HomeMy WebLinkAbout05/07/2019 06B Randall Park Improvement Project East Parking Lot; Project Completion to\'4\lyy tbxk ik 1
PPP
+� PPP
d g.
P A
P p
P 1
PPi
ittYlltYlt.\ta.
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 6.B.
For Meeting of: May 7, 2019
ITEM TITLE: Project Completion and Contract Acceptance for Knobel's Electric,
Inc. - Project 2414, Randall Park Improvements
SUBMITTED BY: Scott Schafer- Director of Public Works
Bob Desgrosellier-Acting Chief Engineer- 509-575-6228
SUMMARY EXPLANATION:
City Project 2414 provided for the completion of improvements at Randall Park. The City
contracted with Knobel's Electric, Inc. for constructing improvements within the east parking lot,
including new concrete curbing,ADA ramps, sidewalk, and installation of pole bases for lighting.
Final inspection for this project was made and the recommendation is that the project be
accepted. A final payment of$2,266.65 (5% retainage) is due from the City to Knobels Electric,
Inc. for the completion of the improvement work at Randall Park.
Project Manager: Bruce Floyd
Contractor: Knobel's Electric, Inc.
Contract Awarded: 4/20/2018
Contract Cost: $49,050.31
Retainage Due: $2,266.65
The total contract cost is for construction only and does not include engineering and other costs.
City Council action is required to accept the project and approve the final construction costs.
ITEM BUDGETED: Yes
STRATEGIC PRIORITY: Neighborhood and Community Building
APPROVED FOR
SUBMITTAL: City Manager
2
STAFF RECOMMENDATION:
Accept Project
BOARD/COMMITTEE RECOMMENDATION:
ATTACHMENTS:
Description Upload Date Type
D Final 4;17/2019 Cover Memo
City of Yakima PROJECT TITLE Randall Park Improvement Project-East Parking Lot&Pathway
City Engineering Division
129 N 2nd Street City Project No.: 2414
Yakima,WA 98901
TO: Knobel's
Progress Estimate No.: FINAL
Date May 7,2019
Total
Item Unit Bid Contract '.... To Date %of Amount Previous Previous '....Quantity AmoUm APCt
No. Description NTY UNIT Puce Amount Quamlty, Contract Quantity Payments tills Period Due Der
I Minor Change 1 FA $5,000.00 $ 5,000.00 0 0% $ - 0 $ - 0 $ -
2 Mobilization 1 LS $4,000.00 $ 4,000.00 1 100% $ 4,000.00 1 $ 4,000.00 0 $ -
3 Project Temporary Traffic Control 1 LS $1,000.00 $ 1,000.00 0 0% $ - 0 $ - 0 $ -
4 Concrete Spill Apron-East Parking Lot 2 EA $960.00 $ 1,920.00 1 50% $ 960.00 1 $ 960.00 0 $ -
5 Cement Conc.Planter Curb-East Parking Lot 1050 LF $13.50 $ 14,175.00 1068 102% $ 14,418.00 1068 $ 14,418.00 0 $ -
6 Cement Conc.Sidewalk 4-inch Thick-West PL 125 SY $59.00 $ 7,375.00 149 119% $ 8,791.00 149 $ 8,791.00 0 $ -
7 Cement Conc.Curb Ramp-East Parking Lot 2 EA $1,600.00 $ 3,200.00 2 100% $ 3,200.00 2 $ 3,200.00 0 $ -
8 Illumination-East Parking Lot Pole Bases 1 LS $13,964.00 $ 13,964.00 1 100% $ 13,964.00 1 $ 13,964.00 0 $ -
SUB TOTAL $ 50,634.00 90% $ 45,333.00 $ 45,333.00
SALES TAX 8.2% $ 4,151.99 $ 3,717.31 $ 3,717.31
TOTAL $ 54,785.99 $ 49,050.31 $ 49,050.31
DUE RETAINAGE 5% $2,266.65
I hereby certify that the foregoing is a true and correct statement of the work performed under this Contract.
CITY ENGINEER /s/Bob Desgrosellier