HomeMy WebLinkAbout11/17/2020 06 3rd Quarter 2020 Capital Improvement Projects Report 't..an,gtntj ka
d E$A
aY
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 6.
For Meeting of: November 17, 2020
ITEM TITLE: 3rd Quarter 2020 Capital Improvement Projects Report
SUBMITTED BY: Scott Schafer, Public Works Director
Bob Desgrosellier, Chief Engineer(Acting) 575-6228
SUMMARY EXPLANATION:
Attached for City Council approval is the City of Yakima Engineering Division's 3rd Quarter 2020
Capital Improvement Projects Memorandum and Project Spreadsheet to provide updates on
current Capital Improvement Projects from the Water/Irrigation, Wastewater/Stormwater, Streets
& Traffic and Engineering Divisions.
The project list assists in the planning of current and upcoming projects. It helps the divisions
coordinate their work efforts so that, for example, a street is not rebuilt or seal coated prior to
scheduled underground work within the same street.
Recent project activity on current public works projects is underlined in the attached report. This
report also introduces a few Water and Wastewater Division projects that are close to beginning
design, permitting, and then proceeding with construction phases in the near future as planned
and budgeted per their Capital Facility Plans.
The PowerPoint presentation will focus on the following projects:
• Mill Site - Municipal Solid Waste Cleanup
• Cowiche Canyon Trail Project
• 64th Ave &Ahtanum Rd. Intersection Improvement Project
• N. 1st St. Phase 2 Project
• Spring Creek Rd. Phase 2 Project
ITEM BUDGETED: Yes
STRATEGIC PRIORITY: Public Trust and Accountability
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
RECOMMENDATION:
2
Accept Report
ATTACHMENTS:
Description Upload Date Type
D Nm-raUves, 3rd Cid OP Report 11/232020 Cover Memo
D report 119,2n2oAer Memo
3
MEMORANDUM
November 1, 2020
TO: Mayor Patricia Byers
Members of City Council
City Manager, Bob Harrison
FROM: Scott Schafer, Director of Public Works
Robert Desgrosellier, Chief Engineer (Acting)
SUBJECT: 2020 Capital Improvement Projects: 3rd Quarter
INTRODUCTION
This Quarterly Report is intended to provide an overview of the City's capital improvement
projects for the 3`d Quarter of 2020, including current project status, milestones, and any new
developments that may significantly alter the schedules or costs of the projects. This narrative
discusses Water/Irrigation Division, Wastewater/Stormwater Division and Engineering Division
projects. **Underlined portions of each project narrative reflect the most recent progress.**
McClure Elementary School Safety Improvements
This project will make various pedestrian safety improvements in the vicinity of McClure
Elementary School, such as, replacing and constructing sidewalk. The project will also construct
sidewalk on Lila Avenue between Karr Avenue and 24th Avenue. Funding for this project is from
a Safe Routes to School grant in the amount of $270,000. Design funds were obligated on July
3, 2018. The required preliminary engineering surveying has been completed and design of the
project is nearly complete. Right of way acquisition continues this year and construction will
occur in 2021.
♦ Projected Completion Date: 4th Quarter 2021
North lst Street Corridor Revitalization - `N' Street to `J' St. (Phase 2)
This arterial street project on N. First Street will extend from "A" St. to the US-12/I-82
Interchange. The improvement project will continue as funding continues to be pursued.
Phase 1: was completed in 2019 using STP Federal Funds $3M; TIB funding for $1M; local
utility funding $1 M; Gas tax $1.38M; and TBD local funds $$$2M.
NEW * * Phase 2: 'N' Street to 'J' Street; design is nearly complete and we are working on a
funding package for the construction of Phase 2 in 2021. We propose a combination of funding
sources such as TBD funds, Water, Sewer, Stormwater and a $500,000 TIB grant. Huibregtse
Louman and Associates (HLA) separated the design of this project phase from existing design.
This phase is expected to be $3.8 million dollars. Water Division is scheduled to contribute
$450,000 to the project to replace aging water mains; replacing two water mains with one
watermain.
♦ Projected Completion Date: 4th Quarter 2021
4
NEW * * Phase 3: 'J' Street to MLK Jr. Blvd., construction is estimated to be about $8,000,000
and is anticipated to be funded with a Federal BUILD Grant, combined with a TIB Grant, and
Stormwater and Water Enterprise Funds. HLA is designing the project. Due to the lack of
funding at the time for the entirety of the N. 1st Street Project at this time, it was determined to
be split into a 3' Phase. Phase 3 will perform the construction from MLK Boulevard to 'J' Street.
We continue to seek a Federal BUILD Grant and/or other grant funding; we will re-apply for a
TIB grant as well. We recently found out we weren't successful with the recent Federal BUILD
Grant application for $26,103,000 to complete construction of N. 1st St. from 'J' St. to MLK Jr.
Blvd.; including the East-West Corridor of the Sawmill Area Projects from 1st St. to
approximately 9'h St.
♦ Projected completion dates: FY2022 (and later)
Cascade Mill Redevelopment Project
This project includes multiple tasks to redevelop the former 225-acre Boise Cascade Mill.
Yakima was awarded $23,446,000 in LIFT funding (Local Infrastructure Financing Tool) from
the State of Washington to create a Revenue Development Area that will assist in the transition
from the former mill to a mixed use economic catalyst including creation of an estimated 4,500
light manufacturing, office park, commercial, retail and entertainment jobs.
The current status of the project includes:
1. The Interchange Justification Report (IJR) was approved on February 22, 2017. The
purpose of the IJR is to provide freeway access to a proposed east - west roadway that will
connect Terrace Height to north Yakima, and thereby, provide direct access from the 1-82 to
the former sawmill site. Design of the preferred alignment of this east-west roadway west of
the interstate is nearing completion, after which the NEPA documentation will be finalized.
The "Connecting Washington" legislation approved last fall provides funds for the
improvements to 1-82, as well as, the bridges over the interstate and Yakima River.
2. Design of a North to South City Boulevard-type Street that will provide access to the mill
site. City of Yakima is project lead. The first phase of this project that constructed the
southernmost 500 feet of this north - south road (named Bravo Company Boulevard), along
with a roundabout that connects Bravo Company Boulevard to Fair Avenue, Lincoln Avenue
and MLK Boulevard has been completed. The construction was done by Granite
Construction Company for a cost around $2,425,000. In mid-December 2016, the City
supplemented the professional services agreement with Lochner to complete the design of
Bravo Company Boulevard from where it currently ends to its connection with 'H' Street at
the intersection of 7th Street. The design of the extension of Bravo Company Boulevard is
about 90% complete. We are still working with the property owners on acquiring the right of
way necessary to construct this section of the roadway. Due to the Yakama Nation appeal of
the SEPA, it has been determined to perform NEPA on the entire East-West Corridor/Bravo
Company Blvd. Roadway Yakima County will be the lead agency and NEPA will be
performed under FHWA direction. The City is participating in the NEPA as a vital project
sponsor. On May 2, 2019 a second meeting was held with the Yakama Nation and other
relative agencies as NEPA stake holders to continue work on the NEPA for the roadways
and associated landfill cleanup. It 1f-dill hopeful th:t NkPA- ill he completed in 202n 14d
. The City will receive an
$8.7M Grant from DOE to cleanup/remove solid waste and extraneous materials of the
associated landfill that lies under the proposed roadways. Halme Construction was awarded
5
the bid of $13.1 M; the difference in cost to come from utilities funds and LYFT Funding.
The project is scheduled to begin Nov 2, 2020.
3. Preliminary Design and alignment of "East-West Corridor Road" - Yakima County project
lead for the portion that will stretch from the extended Bravo Company Boulevard to
Butterfield Road in Terrace Heights. The existing 'H' Street corridor will be improved from
North 1st Street to 7th Street as part of this project. NEPA review is scheduled for the County
portion of this project. SEPA review is scheduled for the portion that is under City purview.
On April 17th, an open-house / "listening session" was held for the public to provide project
information and collect feedback from the community regarding the proposed improvements.
Approximately 100 people were in attendance.
4. Grant funding research, permitting and options for clean-up and remediation of former City
of Yakima municipal landfill has begun. The Department of Ecology (DOE) terminated the
Voluntary Cleanup Program that the City had entered into for this property on April 26, 2016.
On June 19, 2018, the City signed the Agreed Order (AO) with the Department of Ecology
for the cleanup of the site. The AO became official on July 10th. The City is in the process of
developing the draft Interim Action Work Plan, which is required by the AO.
5. We applied for a Federal BUILD Grant this past May for a $26,103,000 federal BUILD Grant
which would construct part of the East-West Corridor from 1n Street to approximately 9th
Street; and it would include North 1st Street Corridor Revitalization - 'J' Street to MLK Jr.
Blvd. (Phase 3). Unfortunately, we were unsuccessful.
6. The Yakama Nation withdrew their lawsuit after the city withdrew the determination of non-
significance. The city is on a path to alleviate the concerns expressed by the Yakama
Nation and is going through the formal process to ensure the project complies with NEPA.
♦ Projected completion dates:
• Fair Avenue Roundabout completed: 1st Quarter 2016.
• IJR Approval: 1st Quarter 2017.
• Landfill cleanup: Scheduled to start Nov. 2' and be completed mid-year, 2021.
• North-South Boulevard (Bravo Company Boulevard): 90% design plans have been
completed and it is anticipated that this project bid period TBD.
• East-West Corridor: A professional services agreement has been entered into with
HW Lochner for the design of this project. Construction funds to construct the
modified interchange and new Yakima River Bridge become available in 2021.
Fruitvale/34tn Avenue and River Road/34th Avenue Roundabouts
The City was successful in obtaining a $914,000 grant for the design and construction of two
roundabouts to improve traffic flow and safety at these closely spaced intersections. Preliminary
Engineering funds have been obligated and the design has begun in earnest. We have met with
employees from WSDOT Traffic Headquarters to discuss the design. They suggested many
minor modifications to improve the functionality of the roundabouts, which have been made. We
are continuing to design the project and have determined the area of potential effects, which is
necessary to complete the environmental documentation. Right-of-way acquisition has started
and environmental work continues. Water Division is scheduled to contribute $225,000 to install
new water mains.
♦ Projected Completion Date: June 2022
6
Cowiche Canyon Trail
This project will construct a 10-foot wide pathway, including two bridges over Cowiche Creek
from Powerhouse Road to the existing Cowiche Canyon Trailhead. The trail will be
approximately 2 miles long. Funding for the project comes from a $2 million "Connecting
Washington" grant. Perteet, Inc. has completed the 60% design plans for this project and a
Property Owner's Meeting was held on February 6, 2018. Following the Stakeholder's Meeting,
we met twice with the landowners that live near the project to get their input. Following the
second meeting, which was held on July 6, 2018, we believe that we have an alignment that will
address their issues. Yakima County has completed additional needed surveying. We plan on
meeting with Cowiche Canyon Conservancy and William O. Douglas representatives along with
Perteet Engineering to determine the "final" proposed alignment prior to setting up a meeting
with Cowiche Canyon property owners. Funds for the construction are now available from the
State Legislature; construction will take place late in FY2021 at the earliest. We split the project
into two phases; we are trying to get all of the down-stream phase started in 2021 and the up-
stream phase in 2022. We continue to work on r/way ownership prior to proceeding with
determination of the final pathway alignment and further work/discussion with adjacent owners.
♦ Projected Completion Date: 4th Quarter 2022 (or later)
Spring Creek Road- Soccer Complex Phase 1 & Phase 2
Phase 1 is complete and reconstructed Spring Creek Road, 36th Avenue and Sorenson Road to
three-lane roadways with curb, gutter, sidewalk and street lights to improve the access to the
new SOZO Soccer Complex. The City received a $900,000 SIED grant and a $900,000 SIED
loan for this project. By inter-local agreement, the City has signed an agreement with Yakima
County Engineering to aid in the design of this project and they are finalizing the 2' Phase.
Phase 2 will start where Phase 1 ended on 36th Avenue, proceed north to Spring Creek Road
and end at Washington Avenue. This project will also construct the recently funded traffic signal
slated for Spring Creek and Washington Avenue. Bidding for Phase 2 of work will take place
this fall/winter and will include wetland mitigation work as well. SIED funding was just approved
to cover $2,000,000 of the remaining $4,750,000.
♦ Projected Completion Date: 4th Quarter 2021
Transportation Benefit District (TBD) Projects (car tab fee revenue)
Using car tab fee revenues that the City of Yakima began receiving in 2018, and the list finalized
by Yakima City Council in December, 2017, Streets and Engineering Divisions have worked on
and are proceeding with the following projects:
1. Naches Ave. Sidewalk Project (Walnut to Pacific) - started in 2018 and will continue
through 2020 to remove problematic trees that are disrupting sidewalks, replant
acceptable trees, repair sidewalks add ADA ramps; $330,000. Tree removal is complete.
ADA ramps were installed up to Race Street. Expect ADA ramp installation to be done
by end of November; replacement trees are on order, planting this fall. Remaining
sidewalk repair to be done in fall 2020. Work is 70% complete.
2. 4th Street Sidewalk Project (Walnut to Pacific) - started in 2019 to remove problematic
trees that are disrupting sidewalks, replant acceptable trees, repair sidewalks add ADA
ramps; $197,000. Tree removal is complete. Replacement trees are on order. Sidewalk
repairs and ADA ramp installation will take place in the fall 2020. Work is under way.
Master Craft Finishing was awarded the contract in the bid amount of$241,074.
7
3. Mead Ave Sidewalk Project (27th Ave to 28th Ave) — will fill in a missing one-half block of
sidewalk; Right/way is needed. $17,000
4. River Road Improvement Project (34th Ave to 40th Ave) - started in May, 2019 to widen
the roadway, grind & overlay, add street lighting, add sidewalk, bike lanes, curb, gutter,
stormwater system; $118,000 (TBD funds to cover the SIED loan). Work from 35th Ave to
40th Ave has been completed. The project from 34th Ave to 35th Ave will be conducted
as part of the Fruitvale/34th Ave project.
5. North 1st Street Revitalization Phase 2, "N" Street to "J" Street - will be bid over the
winter of 2020-2021. Work will include rebuilding the roadway, adding bike lanes,
Upgrading water main, adding a stormwater system, sidewalk, curbing, gutter, ADA
ramps, upgrade/addition of street and ped lighting - $1,500,000 remain of TBD funds.
With the reinstatement of TBD funds, we'll pursue utilizing more of the TBD funds to
complete the project.
Yakima Convention Center Expansion
This project was established for the North Expansion of the Yakima Convention Center. The
expansion is approximately 18,250sf with an additional 8,000sf renovation. Construction began
December 2019 and last for 12-15 months. Bids were opened on 10/31/2019. The low bidder is
Total Site Services out of Richland with a low bid of $10,269,001.24; within budget and after
additive selection, remains in budget. The contract was awarded by Council on November 19,
2019. The project has been underway since January and will continue into the spring of 2021.
♦ Projected Completion Date: 2nd Quarter 2021
S. 64t" Avenue and Ahtanum Rd. - Roadway Intersection
Improvements and addition of a Traffic Signal
This project will reconfigure the intersection and add a traffic signal, curb, gutter and sidewalk at
the intersection tying into existing roadside features. Funding is an award of $497,000 through a
Congestion Mitigation & Air Quality (CMAQ) grant. City's matching obligation is 13.5%, or
$78,000. The project started in October and will continue through the winter.
♦ Projected Completion Date: 2"d quarter, 2021
S. 48th Avenue - Spring Creek & Washington Avenue - Traffic Signal
This project will construct a new signal at the end of Spring Creek Rd. and Washington Ave.
The work will be tied to upcoming roadway improvements for Spring Creek Road. The roadway
alignment will tie to the Spring Creek Road alignment. Funding is an award of a 100% grant of
$650,000 from the 2019-2021 Washington State Transportation Budget. The combined project
will be bid with the Spring Creek project and last through 2021.
♦ Projected Completion Date: 4th quarter, 2021
8
S. 72nd Avenue and Washington Avenue - Roundabout
This project will reconfigure the stop sign controlled intersection into a 2-lane Roundabout. As
we start design we will likely need to purchase some right-of-way and start the environmental
review process. Funding is an award of a 100% grant of $1,000,000 from the 2019-2021
Washington State Transportation Budget. The project is anticipated for 2021 design with 2022
construction.
♦ Projected Completion Date: 4'h quarter, 2022
North-side Alley Paving Project
This project was recently awarded a CMAQ-funded grant through YVCOG for $500,000. The
nine alley block segments are between Fruitvale Blvd/Summitview and 6'h to 16'h Avenues. We
intend to reconstruct approximately 5,000LF of the 15,000 linear feet of alley; and approximately
eighteen (18) alley approaches identified in the North-side Alley Paving project and as listed in
the 2020-2025 Six-Year TIP. This project includes base preparation, the addition of needed
concrete alley approaches, then asphalt paving of alley segments. We will bid early in 2021 and
finish by 4'h quarter 2021.
♦ Projected completion date: 4'h Quarter FY 2021
Water/Irrigation Division Capital Improvements Projects
Water Treatment Plant Intake Improvements
The project will evaluate the river and WTP intake structure for potential modifications and
improvements to maintain the existing river location and flows to into the intake. We are
currently working with Golder & Assoc. for Hydro-technical Engineering Support Services for
design, permitting, funding, construction bid and inspection support of a new intake and flood
plain stabilization structures. Dept. of Ecology has issued a Watershed grant for $250,000 for
this project. City has budgeted $2,475,000 in 2021. A Cultural Survey was conducted and
submitted. A few stakeholder meetings have been held; comments from those meetings are
being incorporated into the design, as well as a river model being run to confirm proposed
improvements. A meeting was held to review model results and suggested modifications to the
design. Currently applying for "in river" permits and working with Yakima County on SEPA and
Shoreline permits. Contract addendum implemented to complete re-submission and re-design
to meet Corps of Engineers requirements. Comments were received from Corps of Engineers
and redesign has been complete and submitted.
♦ Projected completion date: 3rd Quarter FY 2021
Nelson Dam Replacement
This project will consolidate the river diversions for Fruitvale Canal, Naches Cowiche Canal and
Old Union Canal with the existing diversions at the Nelson Dam. We are working on fish
screen/intake project options. Discussions are continuing with the Bureau of Reclamation
(BOR), Washington Department of Fish and Wildlife, Yakima County, National Marine Fisheries
Service, Yakama Nation and Bonneville Power Administration (BPA) on project design and
options. A water right change in point of diversion has been approved by Ecology. An Inter-local
9
Agreement with Yakima County is in place to fit with their flood plain restoration projects.
Stakeholders meetings are being held to determine possible design options. The total cost is
estimated at $24.6 M. Applying for Fish Barrier Removal Board grant funding, requesting just
over $4M. Currently budgeting $5,000,000 in 2020, with balance of project in 2021 - 2024 --
$4.7M from County; $7.5M Bond and reserves from City, $4.3M from Fish Barrier Removal
Board. WDFW, BOR, BPA and Yakima Basin Integrated Plan funding to be determined. A
$1.8M design and permitting contract is in place with HDR Engineering. Final design and bid
documents are scheduled to be complete in January 2021.
♦ Projected completion date: 4th Quarter FY 2024
East Viola Avenue Waterline Improvements
This project installs 4,000 of 12-inch DI waterline in East Viola Avenue, crossings, services and
hydrants, and it replaces existing water mains in East Viola Avenue between South Fair Avenue
and Rudkin Road; replacing the existing 6-inch CI water main. The existing 6-inch CI waterline
has pipe joints joined together with an uncommon two-bolt system, as opposed to the standard
rubber gasket. This waterline is near the end of its useful life. A Task Order has been approved
for HLA Engineering & Surveying, Inc. to provide survey, design and services during
construction. Survey and design are underway.
♦ Projected completion date: 4th Quarter FY
North 40t" Avenue to North 42nd Avenue Waterline Fire Flow
Improvements
This project installs approximately 650 LF of 12-inch DI waterline, fire hydrants and a pressure
reducing valve station in Avalanche Avenue between North 40thAvenue and North 42nd Avenue.
The improvements will increase the fire flows in this area of the water system by connecting two
water services levels in the area. The area between West Lincoln Avenue and Snowmountain
Road, North 40th Avenue to North 42nd Avenue are lined with multifamily residential housing.
The area is located in the southeast corner of the 3rd Level pressure zone and is fed by a
network of 6-inch and 8-inch waterlines. There is a 16-inch water main in North 40th Avenue at
the western edge of the 2nd Level pressure zone. The two pressure zones will be
interconnected by the new waterline and pressure reducing valve station in Avalanche Avenue,
which will provide flows from either pressure zone to the other under fire flow conditions. A Task
Order has been approved for HLA Engineering & Surveying, Inc. to provide survey, design and
services during construction. Survey and design are underway.
♦ Projected completion date: 4th Quarter FY 2021
1st Level Reservoir Repair and Rehabilitation
The City's 6 MG domestic water reservoir, located at North 40th Avenue and Englewood
Avenue, was constructed in 1970. During recent underwater cleaning and inspection of the
reservoir, it was discovered that there were a number of locations in the concrete joints that are
leaking and in need of repair. Some of the piping and appurtenances in the reservoir have also
deteriorated and need to be replaced. Gray & Osborne, Inc. (G&O) has been chosen through a
consultant selection process to provide a detailed condition and seismic inspection of the
reservoir. Scope of work and fees for the consultant services agreement is currently being
developed and to be approved by City Council. Based on the findings by G&O, project plans
10
and specifications will be developed for repair of the reservoir, internal piping, valving, and other
structures within the reservoir. In addition, a new isolation valve will be installed on the 30-inch
fill and supply waterline to the reservoir.
♦ Projected completion date: 4th Quarter FY 2021
Kiwanis Well Pump Replacement
During inspection of the Kiwanis well, located on East Maple Street at Kiwanis Park, it was
discovered that a portion of the pipe column had failed. The project will replace the pipe column,
shaft and pump. The project was advertised and four bids were received, with LAD Irrigation Co.
providing the lowest bid to supply the new well materials. Schneider Equipment Inc. will install
the new materials, as well as the rebuilt pump motor. While the well has been out of service,
other minor updates and modifications are being made to the well facility.
♦ Projected completion date: 2nd Quarter FY 2021
Wastewater Division Capital Improvements Projects
Pipe Rehabilitation - General
The Wastewater Division has identified pipeline segments that need to be rehabilitated or
replaced. In addition, the Wastewater Division identified areas where new manholes are needed
for access in order to perform the required maintenance on existing sewer pipes. Budget was
approved in 2017 to start a pipeline rehabilitation program to address these issues. The City
awarded a Professional Services Agreement with HLA Engineering and Land Surveying, Inc. to
provide engineering services specific to the identified needs through 2019. This program has
been extended. RFQ's were sent to consulting firms to continue this work starting in 2020 and
the City awarded a Professional Services Agreement with HLA Engineering and Land
Surveying, Inc. to provide engineering services specific to the identified needs through 2022.
Scheduled Projects:
Wastewater Collection System Improvements — CIPP Rehabilitation Priority 1
Construction of approximately 15,559 LF of 8", 10", 12" and 15" cured in place pipe for
rehabilitating sanitary sewer mains, 400 side sewer reinstatements, pipe cleaning, video
inspection, sewer bypass, in various locations throughout the City.
Project is bidding Fall 2020
Wastewater Collection System Improvements — Task#2
City is completing inspection of various high priority dig out repairs needed in the
wastewater collections system. Once complete, City and HLA will agree on a task order for
design.
Project is scheduled to bid in Winter 2021.
These and future projects will stabilize current conditions of the city's wastewater pipe
system and reduce infiltration of groundwater which will save treatment costs and limit the
need for upgrades to the Wastewater Treatment Plant. Future projects will be determined
based on need and cost. In addition to these projects, City wastewater crews perform point
repairs, manhole rehabilitations, and other maintenance projects that add to the stabilization
of the pipe system and reduce infiltration of ground water.
♦ Projected completion date: on-going
11
Master Plan Updates
The Wastewater Master Plans for Sewer, Storm, and the Wastewater Treatment Facility are
being updated. The respective 2013 Akel studies for the Sewer Collections system and
Stormwater Drainage system require updates due to significant private and public construction
projects as well as the 2016 incorporation of the legacy DID system into the City Stormwater
Utility. The Yakima Regional Wastewater Treatment Facility (YRVVWTF) has undergone multiple
improvement projects since the 2014 Draft YRVWVTF Masterplan. Wastewater staff has held
consultant interviews for the three masterplans. Akel Engineering Group from Fresno California
was selected to perform the Wastewater and Stormwater Masterplan Updates. RH2
Engineering, Inc. from Bothell Washington was selected to perform the update to the YRVWVTF
Masterplan. Lidar needed for this project with be conducted this fall/winter as soon as the leaves
fall due to the cold weather. All Masterplans are scheduled to be completed by years end of
2022.
♦ Projected completion date: 4th Quarter FY 2022
Wastewater System Mill Site Preparation Project
In anticipation of additional wastewater flows from the Mill Site Development, the existing
wastewater system in Fair Avenue from the Target shopping center to Beech Street needs to be
upgraded. This work will entail upsizing existing sewer main line and installing new sewer and
will be completed in two phases.
Fair Avenue Sanitary Sewer Main Replacement (FA-6) - Project #2487A
Install 1,540 LF of new 15-Inch diameter sanitary sewer main by open-trench construction,
1,040 LF new curb and gutter, 620 SY new sidewalk; Hurst Construction, LLC of East
Wenatchee, WA was awarded this project for $1,159,555.06.
Project is complete
North Fair Avenue Sanitary Sewer Main Replacement (FA-5) - Project#2487B
Upsizing of an existing 10" sewer main to 15" by method of pipe bursting; Belsaas & Smith
Construction, Inc. of Ellensburg, WA was awarded this project for $728,095.49.
Project is complete
Stormwater Capital Improvements Projects 2019 Storm water Projects
This project addressed localized flooding by constructing six projects in different areas of
Yakima. Project locations as follow:
• Englewood Ave./N. 65th Ave.
• Englewood Ave./N. 59th Ave.
• N. 48th Ave./Webster Ave.
• N. 48thAve./Modesto Way/Madera Way
• Summitview Ave./N. 7th Ave.
• Mead Ave./15th Ave.
The City selected Perteet, Inc. for design and construction management of the project. Project
bids were opened on March 28th, 2019. Low bidder was Wheeler Excavation, Inc. of Benton
City, WA, with a bid of$964,102. Construction started early April, 2020 and is now complete.
Project is complete
12
DID CIPP Rehabilitation
This project will install a cured in place pipe liner inside three sections of old Drainage
Improvement District pipe totaling nearly 4,000 linear feet. These sections of pipe are plagued
by heavy root intrusion and require constant maintenance to prevent root blockages and
backups.
The pipe segment locations are:
• Powerhouse Rd. from 23' Ave. to 27'h Ave., then southwesterly to 29'h Ave. & Lincoln.
• Midvale Rd. from 67'h Ave. to 72'Ave.
• Plath Ave. between 16th Ave. and 18th Ave.
Bids were opened on December 4, 2019. Of the three bidders, Michels Corporation, Salem, OR,
was low bidder at $244,495. Construction began in January 2020 and was completed in
February 2020.
Project is complete
Wide Hollow Creek Berm Reconstruction
This project will reconstruct a berm north of Wide Hollow Creek that protects residents between
75th Ave. and 80th Ave. from being flooded. Bids were opened on December 19, 2019. Of the
five bidders, Selland Construction, Inc. of Wenatchee was low bidder at $233,884. Construction
began in January 2020 and was completed in February 2020.
Project is complete.
Arlington Ave. Storm water Improvements - 50th Ave. to 56th Ave.
This project will install new storm pipe on Arlington Avenue between 50th Ave. and 56th Ave. and
will prevent the Arlington Ave./56th Ave. from being flooded. The City selected HLA for design
and construction management of the project. 60% design was achieved 10/14/20.
Advertisement for bids scheduled for December 2020.
♦ Projected completion date: 2nd Quarter FY 2021
DID and Storm Drain Improvement Project
This study will look at ways to minimize and potentially remove or redirect City storm/ground
water from DID pipes prior to leaving the City limits and to minimize and potentially remove City
storm systems within the Union Gap city limits. The City selected HLA for this study. Agreement
to be signed in November 2020. Construction projects to follow completion of the study.
♦ Projected completion date: FY 2021
AFFIRMATIVE ACTION GOALS & W/M/DBE PARTICIPATION
Women, Minority and Disadvantaged Business Enterprises (W/M/DBE) utilization has been
included in the past but is not included with this report. The Engineering Division continues to
request apparent low bidders of public works contracts to document their efforts to achieve the
City of Yakima's goal of 10% MBE, WBE or DBE participation goal prior to contract award.
However, changes in state law due to the passage of Initiative 200 prohibit certain practices by
contracting agencies (i.e. the City) for the award of public works projects such as requiring
13
W/M/DBE subcontracting. While some contractors have voluntarily reported such information in
the past, we have not received any such reporting last year.
Although we do not receive such information voluntarily, the City must still meet certain of these
federal requirements and each contractor must comply with the Standard Specifications that are
included on each City Public Works Contract. The City is responsible to:
• Conduct pre-construction conferences during which Equal Employment Opportunities
(EEO) and City policies are discussed with the contractor.
• Monitor on-site compliance with the EEO and City policies.
• Ensure our contractors locate, qualify, and increase the skills of minority groups, women
employees, and applicants for employment as required by City policies.
• Ensure the preparation of required EEO and related reports.
Proj Proj. Impacted Constrctn. Start Notes
Lead Division Project Name/Location Description of Work Project [lead Status/Schedule
Type No. Divisions Date 10/29/2020
New rights of way, public Engineering, Streets Bravo Company Blvd.will be a boulevard-style street that
Bravo Company Blvd. extension being designed;
Special Projects utilities, roads, lighting, Joan Davenport/ &Traffic Eng., includes 2 more roundabouts. Design work includes road
1 CIP 2337 Cascade Millsite Parkway 2021 ?? Project is 90%designed; after Yakama Nation
(& Engineering) roundabouts, sidewalks, Bob Desgrosellier Water/Irrigation, design& realignment in vicinity of East-West corridor to respond
concerns,withdrew SEPA,will continue with NEPA
pathway, infrastructure Wastewater/Storm to BNSF rail concern;
Streets
Phase 1: Entire Site Engineering, Landau Assoc's, gathered data for evaluation of landfill
Engineering & Cascade Mil/site Parkway Bob Desgrosellier/ &Traffic Eng., Entered into an Agreed Order with DOE 7/9/18.
2 CIP 2355 tbd area and plywood plant site; DOE rejected Voluntary
.
, Working on the draft interim action work plan.
(Special Projects) (continued) ( Joan Davenport) Water/Irrigation
Phase 2: Southern portion Compliance; addressing Yakama Nation concerns,
Wastewater/Storm
East-West Connector; New rights of way, public Engineering, Streets
Yakima County is project lead; NEPA review is
Special Projects "H" St. alignment from 1st St. utilities, roads, lighting, signal(s), Bob Desgrosellier/ &Traffic Eng., Consultant(H.W. Lochner) is being replaced with another
3 CIP 2336 2021? underway; We applied for a Fed. BUILD Grant
(& Engineering) to Terrace Heights; sidewalks, pathway, (Joan Davenport) Water/Irrigation, Consulting Engineer to complete the needs of this project.
on 5/19/20; we were not selected for funding
Through Yakima Resources prop. infrastructure Wastewater/Storm
Interchange Justification Report Working with WSDOT for WSDOT Const. WSDOT& FHWA have approved the IJR;
Special Projects Bob Desgrosellier/ Engineering, Streets City and County developing a plan to implement
portions of the improvements in a phased manner
4 CIP 2356 ( I.J.R.)for modification of modification of Yakima Ave/ timeframe Design&Construction are up to the WSDOT.Engineering) (Joan Davenport) 8 Traffic Eng., in order to defer WSDOT changes to 1-82 and
1-82 and Yakima Avenue 1-82 Interchange 2022 ??? Design Funding in place for 2021
construction interchange portion early.
Engineering, Streets Bids came in with Halme Construction being the low
The excavated area will be lined prior to placing 317,000 tons of
Special Projects Municipal Solid Waste(MSW) Remove and Replace municipal Bob Desgrosellier/ &Traffic Eng., November bidder of 5 bidders with a boy},bid of 513,108,132. The
5 CIP 2529common borrow as replacement material. A future project will
(& Engineering) Removal- Bravo Company Blvd waste under future roadway ( Joan Davenport) Water/Irrigation, 2020 project removes 200,000 tons of Solid Waste&wood
build utilities and a roadway in this alignment
Wastewater/Storm debris from the future Bravo Co. Blvd. Alignment
Design & construction of Engineering, Streets Construction Estimate: 53.84M
North 1st StreetFinal plan preparation is underway;
Special Projects sidewalk, landscape and utility &Traffic Eng., HLA of Yakima is designer of Phase 2;
6 CIP 2340 Corridor Revitalization; Bob Desgrosellier Spring 2021 funding proposed with remaining TBD funds
(& Engineering) upgrades; adding bike lanes Water/Irrigation, Design is 95%complete; We will advertise for bids
Phase 2: °J' St.to'N' St. and bond releases in 2023-2024
removing parking Wastewater/Storm December 20/January'21; for an early Spring start
Design & construction of Engineering, Streets
North 1st Street HLA of Yakima is designer of Phase 3; 90%designed;
Special Projects sidewalk, landscape and utility &Traffic Eng.,
7 CIP ??? Corridor Revitalization; Bob Desgrosellier Spring 2022 We applied for Fed. BUILD Grant in May'20; Funding is incomplete;
(& Engineering) upgrades; adding bike lanes Water/Irrigation,
Phase 3: '.1' St.to MLK Jr. Blvd. vve were not selected for BUILD funding We continue to pursue grants from many sources
removing parking Wastewater/Storm
Wide Hollow& 80th Ave culverts- Engineering, County's worked on right-of-way on our behalf- County will continue design of box culverts, when funded;
Address creek flooding
8 CIP 2456 Engineering Shavy Creek; Wide Hollow Ck. Bob Desgrosellier Streets, unfunded 80th Avenue is 95%designed, but unfunded Less expensive than bridges and better for this need;
with overflow culverts
vic. 93rd Ave 8 80th Ave Wastewater/Storm City/County grant has been submitted Design will continue after a new grant
Design is at 40%; Received$190K grant for R/Way. Rcvd grant award of S190K in RNVay funds;
Engineering,Traffic,
E. Nob Hill Blvd& Fair Avenue, Widen intersection all 4 legs; Bob Desgrosellier/ R/V1iay: ends 2021 R/Way plans complete. RAvay purchasing underway; Received$1.461\1 in STP construction funds for 2023-2024;
9 CIP 2143 Engineering Wastewater,
Intersection Improvements purchase r/vvay; new signal (Randy Tabert) Rdwy:2023 or 2024 Rcvd a federal Surface Transportation Program(STP) R/way appraisals are coming in,
Water/Irrigation
grant of$1,460,000 for 2023-2024 construction we continue with property owner negotiations
Capitol Theatre Safety Improvements Bob Desgrosellier Engineering, Several items completed; Carpeting completed in Replaced aisle lighting; added overhead cable runs;
10 CIP 2354 Engineering ongoing
Safety Improvements Capitol Theatre summer 2016; other work is forthcoming Replaced main lobby, mezzanine& Robertson Rm carpeting
13th& E. Nob Hill - SOLD
Work with DOE to test these Work with DOE and our consulting firm continues;
Tiger Oil Properties Remediation: Bob Desgrosellier/ 56th &Summitview - SOLD
City properties, remediate soils Engineering, 24th& Nob Hill: still monitoring;
11 CIP 2389 Engineering East Nob Hill Blvd; North 1st St.; Joan Davenport/ ongoing 24th& Nob Hill -New sale pending; DOE gave us a
and water as needed and then CED DOE is exploring the plume extent as of 12/2018;
West Nob Hill Blvd Bob Desgrosellier $1.2M grant to do more remedial investigation;
sell to developers N. 1st has'lease to own'thru Council;April 2019
N. 1st St. property- leased to mivn-pending further tests
Economic
Phase 2: 36th Ave& Spring Creek Phase 2 received a $2 Million SIED grant/loan; City of Yakima is furthering the partnership with world-class
Road construction, curb, gutter, Development,
Rd. widening; from SOZO funding will be complete prior to award; Yakima Sports Complex SOZO (soccer& multi-sport fields);
12 CIP 2428 Engineering sidewalk, widening, drainage Bob Desgrosellier Engineering, Phase 2: 2021
entrance on 36th Ave., Construction to start early 2021 In 2021 SOZO will construct an adjacent park to replace the
and a street lighting system Streets,
connecting to 48th&Washington and last into the 4th quarter. areas of Chesterley Park lost to the YMCA Facility
Planning
Widen the intersection: Road construction started in October; All work'except°the signal equipment will be constructed this
64th&Ahtanum Bob Desgrosellier
13 CIP 2474 Engineering add a westbound RTO lane; Engineering October 2020 This project is funded by: year; Due to long-lead time of signal equipment, signal
widening and signalization Randy Tabert
add a new traffic signal Congestion Mitigation&Air Quality funding(CMAQ) equipment will be placed upon delivery as late as Spring'21
Install new sidewalk in the Design is 90%complete; Project was selected&funded by State Legislature;
Safe Routes to School Sidewalks: 2021
14 CIP 2473 Engineering vicinity of the schools. Bob Desgrosellier Engineering RMay negotiations are nearly complete Obligation of PE funds complete.
McClure Elementary School (summer)
(Locations forthcoming) Funding:through Safe Routes To School Program R/way purchase are under way
Perteet Eng. is designer. Phase 1 design is 50%; Had 4
Cowiche Canyon Trail - from Construct 2 mile gravel pathway
Phase 1: Spring'21 Phase 1: vic. Powerhouse to Cowiche Canyon Lane Project Stakeholders mtngs; most recent 7/6/18. Reviewing
15 CIP 2430 Engineering Powerhouse Road to the existing with 2 bridges crossing the Bob Desgrosellier Engineering
Phase 2: late 2021 Phase 2: Cowiche Canyon Lane to trailhead status of all r/way to determine final alignment.
Cowiche Canyon Trailhead Creek
Current work is on permitting and bridge design
River Road Widening Reconstruct and Widen roadvvay Tied to 34th& $110 SIED grant received; Ph. 2 in 2022; working on RMI &
Bob Desgrosellier/ River Road, 40th to vicinity of 35th-Complete
16 CIP 2479 Engineering 34th to 40th Avenues to 3-lane standard with curb, Engineering Fruitvale Blvd environmental, will tie to the new roundabout(s)at
(Randy Tabert) Next phase, vic. 35th ave. to new Roundabout
(remaining 35th to 34th) gutter& sidewalk Roundabout 34th Avenue and Fruitvale Blvd.
Construct 18.000+ sf addition to Contractor: Total Site Services of Richland,WA
Yakima Convention Center-North Bob Desgrosellier/ Engineering&City utilities involved with site work-
1 7 CIP 2498 Engineering the north end of the Convention Engineering 2020 Construction has begun
Expansion Project Randy Tabert Cony. Center has hired a project manager for the building work
Center project to be complete by April 1, 2021
Proj Proj. Impacted Constrctn. Start Notes
Lead Division Project Name/Location Description of Work Project 11 .ad Status/Schedule
Type No, Divisions Date 10/29/2020
2 Roundabouts Construct 2 roundabouts Application for this project was Design is 30% complete;
Bob Desgrosellier/
18 OP 2447 Engineering at Fruitvale Blvd& River Road (Cr double roundabout) Engineering Spring 2022 successful for a $914K Federal Grant. WSDOT is providing design assistance
(Randy Tabert)
at N. 34th Avenue at this compound intersection Pursuing rAvay as NEPA has been approved for this unique double roundabout
Signalize: Construct signal We are on-target with funding obligation paperwork; This project was awarded mid-2019, "PAUSED"when 1-976
Bob Desgrosellier/
19 CIP 2516 Engineering W. Washington & 48th Avenue at this intersection; Engineering Spring-2021 design is being completed and tied to the passed; is now"UNPAUSED";
(Randy Tabert)
(at Spring Creek Road ) (tied to Spring Creek Proj.) Spring Creek Construction Project funding obligation and design underway
We are on-target with funding obligation paperwork. This project was awarded mid-2019, "PAUSED" when 1-976
Roundabout at Construct roundabout Bob Desgrosellier/
20 OP 2517 Engineering Engineering 2022 We are out with a Request For Qualifications (RFQ) passed; is now"UNPAUSED"; funding obligation and other
V . Washington& 72nd Avenue at this compound intersection (Randy Tabert)
for consultant design engineering preliminary work is underway
A Petro-Vend System was identified by staff to have
Fuel system upgrades were long over due.
Fuel Station modifications Replace outdated and Bob Desgrosellier/ Engineering/ interchangeable parts with the existing system.
21 CIP 2512 Engineering 11/2020 Repairs to the existing system were becoming
at Public Works & City-wide problematic equipment (Randy Tabert) Fleet Leslie&Campbell, Inc., Union Gap,
more frequent and more expensive.
is the low-bidder at$201,357
Roofing on two buildings at Public Works was The replacement roof made the roofs water-tight again;
Re-Reof Project Install new roofing on 2 Bob Desgrosellier i Engineering I
22 CIP 2513 Engineering 2020 completed by Mascot Equipment- Pasco, WA; with improved insulation.
at Public Works buildings- Public works complex (Randy Pitney) Bldng Operations
Work has been completed and accepted; We are closing out the project
Extend sidewalk on
Transit Sidewalk Project Bob Desgrosellier/ R/Way acquisition is under way. We'll follow the Procurement Guidelines
23 CIP ???? Engineering N. 16th/Fruitvale from 7-11 to Engineering 2021
N. 16th Ave, Fruitvale Blvd to DOC (Randy Tabert) Design will continue during this period. of the City of Yakima for small works projects
existing sidewalk @ D.O.C.
Low bidder: Leslie& Campbell, Yakima; $58,022
Mausoleum Re-Roof at Rereof the Mausoleum Bob Desgrosellier i Engineering I VVe bid this project using the Small Works Roster from MRSC
24 OF' ???? Engineering i
Tahoma Cemetery (Parks) at Tahoma Cemetery (Randy Tabert) Parks
October 2020 Work s 50%complete, following state and city procurement methods.
will be complete in early November
Yakima Alley Paving Bob Desgrosellier
We applied for a $500K grant&were awarded the The proposed 9 alleys are within the area bound by
/
25 CIP ???? Engineering Pave nine gravel/dirt alleys Streets Spring 2021 Congestion Mitigation&Air Quality funding(CMAQ) Fruitvale to Summitview; 6th to 16th Avenues;
Phase 2 (Randy Tabert) Design this winter and bid early next year Work includes new concrete alley approaches.
Remove and Replace: Funded with TBD funding:
4th Street Sidewalks Bob Desgrosellier/ Engineering, ESF Solutions, LLC-Walla Walla
26 CIP ???? Engineering 3,600 LE of sidewalk; October; 2020 Streets Division will remove sAvalks;
Walnut St. to Pacific Ave. (Randy Tabert) Streets Work begins early November
construct 50 new ADA ramps they will be replaced by the contractor
Two-phased project to upgrade
sanitary sewer preparing for Mill
Site Development. Phase 1 was
Fair Avenue Sanitary Sewer Main new 15"sewer line in Fair Ave.; Dana Kallevig(Mike Phase 1 is now complete Phase 2
27 CIP 2486 Wastewater Wastewater 2020
Improvements Beech St. to E. Spruce. Phase 2 Price is now under construction.
upsizes existing 10"sewer line;
E. Spruce Street to 1-82
interchange near Target.
Project to repair aged sewer
infrastructure by dig out and
adding access manholes in
Collections System City Wide Dana Kallevig/Mike
28 CIP 2501 Wastewater locations City Sewer Wastewater 2020 Project is under construction
Repairs- Priority 5 Price
Maintenance crews have little or
no access. Multiple locations
throughout City
Project to install an odor control
Beech Street Lift Station Odor Dana Kallevig(Mike
29 OP 2502 VVastewater system at the Beech Street Lift Wastewater 2020 Project to be bid Fall 2020, competed early 2021
Control Price
Station
Project to upgrade the existing
maintenance facility on 3rd and
Wastewater I Wastewater Maintenance Facility Dana Kallevig/Mike
30 CIP 2502 Pine. Upgrades include the Wastewater 2020 Project is complete
Stormwater Upgrades Price
bathrooms, offices, and meeting
room.
Pnji Pr''. Lead Division Project Description Project ��ad Impacted Cwnstrctn� Stort Status/Schedule
Notes
Type No.
Divisions Dote 1OC�8/2O2O
.
City& HDR designing and permitting. Stkeho|der- Ecology has issued 401 Water Quality Certification. HPA
xva\emniUa,ion, review vn-gvinU. Project cost a,$z4.um funding 5vm
upp|i�adon�24/20Pr�eudeggnneuring80.� Finu|
Move PoimofD�emioo Rich Senio|o/ USBe 'Yakima Bonu� C|P/eoewe� Fio� 8anierRemova| Boo/dgmnt
N*|�onDamRey|a�em*m/Frui*a|* ' p|anmtpeo scheduled mhe:omp|�edJanua� 2O21
»1 c|p uolu xva\emuiga,ion (improving Dave �
Canal Divemioo |mpmvememo ymprning Nelson Dam fish Brown nomY, vvnFvv' Spring 2021 $4134m, County poo Grant 5^ ^m, vvnFvv Cap ka| DOE approved point of diversion change for Fruhvo|e and Old
screen for additional"mer) Mike Shane North Yakima projects atS82M. Project coordination and design
Conservation District meetings are oo-going. SEPA DNS. JARPA submitted Union,o Nelson Dam. Many attempts m engage EPA
nn2O6/20mUSACE for Nationwide Permit. unsuccessful
vva,e/oaci|�iesima
impacted Mike Shane) xva\emnia,ionUgg �on�i,on,oerr
p �euo(duevamv
32 C|P 22�8 Water/irrigation �ioceao�dineimymvomems� ' 2021 On-going coordination , Majority of work mbe completed by in-house staff.
oy misc. projects Emilio Lopez Stmegs. Eog. paving, chip seal)
Modification of river intake; Dave Brown Golder&Assoc. deggn' permitting, funding. Cuneodyapplying for io /�erpe/mksCommems back hom
33 C|P 233r Water/irrigation machesR�*rVxTP |make P000iN* impmvem*msioh Mike Shane Jeff Water/Irrigation Fail 2021 river ' oon�ru��nWd8iospecdonsuppn�of new imake& Corps niEogioe*oequiedab�nied*s�nCnnoukam
Improvements mmaimaio existing |o,e�oo 'Bond f|oodp|aio stabilization structures. Stakeholder(TAG) working ooJxRPA permit. HPA submitted ,/24/20Working
and flows,nintake me,einnvon'qoinv. with County nnSsp^and Shoreline permit
Replacement n/existing v" z'
Evio|eAxevV�edoe *nKmain vv�onew 12" D| Dave Brown, Task Order appr
oved.34 CIE 2503 Vv�en|nig�mion ' Water/Irrigation 2O2i w Pr�ectis funded by Public VVorks Trust Fund loan.
improvements *utdioefmmS. Fair Ave. m Mike Shane underway
RudkioRd.
Installation o|new 1z" o|
�e\ mweioAva|ao,haxvew
N40hAve/N42nd Ave.VVmanin* Dave Brown, Task Oderfor HL4appmvedSume n
Surveying»� C|P 2504 Water/irrigationimpro,e�ireUo� beuveen2nd ' Water/Irrigation 2021 Pr�ec�i�fundodbyPuh|i�VVork�T/us,Fund |oao
|mpmvememw Mike Shane underway
Level and 3rd Level pressure
zones
Inspect, evaluate, design and Consultant selection process with Hv\and G80G8O
xe|eueowproviuein�pechnnmre�envi/mrwaxv� �nn�e\
1$Level ResewoirRepai/and repuiom the 6-#G1$Level Dave Brown, |noentm negotiate m hearovodh City�8 CIE 2s�� Vvotemnigaxion ' Water/Irrigation 2O21 oeteriomdon �eiomi�oodo�he/oefi�ieo,iec �mvioeepo�of
Rehabilitation xesewoi/located a\^o\hand Mike Shane Manager. Scope m*v*and fees wuenegoha\eu, '
findings, design Englewood � �
construction admin.through project completion.
Replace well piping, shaft, 4 bids weaacei,edLAD |nigudon |o* bid ut
Dave Brown 0myipiogshaft and pump have been emoveuand mmorhas
37 C|P 2520 Water/Irrigation Ki*anisvVeU Pump Replacement pump, ' VVa^p�nigadon 2020 $651i�68Submiva|�hav* beenevie�edand '
' ' Shane. ' been abui� Puindnghas ga�edand valves*iUbeahui|t soon
kksoo valves and poio�og ' approved. Waiting for delivery ofmaterials.
|oma||od000f new 12" D| vVwe�k/igahoo
o4th0�rukva|eVVa�dine Dave Brown, '
�o up z�nz vva\emn|gahvn *a\er|inein�on)un«ivnwith ' s,remavvav,eva�er zuzz cvnminahnguedgnnimEngineering Division
(Roundabout) Shaoe � '
intersection roundabout project Engineering
Pave nine alleys bounded hy
Bids opened 2/12/19 and awarded mSelland
38 C|P 2481 Strm*atr Yakima Alley Improvements chenyxGa«iemano Randy me|oy,
Phase ' Smrm*ate/ S,mem 2019 Construction. Inc. Pr�ectcomy|medin2ndQuuxerFY2020
Levvio«}egooiouudiognew Mike Price ' ' '
"as substantially complete in November 2O18.
concrete alley approaches,
Reconstruct a berm oo the north
Aide Hollow Creek Berm
side mvviuexvo Raody#e|oyvn�ree:,�a\ Bids opened 12/18/18 and awmdedtnSelland
40 CIE 2507 Sm ReconstructionReconstructionrm*nte/ pm^ecmeoiuenmbetween 7sm Mike Price ' St /mwe\ r 2020 Construction, Inc. n|Wenatchee for$233,S84. Work to Project completed in1ot Quarter 2020
Ave. and no,h Ave. from being begin io January 202O.
flooded.
Installing a cured in place pipe
Bids opened 12/4/18 and awarded w Michels Corporation
|inerinoide�he*o*:ti0000io|d RandyWe|oy
41 OF 2496 Swrm*a\er o|ouppxehaoi|ka6on ' x\ rm*a\er zuzo cfSalem� 0Rk�/$244�488.VVonkmbeNninFebm�Y pnie*cvmp|�euinlv,00axerzuzn
DID pipe mt |ingneady4000 Mike
~ ' 202&
linear feet.
|n�aUiognew morm �pingon
�r|ingwnxvenoeswnn*a,e�
AdingmoAvo �atwiUyavom RundyMemy Scheduled udvo�oememdgeof11O4�0Conmzuodon
«2 CIE 2s22 St /m�e\ r |mpmvemenm5(hhxxe� ms8to ' Smrm*nte/ 2O21 oegUohyHL4�60��Pre|imiomYP|anomrnedin10/14O0�
fmndinga�meAdingmnAv*/S Mike Price scheduled m begin in March 2021
Ave.
58th Ave. intersection.
A study w minimize and remove
DID and SmrmDmin |mpmvemem o/ redirect City owrml�muod Randy mewy,
43 C|P 2536 Strm=atr ' Strmeatr 2021 x0e wit
h Construction projects m sfoUn*:omp|*donnistudy
Project water fmmDID pipes prior m Mike Price
' '