Loading...
HomeMy WebLinkAboutR-2019-046 Spring Creek Road Improvements; Contract with TTC ConstructionRESOLUTION NO. R-2019-046 A RESOLUTION authorizing a contract with TTC Construction for Spring Creek Road Improvements for roadway and related improvements in the vicinity of the Yakima Sports Complex. WHEREAS, the Yakima City Council has previously established that development of the Yakima Sports Complex, is an Economic Development priority for the City of Yakima, and WHEREAS, the Yakima City Council has previously established for capital expenditures to invest in capital expenditures toward the acquisition of property, the development of this public park and improvements to 38th Avenue, Sorenson Road, 36th Avenue and Spring Creek Road in the vicinity of the proposed Yakima Sports Complex; and WHEREAS, the Yakima City Council has previously accepted a Yakima County SIED Board grant/loan for $1,800,000 for the engineering, design and reconstruction of certain streets and utilities necessary to support the Yakima Sports Complex; and WHEREAS, roadway plans and contract documents were prepared for the roadway widening and improvements, which include curb, gutter and sidewalk, ADA-compliant curb ramps, stormwater treatment and street lighting, and WHEREAS, the City of Yakima used the procedure established by Washington State law for the bidding and awarding of public capital improvement projects, and WHEREAS, TTC Construction submitted the low bid and has the ability to correctly construct and install the improvements at a cost of $1,058,082 42, and WHEREAS, the City's Chief Engineer has recommended awarding the contract to TTC Construction for constructing and installing the improvements, and WHEREAS, the City Council finds that it is in the best interests of the City of Yakima and its residents to enter into the contract to perform roadway widening and related construction, in the vicinity of the Yakima Sports Complex., now, therefore BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA: The City Manager is hereby authorized to execute the attached contract with TTC Construction, in the amount of $1,058,082.42 for Spring Creek Road Improvements, Phase 1, City Project No 2428, which provides for roadway and related improvements on 38th Avenue, Sorenson Road, 36th Avenue and Spring Creek Road in the vicinity of the Yakima Sports Complex. ADOPTED BY THE CITY COUNCIL this 16th day of April, 2019 ATTEST ea2), Sonya Ciaa ee, City Clerk Kathy Coffey, I1`14ayor CONTRACT THIS AGREEMENT, made and entered into in triplicate, this tI day of t ( , 2019, by and between the City of Yakima, hereinafter called the Owner, and TTC Construction, Inc. a Was ington Corporation, hereinafter called the Contractor WITNESSETH: That in consideration of the terms and conditions contained herein and attached and made a part of this agreement, the parties hereto covenant and agree as follows. I The Contractor shall do all work and furnish all tools, materials, labor and equipment for THE BID AMOUNT OF $1,058,082.42 for Spring Creek Road Improvement Project, Phase 1, City Project No. 2428, all in accordance with, and as described in the attached plans and specifications and the 2014 Standard Specifications for Road, Bridge, and Municipal Construction which are by this reference incorporated herein and made a part hereof, and shall perform any alterations in or additions to the work provided under this contract and every part thereof Work shall start within ten (10) days after the Notice to Proceed and shall be completed in Fifty (50) working days. If work has not commenced within the ten (10) days after the Notice to Proceed, the first chargeable working day shall be the 11 cn day after the date on which the City issues the Notice to Proceed. If said work is not completed within the time specified, the Contractor agrees to pay to the Owner the sum specified in the Standard Specifications for each and every day said work remains uncompleted after expiration of the specified time, as liquidated damages. The Contractors shall provide and bear the expense of all equipment, work and labor of any sort whatsoever that may be required for the transfer of materials and for constructing and completing the work provided for in this contract and every part thereof, except such as are mentioned in the specifications to be furnished by the City of Yakima. II The City of Yakima hereby promises and agrees with the Contractor to employ, and does employ the Contractor to provide the materials and to do and cause to be done the above described work and to complete and finish the same according to the attached plans and specifications and the terms and conditions herein contained and hereby contracts to pay for the same according to the attached specifications and the schedule of unit or itemized prices hereto attached, at the time and in the manner and upon the conditions provided for in this contract. III INDEMNIFICATION The Contractor shall defend, indemnify, and hold harmless the City, its officers, elected officials, employees and agents from and against any and all claims, causes of action, damages, losses, and expenses of any kind or nature whatsoever, including but not limited to, attorney's fees and court costs, arising out of, relating to, or resulting from the Contractor's performance or non-performance of the services, duties and obligations required of it under this Agreement. IV The Contractor for himself, and for his heirs, executors, administrators, successors, and assigns, does hereby agree to the full performance of all the covenants herein contained upon the part of the Contractor V It is further provided that no liability shall attach to the City of Yakima by reason of entering into this contract, except as expressly provided herein. IN WITNESS WHEREOF the parties hereto have caused this agreement to be executed the day and year first herein above written Countersigned. CITY OF YAKIMA this I [ day oIV 2018. CITY CONTRACT NO. o20 Vr 9_/0 RESOLUTION NO' IQ-OM-O-I (, * 'Us ti. v is ? Z (President, Owner, etc.) �(1 ` Y C� 1M i f h `7� o'A dr'eis: , ' r\ V. j \ V \ 1 CONTRACTOR Ethructim a ,'i\C Contractor �\ Corporation 1 ITEM TITLE: SUBMITTED BY: BUSINESS OF THE CITY COUNCIL YAKIMA, WASHINGTON AGENDA STATEM ENT Item No. 6.G. For Meeting of: April 16, 2019 Resolution authorizing a contract with TTC Construction for Spring Creek Road Improvements for roadway and related improvements in the vicinity of the Yakima Sports Complex Scott Schafer, Director of Public Works Bob Desgrosellier, Chief Engineer (Acting) 575-6228 SUMMARY EXPLANATION: In April 2015, the Yakima City Council established that development of the Yakima Sports Complex is an Economic Development priority for the City of Yakima. The City of Yakima entered into agreements with SOZO, a Washington non-profit corporation, for a public -private partnership to create multiple soccer fields, parking lots and related improvements. It was recognized that improvements to the existing public streets in the vicinity of the proposed Yakima Sports Complex will improve public safety, facilitate access to the development and improve the neighborhood. S I E D funds were projected to cover approximately 52% of the cost to upgrade the existing street network to urban standards. Early this year, city staff used the state bidding process to advertise for bids. Four (4) contractors submitted bids with TTC Construction of Yakima submitting the lowest bid of $1,058,052.42. S I E D grant, loan and utility funds will cover the cost of this phase of construction. This 1st phase of the roadway improvement project will start at S. 38th Avenue and Sorenson Road, continue to north on S. 36th Avenue to Spring Creek Road and end at the northern entrance to the Yakima Sports Complex. Later this year, Phase 2 of the roadway improvement will be bid and construction will continue from the ending point up 36th Avenue to Spring Creek Road and continue to S. 48th & Washington Avenues. On both phases, roadway improvements will include road widening, curb, gutter, sidewalk, storm and sanitary sewers, and roadway lighting. ITEM BUDGETED: Yes STRATEGIC PRIORITY: Partnership Development 2 APPROVED FOR SUBMITTAL: City Manager STAFF RECOMMENDATION: Adopt resolution BOARD/COMMITTEE RECOMMENDATION: ATTACHMENTS: Description Upload Date D resolution 4/512019 D Contract 4/2/2019 Type CcAer Memo Contract