RESOLUTION NO. R-97-188
A RESOLUTION authorizing the City Manager to sign a contract
amendment with Huibregtse, Louman, Associates, Inc.
(HLA) to perform engineering services during
construction of 2,220 lineal feet of sewer force main and
fittings with two clean outs, and one 72 inch diameter
manhole.
WHEREAS, in the operation of the City's Wastewater Facilities and to
protect the health and welfare of the citizenry of Yakima, it is essential to
have reliable sewage pumping stations; and
WHEREAS, the City's Race Street lift station has demonstrated
unreliability and unsuitable location; and
WHEREAS, the relocation of Race Street Lift Station and the
installation of the attendant force main and appurtenances is in the best
interest of serving existing customers and new residential and commercial
customers in a partially sewered area; and
WHEREAS, City staff through City Council approval will purchase the
required property, pumps and control panel, conduct appraisals, complete
required environmental studies, and provide construction specifications and
formally requested bids; and
WHEREAS, the City Council deems it to be in the best interest of the
City of Yakima to authorize the City Manager to sign this contract
amendment with HLA for the purposes of engineering services during
construction, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
The City Clerk and the City Manager are hereby authorized to sign this
contract amendment with HLA for the contract price not to exceed $19,814.15.
ADOPTED THIS / 7 day of . , 1997.
ATTEST:
• 7 E9 -e -e- . 2) mow,
CITY CLERK
Race St Resolution
8/12/97
CW
Buchanan, MAYOR
Project No.
Agency
Name of Project
Agreement No.
SUPPLEMENTAL AGREEMENT
STPUS - 4611 (001)
City of Yakima
Fair Avenue Improvement Project
94-57 (R-94-98)
- AMENDMENT NO. 5
Task 7 - Services During
Construction
Race Street Sewer
Force Main
Gentlemen:
The Local Agency of City of Yakima desires to supplement the
agreement entered into withHui bregtse, Louman Associates , Inc. and executed on
J u l y 20, 1994 and identified as Agreement No. 94-57 (R94-98)
All provisions in the basic agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
1
Section 1, SCOPE OF WORK, is hereby changed to read
See attached Exhibit B-1, Supplemental
11
Section IV, TIME FOR BEGINNING AND COMPLETION, ismended to1, change the number of
calendar days for completion of the work to read
December
111
Section V, PAYMENT, shall be amended as follows:
as set forth in the attached Exhibit A, and by this reference made a part of this supplement.
The maximum amount payable under this agreeement as supplemented inclusive of all fees and
other costs is now $ 294,500.43
If you concur in this supplement and agree to the changes as stated above, please sign in the
appropriate spaces below and return to this office for final action.
Sincerely,
Date
Date
7.-2Z-9"7
Consultants &onature
007146069 William L. Huibregtse, President
REVIM4Pape 1of2 Huibregtse, Louman Associates, Inc.
i-- ;IV, /9 97
CITY CONTRACT NO:
RESOLUTION NO:
9 r7-3
Auvwnry
R.A. Zais, Jr.,
City of Yakirja
ATTEST:
City Clerk
EXHIBIT "A"
Summary of Payments
(Amendment No. 5)
(Task 7, Services During Construction)
(Race Street Sewer Force Main)
Basic
Agreement Supplement Total
+Amendment No. 1
+Amendment No. 2
+Amendment No. 3
+Amendment No. 4
+Amendment No. 5
Direct Salary Cost. 83,062.00 6,933.60
Overhead 125,232.58 10,453.79
(including Payroll Activities)
Direct Non -Salary Costs 4,620.00
Fixed Fee 29,071.70
Sub -Consultant 32,700.00
Total 274,686.28
89.995.60
135,686.37
0.00 4,620.00
2,426.76 31,498.46
0.00 32,700.00
19,814.15 294,500.43
Huibregtse, Lou nan Associates, Inc.
City of Yakima
Fair Avenue Improvement Project
Spruce Street to Pacific Avenue
CONTRACT AMENDMENT NO. 5
TASK 7 - SERVICES DURING CONSTRUCTION
EXHIBIT 5-1
Services During Construction - Race Street Sewer Force Main
Task 7 of Exhibit B-1, Scope of Work, of the Original Agreement dated July 20, 1994, provided for services
During Construction with the final scope of that work and fee to be determined.
1. The Race Street Sewer Force Main improvements will consist of installation of approxi-
mately 2,200 LF of 8 -inch sanitary sewer force main and fittings with two cleanouts and
one 72 -inch diameter manhole.
2. Furnish a qualified resident engineer who shall be on the job at aft times that significant
work is in progress, whose duty shall be to provide surveillance of project construction for
compliance with Plans and Specifications.
3. Provide one time only all vertical control and the horizontal base lines for this project The
construction contractor will be responsible for all other construction staking, including
offset points and grade.
4. Prepare daily progress reports on the Project.
5. Consult and advise the AGENCY during construction and make final review and report of
the completed work with representatives of the AGENCY.
6. Review the construction contractor's acceptance sampling and testing for construction
materials.
7. Perform measurement and computation of pay items.
8. Recommend progress payments for the construction contractor.
9. Prepare proposed Contract Change Orders when applicable.
10. Prepare and furnish reproducible record drawings and field notes of completed work in
accordance with project field records.
11. Monitor the construction contractor's labor documents, including certified payrolls.
DOCUMENTS TO BE FURNISHED BY THE CONSULTANT
1 copy of Monthly Progress Pay Estimates
1 copy of Resident Engineer's Daily Reports
1 copy of Materials Testing Results
1 copy of Construction Contractor's Submittals
1 copy of Construction Contractor Labor Documents
1 reproducible copy of Project Record Drawings
1 blueprint copy of Project Record Drawings
YKJ2.24
EXHIBIT D-1 - AMENDMENT NO. 5
CONSULTANT FEE DETERMINATION - SUMMARY SHEET
(COST PLUS FIXED FEE)
PROJECT: CITY OF YAKIMA TASK: Amendment No. 5
FAIR AVENUE IMPROVEMENT PROJECT Task 7, Services During Construction
Spruce Street to Pacific Avenue Race Street Sewer Force Main
DIRECT SALARY COST (DSC):
Classification Man Hours x Rate = Cost
Principal .Engineer 16 x 37.00 = $592.00
Licensed Engineer 40 x 25.00 = 1,000.00
Licensed Land Surveyor 4 x 20.00 = 80.00
Two Man Survey Crew 12 x 30.00 = 360.00
Resident Engineer 248 x 19.00 = 4,712.00
CAD Technician 4 x 14.00 = 56.00
Word Processing Technician 8 x 16.70 = 133.60
TOTAL DSC = $ 6,933.60
OVERHEAD (OH COST - including Salary Additives):
OH Rate x DSC or 150.77 % x $ 6,933.60 = $ 10,453.79
FIXED FEE (FF):
FF Rate x DSC or 35 % x $ 6_933.60 = $ 2,426.76
REIMBURSABLE:
Itemized
SUBCONSULTANT COSTS (See Exhibit G):
GRAND TOTAL
PREPARED BY: William L. Huibregtse
$ 0,00
$ 0.00
$ 19,814.15
DATE: August 11, 1997
•
ITEM TITLE:
SUBMITTED BY:
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. is
For Meeting Of 8/19/97
Contract amendment to perform engineering services during construction for
the new Race Street Lift Station Force Main.
Chris Waarvick, Wastewater Plant Superintendent
Bruce Bates, Assistant Wastewater Superintendent
CONTACT PERSON/TELEPHONE: Bruce Bates, 575-6078
SUMMARY EXPLANATION:
Staff respectfully request City Council approval for the City Manager to approve a contract
amendment with Huibregtse, Louman Associates, Inc. (HLA) for contract administration services
for the Race Street Force Main. Services will include construction inspection and administration
on the construction of 2,200 lineal feet of 8 inch force main and fittings with two cleanouts and
one 72 inch diameter manhole. Funding for this project is in the adopted 1997 budget and has
been previously assigned Project No. 1711.
On 7/20/94 through resolution R-94-98 Yakima City Council approved a contract with HLA to
design the relocation of a new sewer lift station and sewer force main. The new lift station will
replace the existing Race Street lift station located at the corner of 15th Street and Race. Race
Street lift station is unreliable and unable to accommodate projected sewer flows in the area.
City staff with the approval of City Council will purchase the new property, new pumps, control
panel, and conduct the required environmental assessments to prepare for this construction
project.
Resolution X Ordinance Contract X Other (Specify)
Funding Source 476 Sewer Const. Fund Approved 1997 Appropriation -Project #1711
APPROVED FOR SUBMITTAL:
City Manager
STAFF RECOMMENDATION: Approve resolution authorizing City Manager to sign the contract
amendment with HLA for the contract price not to exceed $19,814.15 billed on a time and
material basis.