05/21/2019 14C Yakima River Basin Integrated Water Resource Plan Update to\'4\lyy tbxk ik 1
(44-
• PPP
PPP
g.
A
p
P 1
PPi
ittYlltYlt.\ta.
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEM ENT
Item No. 14.C.
For Meeting of: May 21, 2019
ITEM TITLE: Yakima River Basin Integrated Water Resource Management Plan
May 2019 Project Activity Update
SUBMITTED BY: Scott Schafer, Director of Public Works
David Brown, Water/Irrigation Manager 509-575-6204
SUMMARY EXPLANATION:
The May 2019 Project Activity Update provides information on technical aspects of ongoing
planning studies for the Yakima River Basin Integrated Water Resource Management Plan
(Integrated Plan).
ITEM BUDGETED: NA
STRATEGIC PRIORITY: Partnership Development
ft' if
APPROVED FOR
SUBMITTAL: lir
City Manager
STAFF RECOMMENDATION:
BOARD/COMMITTEE RECOMMENDATION:
ATTACHMENTS:
Description Upload Date Type
D ate 5/ / 019 exhibit
Yakima River Basin Integrated Water Resource Management Plan
Project Activity Update
May 2019
Purpose: To provide updates on technical aspects of ongoing planning studies for the
Yakima River Basin Integrated Water Resource Management Plan (Integrated Plan)
Fish Passage Element
Cle Elum Dam Fish Passage Facilities and Reintroduction Project:
The juvenile fish passage facility will use an innovative helix design to transport juvenile fish
downstream. It will allow fish to leave the reservoir as the water surface fluctuates over the top 63 feet
in elevation. This will provide downstream passage from April 1 through the beginning of June in
most years. The upstream adult fish passage facility will be a trap-and-haul facility where fish are
trapped at the base of the spillway, loaded into a truck, and then hauled for release into Cle Elum
Reservoir or to upstream tributaries.
Construction Update: The access road and spillway bridge is complete. The secant vault construction
is substantially complete. Construction for the downstream passage tunnel is in progress. The Intake,
Gate, and Helix contractor mobilized in late April 2019. Reclamation's goal is to have the contractor
install the lowest intake levels within the reservoir this summer, if level of reservoir is at or below
elevation 2170.
Study Update: In 2018, Reclamation and the Yakama Nation worked with the USGS to conduct an
adult sockeye tracking test to understand their migration between Roza and Cle Elum dams. Results of
the study showed (1) sockeye released at Roza Dam were not falsely attracted to any tributary, (2)
upstream migration was relatively quick with only some minor slowing at the Town Ditch Diversion,
and (3) 100 percent of the tagged sockeye made it to the base of the Cle Elum Dam. Plans are
underway to conduct a sockeye tracking study in the lower Yakima River in Summer 2019.
Box Canyon Creek Fish Passage:
Washington State Department of Fish and Wildlife (WDFW) with input from Reclamation, Ecology
and other passage restoration experts has completed a conceptual design for the Box Canyon Creek
Fish Passage Enhancement Project. Reclamation, Ecology, Yakama Nation and Yakima Basin
Integrated Plan partners will finalize the design. An additional field survey was needed to move the
conceptual design toward final design. This survey work was obtained the week of October 22, 2018
and is being processed for use by the design team. The preliminary final design is anticipated to be
completed by June 2019.
Clear Creek Dam Fish Passage:
Reclamation completed an appraisal level design for fish passage in September 2018. The design
consists of a traditional pool-and-weir-style fishway with a steel bulkhead at the upstream end that
will draw cool water from deeper in the reservoir. Situated along the left abutment of the dam, fish
would enter the fishway in the stilling basin and exit in the reservoir pool. The bulkhead will be deep
enough to maintain suitable water temperature in the fishway for Bull Trout. Reclamation is
coordinating with USFW S, Yakama Nation, WDFW, and others to review and refine the design. The
THEiHEEEYt ,". i t I N C sIc T
U.S. Department of the Interior G a o r
Bureau of Reclamation — Ec 0 E 0 Y
3
final design will be complete by December 2019. Construction timing will depend upon final cost
estimates and funding availability. Until passage improvements are accomplished, USF W S,
Reclamation, and WDFW will continue capturing Bull Trout from below Clear Creek Dam and
transporting them around the dam so they can reach spawning habitat in the North Fork Tieton
River. Fish capture and transport was conducted in 2016, 2017, 2018, and to-date, 66 adult Bull Trout
have been transported above the dam.
Structural and Operational Changes Element
Cle Elum Pool Raise:
The purpose of the Cle Elum Pool Raise Project is to increase the reservoir's capacity for improved
aquatic resources for fish habitat, rearing, and migration in the Cle Elum and upper Yakima River,
thereby fulfilling the intent of the congressional authorization, Title XII of Public Law 103-434.
Completed: Radial Gate construction was completed in April 2017. Reclamation completed
modifications to three saddle dikes as of 2018. The U.S. Forest Service Cle Elum River Campground
shoreline protection was completed in November 2017.
Shoreline Protection Update: Reclamation and Ecology are currently implementing shoreline
protection actions for private and public lands and facilities. Shoreline protection for Speelyi Day Use
Area is in progress and it is anticipated to be completed in May 2019. Shoreline protection actions
will begin for the Wish Poosh Campground in 2019, while other actions will be awarded as funding
becomes available. Shoreline landowners and the public will be notified about shoreline designs and
construction timing via mail and postings at U.S. Forest Service facilities. Reclamation and Ecology
continue to meet with landowners throughout project implementation.
Chandler Pumping Plant Electrification:
Kennewick Irrigation District(KID) and their consultant developed a concept design for an electric
pumping plant at Chandler. Reclamation reviewed the concept design and KID performed a transient
analysis in June 2017, which was reviewed by Reclamation, and comments were sent to KID
September 2017. KID provided an updated concept design and transient analysis for Chandler
Electrification with an isolating reservoir to Reclamation in 2018. Reclamation will continue to
coordinate with KID on Chandler Electrification project design review.
Reclamation, Ecology, and HDR are completing sensitivity analysis modeling for the lower Yakima
River, including examination of return flows in the lower Yakima system to determine impacts from
future conservation efforts on KID. Meetings were held with KID and the Water Use Subcommittee in
October 2018 to share the draft study results.
Lower Yakima River Smolt Survival Study:
This year the lower Yakima River smolt survival study will collect and tag about 1,100 juvenile
Chinook salmon and Steelhead trout to monitor their behavior and survival in the lower Yakima
River. Monitoring equipment was deployed in March 2019; fish collection and tagging started April 1,
2019. Salmon smolts are being released weekly in April, May, and June to determine fish responses to
varying environmental conditions. Data from the 2018 field season are being analyzed, and
preliminary results indicate fish survival is highest in early May and lowest by June when the river
warms. Additional data needed to validate fish migration rates, behavior at dams, and survival is being
collected in 2019-2020. Reclamation also received Science and Technology grant funding($150,000)
to work with Pacific Northwest National Laboratory to obtain 500 tags for juvenile lamprey in 2019-
2020. These tags are not commercially available and are the smallest, lightest tags made for fish; a
2
4
portion of the study will be dedicated to evaluating and improving the performance of these tags. The
Yakama Nation and partners are collecting data related to predator abundance and diet from the lower
river,
Surface Water Storage Element
Kachess Drought Relief Pumping Plant(KDRPP)
The KDRPP is proposed to access 200,000 acre-feet of inactive storage below the current outlet works
in the Kachess Reservoir to use in severe drought. Since the proposed KDRPP and KKC projects are
closely connected, they were analyzed together.
First, the Kachess Drought ReliefPumping Plant and Keechelus Reservoir-to-Kachess Reservoir
Conveyance Draft Environmental Impact Statement(DEIS) was published in January 2015. The DEIS
described the No Action Alternative and five action alternatives.
After two public comment periods, Reclamation and Ecology reviewed comments, collected
additional scientific data as necessary, evaluated new findings, and developed a floating pumping
plant as new alternative. This required Reclamation and Ecology to prepare the Kachess Drought
Relief Pumpzng Plant and Keechelus Reservoir-to-Kachess Reservoir Conveyance Supplemental
Draft Environmental Impact Statement(SDEIS), which was released to the public April 13, 2018.
After an additional public comment period, Reclamation and Ecology prepared the Kachess Drought
Relief Pumpzng Plant and Keechelus Reservoir-to-Kachess Reservoir Conveyance Final
Environmental Impact Statement(FEIS), which was released in March 2019. Responses to all
comments from both the DEIS and the SDEIS are published in the FEIS.
On April 26, 2019, Reclamation signed the Record ofDecision (ROD), which does not approve
implementation of any alternatives but carries forward Alternative 4 - KDRPP Floating Pumping Plant
for further analysis. Consistent with this decision,the remaining alternatives in the FEIS, including the
KKC, will not be carried forward. Reclamation and Ecology have begun work on the additional EIS to
focus site-specific analysis of the floating pumping plant and to present other reasonable alternatives.
Wymer Reservoir
Consideration of site requirements is ongoing. As presented at the March 13, 2019 YRBWEP
Workgroup Meeting, KRD has proposed an alternative to gravity feed Wymer via Kittitas
Reclamation District's system that will further reviewed under Wymer Dam and Reservoir Project.
Bumping Reservoir Enlargement Project
Consideration of site requirements is ongoing.
Groundwater Storage Element
Groundwater Storage—Basinwide Analysis
The Groundwater Storage Subcommittee is reviewing all ongoing groundwater storage projects.
In the Wapato Irrigation Project(WIP), additional monitoring-well locations have been identified,
which will help with observation of the aquifer system response to recharge activities from Toppenish
Creek. Reclamation has completed drilling of three (3) additional wells. Ecology will provide
pressure transducers, and data will be retained and analyzed to determine the benefits of the recharge
activities. Monitoring of existing sites continues.
3
5
Four project proposals were selected for funding for the 2017-2019 biennium. These projects include
(1) Indian Creek Groundwater Dynamics Investigation, Oregon State University(2) Yakima Basin
Focused Managed Aquifer Recharge Assessment, Kittitas Reclamation District(3) Yakima River
Groundwater Infiltration Study, Selah-Moxee Irrigation District and (4) Geochemical Study of
Groundwater in Potential Storage Sites, Central Washington University. These projects are coming
under contract and will be implemented over the next 2 years.
The Lower River Subgroup is exploring opportunities to use groundwater recharge to enhance thermal
refuges for migrating fish along the lower Yakima River. An initial study has been funded to develop
current information on temperature variations in the river from Wapato Dam to the Yakima River
mouth. The USGS is currently processing temperature data from this study and will work with Benton
Conservation District to determine optimum locations for additional monitoring.
Aquifer Storage and Recovery (ASR)
The City of Yakima's ASR program is fully permitted. The City is recharging at the Gardner Well for
35 days in February and March. The City is planning full build-out for the program. They intend to
drill two ASR devoted wells: the first well is estimated for 2020-2021, and the second is estimated for
2025-2026.
Habitat Protection and Enhancement Element
Targeted Watershed Protection and Enhancement
The Washington State Department of Natural Resources (WDNR) and WDFW worked with the
Teanaway Community Forest(TCF) advisory committee to develop a recreation plan, which has been
adopted and incorporated into the TCF management plan. The State-appropriated funds for the 2017-
2019 biennium will be used for habitat, forest, and infrastructure projects. The primary focus of
habitat projects is removing fish-passage barriers and installing fencing, stream-crossings, and
watering stations to keep grazing stock out of sensitive riparian areas. In addition,the Yakama Nation
continues to work on wood placement in TCF streams to improve habitat conditions and watershed
functions. Recent accomplishments of TCF goals include the following:
Goal 1 —WDNR is targeting 20 miles of road maintenance before the end of the fiscal biennium in
June. Models suggest this will mitigate approximatelyl0 tons of sediment delivery to the river.
Goal 2 —Working Lands: Work on the Cle Elum Ridge Shaded Fuel Break begin as roads dry
out. This project connects fuel-break work with that done by WDNR a couple of years ago, and with a
large multifamily private property projects doing the same. Ultimately,the community forest fuel
break will connect to small landowners and The Nature Conservancy lands to create a preestablished
fuel break along Cle Elum Ridge to protect communities below. Several precommercial thinning
projects to control density of young forest stands are planned for summer. For grazing lands, WDNR
plans to install an additional 2.5 to 6.5 miles of fence. A fencing contract was offered last month but
received no bids. WDNR is contacting potential bidders to find out what they didn't like before the
contract is advertised again. The intent is to correct fencing errors for greater success, rebuild old
fences to help protect floodplains, and establish new fence where WDNR has identified need. Other
types of grazing infrastructure including rocked stream-crossings and watering troughs are planned.
Goal 3 —Recreation: Staff are maintaining recreation sites and working on cultural resource
assessments, gathering permits, preparing SEPA documents, and building contracts for the
implementation of two grants. Those grants will renovate the West Fork Teanaway Camping Area
and renovate and expand camping at Indian Camp. DNR installed a new CXT outhouse at the end of
4
6
the West Fork Teanaway Campground and is contracting interpretive signage work with help and
input from the Goal 5 committee.
Goal 4—Habitat Restoration: DNR intends to abandon one fish passage barrier on an unnecessary
road in Story Creek. Additionally, DNR acquired all necessary permits for the replacement of the
Carlson Bridge, which will allow access to more fish passage work and Yakama Nation fisheries
habitat projects in Carlson Creek.
Goal 5 —Community Involvement: The committee has been engaged in advocacy for the capital
request DNR submitted for the TFC. They made contacts and coordinated with the Integrated Plan
team for some of those conversations. The committee is also working on the annual Teanaway Love
Day volunteer event and celebration which is scheduled for May 4.
Mainstem Floodplain and Tributaries Fish Habitat Enhancement Program
A stakeholder group consisting of the City of Richland, Federal and State fisheries managers, irrigation
districts, environmental and commercial interests, the U.S. Army Corps of Engineers (Corps)-Walla Walla
District, the Yakama Nation, and Umatilla Confederated Tribes have been working together on the
Yakima River Delta Enhancement Project. The proposed project to breach a portion or all the Bateman
Island Causeway would change flow patterns and improve temperature conditions, instream flow, water
quality, and fisheries within the Yakima Delta; it is viewed as critical to the long-term success of
numerous upstream fisheries projects being implemented as a part of the Integrated Plan. Additional
project support through the Corps 1135 program has been approved.
Benton Conservation District(BCD), in partnership with Yakama Nation and volunteer partners, have
completed nine thermal profiling floats during summer and early fall 2018. The floats covered the stretch
of the lower Yakima River from Wapato to Mabton, and from Prosser to Bateman Island(Richland).
Eighty-eight river miles were profiled for micro-scale river temperature changes. BCD shared preliminary
results at the September YRBWEP Workgroup meeting, and the full USGS analysis of the 2018 results is
forthcoming.
The Yakama Nation and Kittitas County Conservation District(KCCD) are working to engage landowners
and farm and ranch operators in contracting funds awarded in 2016 by the USDA Natural Resources
Conservation Service (NRCS)through their Regional Conservation Partnership Program (RCPP). The
Yakima Integrated Plan Toppenish-to-Teanaway Project is funded through 2021. The RCPP funding
focuses on insufficient water/drought, water quality degradation, and inadequate fish and wildlife habitat
in priority areas in Kittitas County, and Yakama Nation Reservation lands. The Yakama Nation is working
on "beaver based"restoration projects on Reservation land.
The 5-year agreement between the Yakama Nation and NRCS was finalized in September 2017. KCCD
conducted their first of, at least, four annual sign-ups for the Environmental Quality Incentives Program
(EQIP)receiving 23 applications by the deadline in November, 2017. KCCD staff worked closely with
NRCS staff in 2018 to complete the conservation plans, design the practices to be implemented, and
execute contracts with the highest priority applications totaling more than $770,000. As of December 31,
2018, six of the seven contracts that were signed are under construction and expected to be completed in
the next quarter. The second EQIP sign-up was completed on November 2, 2018. A total of 35
applications were received with five rolled over from the previous signup. Applicants include producers
who have not previously had a contract or worked with the NRCS. An initial ranking was completed and
work on the conservation planning has begun on the highest priority applications. The officially ranking
cannot occur until NRCS enters the contracts in their system.
KCCD conducted a sign-up for the Agricultural Conservation Easement Program (ACEP)in summer
2018. One application was received from Kittitas County and Forterra for a 280-acre farm. The appraisal
report was expected in September but was not completed until November and is still under review by the
5
7
landowner and Forterra. KCCD continues to work with the partners and NRCS to work toward executing
the easement. KCCD will also be setting up a sign-up for the Healthy Forest Reserve Program (HFRP) in
coming months. HRFP is focused on private forestland adjacent to the Teanaway Community Forest.
Enhanced Water Conservation Element
Funding of$5 million for additional projects during the 2017-2019 biennium was appropriated by the
State Legislature in January 2018. In February 2018, recipients of 2017-2019 funded proposals provided
updates to the Water Use Subcommittee. Projects with Kittitas County Conservation District, Kittitas
Reclamation District, and Roza Irrigation District are under contract and moving forward.
Market Reallocation Element
The Kittitas Reclamation District(KRD) and its partner,Trout Unlimited(TU), advanced the Market
Reallocation element of the Yakima Basin Integrated Plan. Initial planning, contracting, and research
began in early 2019. Trout Unlimited is leading research of the technical components e.g. rights analysis,
instream flow needs analysis, smart market development, and outreach and will lead and collaborate
with partners to develop the market strategy. A key part of the effort is the outreach, which began with
both KRD and TU providing information to various groups and media outlets.
Proposed Projects for Consideration
During implementation of the Integrated Plan, an adaptive approach will be used periodically to assess
progress towards meeting the identified instream flow objectives, the 70 percent proratable supply goal for
irrigation, and goals for other out-of-stream needs. The need for additional water supply enhancements
would depend on the effectiveness of projects that are implemented as part of the Integrated Plan, how the
Yakima basin economy develops over time, and the timing of and way climate changes may affect water
supply availability. From time-to-time, new projects may be identified (and proposed)for consideration
under the Integrated Plan. Reclamation, Ecology, Yakama Nation and the Executive Committee are
developing a formalized process to consider new projects. Projects proposed for evaluation and those
currently being evaluated are listed here.
KRD Upper Yakima Basin Storage System(suspended)
The purpose of the KRD Upper Yakima Storage System Study Project is to identify and assess storage
projects within the KRD service area that can use conserved water or water diverted for storage as part
of total water supply available (TWSA)for tangible improvements. This water could be used for the
following: instream flow objectives, tributary supplementation, aquatic habitat improvements,
supporting delisting steelhead and Bull Trout populations, proratable drought-year supply, and TWSA
throughout the Yakima River basin. KRD commissioned a study which resulted in the,Kittitas
Reclamation District Initial Water Storage Assessment Summary Report and Recommendations June
2017.
Reclamation, Ecology and KRD have agreed to suspend the feasibility study at this time. As
presented at the March 13, 2019 YRBWEP Workgroup Meeting, KRD has proposed an alternative to
gravity feed Wymer via KRD's system that will further reviewed under the Wymer Dam and
Reservoir Project.
YTID Diversion Relocation(under evaluation)
In March 2018, Yakima-Tieton Irrigation District(YTID) completed a report that evaluates
alternatives to replace or repair the YTID main canal. Alternatives considered include:
6
8
1. Baseline Alternative (Tieton Main Canal Repair)
2. Tieton Main Canal Replacement
3. Diversion Relocation to Wapatox Diversion Dam (and associated new conveyance system)
4. New North Fork Cowiche Creek Reservoir, either with or without the Wapatox diversion.
YTID continues to evaluate these and new alternatives. On February 7, 2019, YTID met with agencies
to provide an update and introduced a new tunnel alternative also being evaluated. Work is ongoing
for YTID to assess project metrics to demonstrate how it measures up against Integrated Plan goals.
Contacts for Information on the Integrated Plan:
Wendy Christensen, U.S. Department of the Interior, Bureau of Reclamation, Columbia-Cascades Area
Office, (509) 573-8050
Thomas Tebb, Washington State Department of Ecology, Office of Columbia River, (509) 574-3989
Project website: http://www.usbr.govipn`programs/vrbwep`index.html
7