BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 6.1.
For Meeting of: February 19, 2019
ITEM TITLE: Project Completion and Contract Acceptance for L&S Fencing -
Project 2477 Yakima Wastewater Security Fence
SUBMITTED BY: Scott Schafer, Director of Public Works
Mike Price -Wastewater/Stormwater Manager 249-6815
SUMMARY EXPLANATION:
City Project 2477 provided for the completion of the security fence installation at the City of
Yakima's Wastewater Treatment Facility. The City contracted with L&S Fencing to complete the
installation of a security fence and the installation of gates. The security fence is to help protect
the public from the hazards of the wastewater treatment facility particularly since the recent design
and construction of the Yakima Greenway has since placed this pathway in close proximity of the
wastewater treatment facility.
Final inspection for this project was made and the recommendation is that the project be
accepted. A final payment of$4,246.99 (5% retainage) is due from the City to L&S Fencing for
the completion of the Wastewater Treatment Facility Security Fence Project.
Project Manager: Marc Cawley
Contractor: L&S Fencing
Contract Awarded: 9/11/2018
Contract Cost: $91,904.89
Retainage Due: $4,264.99
The total contract cost is for construction only and does not include engineering and other costs.
City Council action is required to accept the project and approve the final construction costs.
ITEM BUDGETED: Yes
STRATEGIC PRIORITY: Public Safety
APPROVED FOR
SUBMITTAL: /11!
City Manager
2
STAFF RECOMMENDATION:
Accept Project
BOARD/COMMITTEE RECOMMENDATION:
ATTACHMENTS:
Description Upload Date Type
D WW1T'Security Fence Firel 112a/2019 Gotier Memo
3
Project 2477 WW Security Fence
FINAL
SUBTOTAL $84,939.82
TAX 8.2% $ 6,965.07
TOTAL $91,904.89
AMOUNT DUE RETAINAGE (5% OF SUBTOTAL) $4,264.99