HomeMy WebLinkAbout02/20/2018 06C 2017 Pavement Repair Project Completion; Granite Construction CompanyITEM TITLE:
SUBMITTED BY:
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
1
Item No. 6.C.
For Meeting of: February 20, 2018
Project completion and contact acceptance for Granite
Construction Company - 2017 Pavement Repair Project (Standard
Motion V -B -Accept the project and approve)
Brett Sheffield - Chief Engineer - 509-576-6797
Scott Schafer, Public Works Director
SUMMARY EXPLANATION:
City Project 2437 provided for the construction of new sections of roadway on the northbound
lanes of N. 16th Ave at the Cherry Ave intersection and of the eastbound lane of Mead Avenue at
14th Ave. The City contracted with Granite Construction Company for this project which also
included curb, gutter, and sidewalk repairs. Final inspection for this project was made and the
recommendation is that the project be accepted. A final payment of $2,316.95 (5% retainage) is
due from the City to Granite Construction Company for the completion of this roadway project.
Project Manager: Brett Sheffield
Contractor: Granite Construction Company
Contract Awarded: 5/31/2017
Contract Cost: $46,338.94
Retainage Due: $2,316.95
The total contract cost is for construction only and does not include engineering and other costs.
City Council action is required to accept the project and approve the final construction costs.
ITEM BUDGETED:
STRATEGIC PRIORITY:
APPROVED FOR
SUBMITTAL:
City Manager
STAFF RECOMMENDATION:
Accept Project
BOARD/COMMITTEE RECOMMENDATION:
ATTACHMENTS:
Description Upload Date
d Final 1/29/2018
Type
Cover Memo
2
City of Yakima
City Engineering Division
129 N 2nd Street
Yakima, WA 98901
TO: Granite Construction, Co.
PROJECT TITLE 2017 Pavement Repair Project
City Project No.:
Progress Estimate No.:
Date
2437
FINAL
January 23, 20 8
Total
Item
No.
Description
QTY
UNIT
Unit
Price
Bid Contract
Amount
To Date
Quantity
% of
Contract
Amount
Previous
Quantity
Previous
Payments
Quantity
this period
Amount
Due
Acct
Def
1
Mobilization
1
LS
$5,000.00
$ 5,000.00
1
100%
$ 5,000.00
0
$ -
1
$ 5,000.00
30
2
Project Temporary Traffic Control
1
LS
$4,100.00
$ 4,100.00
1
100%
$ 4,100.00
0
$ -
1
$ 4,100.00
30
3
Sawcut Pavement
125
LF
$8.00
$ 1,000.00
269
215%
$ 2,152.00
0
$ -
269
$ 2,152.00
30
4
Removing Cement Concrete Sidewalk
66
SY
$35.00
$ 2,310.00
66
100%
$ 2,310.00
0
$ -
66
$ 2,310.00
30
5
Removing Cement Concrete Curb
122
LF
$20.00
$ 2,440.00
122
100%
$ 2,440.00
0
$ -
122
$ 2,440.00
30
6
Removing Asphalt Concrete Pavement
102
SY
$35.00
$ 3,570.00
102
100%
$ 3,570.00
0
$ -
102
$ 3,570.00
30
7
Crushed Surfacing Base Course
33
TON
$80.00
$ 2,640.00
38.75
117%
$ 3,100.00
0
$ -
38.75
$ 3,100.00
30
8
HMA CL 1/2" PG 64-28
37
TON
$250.00
$ 9,250.00
52.55
142%
$ 13,137.50
0
$ -
52.55
$ 13,137.50
30
9
Cement ConcreteTraffic Curb & Gutter
123
LF
$30.00
$ 3,690.00
123
100%
$ 3,690.00
0
$ -
123
$ 3,690.00
61
10
Cement Concrete Sidewalk - 4 inch thick
71
SY
$46.00
$ 3,266.00
58.33
82%
$ 2,683.18
0
$ -
58.33
$ 2,683.18
61
11
Cement Concrete Sidewalk - 6 inch thick
17
SY
$56.00
$ 952.00
12.22
72%
$ 684.32
0
$ -
12.22
$ 684.32
61
12
Cement Conc. Curb Ramp Type PerpendicularA
2
EA
$1,300.00
$ 2,600.00
2
100%
$ 2,600.00
0
$ -
2
$ 2,600.00
61
13
Repair or Replacement
1
EST
$1,000.00
$ 1,000.00
871.94
87%
$ 871.94
0
$ -
871.94
$ 871.94
30
TOTALS
$ 41,818.00
111%
$ 46,338.94
$ -
SUB TOTAL
$46,338.94
RETAINAGE 5%
$2,316.95
AMOUNT NOW DUE
$44,021.99
I hereby certify that the foregoing is a true and correct statement of the work performed under this Contract.
CITY ENGINEER /s/ Brett Sheffield