Loading...
HomeMy WebLinkAbout09/11/2018 11 2nd Quarter 2018 Capital Improvement Projects ReportITEM TITLE: SUBMITTED BY: 1 BUSINESS OF THE CITY COUNCIL YAKIMA, WASHINGTON AGENDA STATEMENT Item No. 11. For Meeting of: September 11, 2018 2nd Quarter 2018 Capital Improvement Projects Report Scott Schafer, Public Works Director Brett Sheffield, P.E., Chief Engineer Bob Desgrosellier, Senior Engineer - 575-6228 SUMMARY EXPLANATION: Attached for City Council review is the City of Yakima Engineering Division's 2nd Quarter 2018 Capital Improvement Projects Memorandum and Report which includes both Water/Irrigation and Wastewater/Stormwater Capital Improvement Projects. Also attached is the current project spreadsheet developed by the Water/Irrigation, Wastewater/Stormwater, Streets & Traffic and Engineering Divisions. The current project listing assists in the planning of current and upcoming projects. It helps the divisions coordinate their work efforts so that, for example, a street is not rebuilt or seal coated prior to planned underground work on the same street. Work performed during the 2nd Quarter included: Safe Routes to School — • Construction began and was completed on the Adams Washington Vicinity Sidewalks project • Acquired the right of way necessary for the Garfield Elementary Safety Improvements projects; working with Pacific Power on relocating their utility poles. • Obligated the preliminary engineering funds for the McClure Elementary School Safety I mprovements project. North 1st Street Revitalization — • The environmental documentation (Categorical Exclusion) was approved by the Federal Highway Administration on Phase 1 of the North 1st Street Revitalization project and discussions continue with Pacific Power on the relocation of their utility poles. 2 • Developed a BUILD grant application for Phase 2 of the North 1st Street Revitalization project. Cascade Mill Site - The City signed the Agreed Order with the Department of Ecology which details cleanup requirements for the former city -operated landfill as part of the Cascade Mill Redevelopment project. Fruitvale/River Rd. - Finalized the design concept for the Fruitvale Boulevard/River Road and River Road/N. 34th Avenue Roundabout projects and began work on the environmental documentation. Cowiche Canyon Trail - Continued working with the adjacent property owners to develop an acceptable alignment for the Cowiche Canyon Trail project. Spring Creek Rd. - Continued working with the FAA on acquiring right of way from the Yakima Air Terminal required for the Spring Creek Road - Soccer Complex project. Water Treatment Plant Intake - Golder and Associates provided Hydro -technical Engineering for design, permitting and funding of the project. In the process of applying for work in river permits. Fruitvale Canal - Nelson Dam Improvements - Continued to have discussions with the Bureau of Reclamation, Washington Department of Fish and Wildlife, Yakima County, National Marine Fisheries Service, Yakama Nation and North Yakima Conservation District on project design options. Hathaway Street Project - O Waterline Replacement Project - HLA continued working on the project design, as the project is scheduled to begin construction early 2019. O Wastewater Line Replacement Project - This project and the waterline replacement project are to be combined and done as one project. HLA continues to work on the design and the project is scheduled to begin construction in early 2019. Speedway Interceptor and Beech Street Lift Station - Rotschy, Inc. continued working on the construction of the Lift Station. It is anticipated that this project will be completed in the third quarter of 2018. 49th Avenue Drainage - This project was substantially completed in November of 2017 by D.W. Excavating. The contractor returned to the site in the second quarter of 2018 to finalize hydroseeding certain areas in Gilbert Park. The project has officially completed as of May 2018. Pleasant Avenue Drain Pipe Repair - This small works project, which repaired a broken section of storm pipe in Pleasant Avenue, was repaired by TTC Construction during the second quarter. PowerPoint Presentation by Bob Desgrosellier ITEM BUDGETED: NA STRATEGIC PRIORITY: Public Trust and Accountability APPROVED FOR SUBMITTAL: STAFF RECOMMENDATION: BOARD/COMMITTEE RECOMMENDATION: ATTACHMENTS: Description Upload Date • Quarterly Report Narrative 7/17/2018 • Project Spreadsheet 7/17/2018 • PP 8/29/2018 3 Type Backup Material Backup Material COM" Memo 4 MEMORAND UM July 17, 2018 TO: Mayor Kathy Coffey Members of City Council FROM: Brett Sheffield, PE, Chief Engineer Robert Desgrosellier, Senior Engineer SUBJECT: 2018 Capital Improvement Projects: 2"d Quarter INTRODUCTION This Quarterly Report is intended to provide an overview of the City' s capital improvement projects for the 2nd Quarter of 2018, including current project status, milestones, and any new developments that may significantly alter the schedules or costs of the projects. This narrative discusses Water/Irrigation Division, Wastewater/Stormwater Division and Engineering Division proj ects. Yakima Valley Trolley Barn & Museum Preservation (Enhancement Funds) Using State Enhancement funds, the City purchased the historic YVT Trolley Repair Barn and Substation on January 31, 2008. Funding also allowed for repairs to the west and south walls and the crane system. That work has been completed. Some funding still remains and will be used to remove and replace approximately 120 feet of bad track starting at the intersection of Yakima Avenue and 6th Avenue, and continue southerly along 6th Avenue. Paperwork for environmental clearance has to be submitted specifically for this deficient crossing. • Projected completion: FY2019 Cascade Mill Redevelopment Project This project includes multiple tasks to redevelop the former 225 -acre Boise Cascade Mill. Yakima was awarded $25 million in LIFT funding (Local Infrastructure Financing Tool) from the State of Washington to create a Revenue Development Area that will assist in the transition from the former mill to a mixed use economic catalyst including creation of an estimated 4,500 light manufacturing, office park, commercial, retail and entertainment jobs. The current status of the project includes: 1. The Interchange Justification Report (IJR) was approved on February 22, 2017. The purpose of the UR is to provide freeway access to a proposed east - west roadway that will connect Terrace Height to north Yakima, and thereby, provide direct access from the I-82 to the former sawmill site. Design of the preferred alignment of this east -west roadway west of the interstate is nearing completion, after which the NEPA documentation will be finalized. The "Connecting Washington" legislation approved last fall provides funds for the improvements to I-82, as well as, the bridges over the interstate and Yakima River. 1 5 2. Design of a North to South City Boulevard -type Street that will provide access to the mill site. City of Yakima is project lead. The first phase of this project that constructed the southernmost 500 feet of this north - south road (named Bravo Company Boulevard), along with a roundabout that connects Bravo Company Boulevard to Fair Avenue, Lincoln Avenue and MLK Boulevard has been completed. The construction was done by Granite Construction Company for a cost around $2,425,000. In mid-December 2016, the City supplemented the professional services agreement with Lochner to complete the design of Bravo Company Boulevard from where it currently ends to its connection with 'H' Street at the intersection of 7th Street. The design of the extension of Bravo Company Boulevard is about 90% complete. We are still working with the property owners on acquiring the right of way necessary to construct this section of the roadway. Construction of the extension of Bravo Company Boulevard to 'H' Street is scheduled to begin in 2019. 3. Preliminary Design and alignment of "East-West Corridor Road" - Yakima County project lead for the portion that will stretch from the extended Bravo Company Boulevard to Butterfield Road in Terrace Heights. The existing 'H' Street corridor will be improved from North 1st Street to 7th Street as part of this project. NEPA review is scheduled for the County portion of this project. SEPA review is scheduled for the portion that is under City purvi ew. 4. Grant funding research, permitting and options for clean-up and remediation of former City of Yakima municipal landfill has begun. The Department of Ecology (DOE) terminated the Voluntary Cleanup Program that the City had entered into for this property on April 26, 2016. On June 19, 2018, the City signed the Agreed Order (AO) with the Department of Ecology for the cleanup of the site. The Agreed Order becomes official on July 10th. • Projected completion dates: • Fair Avenue Roundabout completed: 1st Quarter 2016. • UR Approval: 1st Quarter 2017. • Landfill cleanup: The interim action plan should be completed in late 2018. • North-South Boulevard (Bravo Company Boulevard): 90% design plans have been completed and it is anticipated that this project will go to bid early 2019. • East-West Corridor: A professional services agreement has been entered into with HW Lochner for the design of this project. Construction funds to construct the modified interchange and new Yakima River Bridge become available in 2021. North 1st Street Corridor Revitalization — 'N' Street to SR -12 (Phase 1) North 1st Street Corridor Revitalization — 'N' Street to MLK Jr. Blvd (Phase 2) In 2010, the City received a $25,000 planning grant through Yakima County SLED funding for the first segment of this proj ect; a comprehensive approach to planning for future improvements to North First Street from "A" Street to the US -12/I-82 Interchange. The North First Street Improvement Study was performed in 2011 to develop a design and action plan to address potential arterial street design alternates including an analysis of resulting traffic flow, streetscape and landscape improvements, and required utility upgrades. The final study document was adopted by City Council on October 11, 2011. The City applied for, and received a $250,000 Surface Transportation Program (STP) federal grant for preliminary engineering on August 23, 2012. In January of 2013, the City was awarded $2,718,000 for the construction of Phase 1. A professional services agreement was entered into 2 6 with HDJ Design Group to develop the engineering plans and construction specifications. The engineering plans and construction specifications have been completed. Approval of the environmental documentation is ongoing. The majority of the construction funds are available this year with the remainder available in 2019. The project will be bid in August of this year with construction scheduled for 2019. Emphasis will be placed on safety and improving the appearance of the corridor. Phase 2: 'N' Street to MLK Jr. Blvd., construction is estimated to be $10,000,000 and was planned to be funded by a City of Yakima bond. We interviewed consulting firms to perform the design and Huibregtse Louman and Associates (HLA) was selected to perform the design for us. They have started their work and should be completed towards the end of 2016. Due to the amount of work included in Phase 2, and the amount of impacts that it will have to traffic, businesses and private utilities, it has been determined to split Phase 2 into two phases. Phase 2A will perform the construction from MLK Boulevard to `I' Street. Phase 2B will perform the construction from `I' Street to 'N' Street. With the establishment of the Transportation Benefit District (TBD), a source of funding for the project has been established, as this project is included on the TBD list of projects. We continue to seek for other grant funding and will re -apply for a TIB grant. This project will be submitted for an BUILD grant on July 19, 2018, and possibly apply for an INFRA grant this fall. • Projected completion dates: FY2019 (and later) Adams Elementary/Washington Middle School Sidewalk Improvements This project will make various pedestrian safety improvements in the vicinity of Adams Elementary School and Washington Middle School, such as, constructing sidewalk, improving roadway crossings, installing flashers and installing fencing. Funding for this project is from a Safe Routes to School grant in the amount of $357,000. The environmental documentation has been completed and we are beginning the right of way phase. The project is scheduled to go to bid in August 2017. Bids were opened in September, but the low bid submitted was $80,000 over Engineer's Estimate. The project was modified and re -bid in November. The low bidder was Moreno and Nelson with a bid amount of $286,947.00, which is within budget. The project has begun construction and will be completed in August. • Projected Completion Date: 3rd Quarter 2018 Garfield Elementary Safety Improvements This project will make various pedestrian safety improvements in the vicinity of Garfield Elementary School, such as, constructing sidewalk, improving roadway crossings and installing flashers. Funding for this project is from a Safe Routes to School grant in the amount of $180,000. The environmental documentation has been completed and we have acquired the right of way needed from four of the five parcels. All of the right of way required for this project has been acquired, and we have contacted Pacific Power about their need to relocate their poles on Campbell Lane. As the acquisition of this project took longer than anticipated, the project is scheduled for construction in the summer of 2019. • Projected Completion Date: 3rd Quarter 2019 3 7 Spring Creek Road — Soccer Complex This project will reconstruct and widen Spring Creek Road, 36th Avenue and Sorenson Road to three -lane roadways with curb, gutter, sidewalk and street lights to improve the access to the new SOZO Soccer Complex. The City received a $900,000 SLED grant and a $900,000 SIED loan for this project. By inter -local agreement, the City has signed an agreement with Yakima County Engineering to aid in the design of this project. The design is close to being finished and acquisition of the required right of way is nearly complete, with only the Yakima Air Terminal remaining. It is anticipated that construction of this project will occur in late 2018 or early 2019. • Projected Completion Date: 4th Quarter 2019 Cowiche Canyon Trail This project will construct a 10 -foot wide pathway, including two bridges over Cowiche Creek from Powerhouse Road to the existing Cowiche Canyon Trailhead. The trail will be approximately 2 miles long. Funding for the project comes from a $2 million "Connecting Washington" grant. Perteet, Inc. has completed the 60% design plans for this project and a Property Owner's Meeting was held on February 6, 2018. Following the Stakeholder's Meeting, we met twice with the landowners that live near the proj ect to get their input. Following the second meeting, which was held on July 6, 2018, we believe that we have an alignment that will address their issues. Perteet is in the process of making the required changes. The funds for the construction will not be available until the 2019 — 2021 biennium. • Projected Completion Date: 4th Quarter 2020 Yakima Valley Trolley Improvements: Heritage Capitol Project Grant This project will provide minor restoration of the YVT facilities and trolley system and add enhancements to the Trolley Museum and property. Funding comes from a $50,000 State Heritage Capitol Grant that has been awarded to the city. The funds were matched against Trolley Volunteers labor and other improvement value plus $90,000 in construction completed by the City. The project started early this year and so far has consisted of many small projects such as reopening the Selah Gap by removing rock slides that covered the rail in the Gap for over a year; replaced 12 trolley poles that were failing or missing; purchased milled boards for the flooring in the Car Barn. Other work will include interpretive displays inside and outside the Trolley Museum; replacing a couple of ineffective yard lights with six new LED yard lights, etcetera. • Projected Completion Date: 4th Quarter 2018 Fruitvale/34th Avenue and River Road/34th Avenue Roundabouts The City was successful in obtaining a $914,000 grant for the design and construction of two roundabouts to improve traffic flow and safety at these closely spaced intersections. Preliminary Engineering funds have been obligated and the design has begun in earnest. We have met with employees from WSDOD Traffic Headquarters to discuss the design. They have suggested many minor modifications to improve the functionality of the roundabouts. We are in the process of filling out the NEPA documents, so that we can obligate right of way funds later this year. • Projected Completion Date: 4th Quarter 2019 4 8 McClure Elementary School Safety Improvements This project will make various pedestrian safety improvements in the vicinity of McClure Elementary School, such as, replacing and constructing sidewalk, improving roadway crossings and installing a rectangular rapid flashing beacon at the crossing of 24th Avenue and Viola Avenue. The project will also construct sidewalk on Lila Avenue between Karr Avenue and 24th Avenue. Funding for this project is from a Safe Routes to School grant in the amount of $270,000. Design funds were obligated on July 3, 2018. The project is scheduled for construction in 2019. • Projected Completion Date: 3rd Quarter 2019 River Road, 34th Avenue to 40th Avenue This project will improve River Road from 34th Avenue to 40th Avenue by reconstructing and widening the roadway to a 3 -lane section, with curb, gutter, sidewalk, street lighting and a storm drainage system. A $1,000,000 SLED grant/loan has been obtained for this project. An application for the remaining $650,000 will be made to the Transportation Improvement Board in August. • Projected Completion Date: 4th Quarter 2019 5 9 Water/Irrigation Division Capital Improvements Projects Water Treatment Plant Intake Improvements The project will evaluate the river and WTP intake structure for potential modifications and improvements to maintain the existing river location and flows to into the intake. We are currently working with Golder & Assoc. for Hydro -technical Engineering Support Services for design, permitting, funding, construction bid and inspection support of a new intake and flood plain stabilization structures. Dept. of Ecology has issued a Watershed grant for $250,000 for this project. A Cultural Survey was conducted and submitted. A few stakeholder meetings have been held; comments from those meetings are being incorporated into the design, as well as a river model being run to confirm proposed improvements. A meeting was held to review model results and suggested modifications to the design. Currently contracting and applying for in river permits. • Projected completion date: 4th Quarter FY 2019 Fruitvale Canal - Nelson Dam Improvements This project will consolidate the river diversions for Fruitvale Canal with the existing diversions at the Nelson Dam. We are working on fish screen/intake project options. Discussions are continuing with the Bureau of Reclamation, Washington Department of Fish and Wildlife, Yakima County, National Marine Fisheries Service, Yakama Nation and North Yakima Conservation District on project design and options. A water right change in point of diversion has been approved by Ecology. Discussions with Yakima County are on-going to see how the project fits with their flood plain restoration projects. Stakeholders meetings are being held to determine possible design options. The County's Flood Plain by Design grant that was be held up by the Legislature's Capital budget has been issued. A plan forward is being worked on including an agreement with the county for design and construction. Projected completion date: 1st Quarter FY 2020 Hathaway Street Waterline Replacement Project This project installs 2,650 ft. of 12 -inch DI waterline Hathaway Street between N. 6th Ave. and N. 16th Ave., including crossings, services, valves and hydrants. The existing 16 -inch OD Steel water main has deteriorated and required periodic repair due to leaks. Replacement of the line will reduce unscheduled repairs, as well as improve system operation. The project is also being coordinated with Wastewater Division improvements along the same portion of Hathaway Street. HLA Engineering and Surveying, Inc. is currently working on the project design. Construction is anticipated to begin late 2018/early 2019. Projected completion date: 1st Quarter FY 2019 6 10 Wastewater Division Capital Improvements Projects Pipe Rehabilitation — General The Wastewater Division has identified pipeline segments that need to be rehabilitated or replaced. In addition, the Wastewater Division identified areas where new manholes are needed for access in order to perform the required maintenance on existing sewer pipes. Budget has been approved starting in 2017 to start a pipeline rehabilitation program to address these issues. The City awarded a Professional Services Agreement with HLA Engineering and Land Surveying, Inc. to provide engineering services specific to the identified needs through 2019. 2018 Scheduled Projects: Wastewater Collection System Improvements — Priority 1 1750 LF of sewer pipe rehabilitation with 14 new manholes in various locations; DW Excavating of Davenport, WA was awarded this project for $349,821.42; Project is complete Wastewater Collection System Improvements — Priority 2 3600 LF of sewer pipe rehabilitation by CIPP in various locations; This project is currently in design; Project scheduled to be completed in 2018; These and future projects will stabilize current conditions of the city's wastewater pipe system and reduce infiltration of groundwater which will save treatment costs and limit the need for upgrades to the Wastewater Treatment Plant. Future projects will be determined based on need and cost. In addition to these projects, City wastewater crews perform point repairs, manhole rehabilitations, and other maintenance projects that add to the stabilization of the pipe system and reduce infiltration of ground water. • Projected completion date: on-going Hathaway Street Wastewater line Replacement Project This project installs approximately 1800 LF of 8 -inch sewer main in Hathaway Street between N. 6th Ave. and N. 16th Ave., including side sewer services. This project will consist of installing new sewer as well as replacing a failing sewer line and relocating it in Hathaway where the current sewer is located between 6th avenue and 8th avenue in backyards. This project will move existing connections from the failing sewer line to the new line being installed in Hathaway. Replacement of the line will give City Maintenance crews better access to the sewer main, reduce unscheduled repairs, as well as improve system operation. The project is also being coordinated with Water Division improvements along the same portion of Hathaway Street. HLA Engineering and Surveying, Inc. is currently working on the project design. Construction is anticipated to begin Early 2019. Project completion date: 2nd Quarter FY 2019 7 11 Collection System Plan Update & Initial Stormwater Comp Plan, Wastewater Facility Plan With the adoption of the new stormwater regulations a comprehensive Stormwater System Plan is needed and will be implemented along with the Wastewater Facility and Collection System Plan Update. Akel Engineering Group, Inc. has completed capacity models for both systems and completed a capital projects priority projection based upon the capacity model. The Division retained the services of Gray & Osborne Consulting to update the draft 2013 Wastewater Treatment Plant Facility Plan. The Wastewater Facility Plan project updates the current facility plan by providing current information on the existing wastewater facility and collection system infrastructure, regulatory requirements, future loadings, operation and maintenance, future capital improvements, rate structure and revenue forecasting. The updated facility plan will incorporate the collection system and stormwater system master plans. • Projected completion date: FY 2019 Speedway Interceptor and Beech Street Lift Station Project The existing 36 inch gravity sewer interceptor located between Beech Street and Nob Hill on the west side of I-82 is currently experiencing excessive sedimentation due to flat and adverse pipe slopes with slow fluid speeds and intermittent reverse flows. As part of the 2013 wastewater Master Plan, improvements to that interceptor were identified. The improvements include a force main installed through the existing 36 inch pipe as well as the construction of a new lift station on Beech Street south of Kiwanis Park. Flows currently reaching the Race Street lift station will be redirected in following phases at Beech and 15th and be redirected into the new lift station. The Race Street lift station will then be decommissioned. The project will allow for conveyance of existing flows at higher speeds as well as provide a mechanism for expanding service to the Boise Cascade Mill Site region without increasing the sedimentation problem as flows from that area develop. It will also allow for construction of improvements that will eliminate existing bottlenecks in the sewer interceptor system west of Washington Middle School. RH2 Engineering was hired as the engineering design consultant to address these issues, as well as address issues with the Rudkin Road lift station electrical elements and bypass options. RH2, with the help of City staff, prioritized the following two projects: Rudkin Road Lift Station Improvements: City Project No. 2416 Upgrade to electrical elements of the Rudkin Road lift station and installation of an emergency bypass connection. Farmers Electric II, LLC of Othello, WA was awarded this project for $146,591.52 Project is complete Beech Street Interceptor, Lift Station, and Force Main. City Project No. 2365 • Schedule A — 3000 LF of new gravity sewer Scout Lake Construction, Inc. of Selah was awarded Schedule A for $1,041,578.63 This portion of the project is substantially complete • Schedule B — Construction of new lift station located in southeast corner of Kiwanis Park along Beech Street and sliplining 6550 LF of force main sewer Rotschy, Inc. of Vancouver, WA was awarded Schedule B for $2,971,705.97 This portion of the project is scheduled to be completed in summer 2018. Projected completion date: FY2018 8 12 Stormwater Capital Improvements Projects 49th Avenue Drainage This project installed curb and gutter between 49th and 50th Avenues on Englewood Avenue and upsized existing drain lines on both Englewood Avenue and N. 49th Avenue to improve drainage and prevent flooding during future storm events. The project was awarded to D.W. Excavating from Davenport, Washington for the low bid amount of $439,555.00. Construction began in October 2017 and was substantially completed by November 2017. • Projected completion date: 2nd Quarter FY 2018 Pleasant Avenue Drain Pipe Repair This project will repair a broken section of storm drain pipe in Pleasant Ave., north of Washington Avenue. This small works project has been awarded to TTC Construction of Yakima, WA for the low bid amount of $31,653.00. • Project completion date: May 2018. 9 13 AFFIRMATIVE ACTION GOALS & W/M/DBE PARTICIPATION W/M/DBE utilization has been included in the past but is not included with this report. The Engineering Division continues to request apparent low bidders of public works contracts to document their efforts to achieve the City of Yakima's goal of 10% MBE, WBE or DBE participation goal prior to contract award. However, changes in state law due to the passage of Initiative 200 prohibit certain practices by contracting agencies (i.e. the City) for the award of public works projects such as requiring W/M/DBE subcontracting. While some contractors have voluntarily reported such information in the past, we have not received any such reporting last year. Although we do not receive such information voluntarily, the City must still meet certain of these federal requirements and each contractor must comply with the Standard Specifications that are included on each City Public Works Contract. The City is responsible to: • Conduct pre -construction conferences during which EEO and City policies are discussed with the contractor. • Monitor on-site compliance with the EEO and City policies. • Ensure our contractors locate, qualify, and increase the skills of minority groups, women employees, and applicants for employment as required by City policies. • Ensure the preparation of required EEO and related reports. 10 Proj Type Proj.Impacted No. Lead Division Project Name/Location Description of Work Project Lel d Divisions Constrctn. Start Date Status/Schedule Notes 7/16/2018 1 CIP 2337 Special Projects (& Engineering) Cascade Millsite Parkway New rights of way, public utilities, roads, lighting, roundabouts, sidewalks, pathway, infrastructure Joan Davenport / Brett Sheffield Engineering, Streets & Traffic Eng., Water/Irrigation, Wastewater/Storm ? ? ? Bravo Company Blvd. extension is being designed Project is 90% designed Bravo Company Blvd. will be a Blvd. style street that includes 2 more roundabouts. Design work includes road design & realignment in vicinity of East-West corridor to respond to BNSF rail concern; need funding modification 2 CIP 2355 Engineering & (Special Projects) Cascade Millsite Parkway (continued) Phase 1: Entire Site Phase 2: Southern portion Brett Sheffield / (Joan Davenport) Engineering, Streets & Traffic Eng., Water/Irrigation, Wastewater/Storm tbd Consultant, Landau Assoc's, gathered data for evaluation of landfill area and plywood plant site; DOE rejected Voluntary Compliance Plan We will enter into an Agreed Order with DOE in January/February 2018 3 CIP 2336 Special Projects & Engineering) ( g g) East-West Connector; "H" St. alignment from 1st St. to Terrace Heights; g Through Yakima Resources prop. New rights of way, public utilities, roads, lighting, signal(s), sidewalks, pathway,Joan infrastructure Brett Sheffield / Davenport ( p ) Engineering, Streets & Traffic Eng., Water/Irrigation, gp Wastewater/Storm 2018? NEPA review underway. Yakima Countyis project lead t Consultant (H.W. Lochner) hired for creation of design alternatives and NEPA review (environmental) 4 CIP 2356 Special Projects (& Engineering) Interchange Justification Report ( I.J.R.) for modification of 1-82 and Yakima Avenue Working with WSDOT for modification of Yakima Ave / 1-82 Interchange Brett Sheffield / ( Joan Davenport) Engineering, Streets & Traffic Eng., WSDOT Const. timeframe 2022 ��� City and County developing a plan to implement portions of the improvements in a phased manner in order to defer WSDOT changes to 1-82 and construction interchange portion early. WSDOT & FHWA have approved the IJR; Design & Constuction are up to the WSDOT. Design Funding in place for 2021 CIP 2340 Special Projects (& Engineering) North 1st Street Corridor Revitalization; Phase 1: 1-82 to 'N' St. Design and construction of sidewalk, landscape and utility upgrades Brett Sheffield / ( Joan Davenport) Engineering, Streets & Traffic Eng., Water/Irrigation, Wastewater/Storm Spring 2019 Federal funding of $2.7 M in place for Phase 1. We submitted for a BUILD grant on 7/19/2018. Construction should begin Spring 2019 Work w/ Utilities is underway to identify changes to facitlites to accommodate project needs. Council to meet in August or September to discuss scope of project, project amenities and utility relocations. 6 CIP 2390 Special Projects (& Engineering) North 1st Street Corridor Revitalization; Phase 2: MLK to 'N' St. Design & construction of sidewalk, landscape and utility upgrades; adding bike lanes removing parking; relocating overhead utilities Brett Sheffield Engineering, Streets & Traffic Eng., Water/Irrigation, Wastewater/Storm, Private Utilities 2018? HLA of Yakima was awarded the design contract; a 2018 BUILD Grant was submitted for on 7/19/2018 Phase 2 of this work was included in a 2017 FASTLANE federal grant application. Project was not selected. 7 CIP 2153 Engineering YVT System Restoration 6th Ave. vicinityYakima Ave. ( ) Remove and repair approx. 100 feet of trolleytrack Bob Desgrosellier Engineering, Streets 2018 CarBarn & other work completed, $60K remains for track repair; Parkin lot pavinghas beenpaved p 9 We have to amend existing federal submittals to include the proposed work within federal regulations p p 9 8 CIP 2143 Engineering E. Nob Hill Blvd & Fair Avenue,den Intersection Improvements Widen intersection all 4 legs; purchase r/way; new signal Brett Sheffield / (Randy Tabert) Engineering, Traffic, Wastewater, Water/Irrigation RoadwayDesign 2023? R/VVay 2018 is at 30%; We were awarded $189K in R/Way funds. R/Way plans complete. Search for construction funding on-going Some design funds remain, $190K in R/Way funds in-hand; We received 2023-2024 STP construction funds; R/way purchases to begin 9 CIP 2354 Engineering Capitol Theatre Safety Improvements Safety Improvements Bob Desgrosellier Engineering, Capitol Theatre 2015 & 2016 Several items completed; Carpeting completed in summer 2016; other work is forthcoming Replaced aisle lighting; added overhead cable runs; Replaced main lobby, mezzanine & Robertson Rm carpeting 10 CIP 2389 Engineering Tiger Oil Properties Remediation: East Nob Hill Blvd; North 1st St.; West Nob Hill Blvd Work with DOE to test these City properties, remediate soils and water as needed and then sell to developers Brett Sheffield / Joan Davenport / Bob Desgrosellier Engineering, CED 2015 Work with DOE and our consulting firm continues; 24th & Nob Hill: monitor 4 more quarters. 13th & E. Nob Hill - SOLD 56th & Summitview - SOLD 24th & Nob Hill - For Sale; DOE is pursuing a $1.2M grant to do more remedial investigation; N. 1st Street property is pending more testing 11 CIPEngineering ???? Lower Cowiche Creek Project Work with to release City Brett Sheffield / Rich Sanislo Engineering later The project is the approximate 2,000 feet of creek from SR 12 downstream to the Naches River Discussions have anticipated work occurring after any modification to Nelson Bridge Irrigation Intake Modification property for Cowiche Creek Conservancy 12 CIP ???? Engineering Downtown Yakima Central Plaza Increase the existing Plaza & surroundings into a world-class event center Sean Hawkins / Brett Sheffield Economic Development, Engineering, Streets, Planning, 2019 ? ? ? Council authorized design team to proceed with project plans after projected costs were reduced. GGN finished plans; SEPA checklist complete. Working with utilities for theft relocation Gustafson Guthrie Nichol (GGN) preparing construction doc's; also provide construction administration services Pledges are at $9.7M. 13 CIPEngineering ???? Multi-Sport Complex with SOZO Sports of Central WA, S. 38th Avenue just north of Ahtanum 58 acre site; Fields: 17 soccer/multi-sport; 14 FIFA sized grass; 3 FIFA sized lighted synthetic turf; Sports Campus & other facilities Sean Hawkins / Brett Sheffield Economic Development, Engineering, Streets, Planning, 7/11/05 Design plans are at 90%+ for improvements to Spring Creek, Sorenson Rd & 36th Ave. Making progress with R/Way acquisition & closer to getting FAA r/way as well Work continues on the collaboration of design, development and operation of a world-class Ya Yakima Sports Complex consisting of soccer/multi-sport fields and an indoor sports facility 14 CIP ???? Engineering Safe Routes to School Sidewalks: Adams Elementary School & Washington Middle School Install new sidewalk in the vicinity of the schools. (Locations forthcoming) Bob Desgrosellier Engineering summer 2018; after school is out Funded through Safe Routes To School Program. Contractor: Moreno & Nelson - Walla Walla Construction started; to be completed in August 15 CIPEngineering ???? Safe Routes to School Sidewalks: Garfield Elementary School Install new sidewalk in the vicinity of the school. (Locations forthcoming) Bob Desgrosellier Engineering summer 2019; after school is out This project was awarded through the Safe Routes To School Program Design is at 95%; Waiting on R/Way completion; Working with PP&L to get poles moved 16 CIP ???? Engineering 64th & Ahtanum widening and signalization Widen the intersection adding a westbound RTO lane and adding a signal Brett Sheffield Randy Tabert Engineering 2019? Application for this project was successful for Congestion Mitigation & Air Quality funding (CMAQ) We'll start design in 2018; Project has been selected for funding in 2019, design funding is now available; We're in the process of obligating design funds Proj Type Proj.e1a No. Lead Division Project Name/Location Description of Work Project Lad Impacted Divisions Constrctn. Start Date Status/Schedule Notes 7/16/2018 17 CIPEngineering ???? Heritage Capitol Project Grant for YVTrolley Improvements Restore parts of the YVT facilities and trolley system Bob Desgrosellier Engineering,Trolley Streets 2017 thru 2018 Work proceeds on "sub -projects". Work covers a variety of construction disciplines we cannot package into one large proejct. $50K of State Heritage Capitol Projects; matched against volunteers labor, improvements & $90,000 in matching City construction funds; Museum interpretive displays, door replacement and parking lot lighting are pending 18 CIPEngineering ???? Safe Routes to School Sidewalks: McClure Elementary School Install new sidewalk in the vicinity of the schools. (Locations forthcoming) Bob Desgrosellier Engineering 2019 This project was awarded through the Safe Routes To School Program Project was selected & funded by State Legislature; Obligation of PE funds just completed. 19 CIP ???? Engineering Cowiche Canyon Trail - from Powerhouse Road to the existing Cowiche Canyon Trailhead Construct 2 mile gravel pathway with 2 bridges crossing the Creek Brett Sheffield Engineering 2019 - 2021 Funded by a $2M Connect Washington Grant. Received $200k in design funds but construction funding is not available until the 2019-2021 biennium. Perteet Eng. is the designer. Design is 50% complete; We've had four (4) Project Stakeholders meetings; the most recent was 7/6/18. We're modifying path alignment to meet concerns. Design may be completed in 2018 20 CIP ???? Engineering g g 2 Roundabouts at Fruitvale Blvd & River Road at N. 34th Avenue Construct 2 roundabouts or double roundabout)Brett at this compound intersection Sheffield / (Randy Tabert) Engineering g g 2019? Application for this project was successful for a $914K Federal Grant. Design is 20% complete; WSDOT is providingdesign assistance for this unique double roundabout 21 CIP ???? Engineering Complete Streets - 5 locations; 4 sidewalks in 2018; 1 sidewalk in 2019 Construction of new sidewalk in 5 locations Brett Sheffield / (Randy Tabert) Engineering 2018 & 2019 Swan Ave, McGuiness Pk to Campbell Ln, So. Side Race St, 8th Street to Naches Ave. where missing Viola Ave., 4th Ave to 10th Ave, So. Side Powerhouse, Robertson School to Englewood, West side 2019: Prasch Ave., 16th to 20th Ave. (r/way needed ) 22 CIP ���� EngineeringPub. N. 2nd St. Pkg Lot landscaping; Wks. - Landscape Im rvmnt's p p Experimental landscaping to reduce wateringneeds Brett Sheffield / (RandyTabert)Water Engineering / & Irrig2018 N. 2nd Street Parking Lot work is complete. Similar project at Public Works starts 23rd July Experimental landscaping to reduce watering needs. Contractor: Evergreen Services - Yakima 9 23 CIP ???? NEW" Engineering's River Road Widening 34th to 40th Avenues Reconstruct and Widen roadway to 3 -lane standard with curb, gutter & sidewalk Brett Sheffield / (Randy Tabert) Engineering 2019? This proejct will tie to the new roundabout(s) at 34th Avenue and Fruitvale Blvd_ Design has started; $1M SIED grant received 7/17/2018; We are submitting for a TIB grant mid-August; TIB selects next grant award winners mid-November 24 CIP 2416 Phase II Wastewater Speedway/Race street Interceptor Slipline existing interceptor with new force mains, refit of Rudkin Road lift station and new lift station on Beech. Engineering/ Dana Kallevig Wastewater 2017 This project is under construction; 98% complete This project will address adverse flow conditions; Flows need to be rerouted from the Fair Ave basin & parts of the 2nd Avenue basin and will pick up flows with the redevelopment of the sawmill area. 25 CIP 2010 Water/Irrigation Nelson Dam Replacement / Fruitvale Canal Diversion Improvements Move Point of Diversion (Improving Nelson Dam fish screen for additional water) Rich Sanislo / Dave Brown / Mike Shane Water/Irrigation, USBR, Yakima County, WDFW, North Yakima Conservation District 2020 City's working w/USBR & HDR on fish screen/intake options. Assessment received 6/13 w/design alts & recommendations. HDR finalized report & options; met stakeholders 9/13 to discuss options. Final HDR report based on comments. Stakeholder review on-going. Working w/Yakima County to review coordination with flood plan restoration project, and develop MOU to utilize single consultant for design of overall project (river modifications & diversion structure) Applied to DOE for point of diversion change to Nelson Dam. Point of Diversion change on public notice 7/13/12 and 7/20/2012. USBR project is out of funding. Water Division budgeted $8M in 2017 for project infrastructure 26 CIP 2288 Water/Irrigation Misc. waterline improvements. Water facilities impacted bymisc. projects p J Mike Shane / Emilio LopezStreets, p Water/Irrigation, Eng.2018 On-going coordination with other projects (sidewalks, paving, chip seal)Majority of work to be completed by in-house staff. 27 CIP 2335 Water/Irrigation Naches River WTP Intake Improvements Modification of river intake; Possible improvements in river to maintain existing location and flows to intake Dave Brown, Mike Shane Water/Irrigation 2018/19 Working w/Golder & Assoc. for Hydrotech Eng Support Services for design, permitting, funding, construction bid & inspection support of new intake & floodplain stabilization structures. Conceptual design for new river structures provided 12/13; final design underway. Additional stakeholder (TAG) meetings determine final design criteria. Yakima County to survey area & water levels at intake for additional information to stakeholders regarding design. Modified design proposal provided to stakeholders. Additional river modeling to be completed by Golder and results reviewed by stakeholders. Ecology has issued a Watershed grant for $250,000 for this project. 28 CIP 2463 Water/Irrigation g HathawayWaterline Replacement p Replace existing 16" OD steel with 12" DI waterline from N. 6th Ave. to N. 16th Ave. Dave Brown, Mike Shane Water/Irrigation, Streets, Eng. 2018/19 Consultant selection process completed. HLA Engineering and Land Surveying,Inc. selected for multi- g g year projec design contract, Design is underway. Coordinating project with Wastewater system improvements alongsameportion of Hathaway. Y p Roadway to be rebuilt after completion of undergound work. Capital Improvement Projects 2nd Quarter of 2018 Adams/Washington Vicinity Sidewalks Estimated Project Cost: $380,000 SRTS Grant: $357,000 Gen. Fund (Gas Tax): $23,000 Construction End Date: August 22, 2018 8th Street and Adams St 8th Street & Race Street Adams/Washington Vicinity Sidewalks Estimated Project Cost: $380,000 SRTS Grant: $357,000 Gen. Fund (Gas Tax): $23,000 Construction End Date: August 22, 2018 North Side of Race Street South Side of Maple Street Adams/Washington Vicinity Sidewalks Estimated Project Cost: $380,000 SRTS Grant: $357,000 Gen. Fund (Gas Tax) : $23,000 Construction End Date: August 22, 2018 Sidewalk on school grounds to eliminate the need for students to walk across parking lot Garfield Elementary Safety Improvements Estimated Project Cost: $200,000 SRTS Grant: S180,000 Gen. Fund (Gas Tax): $20,000 Scheduled Construction Start: mid-June, 2019 Scheduled Construction End: mid-August, 2019 Acquired the needed right of way on Campbell Lane Have Contacted Pacific Power and Have Received Assurance that the Utility Poles will be Relocated before Summer 2019 Garfield Elementary Safety Improvements Estimated Project Cost: $200,000 SRTS Grant: S180,000 Gen. Fund (Gas Tax): $20,000 Scheduled Construction Start: mid-June, 2019 Scheduled Construction End: mid-August 2019 LEGEND •••••••••••••••••••••••• #r. kWi *AT Ek MN" Cf ANT 33 Ek•tieNT 33 aE*9-4:1AE MEV CHTP.CF *AT AAR, Garfield Right of Way Plan R •, •Al Afit MA BA. 4,233 :814-3 :1331 3 '4441: Rees • •4&3 '(303 •:.433+1',3kr9t. +.1 S 1243 32.35.4 04: 3.$13 113'3-345! 43383433 9 3 3 3,33444 f•; ',4341) FLVERI CLAREWX MAAK 3 13 id1313-51510 EISEHICJ HENTEHA 34 4±2 C1R1311-0,11IG', JOSE 3, & t, AR 1"04E 11311 ;1±3—±3441Y) 4A;;11,E: & ANA M 76' McClure Elementary School Safety Improvements Estimated Project Cost: $300,000 SRTS Grant: S270,000 Gen. Funds (Gas Tax): S30,000 Scheduled Construction Start: mid-June, 2020 Scheduled Construction End: mid-August, 2020 Obligated Preliminary Engineering Funds North 1st Street Revitalization, Phase 1 Estimated Project Cost: $3,584,400 STP Grant: $2,968,000 Stormwater and Water Enterprise Funds: $616,400 Scheduled Construction Start: March, 2019 Scheduled Construction End: November, 2019 Environmental Documentation was submitted and approved Allows for obligating construction funds. Continued to work with utility companies on relocating overhead lines NEPA Catayo mal Exclusion Documentation Form North 1St Street Revitalization, Phase 2 '1' Street to 'N' Street Estimated Project Cost: $3,286,500 Projected Transportation Improvement Board Grant: 5526,300 BUILD Grant or TBD Funds: $1,918,800 Stormwater and Water Capital Project Funds: $616,400 General Fund (Gas Tax): $225,000 Scheduled Construction Start: March, 2020 Scheduled Construction End: September, 2020 Developed a BUILD Grant Application North 1 st Street Revitalization, Phase 3 MLK Boulevard to `I' Street Estimated Project Cost: $9,713,000 Projected Transportation Improvement Board Grant: S 1,553,700 BUILD Grant or TBD Funds: $5,789,400 Stormwater and Water Capital Project Funds: S 1,694,900 General Fund (Gas Tax): $675,000 Scheduled Construction Start: February, 2021 Scheduled Construction End: November, 2021 Developed a BUILD Grant Application Cascade Mill Redevelopment Project Estimated Project Cost: S28,446,000 LIFT Funds: $23,446,000, Projected BUILD or TIB Grant: $5,000,000 Scheduled Construction Start: March, 2019 Scheduled Construction End: November, 2024 Entered into an Agreed Order with the Department of Ecology Includes interim action plan for the roadway, which allows the roadway to be constructed prior to determination of the cleanup required for the full site. Provides for better interaction with the Department of Ecology Developed BUILD Grant Application for the Widening and Redevelopment of `H' Street from 1st Street to 7th Street Cascade Mill Redevelopment Project Estimated Project Cost: S28,446,000 LIFT Funds: $23,446,000, Projected BUILD or TIB Grant: $5,000,000 Scheduled Construction Start: March, 2019 Scheduled Construction End: November, 2024 wASMN, It V4 114 FAit.1.,t Of 0.H.1 t1,1.1,1t2V, '•:)3:1, 0.0.1 r. :.. 1.1 Agreed Order .4•01,4•ENI•Nt :1V". •.•;":••.• • Fruitvale/River Rd. & 34th Ave./River Rd. Roundabouts Estimated Project Cost: S1,012,898 HSIP Grant: 5911,608 Gen. Fund (Gas Tax): $101,290 Scheduled Construction Start: April, 2019 Scheduled Construction End: November, 2019 Cowiche Canyon Trail Estimated Project Cost: $2,000,000 Connect Washington Grant: $2,000,000 Scheduled Construction Start: April, 2020 Scheduled Construction End: November, 2020 -Met with Adjacent Property Owners to Work on Developing an Acceptable Alignment Spring Creek Road -Soccer Complex Access Estimated Project Costs: $3,500,000 SIED Funds: $1,800,000 City Bond: $1,700,000 Scheduled Project Start: February 2019 Scheduled Project End: May 2019 Continued working with the Federal Aviation Administration on acquiring right of way from the Yakima Air Terminal required for the road widening Water Treatment Plant Intake Improvements Estimated Project Cost: $950,000 DOE Watershed Grant: $250,000 Water Enterprise Fund: S700,000 Scheduled Construction Start: February 2019 Scheduled Construction End: June 2019 Modifications to the Naches River to ensure that the Water Treatment Plant Intake continues to function properly. Golder and Associates working on the design for a bid in 2019 Applying for "work in river" permits Fruitvale Canal - Nelson Dam Improvements Estimated Project Cost: $13,000,000 Yakima County Floodplain by Design Grant: S3,800,000 Water Enterprise Fund: S3,200,000 City Bond: $6,000,000 Scheduled Construction Start: January 2020 Scheduled End Construction: June 2022 Existing Nelson Dam to be replaced with a new irrigation diversion structure. On-going discussions with BOR, WDFW, Yakima County, NMFS, Yakama Nation and North Yakima Conservation District. 2.5% GRADIENT NATURE -LIKE FISHWAY WITH FIXED CREST Neches River CONSOLIDATED INhAKF STRUCTURE: CONVEYANCE PIPELINES • Hathaway Street Waterline and Wastewater Line Replacement Estimated Project Cost: S1,400,000 Water Capital Project Funds: $750,000 Wastewater Capital Project Funds: $650,000 Scheduled Construction Start: January 2019 Scheduled Construction End: May 2019 Replaces 2,650 linear feet of existing steel water line pipe with 12 -inch ductile iron pipe Installs approximately 1,800 linear feet of 8 -inch sewer main, along with side sewer services. Relocates a failing section between 6th Avenue and 8t" Avenue that is currently located in back yards. HLA Engineering and Surveying, Inc. continued working on the design for an early 2019 construction. Beech Street Lift Station Estimated Project Cost: $3,200,000 Wastewater Capital Project Funds: $3,200,000 Scheduled Construction End: September 2018 Construct new lift station east of Kiwanis Park and construct new force main between Beech Street and Nob Hill Blvd. to address current sewer problems and future needs Will allow for the decommissioning of the old Race Street lift station. 49th Avenue Drainage Improvements Total Project Cost: $500,000 Stormwater Project addressed flooding issues on 49th Avenue Substantially completed in November, 2017 Completed May 2018 Pleasant Avenue Drain Pipe Repair Total Project Cost: $35,000 Stormwater Capital Fund: $35,000 Repaired broken pipe Construction completed May, 2018