HomeMy WebLinkAbout01/05/2010 13 Heritage Trails Yak YVT 3 Bridge Restoration Final Contract Payment, Project No AS2167 BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
110 Item No. 13
For Meeting Of January 10, 2010
ITEM TITLE: Final Contract Payment for Heritage Trails Yak YVT 3 Bridge Restoration — City
Project No: AS2167
SUBMITTED BY: Doug Mayo — City Engineer
Brett Sheffield - Chief Engineer
CONTACT PERSON/TELEPHONE: Doug Mayo — City Engineer, 509-576-6678
SUM MARY EXPLANATION:
This project consisted of furnishing all labor, materials and equipment to clean and paint all of
the metal surfaces of the Yakima Valley Transit Company Trolley Bridge over the Naches River
(Bridge No. YAK YVT 3). - The steel truss bridge was approximately 322 feet in length and
contained approximately 120 tons of steel.
Final inspection for this project was made and the recommendation is that the project be
accepted.
•
This Council action is to accept the project and approve the final construction costs.
Contractor:
Contract Award:
Contract Cost: 7/28/09
Contract Company
$246,750.00
Final Contract Cost: $200,684.34
Amt. This Payment: -0-
The above total contract cost is for construction only and does not include engineering and other
costs.
Resolution Ordinance X Other (Specify) Final Contract Payment
Contract , Mail to (name and address):
Funding Source Arterial Street
APPROVED FOR SUBMITTAL: 42:5 401 iLtzei City Manager
STAFF RECOMMENDATION: Accept the project and approve final estimate.
BOARD/COM MISSION/COMMITTEE RECOMMENDATION:
COUNCIL ACTION:
• •
111._ . Clip YAKIMA
' PROJECT #2167 PROJECT NAME: HERITAGE TRAILS 12/22/2009
CONTRACTOR: LONG PAINTING
PROGRESS ESTIMATE NO. FINAL
BID TOTAL TO
NO. • ITEM BID UNIT UNIT PRICE CONTRACT DATE % OF
QUANTITY AMOUNT QUANTITY CONT AMOUNT
1 SPCC PLAN 11 LS $250.00 $250.00 100% 100% $250.00
2 MOBILIZATION . 1 LS $20,000.00 $20,000.00 100% 100% $20,000.00
3 CLEANING AND PAINTING-YVT TROLLEY BRIDGE 1 LS $117,000.00 $117,000:00 100% 100% $117,000.00
4 SPOT ABRASIVE BLAST CLEANING 500 SF $25.00 $12,500.00 0% 0% $0.00
CO-1 PRE PRIME BRIDGE 1 LS $12,500.00 $12,500.00 100% 100% $12,500.00
5 MISCELLANEOUS BRIDGE REPAIR 1 FA $20,000.00 $20,000.00 0% 0% $0.00
6 CONTAINMENT OF ABRASIVES 1 LS $50,000.00 $50,000.00 100% 100% $50,000.00
7 TESTING AND DISPOSAL OF CONTAINMENT WASTE 1 FA $27,000.00 $27,000.00 934.34 3% $934.34
TOTAL $246,750..00 81% $200,684.34
•
•
•
•
•
•