HomeMy WebLinkAbout06/06/2017 11 2018-2023 Six-Year Transportation Improvement Program; Metropolitan Transportation Plan; UACP Capital Facilities ElementBUSINESS OF THE CITY COUNCIL YAKIMA, WASHINGTON AGENDASTATEMENT Item No. 11. For Meeting of: June 6, 2017 ITEM TITLE: Public Hearing to consider: A) Adoption of the 2018-2023 Six-year Transportation Improvement Program and amending the Metropolitan Transportation Plan; and B)Amending the Yakima Urban Area Comprehensive Plan Capital Facilities Element SUBMITTED BY: Brett Sheffield, Chief Engineer -576-6797 Scott Schafer, Public Works Director SUMMARY EXPLANATION: A) Each year the City is required by RCW 35.77.010 and RCW 36.81.121 to update its Six-year Transportation Improvement Program (TIP) for submittal to the Washington State Department of Transportation. This Plan must include all transportation projects for which state gas tax revenue and federal revenue will be used. The proposed 2018-2023 Transportation Improvement Plan includes fourteen projects that have funding. The funded projects are: #1 — North 1 st Street Revitalization, `N' Street to S R 12 #4 — Powerhouse Road Sidewalk #5 — Garfield Elementary Safety Improvements #6 — Yakima Valley Transportation Company Preservation #7 — Spring Creek Road Reconstruction #8 — South 36th Avenue Reconstruction #9 — Sorenson Road Reconstruction #10 — Bravo Company Boulevard #12 — Northside Alley Pavers #14 — Cowiche Canyon Trail #15 — N.34th Avenue/Fruitvale Boulevard & N. 34th Avenue/River Road Roundabouts #16 — Complete Street Projects #18 — S. 80th Avenue (Wide Hollow Creek) Bridge #19 — Wide Hollow Road (Wide Hollow Creek) Bridge A summary of the proposed changes are listed below. Add projects: #15 N. 34th Avenue/Fruitvale Blvd & N. 34th Avenue/River Road Roundabouts O #16 Complete Street Projects #20 West River Road Improvements Divide the North 1 st Street Revitalization project into two phases: #2 North 1 st Street Revitalization, Phase 2 — `N' Street to `H' Street, and #3 North 1St Street Revitalization, Phase 3 — `H' Street to MLK Remove project #4 — Adams Elementary/Washington M.S. sidewalk improvements since the project was completed Funding for the remainder of the projects will continue to be sought. In order to use federal funds, such as those administered by the Federal Highway Administration (FHWA) and the Federal Transit Authority (FTA), projects must be included in the Statewide Transportation Improvement Program (STIP). The STIP is a prioritized program of transportation projects, complied from local and regional plans, along with the Washington Transportation System Plan (WTP), which provides a backbone for developing projects for the intermodal transportation network in the State of Washington. The STIP contains federally funded projects plus state and local projects that are regionally significant. These projects have been identified through the planning process as the highest priority for the available funding to the state's Transportation Program. Planning activities of state and local governments are essential parts of integrated regional planning processes. Long range transportation planning is a part of the comprehensive land use planning carried out by local governments. Citizen participation is an integral part of the planning process at all levels. Local agencies are required to develop and adopt a Six-year Transportation Program; holding at least one public hearing during its development. B) The City needs to amend the Yakima Urban Area Comprehensive Plan Capital Facilities Element to incorporate the adopted Six-year TI P for 2018 to 2023. This will ensure that we are in compliance with the Growth Management Act and that we are consistent with the Comprehensive Plan as required. The amendment is limited to incorporate only those projects that are adopted in the STIP and is not subject to the "once a year' change required under the regulations of the Growth Management Act. ITEM BUDGETED: STRATEGIC PRIORITY: APPROVED FORce* ,, SUBMITTAL: City Manager STAFF RECOMMENDATION: Hold the Public Hearing and continue Public Hearing to June 20, 2017 Council meeting for second Public Hearing and possible adoption of Plan. BOARD/COMMITTEE RECOMMENDATION: ATTACHMENTS: Description Upload Date Type 2018 - 2023 Six 5/22/2017 Ccxer Me Agency: Yakima Co. No.: 39- Co. Name: Yakima Co. City No.: 1485 MPO/RTPO: YVCOG MMMM2312 = Hearing Date: 6/6/17 & 6/20/17 Adoption Date: Amend Date: Resolution No.: 6/20/2-017 Project Costs in Thousands of Dollars Federally Funded Expenditure Schedule Z5 Project Identification Fund Source Information (Loc al Agency) Projects Only R/W A. PIN/Federal Aid No, B. Bridge No, c s Federal Funding C. Project Title E M 0 Phase Federal State State Local Total Envir. Required D. Street/Road Name or NumberStart 0 Federal Fund Cost by Fund Code Funds Funds Funds 3rd 4 to Type Date E. Beginning MR or Road - Ending MR or Road 1 CL 1. - .6 Code F. Describe Work to Be Done r-- 4% 0 r- a— 2� Phase (MM/YY) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 14 1 North 1st Street Revitalization 3 S 0,42 P CN 1/1/20.18 SIP(c)) 2,713 424 3,142 3,1421 CE No North .1st Street 06 1 from: 'N' Street to: SR 12 0 Improve North Ist Street by rehabilitating the pavement C and lane markings, removing on -street parking, W enhancing street and pedestrian lighting, constructing S median islands and installing various pedestrian and decorative elements. Totals 2,713 424 3,142 13,1.42 14 2 North Ist Street Revitalization, Phase 2 06 S 0.50 P CN 1/1/2018 FASTLAN E 4,250�718 750 0 5,000 5,000� CE Yes N. 1st Street 12 � from: 'H' Street to: 'N'Street G 12/31/2017 Improve North .1st Street by rehabilitating the pavement C and lane markings, removing on -street parking, W enhancing street and pedestrian lighting, constructing S median islands and installing various pedestrian and 0 decorative elements. Totals 4,250 5,000 5,000 0 14 3 North 1st Street Revitalization, Phase 2 06 S 0.48 P CN 1/1/2018 FASTLAN E 4,250 TIB 750 0 5,000 5,000 CE Yes N. 1st Street 1.2 � from: 'H' Street to: 'N'Street G 12/31/2018 Improve North Ist Street by rehabilitating the pavement C and lane markings, removing on street parking, W enhancing street and pedestrian lighting, constructing S median islands and installing various pedestrian and 0 decorative elements. Totals 4,250 5,000 5,000 0 17 4 Powerhouse Road Sidewalk 05 S 0.6 0 CIN 1/1/20181 TAP 2451 2451 2451 CE No Powerhouse Road 12 C 1 1 1 1 1 1 from: Cowiche Canyon Rd to: Mobile Home Park T Widen westbound lane to provide a 14 -foot wide shared bike lane and construct curb, gutter and sidewalk on the north side of the road. Totals 245 245 245 Agency: Yakima Co. No.: 39- Co. Name: Yakima Co. City No.: 1485 MPO/RTPO: YVCOG MMMMM312 = Hearing Date: 6/6/17 & 6/20/17 Adoption Date: Amend Date: Resolution No.: 6/20/2-017 Project Costs in Thousands of Dollars Federally Funded Project Identification Fund Source Information Expenditure Schedule Projects Only A. PIN/Federal Aid No, B. Bridge No. Federal Funding (Local Agency) R/VV C. Project Title ap Ma 0 Federal State State Local Total Envir, Required .2 D. Street/Road Name or Number t Start Federal Fund o E. Beginning MR or Road - Ending MR or Road 15' 7 Code Cost by Fund Code Funds Fu rids Funds2nd grid 4th Type Date F. Describe Work to Be Done Phase (MM/YY) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 19 5 Garfield Elementary Safety Improvements 12 S N/A P CN 5/1/20181 SRTS 141 141 141 CE Yes Various Streets T 1 from: to: 0 1/1%2017 This Project will make various pedestrian safety improvements in the vicinity of Garfield Elementary School, such as, constructing sidewalk, improving roadway crossings, installing flashers. Totals 141 141 141 14 6 Yakima Valley TransPortation Company Preservation 03 S OM 0 CN 1/1/2018� STP(E) 12� 11� 51� CE No Yakima Avenue from: Yakima Avenue to: 6th Avenue This project will remove and replace a portion of the existing trolley rail in the vicinity ot the intersection of 6th Avenue and Yakima Avenue. Totals 52 52 52 17 7 Spring Creek Road Reconstruction 03 S 0S5 S SIED 1,100� 82.0� 1,920� 1,920� SEPA Yes Spring Creek Road W from: Washington Ave. to: 36t,h Avenue 3/1/2017 Widen roadway to three lanes, install curb, gutter, sidewalk and street lights. 1,100 820 1,920 1,9---0 17 8 S. 36th Avenue Reconstruction 03 0.40 S SIED 520� 385� 905� 905� SEPA Yes 36th Avenue W from: Spring Creek Rd. to: Sorenson Rd. 3/1/2017 Widen roadway to three lanes, install curb, gutter, sidewalk and street lights. 520 385 905 905 Agency: Yakima Co. No.: 39- Co. Name: Yakima Co. City No.: 1485 MPO/RTPO: YVCOG It to # f, I Hearing Date: 6/6/178,6/20/17 Adoption Date: 6/20/2017 Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded Project Identification Fund Source Information Expenditure Schedule projects Only A. PIN/Federal Aid No. B. Bridge No, c v s Federal Funding (Local Agency) R/W C. Project Title E V. Phase Federal State State local Total ----T Envir. Required D. Street/Road Name or Number Start Federal Fund L Beginning ME or Road - Ending Me or Road Cost by Fund Code Code Funds Funds Funds 1st 2nd 3rd 4th Type Date LL F. Describe Work to Be Done Phase (MM/YY) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 17 9 Sorenson Road Reconstruction 03 S 0.14 S CN 1/1/2018 SIED 180 140 320 320 Yes Sorenson Read W from: 36th Avenue to: 38th Avenue 3/1/2017 Widen roadway, install curb, gutter, sidewalk and street lights. Totals 180 140 320 320 16 10 Bravo Company Boulevard 01 S 0.65 P RW 1/1/20181 1. T 8 2001 1,0001 1,0001 CE Yes North 10th Street 06 T CN 1 1/1/2-018 1 1 LIFT 1 4�408001 1, 120 5,6001 1 5,6001 1 from: 'H' Street to: Lincoln Ave. W 1/1/2018 Construct new roadway including water, sewer, curb, S gutter, sidewalk, street lighting and storm drainage 0 system. I Totals 5,280 1,320 6,600 1,000 5,600 16 11 E 'H' Street Extension, Ph. 1 01 P I �10 P RW J/1/2018:: -T� 500� 500� CE Yes E,'H'Street 08 T CN I/l/2019:: TIB 1,500 1100 4,500� 600 4,600 � from: I st Street to: 10th Street W 12/1/2018 Construct new roadway including water, sewer, curb, gutter, sidewalk, street lighting and storm drainage 0 system. Totals 3,600 5,100 500 4,600 00 12 North side Alley Paver 07 S 15 P CN 1/1/2018� CMAQ 353� 57� 41.0� 410� CE No Alleys between Folsom Ave. and Fruitvale Blvd. T � from: 16th Avenue to: 6th Avenue C Pave the east/west gravel alleys between Folsom 0 Avenue and Fruitvale Boulevard From 16th Avenue to 6th Avenue Totals 353 57 410 410 Agency: Yakima Co. No.: L9 - City No.: JARS. Co. Name: Yakima Co. MPO/RTPO: YVCOG From 2018 to 2023 Hearing Date: 6/6/17 & 6/20/1.7 Adoption Date: 6/20/2017 Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded Project Identification Fund Source Information Expenditure Schedule Projects Only A. PIN/Federal Aid Na. B. Bridge No. X a Federal Funding (Local Agency) R/W 6 C. Project Title E ii Phase Federal State State l.ocal Total 4th Envir. Required D. Street/Road Name or Number d Start Federal Fund E. Beginning MR or Road - Ending Me or Road T CL 1. 75 - Code Cost by Fund Code Funds Fu rids Funds 3rd Thru Type Date F. Describe Work to Be Done to Phase 6th (MM/YY) 1 2 3 4 5 6 7 8 9 10 11 12. 13 1.4 15 16 17 18 19 20 21 16 13 E 'H'Street Extension, Ph. 2 01 P 035 P RW 1/1/20191 STP(U) 432 68 500 500 CE Yes E.'H'Street 08 T CN 1/1/2021 STP(U) 2,162 3381 2,500 2,500 ,rom: 10th Street to: 1-82 w 1/1/2018 Construct new roadway including water, sewer, curt), S gutter, sidewalk, street lighting and storm drainage system. Totals 2,594 406 3,000 500 2,500 00 14 Cowiche Canyon Trail 28 P 2.00 RW 7/1/20191 CVvA 10111 1011 1051 Cowiche Canyon CN 1/1/20201 1 1 CVvA 1 1,695 1,695 1 1 1,695 from: Powerhouse Road to: Trailhead 1/1/2020 Construct a 10 -foot wide pathway, including two bridges over Cowiche Creek. Totals 1,800 105 1,695 Al. 34th Ave.lFruitvafe Blvd. & N. 34th Ave./River 14 15 Rood Roundabouts 03 S N/A P PE 6/1/2017 HS�P 1,1,7 13 130 130 CE Yes 34th Avenue 12 T RW 7/1/2017 HSIP 9 1 10 10 JTrom: Frultvale Blvd, to: River Road 0 CN 7/1/2018 HSIP 788 88 876 876 1/1/201.8 Improve the intersections of N. 34th Avenue & S Fruitvale Boulevard and N. 34th Avenue & River Read W by installing roundabouts I I I I lTotals 914 102 1,016 0 0 19 16 Complete Streets Projects 32 S N/A P PE 6/1/20171 1 T�B 35� 35 3' Yes Various Streets T RW 7/1/2017 TIB 100 100 � 1 00 � from: N/A to: N/A C CN 1/1/20181 1 TIB 365 365 365 1/1/2018 Construct ,id—alk - the south nd, If !ovan Avenue from MCG.me. Part, to Coinpirall Lane, on It— M. between Sri' M. and Nadle" Ave., south side of P,a,,h A,,, f,,,, 20th to 16va, south 1,1dy of Viola from n)v, Ave. to 4th Ave. and on Powerhouse road from Robert— Elementary to Englewood. 500 Agency: Yakima Co. No.: 39- Co. Name: Yakima Co. City No.: 1485 MPO/RTPO: YVCOG MMMMM312 = Hearing Date: 6/6/17 & 6/20/17 Adoption Date: Amend Date: Resolution No.: 6/20/2-017 Project Costs in Thousands of Dollars Federally Funded Project Identification Fund Source Information Expenditure Schedule Projects Only A. PIN/Federal Aid No, B. Bridge No. Federal Funding (Local Agency) R/VV C. Project Title EPhase C 0 Federal State State Local Total Envir, Required .2 D. Street/Road Name or Number �11 t Start Federal Fund o E. Beginning MR or Road - Ending MR or Road 15, 7 Code Cost by Fund Code Funds Fu rids Funds rid 3rd 4th Type Date F. Describe Work to Be Done Phase (MM/YY) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 14 17 E. Nab Hill Blvd. & Fair Ave. IIS improvements 03 P N/A P RW 1/1/2018 STP(U) 187 29� 216 216 CE Yes Non Hill Boulevard 04 T CN 6/1/2019 Sl F(u) 1,457 � 227 1, 684 1,684 from: E. Nab Hill Blvd. to: Fair Ave.. 31 W 1/1/2019 C Widen Nod Hill Boulevard through the intersection, 0 construct left -turn lane, Curb, gutter, sidewalk, street lighting and drainage. Upgrade signal by installing mast arm structures. Totals 1,644 256 1,900 216 1,684 17 18 S. 90th Avenue Bridge 09 S OM P PE 1/1/2017� DOE 25� O� 25� 25 CE No S. 80th Avenue T CN 1/1/2018 DOE 75 0 75 75� from: Wide Hollow Rd. to., Plath Ave. 0 Replace existing two-lane bridge over Wide Hollow Creek with three -lane bridge, The City's involvement is only to pass through of an Ecology grant in conjunction with the County's flood plain management project. Totals 100 75 17 19 Wide Hollow Road Bridge 09 S 0.05 P PE DOE 25 25� 21 CE No Wide Hollow Road T CN �1/1/2017� 1/1/2018 DOE 75 75 75� from: 89th Avenue to: 88th Avenue 0 Replace existing two-lane bridge over Wide Hollow Creek with three -lane bridge, The City's involvement is only to pass through of an Ecology grant in conjunction with the County's flood plain management project. Totals 100 100 25 75 19 20 West River Road Improvements 03 P 0.36 P PE 1/1/2018 S�ED 55� 55� 110� 110� CE Yes River Road 04 T RW 6/1/2018 � S ED 00 00 '_00 200� from: 40th Avenue to: 34th Avenue G CN 1/1/2019 SIED 550 550 1,100 1,10J 1/1/2019 S C Reconstruct and widen roadway to three lanes, install 0 curb, gutter, sidewalk, street lights and drainage. 1 705 705 1,410 110 200 1,100 I I I I I 1 Agency: Yakima Co. No.: 39 City No.: J.485 Co. Name: Yakima Co. MPC/RTPC: YVCCG Jill From 2018 to 2023 Hearing Date: --- 6/6/117 & 6/20/17 Adoption Date: 6/120/12017 ----------- Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded Project Identification Expenditure Schedule Projects Only Fund Source Information 0 E A. PIN/Federal Aid No, B. Bridge No, Federal Funding (Local Agency) R/W C. Project Title E V. 0, Phase Federal State Statat Local Total Envir, Required D. Street/Road Name or Number Start Federal Fund 8 E. Beginning MR or Road - Ending MR or Road 0 f Code d l Cost by Fund Co Fund Funds Funds 1st 2nd 3rd 4th Type Date F. Describe Work to Be Done .9 1-- 10 Phase 1 1 2 1 3 4 5 6 7 1 8 9 10 11 12 13 1.4 15 1 '16 17 18 19 20 1 21 14 21 16th Ave. & Deton Dr. Intersection Improvements 5 P CAD P PC 1/1/2019 STP(U) 260 70 3l 300 CE Yes 16th Avenue 7 T RW 1/1/2020 STP(U) 3,460 5401 4,000 3,460 from: 16th Ave. to: Tinton Dr. G CN 4/7/2021 STP(U)1,300 200 1,500 1,500 4/1/2021 0 Reconstruct and widen 16th Avenue and Tinton Drive C S by adding left -turn lal for all movements at the W intersection, Upgrade the traffic signal. Totals 5,020 780 5,800 300 3,460 1,500 14 22 19th Street Underpass 12 P 0.02 P PE BRAC240� 60 300� 300 CE No Yakima Avenue T �1/1/2019� CN 1/1/2020 BRAC 2,288 572� 2,860 860 from: Yakima Ave. to., 18th Street 0 S W Replace t�he bridge on E. Yakima Avenue that', crosses over 18th Street. Totals 2,528 632 3,160 300 2,860 17 23 64th Ave. & Ahtonum Intersection improvements 12 S N/A P PC 1/1/2l CMAQ 56� 9� 65� 65� CE Yes 64th Avenue T RW � 1/1/---019 CMAQ 43 7 50 50 ,from: 64th Ave. to: Ahtanurn Rd. C CN 1/1/2020 CMAQ 433 67 500 500 Sol 1/1/2020 0 Improve the 64th Avenue and Amanum Road intersection by constructing a westbound right -turn lane on Ahcanum and installing a traffic signal. lTotals 532 83 615 65 550 I I I I 14 24 South 15th Avenue Sidewalks 12 P 0.88 P PE 1/1/2018 PBp 54� 6 60 60 CE Yes 1.6th Avenue TRW 6 /1/2018 PBP 234 26� 260� 260 from: Washington Ave. to: Nob Hill Blvd, C CN 6/1/-_-01q PBP 369 41 410 0 Install 7 -foot sidewalk on the west side of 16th Avenue. Totals 657 73 730 320 410 Agency: Yakima Co. No.: 39 Co. Name: Yakima Co. City No.: 1,485 MPO/RTPO: YVCOG MMMM2312 = zzmsfit : k� Hearing Date: 6/6/17&6/20/17 Adoption Date: Amend Date: Resolution No.: 6/20/2017 Project Costs in Thousands of Dollars Federally Funded 'a Project Identification Fund Source Information Expenditure Schedule Projects Only ci A. PIN/Federal Aid No, B. Bridge No. I �11 m Federal Funding (Local Agency) R/W '7. C. Project Title E V. 0- Phase Federal State State local Total Envir. Required D, Street/Road Name or Number Start Federal Fund Z5 E. Beginning MR or Road - Ending MR or Road a 15 = aCode Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date ii F. Describe Work to Be Done .9 6; o n Q- Phase (MM/YY) 1 2 1 3 4 5 --tw 6 7 8 9 10 11 12 7.3 14 7.5 7.6 17 18 19 20 21 19 25 McClure Elementary School Safety Improvements 12 P N/A P PE I/7/2018 SRTS 46 30 30 CE No Various locations T CN 1/1/2019 SRTS 380 240 240 from: to., C 0 This project will make various pedestrian safety improvements in the vicinity of McClure Elementary School, such as, constructing sidewalk, ADA ramps and improving crosswalks. Totals 426 270 30 240 19 26 McKinley Elementary School Safety Improvements 12 P N/A P PE SRTS 50 SO 50 C. No Various locations T �1/1/2018� CN 1/1/2019 SRTS 4 30 430 430 from: to: C 0 This project will make various padestrian safety improvements in the vicinity of McKinley Elementary School, such as, replacing delapitated sidewalk, constructing ADA ramps, and installing a HAWK pedestrian crossing system. Totals 480 0 480 50 430 19 27 6th Avenue Roadway Improvements 03 P 7...51. 0 PE OTHER 1 2001 200 4001 400 CE No 6th Avenue 07 P 11/1/20201 CN 1/1/2021 1 1 OTHER 1 2,0001 2,0001 4,000 1 1 4,000 from: Walnut Street to: River Road T Reconstruct the existing trolley rail and impacted roadway, grind and overlay the remaining width of 6th Avenue, Totals 0 2,200 4,400 0 400 4,000 12 28 SR 12 & 16th Avenue Interchonge 03 P N/A 0 PE 1/1/2019 STP( U) 861 14 1001 1001 CE No Westbound ramps of SR 12 06 CN 1/1/2020 1 STP(U) 1 779 1 1 121 900 9001 1 from: 16th Avneue to: SR 12 Construct a roundabout where the westbound ramps intersect with N. 16th Avenue. Totals 865 135 1,000 100 900 Agency: Yakima Co. No.: 39 Co. Name: Yakima Co. City No.: 1,485 MPO/RTPO: YVCOG MMMMM312 = zzmsfit : k� Hearing Date: 6/6/17&6/20/17 Adoption Date: Amend Date: Resolution No.: 6/20/2017 Project Costs in Thousands of Dollars Federally Funded 'a Project Identification Fund Source Information Expenditure Schedule Projects Only ci A. PIN/Federal Aid No, B. Bridge No. I �11 m Federal Funding (Local Agency) R/W '7. C. Project Title E V. 0- Phase Federal State State local Total Envir. Required D, Street/Road Name or Number Start Federal Fund C Z5 E. Beginning MR or Road - Ending MR or Road a a 15 = Zi, Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date ii F. Describe Work to Be Done 6; tw o n Q_ Phase ((r9M/YY) 1 2 3 4 5 6 7 8 9 10 11 12 7.3 14 7.5 7.6 17 18 19 20 21 14 29 S. 1st St. & E. Washington Ave. IIS Improvements 03 P N/A P PC I/7/2019 STP(U) 260 40 300 300 CC Yes South 1st Street 06 W RW 1/1/2020 STP(U) 260 401 3001 300 from: S. Ist Street to., E. Washington Ave. S CN 1/1/2021 STP(U) 1,211 189 1, 400 1,400 1/1/2020 Realign intersection, widen E. Washington Avenue to T accommodate an additional lane, replace curb, gutter 0 and sidewalk, and install a new traffic signalization systern. Totals 1,731 269 2,000 300 300 1,400 14 30 Washington Ave. & Longfiber Rd. Intersection 03 P N/A C PE 1/1/201J STP(U) 1 1001 14� 114� 114� CE Yes Washington Avenue 05 T RW � I/J/2020 STP(U) 1 1001 1.4 114 114 from: Washington Ave. to: Longfiber Rd. 06 W CN 1/1/2021 STP(U) 1 6881 107 795 795 I/1/2020 S Improve the Washington Avenue and Longfiber Road 0 intersection by constructing an eastboung left -turn lane on Washington and a northbound left -turn lane on Longfiber, install or replace curb, gutter, sidewalk, street lighting, storrn drainage and safety flashing signal Totals 888 135 1,023 114 114 795 14 31 E Nab Hill Boulevard Reconstruction 03 P 0,85 C PC STP(U) 1 545 111� 630 630� CC Yes E. Non Hill Boulevard 04 T �1/1/2019� RW 1/1/2020 STP(U) 1 1,0901 170 1, 60� 1,260 from: S. 6th Street to: S. 7.8th Street 06 W CN 1/1,12021 STP(U) 1 6,5321 1,020 7,552 7,552 1/2020 S Reconstruct and widen roadway to 5 lanes with 0 intersection improvements, curb, gutter, sidewalk, P street lighting and drainage system G lTotals 8,167 1,275 9,442 630 1,260 7,552 I I I I 14 32 N. 40th Ave. & Summitview Ave. Intersection 12 P N/A P PE 1/1/2019 STP(U) 126� 17� 141� 143�� CE Yes N. 40th Avenue T RW I/7/2020 STP(U) 130 20 150 150 from: N. 40th Ave. to: Summitview Dr. W CN 1/1/2021 STP(U) 692 108 800 800 1/1/2020 Improve the intersection by constructing larger 5 corner radii, lengthening the turn lanes, and 0 upgrading the tratfic signal system. Totals 948 145 1,093 143 150 800 Agency: Yakima Co. No.: 39 Co. Name: Yakima Co. City No.: 1485 MPO/RTPO: YVCOG MMMM2312 = Hearing Date: 6/6/17 & 6/20/17 Adoption Date: Amend Date: Resolution No.: 6/20/2-017 Project Costs in Thousands of Dollars Federally Funded Project Identification Fund Source Information Expenditure Schedule Projects Only A. PIN/Federal Aid No, B. Bridge No. cFederal Funding (Local Agency) R/VV C. Project Title E t6 C 0 C, Phase Federal State State Local Total 4th Envir, Required I D. Street/Road Name or Number Start Federal Fund U A� Z5 E. Beginning MR or Road -Ending Ending MR or Road 75 - & .6 Code Cost by Fund Code Funds Funds Funds 3rd Thru Type Date 5 1- L F. Describe Work to Be Done 0 Phase 6th (MM/YY) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 14 33 N. 16th Avenue & Fruitvale Blvd. 1/5 12 p N/A P PE 1/1/2019 STP(U) 126 1.8 144 144 CE Yes N, 16th Avenue T RW 1/1/2020 STP(U) 173 171 200 200 from: N. 16th Ave. to: Fruitvale Blvd. 0 CN 1/1/2021 STP(U) 400 62 462 462 1/1/2020 Improve the intersection by constructing larger curb S radii, installing ADA ramps, and upgrading the traffic W signal system. Totals 699 107 806 144 200 462 16 34 E Mead Avenue Reconstruction 03 P 0.76 P PE STP(S) 1 122 TPP 23 7 152� 152 CE No E, Mead Avenue 06 T �1/1/2020� CN 1/1/2021 STP(S) 1,730 TPP 206 71 2,006 2,006 from: Ruclion Rd. to: Fair Ave. S 1 Partner with Union Gal) to reconstruct E. Mead C Avenue, install curb, gutter., sidewalk and storm G drainage system. 0 Totals 1,852 77 2,158 152 2,006 17 35 S. 49th Avenue Reconstruction 03 P 1.00 P PE 1/1/2019 STP(U) 1 2231 35� 258� CE Yes South 48th Avenue 05 T RW 7/1/20 20 STP(U) 1 5191 83. 600 600� from: SummitviewAve. to: Nob Hill Blvd. W CN 1/1/2021 STP(U) 1 1,4851 232 1, 717 1,717 1/1/2020 S Reconstruct and widen 48th Avenue, install curb, 0 gutter, sidewalk, street lighting and drainage system. Totals 2,227 348 2,575 258 600 1,717 17 36 Powerhouse Rd. & Englewood Ave.IIS 12 P N/A P PE STP(S) 1 431 7� 50� 50� CE Yes Powerhouse Rd. T �1/1/2019� RW 1/1/2020 STP(S) 871 13 100 100� from: Powerhouse Rd. to: Englewood Ave. C CN 1/1/2021 STP(S) 1 5001 78 578 578 1/1/2021 Realign intersection, install curb, gutter, sidewalk and S safety flashing signal. Possibly construct a 0 roundabout. W Totals 630 98 728 100 578 Agency: Yakima Co. No.: L9 - City No.: JARS. Co. Name: Yakima Co. MP0/RTPCh YVCOG From 2018 to 2023 Hearing Date: 6/6/17 & 6/20/1.7 Adoption Date: 6/20/2017 Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded Project Identification Fund Source Information Expenditure Schedule Projects Only A. PIN/Federal Aid No. B. Bridge No. X a Federal Funding (Local Agency) R/W 6 C. Project Title E ii Phase Federal State State Local Total 4th Envir. Required D. Street/Road Name or Number d Start Federal Fund E. Beginning MR or Road - Ending Me or Road T CL 1. 75 - Code Cost by Fund Code Funds Fu Funds Funds 3rd Thru Type Date F. Describe Work to Be Done to Phase 6th (MM/YY) 1 2 3 4 5 6 7 8 9 10 11 12. 13 1.4 15 16 17 18 19 20 21 14 37 W. Lincoln Ave. & MLK Blvd. Realignment 01 P 030 C PE 1/1/201J STP(E) 424 67 491 491 CE Yes W. Lincoln Avenue 12 T RW 1/1/2020 STP(E) 1,047 1631 1,210 1,210 from: N. 5th Ave. to., Custer St. W CN 1/1/2021 STP(E) J.'801 283. 2 ,082 1 2 , 082 1/1/2020 5 0 Realign W. Lincoln Avenue, install curb, gutter, P sidewalks, street lighting, drainage. G Totals 3,272 511 3,783 491 1,210 2,082 I I I I 16 38 Tieton Dr. & S. 5th Ave. J/ -S Improvements 12 P N/A P PE STP(U) 6 80� CE Yes Tieton Drive W �1/1/2019� RW 1/1/20 20 STP(U) 4 10 1 16 1 1 20 120 from: Tieton Dr. to: S. 5th Ave. S CN 1/1/2021 STP(U) 865 135 000 1,000 1/1/2021 Remove existing traffic signal and construct a T roundabout, remove and replace curb, gutter, 0 sidewalk, street lighting and drainage Totals 1,038 162 1,200 80 120 1,000 17 39 Yakima Downtown Future Initiatives, Phase 5 06 P N/A P PE 1/1/20 121 1 5001 500� 500� CE No 12 T CN 4/1/20 0 �OTHER OTHER 5,500 5,500 5'500� from: 1st Street to: 9th Street C 1 1 Install historic lighting, sidewalk modifications and S other improvements. Exact improvement area(s) to be determined Totals 6,000 6,000 500 5,500 14 40 E Nod Hill Blvd. & S. 18th Street I/S improvements 01 P 0.10 C PE 1/1/2019 STP(U) 1 501 CE Yes E. Non Hill Boulevard 04 T RW 1/1/2020 STP(U) 1 .50 1 8 58 58 from: E. Nab Hill Blvd. to: S. 18th Street W CN 1/1/202-1 STP(U) 1 3461 54J 4"'� 00 400 111/2021 Widen south leg for double left turn frorn west�bound S Non Hill, install curb, gutter, sidewalk, upgrade traffic signal systema Totals 446 70 516 58 58 400 Agency: Yakima Co. No.: 39 Co. Name: Yakima Co. City No.: 1,485 MPO/RTPO: YVCOG 0 - is - a , , . zzmsfi�� Hearing Date: 6/6/178,6/20/17 Adoption Date: 6/20/2017 Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded Project Identification Fund Source Information Expenditure Schedule Projects Only Ci J?A. PIN/Federal Aid No. B. Bridge No. Federal Funding (Local Agency) R /W C. Project Title E t Phase Federal 1 State State local Total 4th Envir. Required —6 D. Street/Road Name or Number 9 7 -W Start Federal Fund t L Beginning ME or Road - Ending Me or Road 'n .6 Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 17 Thru Type Date LL F. Describe Work to Be Done 15 o M CL Phase 6th (MM/YY) 1 2 3 4 5 6 7 8 9 10 11 12 7.3 14 7.5 7.6 17 18 19 20 21 14 41 S. 48th Ave. & Summitview Ave. Signalization 12 P N/A P PC 1/7./2020 STP(S) 25 4 29 29 CE Yes Summitview Avenue T RW 6/1/2020 STP(S) 25 4 291 29 from: Summitview Ave. to: S. 48th Ave. CN 1/1/20211 STP(S) 554 81 635 635 1/1/2021 Install traffic signal at the intersection of Summitview Averme and 48t,h Avenue. Totals 604 89 693 58 635 14 42 S. 72nd Ave. & W. Washington Ave. IIS 12 P N/A P PE STP(C) 1 911 14� 105� 105� CE Yes S. 72nd Avenue 06 T �1/1/2019� RW 1/1/2020 STP(C) 1 911 14 105 105 from: s. 72nd Ave. to: W. Washington Ave. 0 CN 1/1/2021 STP(C) 1 5441 86 630 630 1,11/2021 Improve intersection by installing a tratfic signal 5 system or roundabout. W Totals 726 114 840 105 105 630 14 43 N. 40th Ave. & Englewood Ave. Intersection 12 P N/A P PE 1/1/2020 STP(U) 43� 7� 50� 50� CC No N. 40th Avenue T CN 6/1/2020 0 STP(U) 260 40 3 00 300 from: N. 40th Ave. to: Englewood Replace traffic: signal poles and upgrade controller. Totals 303 47 350 350 14 44 Nab Hill Boulevard Sidewalk improvements 12 P 2.50 P PC STP(S) 1 1 551 8� 63� 63� CE Yes Not) Hill Boulevard T �1/1/2020� RW 7/1/2021 STP(S) 1 1071 1.9 1 26 3.26 from: S. 16th Ave. to: S. 5th Street S CN 1/1/2022 STP(S) 1 3271 51 378 378 1/1/2022 Construct sidewalk in locations where it doesn't exist W on the south side of Nob Hill iTotals 489 78 567 504 Agency: Yakima Co. No.: 39 Co. Name: Yakima Co. City No.: 1485 MPO/RTPO: YVCOG MMMM2312 = Hearing Date: 6/6/17 & 6/20/17 Adoption Date: Amend Date: Resolution No.: 6/20/2-017 Project Costs in Thousands of Dollars Federally Funded Project Identification Fund Source Information Expenditure Schedule Projects Only A. PIN/Federal Aid No, B. Bridge No. cFederal Funding (Local Agency) R/VV C. Project Title E t6 C 0 C, Phase Federal State State Local Total 4th Envir, Required I D. Street/Road Name or Number Start Federal Fund U A� Z5 E. Beginning MR or Road -Ending Ending MR or Road 75 - & .6 Code Cost by Fund Code Funds Funds Funds 3rd Thru Type Date 5 1- L F. Describe Work to Be Done 0 Phase 6th (MM/YY) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 14 45 E. Yakima Ave. &J'air Ave..Signalization 12 p N/A P PE 1/1/2020 STP(U) 86 1.4 100 100 CE No Yakima Avenue T CN 6/7/2021 STP(U) 519 83.1 600 600 from: E. Yakima Ave. to: Fair Ave. W Install traffic signal at the intersection of Yakima S Avenue and Fair Avenue. 0 Totals 605 95 700 100 600 16 46 S. 3rd Avenue & W. Washington Ave. Signal 12 p N/A P PE 4/1/20191 20� 20 20 CE No S. 3rd Avenue T CN 9/1/2019 I 210 �' 210 from: S. 3rd Ave. to: W. Washington Ave, Upgrade the traffic signalization system 230 230 230 1 1 Totals 230 230 230 19 47 75th Avenue Improvements 01 P 0.50 P PE 11/1/2020 STP(U) 87� 13� 100� 100 CE Yes 75th Avenue 08 W RW 1/1/2021 STP(U) 173 27 200 200 from: Mead Ave. to: Nab Hill Blvd. S CN 1 1/1/2022� STP(U) 1,038 162 1,200 1,200 1/1/2022 T Construct a new two-lane roadway and widen 0 portions of existing roadway, install curb,, gutter, sidewalk, street lighting arid storm drainage system. Totals 1,298 202 1,500 100 1,400 17 48 S. 55th Avenue Improvements 03 P 036 P PE STP(U) "76 14� 100 100 CE Yes 66th Avenue 04 T �1/1/2019� RW 1/1/2020 STP(U) '13� 27 200 200� from: Summitview Ave. to: Scenic Dr. W CN 1/1/2-02- 1 STP(U) 1,096 164 1� 1,260 1/1/2021 Reconstruct and widen roadway to three lanes, install 5 curb, gutter, sidewalk, storrn drainage system and 0 utililies. Totals 1,355 205 1,560 100 200 1,260 Agency: Yakima Co. No.: 39 Co. Name: Yakima Co. City No.: 1,485 MPO/RTPO: YVCOG MMMMM312 = zzmsfit : k� Hearing Date: 6/6/17&6/20/17 Adoption Date: Amend Date: Resolution No.: 6/20/2017 Project Costs in Thousands of Dollars Federally Funded 'a Project Identification Fund Source Information Expenditure Schedule Projects Only ci A. PIN/Federal Aid No, B. Bridge No. I �11 m Federal Funding (Local Agency) R/W '7. C. Project Title E V. 0- Phase Federal State State local Total 4th Envir. Required D, Street/Road Name or Number Start Federal Fund Z5 E. Beginning MR or Road - Ending MR or Road a a = Zi, Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd Thru Type Date ii F. Describe Work to Be Done 6; o n Q- Phase 6th (MM/YY) 1 2 3 4 5 --t15w 6 7 8 9 10 11 12 7.3 14 7.5 7.6 17 18 19 20 21 17 49 Rudkin Road Reconstruction 03 P 036 P PC I/1/20191 STP(C) 109 27 136 136 CC No Rudkin Road 06 T CN 1/9/2020 STP(C) 945 TPP 945 1061 1,9961 I996 from: E Viola Ave, to: Rainier Pl. W S Reconstruct roadway, install curb, gutter, sidewalk and storm drainage. Partner with Union Gap to install additional sewer force main. Totals 1,054 945 133 2,132 136 1,996 17 50 Engifewood Avenue Improvements 05 P 1.00 P PE 1/1/2021: STP(C) 272 43 15 315 CE Yes Englewood Avenue 06 T RW 7/1/2022 STP(C) 349 � 55 404 404 from: N. 40th Ave. to., N. 56th Ave. W CN 1/1/2023:: STP(C) 2,329 363� 2,369 2 2,692 1/1/2023 5 Widen roadway to three lanes, install curb, gutter, 0 sidewalk, street lighting and storm drainage system. C Totals 2,950 461. 3,411 3,411 17 51 Englewood Avenue Improvements 05 P 0.50 P PE I/1/2021:: STP(U) 136� 21� 157� 157 CE Yes Englewood Avenue 06 T RWSTP(U) 173 27 200 200 from: N. 16th Ave. to: N. 24th Ave. W CN ��/1/2022: /1/2023: STP(U) 164 182 1,346 1,346 1/1/2023 Widen roadway to three lanes, install curb, gutter, S sidewalk, street lighting and storm drainage system, water and sewer lines. Totals 1,473 230 1,703 1,703 17 52 S. 90th Avenue Improvements 04 P 1,30 P PE 11/1/2021: T�13 3 11 20� 151� 151 CE Yes S. 80th Avenue T RW J/1/20221 TIB 3 82 59 441 441 from: Tieton Drive to: Zier Road 0 CN I/l/2023:: TIP 1'667� 260 1, 927 1,927 1/1/2023 5 Widen roadway to three lanes, install curb, gutter, W sidewalk, street lighting and storm drainage systern. C Totals 2,180 339 2,519 2,519 Agency: Yakima Co. No.: 39 Co. Name: Yakima Co. City No.: 1,485 MPO/RTPO: YVCOG MMMMM312 = zzmsfit : k� Hearing Date: 6/6/17&6/20/17 Adoption Date: Amend Date: Resolution No.: 6/20/2017 Project Costs in Thousands of Dollars Expenditure Schedule Federally Funded 'a ci Project Identification I �11 Fund Source Information (Local Agency) Projects Only R/W A. PIN/Federal Aid No, B. Bridge No. m Federal Funding '7. C. Project Title E V. 0- Phase Federal State State local Total 4th Envir. Required D, Street/Road Name or Number Start Federal Fund C Z5 E. Beginning MR or Road - Ending MR or Road a a = Zi, Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd Thru Type Date ii F. Describe Work to Be Done 6; t15w o n Q_ Phase 6th (MM/YY) 1 2 3 4 5 6 7 8 9 10 11 12 1.3 14 1.5 1.6 17 18 19 20 21 17 53 Englewood Avenue Improvements 03 P I M P PE 1/1/2021 STP(U) 218 34 252 252 CE Yes Englewood Avenue 05 T RW 1/1/2022 STP(U) 327 5 11 378 from: N. 24th Ave. to: N.40th Ave. 06 W CN 1/1/2023 STP(U) 2�789 435 '3781 3224 3,224 1/1/2023 S Reconstruct and Widen roadway to three lanes, install 0 curb, gutter., sidewalk, street lighting and storm drainage systern. install sewer and water lines. Totals 3,334 520 3,854 3,854 17 54 88th Avenue Improvements 06 P 0A8 P PE 1/1/2020 STP(U) 43 7 0 50 CE Yes 88th Avenue 12 T RW 7/1/2021 � LU j STP(U) '52� 8 60 60 from: Tieton Dr. to: Summitview Ave. C CN 6/1/2021 STP(U) 285 45� 3530� 330 6/1/2021 G Construct curb, gutter, sidewalk and storm drainage systern cm the east side of 88th Avenue. Totals 380 60 440 50 390 17 55 64th Avenue Improvements 03 P I M P PE 1/1/2020 STP(U)200 32� 232� 232� CE No 64th Avenue 04 T CN I STP(U) 1,600 � 249 1' 849 1,849 from: Washington Ave. to: Nob Hill Blvd. 06 W C G Widen roadway to three lanes, install curb, gutter, 0 sidewalk, street lighting and storm drainage system. 7,800 281 2,081. 232 1,849 0 16 56 1-82 & Lincoln Avenue Interchange 01 P N/A 0 PE 1/1/201J STP(U) 1 260 1 40 0 300 CE Yes Lincoln Avenue P RW 1/1/2-02-0 STP(U) 1 1731 27 200 200 from: E,'G'Street to: 1-82 G CN 6/l/2021 STP(U) 1 1,7301 270� 2,30000 2,000 6/1/2021 Reconstruct/extend off -ramp from existing 1-82 off - ramp for Lincoln Avenue to UG'Street. 2,163 337 2,500 300 200 2,000 Agency: Yakima Co. No.: 39 Co. Name: Yakima Co. City No.: 1,485 MPO/RTPO: YVCOG MMMMM312 = zzmsfit : k� Hearing Date: 6/6/17 & 6/20/17 Adoption Date: Amend Date: Resolution No.: 6/20/2-017 Project Costs in Thousands of Dollars Federally Funded Project Identification Fund Source InformationProjects Expenditure Schedule Only 0 A. PIN/Federal Aid No, B. Bridge No. W" Federal Funding (Local Agency) R/yV C. Project Title E t6 M aPhase Federal State State Local Total 4th Envir, Required .2 z: D, Street/Road Name or Number E. Beginning MR or Road - Ending MR or Road 0 z '75 Start Federal Fund Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd Thru Type Date F. Describe Work to Be Done 6; 0 Phase 6th (MM/YY) -LE— 1 2 3 4 5 --tw 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 14 57 16th Avenue Corridor improvement 04 P 3..50 P PE 1/1/2020 STP(U) 120 7.7 137 137 16th Avenue T from: SR 12 to: Washington Ave. W C G Study to determine strategies for improving the 16th 0 Avenue corridor S 120 17 137 137 1 14 58 40th Avenue Corridor improvements 04 P 120 P PE STP(U) 120� 17� 137� 137� 40th Avenue T �1/1/2021 ,rare: SR I'-- to: Washington Ave. W C G Study to determine strategies for improving the 40th 0 Avenue corridor. S Totals 120 1.7 137 137 14 59 Nab Hill Boulevard Corridor Improvements 03 P 2.70 P PE 1/1/2020 STP(U) 120 17� 137� 137� Nob Hill Boulevard 04 T � from: 1-82 to: 16th Ave. 0 5 W Study to determine strategies for improving the Nab C Hill Boulevard corridor, G 120 17 137 137 1 1 14 60 North.lSouth Connector to West Valley 01 P 6.00 P PE STP(U) 432� 68� 100� 101 CC Yes Unknown Road 04 T �1/1/2020� from: Ahtanurn Rd. to: Summitview Ext,. 06 Va S Corridor study to determine the best location for a C north/south limited access route in West Valley. City G and County joint project. 0 432 68 500 500 Agency: Yakima Co. No.: 39- Co. Name: Yakima Co. City No.: 1485 MPO/RTPO: YVCOG It to # f, I Hearing Date: 6/6/178,6/20/17 Adoption Date: 6/20/2017 Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded Project Identification Expenditure Schedule Fund Source Information projects Only A. PIN/Federal Aid No. B. Bridge No, c v s (Local Agency) Federal Funding R/W C. Project Title E V. Phase Federal State State local Total 4th Envir. Required D. Street/Road Name or Number Start Federal Fund L Beginning ME or Road - Ending Me or Road t 2nd 1ST Cost by Fund Code Funds Funds Funds 3rd Thru Code Type Date LL F. Describe Work to Be Done Phase 6th (MM/YY) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 14 61 S. 1st StreetlMoin Street Corridor Improvements 01 P 2.00 P PE STP(U) 120 17 137 137 No S. I st Street/Main Street �1/1/2020� from: Nob Hill Blvd, to: Barker Mill Bridge S Joint project with Union Gap. Stucy to determine W strategies for improving the 1st', Street/Main Street C corridor. G 120 17 137 137