Loading...
HomeMy WebLinkAbout03/20/2018 13B Yakima River Basin Integrated Water Resource Management Plan Project Activity UpdateBUSINESS OF THE CITY COUNCIL YAKIMA, WASHINGTON AGENDASTATEMENT Item No. 13.B. For Meeting of: March 20, 2018 ITEM TITLE: Yakima River Basin Integrated Water Resource Management Plan Project Activity Update SUBMITTED BY: Scott Schafer, Director of Public Works David Brown, Water/Irrigation Manager, 509-575-6204 SUMMARY EXPLANATION: Quarterly update on Yakima River Basin Integrated Water Resource Management Plan (YB I P) project activity. ITEM BUDGETED: NA STRATEGIC PRIORITY: Partnership Development APPROVED FOR SUBMITTAL: STAFF RECOMMENDATION: BOARD/COMMITTEE RECOMMENDATION: ATTACHMENTS: Description Upload Date i Project Actiuty Report 3/5!2018 Type Coyer Memo Yakima River Basin Integrated Water Resource Management Plan Project Activity Update February 2018 Purpose: To provide updates on technical aspects of ongoing planning studies for the Yakima River Basin Integrated Water Resource Management Plan (Integrated Plan) Fish Passage Element Cle Elum Dam Fish Passage Facilities and Reintroduction Project: The construction contract for the access road and bridge was awarded in July 2015 and was completed in October 2016. The construction contract for a portion (secant pile vault) of the juvenile fish passage facility was awarded in July 2016; the onsite work began in April 2017. The secant pile drilling was completed November 2017, and excavation of the secant pile vault began in November 2017. Due to the mild winter conditions, vault excavation has continued through the winter months and is approximately 40 feet deep (total depth per contract is 85 feet). The construction contract for the tunnel bypass was awarded in August 2017. The contractor has begun to mobilize equipment and construction will begin in March 2018. Reclamation continues to work through the award process for the gate/helix and intake contract to be awarded later this summer The juvenile fish passage facility has an innovative helix design to transport juvenile fish downstream over 63 feet of fluctuation in the reservoir. The upstream adult fish passage facility currently includes trap-and-haul—fish are trapped at the base of the dam, loaded into a truck and then hauled for release into Cle Elum Reservoir or upstream tributaries. Project managers are evaluating the Whooshh® —an innovative fish transport system that can provide adult upstream passage. The Whooshh® fish passage technology was tested at the Roza Fish Trap in summer 2016 for spring Chinook as a surrogate for possible application at Cle Elum Dam. A similar test was performed in fall 2016 at the Yakama Nation Fisheries Facility at Prosser Dam for fall Chinook and Coho Salmon. Data for both tests are being analyzed. A third test of the Whooshh® fish transport system was conducted in July 2017 at Cle Elum Dam. USGS has completed the draft report of the Whooshh test results and the report is currently undergoing review by the Yakama Nation, WDFW, and Reclamation. A final Report is expected at the end of March 2018. Reclamation and the Yakama Nation are planning to conduct a Sockeye tracking test to understand Sockeye migration between Roza and Cle Elum Dam and test the fish's ability to locate an attraction flow and enter into a trap system set up at the base of the dam. Sockeye returns are expected to be low again this year so the tracking may be postponed until 2019, depending on the number of fish that return. U.S. Department of the Interior Bureau of Reclamation A S H I N E T D N STATE DEPARTPENT OF ECOLOGY Box Canyon Creek Fish Passage: The appraisal report for Box Canyon Creek passage was completed in February 2016. The Passage Workgroup met in June 2016 to review and discuss several passage options for Box Canyon Creek. The workgroup decided to move forward with constructing a roughened channel with channel control structures as the preferred option. WDFW is coordinating with Reclamation to complete preliminary design for the Box Canyon Creek Fish Passage, Currently, WDFW has completed the 30% design. Reclamation will work to finalize the design. Additional survey work is needed and is expected to be complete by October 2018. The preliminary final design is anticipated to be completed by June 2019. Clear Creek Dam Fish Passage: U.S. Fish and Wildlife Service, Reclamation, and WDFW completed a study of fish passage at Clear Creek Dam in 2015, finding that existing fish passage facilities were not functional and that Bull Trout from the North Fork Tieton River were unable to reach critical spawning and rearing habitat. Ecology received funding for fish passage improvements at this location in the State funding biennium request (2017-2019). Reclamation is coordinating with USFWS, Yakama Nation, and WDFW on design options for a fish ladder at Clear Creek Dam. Current schedule is 30% design by the end of September 2018, final design complete by September 2019, and construction to begin in 2020. Until passage improvements are accomplished, USFWS, Reclamation, and other partners will continue capturing Bull Trout from below Clear Creek Dam and transporting them around the dam so they can reach spawning habitat in the North Fork Tieton River. Fish capture and transport was conducted in 2016 and 2017 and to date, 36 adult Bull Trout have been transported above the dam. Structural and Operational Changes Element Keechelus-to-Kachess Conveyance (K KC) Project: Refer to KDRPP project below. Cle Elum Pool Raise: Radial Gate construction was completed in April 2017. Reclamation will award several contracts over several years for shoreline protection actions. The construction contract for improvements on U.S. Forest Service facilities (specifically, Cle Elum Campground) was awarded September 2017 and construction was completed November 21, 2017. Reclamation and Ecology anticipate awarding the construction contract for Speelyi Day Use Area shoreline protection in FY18. Speelyi Day Use Area will be closed during construction, September 10, 2018 — December 31, 2018. Reclamation and Ecology are meeting with local landowners. Additional public notices about the timing of construction and informational meetings on existing shoreline designs will be mailed to shoreline parcel owners and posted at USFS facilities. Chandler Pumping Plant Electrification Kennewick Irrigation District (KID) and their consultant developed a concept design for an electric pumping plant at Chandler. Reclamation has reviewed the concept design and KID performed a transient analysis which has been reviewed by Reclamation. Reclamation, Ecology and HDR recently completed Phase 3 modeling, including examination of return flows in the lower Yakima System to determine impacts on KID from future conservation efforts. Modeling is ongoing. Reclamation will continue to coordinate with KID on review of Chandler Electrification project. 2 Lower Yakima River Smolt Survival Reclamation is coordinating with Yakama Nation, USGS, NMFS, USFWS, WDFW, Irrigation Districts and others to develop a Lower Yakima River Smolt Survival Study in collaboration with the Lower River Subgroup. The study will begin in Spring 2018. Yakima-Tieton Irrigation District (YTID) Main Canal Repair/Replacement YTID is nearing completion of a report that evaluates alternatives to repair or replace the YTID main canal. Alternatives considered include: 1. Baseline Alternative (Tieton Main Canal Repair) 2. Tieton Main Canal Replacement 3. Diversion Relocation to Wapatox Diversion Dam (and associated new conveyance system) 4. New North Fork Cowiche Creek Reservoir, either with or without the Wapatox diversion. YTID plans to begin environmental review under SEPA and NEPA, with possible participation by Ecology and Reclamation as partners in the review. Surface Water Storage Element Kachess Drought Relief Pumping Plant (KDRPP) Reclamation and Ecology anticipate releasing the Kachess Drought Relief Pumping Plant and Keechelus to Kachess Conveyance Supplemental Draft Environmental Impact Statement to the public in 2018 in coordination with Roza Irrigation District. The SDEIS is currently under review by the US Department of the Interior. A Notice of Availability will be published in the Federal Register prior to the release of the SDEIS. Public meetings will be held following the release of the SDEIS. Wymer Reservoir Consideration of site requirements is ongoing. Bumping Reservoir Enlargement Project Consideration of site requirements is ongoing. Groundwater Storage Element Groundwater Storage — Basinwide Analysis A new Groundwater Storage Subcommittee was established with chair, Tom Ring, Yakama Nation. The subcommittee is reviewing all ongoing groundwater storage projects and developing a mission statement and objectives. The committee reviewed ongoing groundwater storage projects in October 2017. In the Wapato Irrigation Project, additional monitoring -well locations have been identified, which will help with observation of the aquifer system response to recharge activities from Toppenish Creek. Reclamation is working with Yakama Nation Engineering to locate and drill the three (3) additional wells in 2017. Ecology will install pressure transducers, and data will be analyzed to determine the benefits of the recharge activities. Monitoring of existing sites continues. Yakama Nation is getting permitting for wells and coordinating with Reclamation drill crew to schedule drilling. 3 In spring 2018 the Committee anticipates reviewing research on the Yakima Basin conducted by a graduate student in hydrogeology at Oregon State University. The Lower River Subgroup is exploring opportunities to use groundwater recharge to improve thermal refuges for migrating fish along the lower Yakima River. An initial study has been funded to develop current information on temperature variations in the river from Wapato Dam to the Yakima River mouth. Aquifer Storage and Recovery (ASR) The City of Yakima's Quality Assurance Project Plan was approved by Ecology in January 2018. Additional documentation on the ASR program is now being finalized. The City plans to recharge in the winter of 2018-2019. Habitat Protection and Enhancement Element Targeted Watershed Protection and Enhancement The Washington State Department of Natural Resources and Washington Department of Fish and Wildlife are working with the Teanaway Community Forest (TCF) advisory committee to develop a recreation plan for the TCF. Actions will be guided by the recently approved management plan. Funding appropriated by the State for the 2017-2019 Biennium will be used for habitat, forest and infrastructure projects. The primary focus of habitat projects will be continued removal of fish passage barriers; and installation of fencing, stream crossings, and watering stations to keep grazing stock out of sensitive riparian areas. In addition the Yakama Nation continues to work on wood placement in TCF streams to improve habitat conditions and watershed functions. Mainstem Floodplain and Tributaries Fish Habitat Enhancement Program Recipients of funding from the State's 2015-17 biennium are continuing installation of fish habitat restoration projects at several locations. Funding of $5.4 million for additional projects during the 2017-2019 biennium was appropriated by the State Legislature in January 2018. The Habitat Subcommittee reviewed the proposed projects in February 2018 to bring information up to date. Ecology is working with the funding recipients to establish contracts for these projects. A stakeholder group consisting of the City of Richland, federal and state fisheries managers, irrigation districts, environmental and commercial interests, the USACE Walla Walla District, and the Yakama and Umatilla tribes has been working together on the Yakima River Delta Enhancement project. The proposed project to breach a portion or all of the Bateman Island causeway will change flow patterns and improve temperature conditions, instream water flows, water quality, and fisheries within the Yakima Delta, and is viewed as critical to the long-term success of numerous upstream fisheries projects being implemented as a part of the Integrated Plan. Additional project support has been requested through the US Army Corp of Engineers 1135 Program, with a possible decision on support anticipated soon. The Yakama Nation and Kittitas County Conservation District are working to engage landowners and farm and ranch operators in contracting funds awarded in 2016 by the USDA Natural Resources Conservation Service (NRCS) through their Regional Conservation Partnership Program (RCPP). The "Yakima Integrated Plan — Toppenish to Teanaway Project" is funded through 2021. The RCPP funding focuses on insufficient water/drought, water quality degradation, and inadequate fish & wildlife habitat in priority areas in Kittitas County and on the Yakama Nation Reservation lands. The Yakama Nation is working on "beaver based" restoration projects on Reservation land. 4 6 The 5- year agreement between the Yakama Nation in September 2017, and a kickoff meeting was held in October 2017. KCCD received 24 applications for the Environmental Quality Incentives Program (EQIP). KCCD also held a meeting with partners and the NRCS staff knowledgeable about their easement programs in order to prepare for implementation of that portion of this project. KCCD staff are working with NRCS on conservation plans and contracting with 8 producers for sprinkler conversion projects in priority areas. They received one application and will be working on the plan and contract for stream habitat improvement. Construction of these projects is expected to begin in fall 2018. KCCD is also beginning to work on the easement programs with Forterra and local producers. Enhanced Water Conservation Element Funding of $5 million for additional projects during the 2017-2019 biennium was appropriated by the State Legislature in January 2018. The Water Use Subcommittee reviewed the proposed projects in February 2018 to bring information up to date. Ecology is working with the funding recipients to establish contracts for these projects. Market Reallocation Element In September 2017, Kittitas Reclamation District was awarded Reclamation's WaterSMART Water Marketing Strategies grant (https://wwwusbrgovinewsroonllnewsrelease/detaiLcfm?RecordlD=60457) The funding from Reclamation are being matched with funding from Ecology's Water Resources Program and Office of Columbia River to analyze issues that limit market transactions throughout the Yakima River basin. KRD and Trout Unlimited are partnering in this study and will seek collaboration with other entities in the basin. Contacts for Information on the Integrated Plan: Wendy Christensen, U.S. Department of the Interior, Bureau of Reclamation, Columbia -Cascades Area Office, (509) 575-5848, ext. 203 Thomas Tebb, Washington State Department of Ecology, Office of Columbia River, (509) 574-3989 Project website: http://www.usbr.gov/pn/programs/yrbwep/index.html 5