BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 5.C.
For Meeting of: May 5, 2020
ITEM TITLE: Project Completion and Contract Acceptance for Michels
Corporation - Project SW2496 Drainage Improvement District
(DID) CIPP Rehabilitation
SUBMITTED BY: Scott Schafer, Director of Public Works
David Brown,Assistant Director of Public Works
Mike Price, Wastewater/Stormwater Division Manager 249-6815
SUMMARY EXPLANATION:
City project SW2496 provided for cured in place pipe (CIPP) rehabilitation of DID pipelines.
The City contracted with Michels Corporation for the construction of approximately 3,990 LF of
10" and 12" DID pipelines utilizing CIPP, pipe cleaning, and video inspection.
Final inspection for this project was made and the recommendation is that the project be
accepted. A final payment of$10,871.97 (5% retainage) is due from the City to Michels
Corporation for the completion of the rehabilitation work.
Project Manager: Randy Meloy
Contractor: Michels Corporation
Contract Awarded: 12/6/19
Contract Cost with tax: $235,269.41
Contract Cost less tax: $217,439
Retainage Due (5% of Contract Cost less tax): $10,871.97
The total contract cost is for construction only and does not include engineering and other costs.
City Council action is required to accept the project and approve the final construction costs.
ITEM BUDGETED: Yes
STRATEGIC PRIORITY: Public Safety
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
RECOMMENDATION:
2
Accept Project
ATTACHMENTS:
Description Upload Date Type
D Final 4115'2020 Cn'er Memo
3
City of Yakima DID CIPP REHABILITATION
2220 East Viola Avenue City Project No,: 2496
Yakima,WA 98901 HLA Project No.: 19107C
TO: Michels Corporation Progress Estimate No.: 2 AND FINAL
1715 16th Street SE
Salem,OR 97302 Date: March 2,2020
[fora , . . Contract.-. tsttrriato'Z 7,4uantiv:.::::. .".""'"
No. bacitottan : Link ,Quantity . 'PriCo.:. :41044Ni:: to Date Amount Quantity
1 Minor Change FA EST, $5,000.00 0.00 1,564.38 $1,564.38 31%
2 Mobilization LS 1 $23,175.00 0% 100% $23,175.00 100%
..........
3 Project Temporary Traffic Control LS 1 $7,048.00, 0% 100% $7,048.00 100%
_-
4 Clean and Video Inspect Existing Pipe LF 3,990 $5.00 0 3,990 $19,950.00 100%
. .
5 Stormwater Bypass LS 1 $2,589,00 0% 100% $2,589.00 100%
6 Obstruction Removal,CIPP Preparation EA 1 $744.00 0 0 $0.00 0°/0 ;
7 Cured in Place Pipe Rehabilitation 12 In.Diam. LF 2,750 $43.00 0 2,581 $110,983.00 94%
.......
8 Cured in Place Pipe Rehabilitation 10In.Diam, LF 1,240 $37,00 0 1,400 ' $51,800.00 113%
......
9 Reinstate Existing Side Service,Internal EA 1 $330.00 0 1 $330.00 100%
10 Landscape Restoration FA EST, $3,000.00 0.00 0.00 $0,00 0%
SUBTOTAL $217,439.38
. —
.... .
SUBTOTAL,WORK TO DATE $217,439.38'
. .
PLUS MATERIALS ON HAND $0.00
SUBTOTAL AMOUNTS $217,439.38
...... .
8.2%STATE SALES TAX $17,830.03
TOTAL $235,269.41
LESS TOTAL RETAINAGE $10,871.97
LESS AMOUNTS PREVIOUSLY PAID $224,397.44
AMOUNT NOW DUE $0.00
G1PROJLCTS%201919107C CA DOC PP REHABLTATION-MCA),S CORI IONATIOFFPROGRESS AS TIMA t ESWINAL FROG EAT NO12020-03-02 FROG AST NO 2 FINAL x2 1
4
I Con ,•ct ()nit Estiml 4. 2 Qua 1%
Description Unit Quantity P Quan to Date • aunt QuantJty
Progress Estimate No. 1 $ 224,397.44 Retainage$: 10,871.97
Progress Estimate No.2 FINAL $ 0.00 Retainage$: 0.00
I hereby certify that the foregoing is a true and correct statement of the work performed under this Contract.
Benjamin A. en,PE
ACCEPTED:
I hereby accept the Final Progress Estimate and Final Contract Voucher Certification,in accordance with Section 1-09.9 of the
WSDOT Standard Specifications.
2--6)
I I
Michels Car eon Date:
GIPROJECTS 2019V19107C VA DID SIR,REHABILITATION-MICHELS CORPORA I IONPROGRESS ESTIMAJESTINAL FROG EST NO12020-03-02 FROG EST NO 2 FINAL Ns
City of Yakima DID CIPP REHABILITATION
2220 East Viola Avenue City Project No.: 2496
Yakima,WA 98901 HLA Project No.: 19107C
LC)
TO: Michels Corporation Progress Estimate No.: 2 AND FINAL
1715 16th Street SE
Salem, OR 97302 Date: February 21,2020
MINOR CHANGE
.. : TOTAL — " SUN
TIME
rEAOUT AMOUt AMOUNT NAME . EXTEStON
ON PLATH PORTION OF PROJECT,MICHELS
ENCOUNTERED A REDUCTION IN PIPE SIZE FROM 10
IN TO 8 IN AT MH 74,SHEET 4 OF PLANS. THIS
REDUCTION IN PIPE SIZE CAUSED A DELAY IN
2/19/2020 INSTALLATION OF THE CIPP. 1 $1,564.38 $1,564.38
.„.
Subtotal $1,564.38
cc: Nate Rodriguez,Michels Corporation
Ben Annen,PE,HLA
Eric Stein,HLA