BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 6.R.
For Meeting of: March 17, 2020
ITEM TITLE: Resolution to authorize a contract supplement to the Maul, Foster
and Alongi contract(2014-180)to add additional tasks for clean-up
at 2312 West Nob Hill Boulevard
SUBMITTED BY: Joan Davenport, Community Development Director
SUMMARY EXPLANATION:
The City of Yakima established a contract for professional engineering services in 2014 for the
purpose of developing and implementing a clean-up plan for the former Tiger Oil site at 2312
West Nob Hill Boulevard. The engineering firm (Maul Foster Alongi, MFA) has managed the
clean up of the site, as funded primarily from the Department of Ecology. This contract
supplement represents two additional tasks for MFA to perform under the contract with the City of
Yakima.Adequate grant funding still exists from Department of Ecology Remedial Action Grant
to cover this Supplement.
ITEM BUDGETED: Yes
STRATEGIC PRIORITY:
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
RECOMMENDATION:
Adopt the Resolution
ATTACHMENTS:
Description Upload Date Type
D resolution 3/13/ 0 0 r Me o
D contract 3/13/2020 r Me o
I cape of Vic rk Task scriptions fir upplement 3/13/2020 backup Material
D upple ent MF1 retract daft schedule 3/13/2020 backup Material
2
RESOLUTION NO. R-2020-
A RESOLUTION authorizing a Supplement to the Professional Services Agreement
with Maul Foster Alongi, Inc. (MFA) to prepare additional tasks in
the remedial design and construction oversight for the
environmental cleanup of the former Tiger Oil site at 2312 West
Nob Hill Boulevard.
WHEREAS, the Yakima City Council established that the environmental cleanup
and redevelopment of the former Tiger Oil property at 2312 West Nob Hill Boulevard is both
an "Economic Development" and "Improving the Build Environment" priority; and
WHEREAS, the Washington State Department of Ecology has provided funding for
the cleanup of this site exceeding $1.2 million with budget reserve still available for this
supplement; and
WHEREAS, the City of Yakima entered into a contract with Maul Foster Alongi, Inc.
(M FA) in 2014(Contract 2014-180)to prepare the engineering plans and manage the clean-
up of the site; and
WHEREAS, the Scope of Work and Budget included in this Professional Services
Agreement meet the needs and requirements of the City of Yakima for this project;therefore
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
The City Manager is hereby authorized to execute Contract Supplement 6 of the
Professional Services Agreement with Maul Foster Alongi, Inc. (MFA) attached hereto
and incorporated herein by this reference not to exceed One Hundred Fifty-Six Thousand,
One Hundred Thirty-Six Dollars ($156,136) to provide the Professional Services as
described in the tasks of the Agreement, now, therefore,
ADOPTED BY THE CITY COUNCIL this 17'h day of March, 2020.
ATTEST: Patricia Byers, Mayor
Sonya Claar-Tee, City Clerk
�
Contract
~ f | Supplemental /1 f
w��`���` n���������`
��
Supplemental Agreement Or§ani and Address:
0dumKn��� K8au| Foster and A|ongi
�
— - 1329N. State Street, Suite 301
Bellingham, VVA9H2Z5
Original Contract Number: Execution Date nfSupplement:
2014-180 March 17, 7070
City Engineering Project Numnb*r: 7389 Completion Date ofSupplement:
December ]l, 20II
Project Title: Maximum Amount Payable this Supplement:
Former Tiger Oil Site Interim Remedial Action <156'136
Maximum Total Amount Payable for the
$935,588
Agreement:
Section 1: Supplemental Agreement
ThrCik' nfYukimo. VVunhingtnndroi/rn\nnupp|crncnt\hccnn8uo\uU/crmcn\ cntr/rdintnx/ithk1uul
FnntrrA|nngi, nc. and executed nn October 8. 2014hy Resolution No. 2014'121 and identified un
Contract 2014-180. All provisions in the basic contract remain in effect except as expressly modified by
this supplement. The changes to the agreement are described a»[ol|ow'o�
Task 211—Semi-Annual Groundwater Monitoring & Soil Vapor Probe Monitoring Events 2020- 2021
Continue to assess the groundwater quality and the effectiveness of interim remedial actions that have
been conducted at the site. Evaluate key data parameters in support of Natural Source Zone Depletion
through grounUw'ater and soil vapor data and data analysis. Provide data support for decision making
regarding additional actions that may be needed to achieve a satisfaction of consent decree.
Task Z2--Pr#jeot Management ZQ3Q` ZQ31
Facilitate ongoing and consistent communication between the Washington State Department of Ecology
(Ecology), City of Yakima (City), and Maul Foster & Alongi, Inc. This task includes providing quarterly
project progress reporting, budget management and invoicing, and responding to City and/or Ecology
communications related to invoicing, budget tracking, and other requests.
Task Z3--|nd#or & Ambient Air Quality Assessments (Zevents)
Continue to assess the indoor and ambient air quality at adjoining businesses (Xochimilco Mexican
Restaurant, Barber HQ, and 1 Up Games) after previous completion of interim actions to reduce the
potential o[ petroleum vapor intrusion.
Section 2: Compensation
Payment for this supplemented work will. ao shown on Exhibit Aio not toexceed $15U.1JU. bringing the
total amount of the Agreement to $9J5.5UU
|f you concur with this supplement and agree to the changes ao stated above, please sign the appropriate
spaces Ue|ow and return to this office for final action.
rDK�8U
By: Jim By:
/
| con5uxantuonam,c City Manager
oate
4
EXHIBIT A
SEMI-ANNUAL GROUNDWATER MONITORING AND SOIL VAPOR PROBE MONITORING EVENTS—
2020—2021 AND
SUPPLEMENTAL INDOOR/AMBIENT AIR QUALITY ASSESSMENTS
SCOPE OF WORK
TIGER OIL WEST NOB HILL BLVD SITE, YAKIMA,WASHINGTON
Task 21—Semi-Annual Groundwater Monitoring & Soil Vapor Probe Monitoring Events—2020-
2021
Purpose:
Continue to assess the groundwater quality and the effectiveness of interim remedial actions that have
been conducted at the site. Evaluate key data parameters in support of Natural Source Zone Depletion
through groundwater and soil vapor data and data analysis. Provide data support for decision making
regarding additional actions that may be needed to achieve a satisfaction of consent decree.
Scope:
This task includes:
• Perform fieldwork, laboratory analysis, and investigation-derived waste disposal in accordance
with the Groundwater Monitoring Plan
• Complete data validation, data analysis, and reporting following each semi-annual monitoring
event
Schedule:
• Semi-annual monitoring events will continue to be conducted in May and November of 2020 and
2021
Assumptions:
• Assumes two (2) monitoring events (semi-annual sampling) consistent with the Groundwater
Monitoring Plan
• Report will be issued in electronic and hard copy format.
Deliverables:
• Semi-annual groundwater monitoring summary reports (two [2] total provided in letter report
format consistent with prior reports)
Task 22—Project Management 2020-2021
Purpose:
Facilitate ongoing and consistent communication between the Washington State Department of Ecology
(Ecology), City of Yakima (City), and Maul Foster& Alongi, Inc. (MFA) team to ensure the entire team is
apprised of findings regarding the site's ongoing groundwater quality assessments, data interpretation,
potential long term site management options, and compliance with the amended consent decree.
Scope:
MFA will participate in meetings and/or conference calls with Ecology, City, and City-identified individuals,
as appropriate; and will schedule and coordinate with MFA staff, Ecology, City, and other appropriate
parties to complete this scope of work. This task includes providing quarterly project progress reporting;
budget management and invoicing; and responding to City and/or Ecology communications related to
invoicing, budget tracking, and other requests.
Assumptions:
• Project status conference calls will be held on an as needed basis
• Attend project status meetings, to be held in the Yakima area, on an as needed basis. Note: the
current scope of work does not include budget nor allotted time for status meetings
5
Deliverables:
• Quarterly Progress Reports (in letter format) for the 2020 - 2021 biennium (four [4] total reports
per year)
Schedule:
• Activities will be conducted throughout the life of the change order associated with this scope of
work
• Progress reports will be issued quarterly
Task 23—Indoor&Ambient Air Quality Assessments (2 events)
Purpose:
Continue to assess the indoor and ambient air quality at adjoining businesses (Xochimilco Mexican
Restaurant, Barber HQ, and 1 Up Games) after previous completion of interim actions to reduce the
potential of petroleum vapor intrusion.
Scope:
This task includes:
• Coordinate with adjoining businesses' owners/tenants to obtain site access for air quality
assessments
• Perform fieldwork and laboratory analysis
• Complete data validation, data analysis, and reporting following each indoor& ambient air quality
assessment event
Schedule:
• Air quality assessments are anticipated to be conducted after completion of groundwater
monitoring events and evaluation of the data
Assumptions:
• Report will be issued in electronic and hard copy format.
Deliverables:
• Technical Memos (two [2]total provided consistent with prior memo)
ESTIMATED BUDGET C006
FORMER TIGER OIL
GROUNDWATER MONITORING EVENTS 2020 - 2021 and AIR QUALITY ASSESSMENTS
2312 WEST NOB HILL BLVD
YAKIMA, WASHINGTON
Maul Foster& Alongi, Inc.
Task Subcontractors Total
Hours Labor Direct
21 Semi-Annual Groundwater&Soil Vapor Probe Monitoring- 1 semi-annual
event 159 $20,135 $4,200 $4,686 $29,021
22 Project Management, Quarterly Progress Reports, Agency Communications-
1 semi-annual event 10 $1,773 $500 $0 $2,273
Sub-Total Estimated Cost for 1 semi-annual event $31,294
21 Semi-Annual Groundwater& Soil Vapor Probe Monitoring 2020 - 2021 (4 semi-
annual events) $116,084
22 Project Management, Quarterly Progress Reports, Agency Communications
2020 - 2021 (4 semi-annual events) $9,092
Sub-Total Estimated Cost for 2020 - 2021 (4 semi-annual events) $125,176
23ISupplemental Indoor& Ambient Air Quality Assessment(2 events) 139 I $23,860 I $1,350 I $5,750 $30,960
Total Estimated Cost $156,136
R:A0818.02 City of Yakima V Contract V01 2020.02.24 Change Order No.6\Tiger Oil C006 budget est 022420.xls\Summary Budget 2/24/2020
7
City of Yakima—West Nob Hill Former Tiger Oil Site
Environmental Tasks
Updated February 24, 2020
. ECOLOGY CITY j A :11/ATE
::E::::..H::.:B O..:�:.:: :.. .....:.::........:...... ::: :.:,:;....�::�IEP.,:. ::.....:.:..N: .,..:.:..:.:...::...,::::::: :::::::n..::::::::::::::::::::::::::::::..::::::::::::::::::::::::::::::::::::::::::x::::::::::c: .:::::::::::::::::::::::
ss :s : f I: 1 E gI 1 t..1 E tuttea:s: ::s u mpvtau::uur r t r assssssssssssssssssss:
rt # # trt t t #s # #s t t#tEassountettattstassiongstssgmtanwt':sss p rt#sf+ ter site Ettt # ' IgMt*ssssssssssssssssssssssssssss
+v s's s: # # xssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssss
2. Conduct HRSC Field Investigation Oversight as needed Support Conduct November 26-
December 7
Completed
3. Draft Report Review Review Prepare April 26, 2019
Completed
4. Additional CO2 Monitoring Review Review Conduct July 9 -10, 2019
Completed
5, Draft Final HRSC Report Review Review Prepare Dec 11, 2019
Submitted
..................................................................................................................................................................................................................................................................................................................................................................................
::.:.... c. :::.
E## '#'#: :#s:: :: .d#:d t s............'t :# ':'r# ':' �##. . ...:':'dtd €#:tt.;;.: .. ..�..........:.:s: td#: #sssssssssssssssss3
s .t #: :c # tsos ssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssss
6. Draft Site Management Plan Review Review Prepare November 2019
Completed
7. Draft Fact Sheet Version of Site Management Review Review Prepare November 2019
Plan Completed
8. Finalize Site Management Plan and Fact Sheet Review Review Prepare January 2020
Version—Awaitin Ecolo Comments
## . :ss:xti#ss:i### . r# Q r sssssssr#s # r �1 hrnn r r # Q#r # xssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssss
..................................................................................................................................................................................................................................................................................................................................................................................
.................................................................................................................................................................................................................................................................................................................................................................................
..................................................................................................................................................................................................................................................................................................................................................................................
.................................................................................................................................................................................................................................................................................................................................................................................
..................................................................................................................................................................................................................................................................................................................................................................................
.................................................................................................................................................................................................................................................................................................................................................................................
gtBBBBBBBBBBBBBBBBBBBBE
..................................................................................................................................................................................................................................................................................................................................................................................
9, Indoor Air Samples Review Review Conduct July 9 - 10,2019
Completed
10, Conduct bio-slurping and seal cracks in Review Review Prepare September 24-
foundations of existing buildings 25,2019
11, Conduct confirmation air samples Review Review Conduct November,
2019
Completed
12. Prepare report documenting interim cleanup Review Review Prepare March 2020
action and confirmation sample results
13. Conduct follow up confirmation air sample— Review Review Conduct June-July
dependent on semi-annual groundwater event 2020*
data* (Change Order pending)
.................................................................................................................................................................................................................................................................................................................................................................................
::#...s.:sp#E s:l ::::..s::;:::s;:::: s #:::#s ss tt #s':'p flt:1#Nsss sst ...:...::art....##art' #s 11Sk.... .::ice': :£t€...sd ems.......:#ss
.
# r11 ass#s ::l::l:101611 rt## '`#1 r#r t s rt#:::611 ` r ''xsssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssss
13. Spring 2019 Review Review Conduct May,2019
Completed
14. Fall 2019 Review Review Conduct November,
2019
15. Spring 2020 (Change Orderpending) Review Review Conduct May 2020
16. Fall 2020 (Change Orderpending) Review Review Conduct November 2020
Note: All tasks listed above are eligible for reimbursement through the Remedial Action Grant and are included in
the scopes of work in the Consent Decree for the site and the MFA task orders with the City of Yakima.
Page 1