260 7,552 Agency: Yakima Six Year Transportation Improvement Progra Co. No.: 39 Co. Name: Yakima Co. From 2013 to 2018 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: Adoption Date: Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded iv Project Identification Fund Source Information Expenditure Schedule Projects Only 0 E A. PIN /Federal Aid No. B. Bridge No. c a^ (Local Agency) y z' .Prolectera E c a Phase F ederal Funding t R/W 72 o m _ J Federal State State Local Total Envir Required D. Street /Road Name or Number c N Y Start Federal Fund o E. Beginning MP or Road - ending MP or Road a r„.' m a o Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date , 1 F Describe Work to Be Done E o Phase (MM /YY) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 16 25 5. 72nd Ave. & W Washington Ave. I/S 12 P N/A P PE 1/1/2014 STP(C) 91 14 105 105 CE Yes S. 72nd Avenue 06 T RW 1/1/2015 STP(C) 91 14 105 105 ' from: s. 72nd Ave. to: W Washington Ave. 0 CN 1/1/2016 STP(C) 544 86 630 630 12/1/2015 Improve intersection by installing a traffic signal 5 system or roundabout. W _ Totals 726 114 840 105 105 630 17 26 S. 66th Avenue Improvements 03 P 0.76 P PE 1/1/2014 STP(E) 86 '14 100 100 CE Yes 66th Avenue 04 T RW 1/1/2015 STP(E) 173 27 200 200 from: Summitview Ave. to: Scenic Dr W CN 1/1/2016 STP(E) 1,096 164 1,260 1,260 12/1/2014 5 Reconstruct and widen roadway, install curb, gutter, 0 sidewalk, storm drainage system and utilities. Totals 1,355 205 1,560 100 200 1,260 14 27 N. 40th Ave. & Summitview Dr VS 12 P N/A P PE 1/1/2014 STP(U) 126 17 143 143 CE Yes N.40th Avenue T RW 1/1/2015 STP(U) 63 8 71 71 from: N. 40th Ave. to: Summitview Dr W CN 1/1/2016 STP(U) 544 86 630 630 12/1/2015 Improve the intersection by constructing larger curb 5 radii, lenghtening the turn lanes, and upgrading the 0 traffic signal system. Totals 733 111 844 143 71 630 14 28 N. 40th Ave. & Englewood VS 12 P N/A P PE 1/1/2015 STP(U) 43 7 50 50 CE No N. 40th Avenue T 09 6/1/2015 STP(U) 260 40 300 300 from: N. 40th Ave. to: Englewood Replace traffic signal poles and upgrade controller . Totals 303 47 350 350 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co. From 2013 to 2018 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: Adoption Date: Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded m a Project Identification a Fund Source Information Expenditure Schedule Projects Only V E A. PIN /Federal Aid No. B. Bridge No. t (Local Agency) R/W ,� '^ m Federal Funding C. Project Title E v d Phase g 0 « D. Street /Road Name or Number ; a u ° Federal State State Local Total Envir Required c o E. Beginning MP or Road - Ending MP or Road a L o Start Federal Fund Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date ii & F. Describe Work to Be Done E ,2 n r 5 o . Code Phase (MM /YY) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 14 29 N. 16th Avenue & Fruitvale Blvd. 1/5 12 P N/A P PE 1/1/2013 STP(U) 126 18 144 144 CE Yes N. 16th Avenue T RW 6/1/2013 STP(U) 173 27 200 200 • from: N. 16th Ave. to: Fruitvale Blvd. 0 CN 3/1/2014 STP(U) 315 43 358 358 2/1/2014 Improve the intersection by constructing larger curb S radii, installing ADA ramps, and.upgrading the traffic W signal system. Totals 614 88 702 344 358 14 30 N. 1st Street &'I' Street l /SImprovement 12 P N/A P PE 1/1/2015 STP(E) 32 5 37 37 CE No N. 1st Street T CN 6/1/2015 STP(E) 126 17 143 143 from: N. 1st Street to: 'I'Street W S Replace and upgrade traffic signal system 0 Totals 158 22 180 180 17 31 Rudkin Road Reconstruction 03 P 0.76 P PE 1/1/2014 STP(C) 109 27 136. 136 CE No • Rudkin Road 06 T CN 1/1/2015 STP(C) 945 TPP 945 106 1,996 1,996 from: E. Viola Ave. to: Rainier PI. W S Reconstruct roadway, install curb, gutter, sidewalk and storm drainage. Partner with Union Gap to install additional sewer force main. Totals 1,054 133 2,132 136 1,996 0 16 32 E. Mead Avenue Reconstruction 03 P 0.76 P PE 1/1/2015 STP(S) 122 TPP 23 7 152 152 CE No E. Mead Avenue 06 T CN 1/1/2016 STP(S) 1,730 TPP 206 70 2,006 2,006 from: Rudkin Rd. to: Fair Ave. 5 Partner with Union Gap to reconstruct E. Mead C Avenue, install curb, gutter, sidewalk and storm G drainage system. 0 Totals 1,852 229 77 2,158 152 2,006 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co. From 2013 to 2018 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: Adoption Date: Amend Date: Resolution No.: Project Costs in Thousands of Dollari Federally Funded Expenditure Schedule v Project Identification N Fund Source Information (Local Agency) Only 0 E A. PIN /Federal Aid No. B. Bridge No. c -c m C L Federal Funding R/W c z C. Project Title E 'moo c -_ Phase 4 a D. Street /Road Name or Number i — " St art F Fund Federal State State Local Total 4th Envir Required ° u 3 m 8 ' a Cost by Fund Code Funds Funds Funds 1st 2nd 3rd Thar Type Date c `o E. Beginning MP or Road - Ending MP or Road o. n ,� _ o Code Y Yp u ci , F. Describe Work to Be Done ' E 5 ig F j it Phase 6th (MM /YY) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 i 20 21 17 33 S. 80th Avenue Improvements 04 P 1.30 P PE 1/1/2015 AIP 131 20 151 151 CE Yes S. 80th Avenue T RW 1/1/2016 AIP 382 59 441 441 from Tieton Drive to: Zier Road 0 CN 1/1/2017 AIP 1,667 260 1,927 1,927 12/1/2016 S Widen roadway, install curb, gutter, sidewalk, street W lighting and storm drainage system. C Totals 2,180 339 2,519 151 2,368 17 34 Englewood Avenue Improvements 05 P 1.00 P PE 1/1/2015 STP(C) 272 43 315 315 CE Yes Englewood Avenue 06 T RW 1/1/2016 STP(C) 349 55 404 404 from: N. 40th Ave. to: N. 56th Ave. W CN 1/1/2017 STP(C) 2,352 340 2,692 2,692 12/1/2016 S Widen roadway, install curb, gutter, sidewalk, street O lighting and storm drainage system. C Totals 2,973 438 3,411 315 3,096 17 35 Englewood Avenue lmprovements 05 P 0.50 P PE 1/1/2015 STP(U) 136 21 157 157 CE Yes Englewood Avenue 06 T RW 1/1/2016 STP(U) 173 27 200 200 from. N. 16th Ave. to: N. 24th Ave. W CN 1/1/2017 STP(U) 1,164 182 1,346 1,346 12/1/2016 Widen roadway, install curb, gutter, sidewalk, street 5 lighting and storm drainage system. Totals 1,473 230 1,703 157 1,546 • 14 36 Nob Hill Boulevard Sidewalk Improvements 12 P 2.50 P PE 1/1/2015 STP(S) 55 8 63 63 CE Yes Nob Hill Boulevard T RW 1/1/2016 STP(S) 107 19 126 126 from: 5. 16th Ave. to: 5. 6th Street S CN 1/1/2017 STP(S) 321 57 378 378 12/1/2017 Construct sidewalk in locations where it doesn't exist W on the south side of Nob Hill • Totals 483 84 567 63 504 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co. From 2013 to 2018 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: Adoption Date: Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded Project Identification Fund Source Information Expenditure Schedule Projects Only U E A. PIN /Federal Aid No. B. Bridge No. L 6 R/W c z' C. Proles Title E E -o a Phase Federal Funding Z . - D. street /Road Name or Number ; N Federal State State Local Total 4th Envir Required Start Federal Fund c `o E. Beginning MP or Road - Ending MP or Road . a o Cost by Fund Code Funds Funds Funds 1st 2nd 3rd Thru Type Date u.. ` F. Describe Work to Be Done .E r Si 2 5 o' Cod Phase 6th (MM /YY) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 17 37 N. 34th Ave. & Fruitvale Blvd. I/S Improvements 12 P N/A P PE 1/1/2015 STP(U) 63 S 68 68 CE No ' Fruitvale Boulevard T CN 1/1/2016 STP(U) 567 76 643 643 from: Fruitvale Blvd. to: N. 34th Ave. 0 Improve intersection installing a traffic signal system, 5 curb, gutter and sidewalk. W Totals 630 81 711 68 643 17 38 Englewood Avenue Improvements 03 P 1.00 P PE 1/1/2015 STP(U) 218 34 252 252 CE Yes Englewood Avenue 05 T RW 6/1/2016 STP(U) 327 51 378 378 from: N. 24th Ave. to: N. 40th Ave. 06 W CN 6/1/2017 STP(U) 2,980 244 3,224 3,224 5/1/2017 S • Reconstruct and widen roadway, install curb, gutter, 0 sidewalk, street lighting and storm drainage system. Totals 3,525 329 3,854 252 3,602 14 39 North /South Connector to West Valley 01 P 6.00 P PE 1/1/2015 STP(U) 432 68 500 500 CE Yes Unknown Road 04 T from: Ahtanum Rd. to: Summitview Ext. 06 W 5 Corridor study to determine the best location for a C north /south limited access route in West Valley City G and County joint project. 0 Totals 432 68 500 500 14 40 River Road Improvements 03 5 0.50 P PE 1/1/2013 140 140 140 CE Yes River Road 05 T RW 6/1/2013 150 150 150 from: S. 16th Ave. to: S. 6th Ave. 06 G CN 3/1/2014 FMSIB 639 491 1,130 1,130 2/1/2014 07 W Reconstruct and widen roadway, install curb, gutter, 0 sidewalk, street lighting and storm drainage system. Totals 781 1,420 290 1,130 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co. • From 2013 to 2018 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: Adoption Date: Amend Date: Resolution No.: Project Costs in Thousands of Dollars ' Federally Funded Project Identification Fund Source Information Expenditure Schedule Projects Only U 6 A. PIN /Federal Aid No. B. Bridge No. c t c (Local Agency) W m F e d era l Funding R/W Z C.ProlectTitle E o a Phase o _ D.street /Road Name or Number > . V Start Federal Fund Federal State State Local Total 4th Envir Required B ` m 9 t .14 Cost by Fund Code Funds Funds Funds 1st 2nd 3rd Thru Type Date o a E. Beginning MP or Road - Ending MP or Road 2 . a F Describe Work to Be Done E F Si 2 n.. Cod Phase 6th (MM /YY) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 ' 18 19 20 21 14 41 18th Street Underpass 12 P N/A P PE 1/1/2015 BRAC 240 60. 300 300, CE No Yakima Avenue T CN 1/1/2016 BRAC 2,288 572 2,860 2,860 from: Yakima Ave. to: 18th Street O Replace the bridge on E. Yakima Avenue that crosses 5 ' over lath Street. W Totals 2,528 632 3,160 300 2,860 17 42 88th Avenue Improvements 06 P 0.48 P PE 1/1/2015 WSDOT 50 0 50 50 CE Yes 88th Avenue 12 T RW 1/1/2016 WSDOT 25 0 25 25 from: Tieton Dr to: Summitview Ave. C CN 1/1/2017 WSDOT 320 10 330 330 12/1/2016 G Construct curb, gutter, sidewalk and storm drainage ; system on the east side of 88th Avenue. Totals 395 10 405 50 355 16 43 64th Avenue Improvements 03 P 1.00 P PE 1/1/2014 STP(U) 200 32 232 200 CE No 64th Avenue 04 T CN 1/1/2015 STP(U) 1,600 249 1,849 1,849 from: Washington Ave. to: Nob Hill Blvd. 06 W C Widen roadway, install curb, gutter, sidewalk, street G ' lighting and storm drainage system. 0 . . _ Totals 1,800 281 2,081 200 1,849 14 44 ■. North 1st Street Revitalization 06 P 0.50 P PE 1/1/2016 STP(U) 605 95 700 700 CE No N. 1st Street 12 T CN 1/1/2017 STP(U) 5,165 806 5,971 5,971 from: MLK Blvd. to: 'N'Street G C Improve North 1st Street by rehabilitating the pavement and lane markings, removing on- street parking, enhancing street and pedestrian lighting, constructing median islands and installing various • . pedestrian and decorative elements. Totals 5,770 901 6,671 6,671 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co. From 2013' to 2018 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: Adoption Date: Amend Date: Resolution No.: Protect Costs in Thousands of Dollars Federally Funded Expenditure Schedule m Project Identification N Fund Source Information Projects Only iJ E A. PIN /Federal Ald No. B. Bridge No. c t (Local Agency) a, t F e d er al Fu nding R/W o Z C. Project Title u -, a Phase Federal State State Local Total 4th Envir Required D. Street/Road Name or Number > Start Federal Fund o E.BeglnningMParRoad- Ending MP or Road P. _ n . o Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd Thru Type Date ,i i F Describe Work to Be Done E r2 7 0 - Phase 6th (MM /YY) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 14 45 Tieton Dr & 64th Ave. l/S Improvements 13 P N/A P PE 1/1/2014 STP(U) 87 13 100 100 CE Yes Tieton Drive 05 T RW 1/1/2015 STP(U) 260 40 300 300 from: Tieton Dr to: 64th Ave. 12 0 CN 1/1/2016 STP(U) 692 108 800 800 12/1/2015 S Improve intersection by constructing a left -turn lane W on Tieton Drive, installing a traffic signal system, curb, C ' gutter, sidewalk and street lighting. G Totals 1,039 161 1,200 100 300 800 16 46 S. 80th Avenue Bridge 01 P 0.25 P PE 1/1/2014 STP(U) 44 6 50 50 CE Yes S. 80th Avenue T CN 1/1/2015 STP(U) 433 67 500 500 from: Wide Hollow Rd. to: Plath 0 12/1/2016 Construct new bridge over Wide Hollow Creek. Joint project with the County Totals 477 73 550 50 500 14 47 16th Avenue Corridor Improvement 04 P 3.50 P PE 1/1/2015 STP(U) 120 17 137 137 CE 16th Avenue T from: SR 12 to: Washington Ave. W C G Widen roadway, install curb, gutter, sidewalk, street 0 lighting and storm drainage system. 5 • • Totals 120 17 137 137 14 48 40th Avenue Corridor Improvements 04 P 3.20 P PE . 1/1/2015 STP(U) 120 17 137 137 CE 40th Avenue T from: SR 12 to: Washington Ave. W C G Widen roadway, install curb, gutter, sidewalk, street 0 lighting and storm drainage system. S Totals 17 137 137 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co. From 2013 to 2018 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: Adoption Date: Amend Date: . Resolution No.: Project Costs in Thousands of Dollars Federally Funded m r, Project Identification Fund Source Information Expenditure Schedule Pro Only • a A. PIN /Federal Aid No. B. Bridge No. c ^' (Local Agency) y E g „ c is v a, a Phase Federal Funding R/W • z ' C. Protect title E w c o Federal State State Local Total 4th Envir Required D. Street/Road Name or Number > ^ Y Start Federal Fund Q c o E. Beginning MP or Road - Ending MP or Road o n 8 1° . o Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd Thru Type Date , A: F. Describe Work to Be Dane E _i a Phase 6th (MM /YY) 1 2 3 4 5 -6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 14 49 Nob Hill Boulevard Corridor lmprovements 03 P 2.70 P PE 1/1/2015 STP(U) 120 17 137 • 137 CE Nob Hill Boulevard 04 T from: 1 -82 to: 16th Ave. 0 5 W Widen roadway, install curb, gutter, sidewalk, street C lighting and storm drainage system. G Totals 120 17 137 137 14 50 5. 1st Street /Main Street Corridor Improvements 01 P 2.00 P PE 1/1/2015 STP(U) 120 17 137 1371 CE 5. 1st Street /Main Street T from: Nob Hill Blvd. to: Barker Mill Bridge 0 5 Joint project with Union Gap. Widen roadway, install W curb, gutter, sidewalk, street lighting and storm C drainage system. G Totals 120 17 137 137 16 51 Washington Ave. Railroad Grade Separation 01 P 0.25 P PE 1/1/2015 STP(U) 1,730 270 2,000 2,000 CE Yes Washington Avenue T RW 6/1/2016 STP(U) 1,730 270 2,000 2,000 from: Russel Ln. to: Longfiber Rd. W CN 1/1/2018 STP(U) 8,650 1,350 10,000 10,000 12/1/2017 Construct railroad grade overcrossing, including all 0 utilities 5 . Totals 12,110 1,890 14,000 2,000 12,000 • 16 52 Mead Avenue Railroad Grade Separation 1 P 0.25 P PE 1/1/2015 STP(U) 1,730 270 2,000 2,000 CE Yes Mead Avenue T RW 6/1/2016 STP(U) 1,730 270 2,000 2,000 from: Presson PI. to: Maryland W CN 1/1/2018 STP(U) 8,650 1,350 10,000 10,000 12/1/2017 Construct railroad grade overcrossing, including all 0 utilities S . Totals 1,890 14,000 2,000 12;000 •