HomeMy WebLinkAbout04/18/2017 06C 1st Quarter 2017 Capital Improvement Projects ReportBUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDASTATEMENT
Item No. 6.C.
For Meeting of: April 18, 2017
ITEM TITLE: 1st Quarter 2017 Capital Improvement Projects Report
SUBMITTED BY: Brett Sheffield, P.E., Acting Manager, Engineering - 576-6797
Scott Schafer, Public Works Director
SUMMARY EXPLANATION:
Attached is the Engineering Division's 1 st Quarter Capital Improvement Projects Memorandum
and Report which includes Water/I rrigation and Wastewater Capital I mprovement Projects. Also
attached is the current project spreadsheet developed by the Sewer, Water, Irrigation, Streets,
Traffic and Engineering Divisions.
The current project listing assists in the planning of current and upcoming projects. It helps the
divisions coordinate their work so that, for example, a street is not rebuilt or seal coated prior to
planned underground work on the same street.
ITEM BUDGETED:
STRATEGIC PRIORITY:
APPROVED FORcl*�
SUBMITTAL: '"c"`City Manager
STAFF RECOMMENDATION:
Accept the report
BOARD/COMMITTEE RECOMMENDATION:
ATTACHMENTS:
Description
D Project Narratimes
i
Upload Date
4/612017
416/2017
NA
Type
Backup Material
Backup Material
O
MEMORANDUM
April 5, 2017
TO: Mayor Kathy Coffey
Members of City Council
FROM. • Brett Sheffield, PE, Acting Division Manager, Engineering Division
Robert Desgrosellier, Senior Engineer
SUBJECT. • 2017 Capital Improvement Projects: 1St Quarter
INTRODUCTION
This Quarterly Report is intended to provide an overview of the City's capital improvement
projects for the 1St Quarter of 2017, including current project status, milestones, and any new
developments that may significantly alter the schedules or costs of the projects. This narrative
discusses Water/Irrigation Division, Wastewater/Stormwater Division and Engineering Division
proj ects.
Railroad Grade Separations, Phase 4: Proiect Aesthetics
This project consists of constructing the "Bins of Light" art piece on Lincoln Avenue just east of
the Front Street Bridge, and constructing an elevated sidewalk on the south side of Lincoln
Avenue from 1St Avenue to 1St Street. Bids were opened on March 3rd for this project, with the
low bid of $669,490 being submitted by Belsaas and Smith. Although the project began
construction on July 19th, 2016, due to complications with the aluminum manufacturing (label
cutouts), the project working days were suspended in August as the contractor has to wait for
delivery of the art pieces (glass, aluminum label cutouts and framing). The sidewalk was
completed in October. Delivery of all the parts required to install the "Bins of Light" should be
received in early April, at which time the installation will begin. The "Bins" should be installed
and operational by mid-May.
♦ Projected completion: 2nd Quarter FY2017
Yakima Valley Trolley Barn & Museum Preservation
Using State Enhancement funds, the City purchased the historic YVT Trolley Repair Barn and
Substation on January 31, 2008. Funding also allowed for repairs to the west and south walls and
the crane system. That work has been completed. Some funding still remains and will be used to
remove and replace approximately 120 feet of bad track starting at the intersection of Yakima
Avenue and 6th Avenue, and continue southerly along 6th Avenue. Paperwork for environmental
clearance has to be submitted specifically for this deficient crossing.
♦ Projected completion: FY2017
1
3
Cascade Mill Redevelopment Proiect
This project includes multiple tasks to redevelop the former 225 -acre Boise Cascade Mill.
Yakima was awarded $25 million in LIFT funding (Local Infrastructure Financing Tool) from
the State of Washington to create a Revenue Development Area that will assist in the transition
from the former mill to a mixed use economic catalyst including creation of an estimated 4,500
light manufacturing, office park, commercial, retail and entertainment jobs.
The current status of the project includes:
1. The Interchange Justification Report (IJR) was approved on February 22, 2017. The
purpose of the IJR is to provide freeway access to a proposed east - west roadway that
will connect Terrace Height to north Yakima, and thereby, provide direct access from the
I-82 to the former sawmill site. Design of the preferred alignment of this east -west
roadway west of the interstate is nearing completion, after which the NEPA
documentation will be finalized. The "Connecting Washington" legislation approved last
fall provides funds for the improvements to I-82, as well as, the bridges over the interstate
and Yakima River.
2. Design of a North to South City Boulevard -type Street that will provide access to the mill
site. City of Yakima is project lead. The first phase of this project that constructed the
southernmost 500 feet of this north - south road (named Bravo Company Boulevard),
along with a roundabout that connects Bravo Company Boulevard to Fair Avenue,
Lincoln Avenue and MLK Boulevard has been completed. The construction was done by
Granite Construction Company for a cost around $2,425,000. In mid-December 2016, the
City supplemented the professional services agreement with Lochner to complete the
design of Bravo Company Boulevard from where it currently ends to its connection with
`H' Street at the intersection of 7th Street.
3. Preliminary Design and alignment of "East-West Corridor Road" - Yakima County
project lead. The existing `H' Street corridor will be improved from North 1st Street to
7th Street as part of this project. NEPA review is scheduled for the East-West Corridor
from the bridge over 1-82 and east. SEPA review is scheduled for the section that is west
of the Interstate overpass.
4. Grant funding research, permitting and options for clean-up and remediation of former
City of Yakima municipal landfill has begun. The City has entered into the Voluntary
Cleanup Program with the Department of Ecology (DOE). The City has submitted the
remedial investigation report to DOE and will soon be developing a feasibility study that
will detail the cleanup requirements. The DOE is pushing the City to enter into an
Agreed Order for the cleanup of the site, which is being reviewed by the City's Legal
Team
♦ Projected completion dates
• Fair Avenue Roundabout completed: 1st Quarter 2016.
• UR Approval: 1st Quarter 2017.
• Landfill cleanup, East-West Corridor and remainder of the North-South Boulevard
are all pending.
2
4
— 'N' Ctroot to CR_ 17 /Phnco 11
North I" Street Corridor Revitalization — `N' Street to MLK Jr. BlvtL (Phase 2)
In 2010, the City received a $25,000 planning grant through Yakima County SIED funding for
the first segment of this project; a comprehensive approach to planning for future improvements
to North First Street from "A" Street to the US -12/I-82 Interchange. The North First Street
Improvement Study was performed in 2011 to develop a design and action plan to address
potential arterial street design alternates including an analysis of resulting traffic now,
streetscape and landscape improvements, and required utility upgrades. The final study
document was adopted by City Council on October 11, 2011.
The City applied for, and received a $250,000 Surface Transportation Program (STP) federal
grant for preliminary engineering on August 23, 2012. In January of 2013, the City was awarded
$2,718,000 for the construction of Phase 1. A professional services agreement was entered into
with HDJ Design Group to develop the engineering plans and construction specifications. The
engineering plans and construction specifications have been completed. Approval of the
environmental documentation is ongoing. Originally, it was anticipated that the project would
bid in the spring of 2015. We have since been informed that the STP construction funds will not
be available until 2019. Emphasis will be placed on relocating/under-grounding of overhead
utilities, as well as safety and improving the appearance of the corridor.
Phase 2: `N' Street to MLK Jr. Blvd., construction is estimated to be $10,000,000 and was
planned to be funded by a City of Yakima bond. We interviewed consulting firms to perform the
design and Huibregtse Louman and Associates (HLA) was selected to perform the design for us.
They have started their work and should be completed towards the end of 2016. Due to the
amount of work included in Phase 2, and the amount of impacts that it will have to traffic,
businesses and private utilities, it has been determined to split Phase 2 into two phases. Phase 2A
will perform the construction from MLK Boulevard to `I' Street, and is anticipated for
construction in 2017. Phase 2B will perform the construction from `I' Street to `N' Street and is
anticipated for construction in 2018. We applied for and were successful in receiving a
$1,500,000 grant from the Transportation Improvement Board (TIB) for the Phase 2 project.
Both phases of this work are included in a 2017 FASTLANE federal grant application that was
submitted on December 18, 2016.
♦ Projected completion dates: FY2018 (and later)
Alley Pavers
This project will pave unpaved alleys located within the following limits: Fruitvale Boulevard
(north boundary), Lincoln Avenue (south boundary), 5th Avenue (east boundary) and 16th Avenue
(west boundary). This project is funded by a federal "Congestion Mitigation/Air Quality"
(CMAQ) grant.
Design funds are in the process of being obligated. Design should be completed in the spring of
2017, with construction anticipated for the summer of 2017.
♦ Projected completion date: 4th Quarter FY2017
3
Powerhouse Road Sidewalk
This project will widen the westbound lane of Powerhouse Road from 800 feet west of Peck's
Canyon Road to Cowiche Canyon Road from its' existing width to 14 feet in width so that the
lane can function as a shared bicycle/vehicle lane. The project will also construct curb, gutter
and sidewalk on the north side of the road. This project is funded with a $275,000 TAP Grant.
Design of this project has begun and construction is anticipated for the spring of 2017.
♦ Projected completion date: 3rd Quarter FY 2017
Airport Lane Realignment and 21st Avenue Extension
This project will realign Airport Lane from the National Guard Armory to 20 Avenue,
improving the access to existing airport hangars and providing development opportunities for
additional airport hangars. Funding for the project comes from the following: $307,000 SIED
grant, $307,000 SIED loan, $175,000 City general fund, $50,000 Water Capital, $50,000
Wastewater Capital.
The construction project was awarded to Scout Lake Construction in August 2016 for the low bid
amount of $793,565.38. Construction of the project began mid-October 2016, and will continue
to mid -year 2017. The Contractor is back on-site to complete the work.
♦ Projected Completion Date: 2nd Quarter 2017
Adams Elementary/Washin-ton Middle School Sidewalk Improvements
This project will make various pedestrian safety improvements in the vicinity of Adams
Elementary School and Washington Middle School, such as, constructing sidewalk, improving
roadway crossings, installing flashers and installing fencing. Funding for this project is from a
Safe Routes to School grant in the amount of $357,000. The environmental documentation has
been completed and we are beginning the right of way phase. The project is scheduled for
construction in the summer of 2017.
♦ Projected Completion Date: 3rd Quarter 2017
Garfield Elementary Safety Improvements
This project will make various pedestrian safety improvements in the vicinity of Garfield
Elementary School, such as, constructing sidewalk, improving roadway crossings and installing
flashers. Funding for this project is from a Safe Routes to School grant in the amount of
$180,000. The environmental documentation has been completed and we are beginning the right
of way phase. The project is scheduled for construction in the summer of 2017.
♦ Projected Completion Date: 3rd Quarter 2017
4
Spring Creek Road - Soccer Complex
This project will reconstruct and widen Spring Creek Road, 36th Avenue and Sorenson Road to
three -lane roadways with curb, gutter, sidewalk and street lights to improve the access to the new
SOZO Soccer Complex. The City received a $900,000 SIED grant and a $900,000 SIED loan
for this project. By inter -local agreement, the City has signed an agreement with Yakima County
Engineering to aid in the design of this project. The design is close to being finished and
acquisition of the required right of way has begun. It is anticipated that construction of this
project will begin in August 2017 with project completion scheduled for November 2017.
♦ Projected Completion Date: 4th Quarter 2017
Cowiche Canyon Trail
This project will construct a 10 -foot wide pathway, including two bridges over Cowiche Creek
from Powerhouse Road to the existing Cowiche Canyon Trailhead. The trail will be
approximately 2 miles long. Funding for the project comes from a $2 million "Connecting
Washington" grant. Design funds of $200,000 were just recently obligated, and we are in the
process of hiring an engineering firm to do the design. Consultants were interviewed to perform
the design of the trail. Perteet, Inc. was selected to perform the work. It is anticipated that they
will be under contract by the end of April. The remaining funds for the construction will not be
available until the 2019 - 2021 biennium.
♦ Projected Completion Date: 4th Quarter 2020
Yakima Valley Trolley Improvements: Herita,-e Capitol Noiect Grant
This project will provide minor restoration of the YVT facilities and trolley system and add
enhancements to the Trolley Museum and property. Funding comes from a $50,000 State
Heritage Capitol Grant that has been awarded to the city. The funds were matched against
Trolley Volunteers labor and other improvement value plus $90,000 in construction completed
by the City. The project is scheduled for construction this year.
♦ Projected Completion Date: 4th Quarter 2017
5
7
Water/Irrigation Division Capital Improvements Projects
Water Treatment Plant Intake Improvements
The project will evaluate the river and WTP intake structure for potential modifications and
improvements to maintain the existing river location and flows to into the intake. We are
currently working with Golder & Assoc. for Hydro -technical Engineering Support Services for
design, permitting, funding, construction bid and inspection support of a new intake and flood
plain stabilization structures. Dept. of Ecology has issued a Watershed grant for $250,000 for
this project. A couple of stakeholder meetings were held; comments from those meetings were
incorporated into the design and another meeting is being scheduled to review suggested
modifications to the design and to determine the next steps to move forward. A Cultural Survey
was conducted and submitted.
♦ Projected completion date: 2nd Quarter FY2017
Fruitvale Canal - Nelson Dam Improvements
This project will consolidate the river diversions for Fruitvale Canal with the existing diversions
at the Nelson Dam. We are working on fish screen/intake project options. Discussions are
continuing with the Bureau of Reclamation, Washington Department of Fish and Wildlife,
Yakima County, National Marine Fisheries Service, Yakama Nation and North Yakima
Conservation District on project design and options. A water right change in point of diversion
has been approved by Ecology. Discussions with Yakima County are on-going to see how the
project fits with their flood plain restoration projects. Stakeholders meetings are being held to
determine possible design options.
Project completion date: On-going
East Viola Avenue (I--82 Crossin-) Waterline Replacement
The project will replace an undersized, deteriorating waterline crossing under I-82 at East Viola
Avenue, between Rudkin Road and the Wastewater Treatment Plant. Replacement of the
waterline will improve flows and reliability in this part of the water system, as well as replace a
sub -standard, direct bury waterline across I-82 with a new ductile iron waterline in a steel casing
within the limits of the interstate highway. HLA Engineering and Land Survey, Inc. is
completing the design. The project will be constructed spring of 2017.
♦ Project completion date: 2nd Quarter FY2017.
6
Wastewater Division Capital Improvements Projects
Billy's Pond and floodplain Enhancement Proiect
The purpose of this project is to ensure successfully meeting the goals of the original 2013 Billy's
Pond Restoration project. This original project was intended to provide diverse and complex
floodplain habitat for aquatic and terrestrial species by increasing total area of high quality wetland
and riparian areas; and better utilization of site topography and groundwater conditions. The net
outcome of the project was intended to be an increase in open waters and wetlands, as well as
enhanced emergent and riparian areas adjacent to the Yakima River. Additionally, the project
provided floodplain restoration and connectivity with the Yakima River as well as fish passage for
salmonids and other native fish. Aquatic habitat functions and services were expanded and
improved from the previous state. The project was also intended to create an opportunity to restore
some of the river's natural physical and ecological processes to the floodway and floodplain.
Much of the original work was successful in achieving the goals of the 2013 restoration project.
The purpose of current work is addressed below:
Increase pond flow-through. The 2013 Billy's Pond restoration proj ect included removal of
culverts and a weir structure at the pond outlet channel. The existing manmade ditch that drained
the pond was backfilled with clean fill and a new outlet channel was excavated to remove the
fish passage barrier. The new excavated channel was not dug deep enough at the inlet to provide
flow-through from the pond and through the channel to the Yakima River. This channel will be
dug down an additional 8 to 12 inches below existing grade adjacent to where the channel meets
the pond.
Enhancement of wetland and riparian vegetation in southern pond aspects. The above -water
constructed habitat that was created for vegetation growth did not succeed and will be
contoured to support vegetation growth. The constructed peninsulas and hummock in the
southern portion of the pond will be excavated as funding allows. Lower elevations will
create better equipment and crew access for replanting activities and reduce depth to the
water table for planted riparian shrubs and trees. Where soil is not excavated in replanting
areas around the pond, planting techniques will be used to allow plant roots to access deep
groundwater, such as augering holes and installing tall container plants of vigorously -rooting
species. Live stakes and emergent species will be planted at the pond edge.
Stabilize floodplain with native buncatm h Approximately 42 acres of the floodplain will
be replanted with native bunchgrasses. Soils will be de -compacted where necessary prior to
seeding. Following native grass seeding, weeds will be controlled to promote grass
establishment.
Contouring -or remove soil piles. The previous project left soil piles on the floodplain,
adjacent to the pond, which is a source of weeds that will continually infest the floodplain
without treatment. The soil piles were created from material excavated from channels
leading to the pond and from new outfall channels created for the wastewater treatment plant.
These piles will be contoured to allow equipment access for soil stabilization measures of
weed control and reseeding with native bunchgrasses.
Proiect status.
Overall project is substantially complete.
Wildlands, Inc. will return in spring to do seeding maintenance & site evaluations thw 2017
The construction work to improve Billy's Pond flow-through is complete.
Success of work completed will be determined by monitoring pond depths & temperatures.
Contouring Billy's Pond is complete. All peninsulas and hummock in the southern
portion were excavated and planting benches were constructed. The constructed areas
have been planted with native riparian vegetation; beaver fencing is under construction to
protect the newly planted areas at the southern end of the pond and peninsula.
Floodplain contouring and de -compacting the ground in preparation for seeding is
complete. Contractor was scheduled to apply the native grass seed mix to approximately
42 acres in November 2016.
♦ Projected completion: 4th Quarter FY2018
Pipe Rehabilitation — General
The Wastewater Division will be identifying pipeline segments that need to be rehabilitated or
replaced. In addition, the project will address access issues by installing new manholes in streets
where otherwise access for performing maintenance is insufficient. The project timing and size
will be dependent on funding available for the project. Final scope of the project will be
determined after a cost evaluation. Budget has been approved to start a pipeline rehabilitation
program to address the old and deteriorating wastewater collection system. The program will
consist of pipe and manhole rehabilitation and replacement along with addressing access issues
throughout the city. Scoping activities are under way. Construction will be ongoing having
started in the 1st Quarter this year until the system conditions are addressed. The project will
stabilize current conditions of the pipe system and reduce infiltration of groundwater which will
save treatment costs in the future and limit the need for upgrades to the Wastewater Treatment
Plant.
Completed in 2016:
• 21 point repairs installed by city wastewater crews
• 2400 feet of sewer pipe rehabilitation completed
• 48 manhole repair/replacements
♦ Projected completion date: on-going
Collection System Plan Update & Initial Stormwater Comp Plan, Wastewater Facility Plan
With the adoption of the new stormwater regulations a comprehensive Stormwater System Plan
is needed and will be implemented along with the Wastewater Facility and Collection System
Plan Update.
Akel Engineering Group, Inc. has completed capacity models for both systems and completed a
capital projects priority projection based upon the capacity model.
Design of stormwater improvements for N. 1st Street and Randall Park projects are under way
H.,
The FCS Group completed a Wastewater and Stormwater rate structure and a wholesale
customer billing model that meets the specifications of the 3 -Party Wholesale Service
Agreement.
The last Wastewater Facility Plan was completed in February 2004. This project updates the
current facility plan by providing current information on the existing wastewater facility and
collection system infrastructure, regulatory requirements, future loadings, operation and
maintenance, future capital improvements, rate structure and revenue forecasting. The updated
facility plan will incorporate the completed Akel collection system and stormwater system
documents. Division staff is evaluating the draft 2013 Wastewater Treatment Plant Facility Plan
for potential completion.
♦ Projected completion date: FY2018
Speedway Interceptor and Beech Street Lift Station PMiect:
The existing 36 inch gravity sewer interceptor located between Beech Street and Nob Hill on the
west side of I-82 is currently experiencing excessive sedimentation due to flat and adverse pipe
slopes with slow fluid speeds and intermittent reverse flows. As part of the 2013 wastewater
Master Plan, improvements to that interceptor were identified. The improvements include a
force main installed through the existing 36 inch pipe as well as the construction of a new lift
station on Beech Street south of Kiwanis Park. Flows currently reaching the Race Street lift
station will be redirected in following phases at Beech and 15th and be redirected into the new lift
station. The Race Street lift station will then be decommissioned. The project will allow for
conveyance of existing flows at higher speeds as well as provide a mechanism for expanding
service to the Boise Cascade Mill Site region without increasing the sedimentation problem as
flows from that area develop. It will also allow for construction of improvements that will
eliminate existing bottlenecks in the sewer interceptor system west of Washington Middle
School.
Included in this project will be minor upgrades to the electrical elements of the Rudkin Road
lift station and installation of an emergency bypass connection along with modifications to
the existing junction box at the intersection of Rudkin Road and East Viola Ave.
• This portion of the project is scheduled to be completed early 2017.
RI -12 Engineering has been selected as the design consultant. The professional services contract
has been completed and designs are currently under way. Rudkin Road Lift Station
Improvements will be completed by the end of 2016 or early 2017. The Speedway Interceptor
and Beech Street Lift Station Project is projected to start construction in summer of 2017.
♦ Projected completion date: FY2018 (?)
9
Stormwater Capital Improvements Protects 11
DID #29 Reroute:
The drainage improvement district (DID) #29 pipe collapsed underneath a home at 320 N. 29th
Avenue. A construction project rerouted the drain line out to 29th Avenue and then north to an
existing DID manhole.
The project was awarded to Tri -Valley Construction, Inc. for the low bid amount of $51,927.29
in November 2016. Funding for the project was from the Stormwater Capital Fund. Construction
was substantially completed in December 2016, with a small amount of revegetation work to be
completed in spring of 2017.
♦ Projected completion date: FY2017
49th Avenue Draina,-e
This project will install curb and gutter between 48th and 50th Avenues on Englewood Avenue
and upsize existing drain lines on both Englewood Avenue and N. 49th Avenue to improve
drainage and prevent flooding during future storm events. This project will be funded through
the Stormwater Capital Fund. Design of this project has begun and construction is anticipated for
the spring of 2017.
♦ Projected completion date: 3rd Quarter FY 2017
10
PRIVATE PROJECTS (Current Listing) 12
Listing private developer projects shows the amount of private projects that are "on the books" and
pending or under construction with some (not all shown) that go back several more years. These projects
have all been approved since February 2008 and are either pending construction, under construction,
started but not completed or recently completed. The projects, most recent at top, include:
Project Name
Address
Permit Type
Status
2016
My Hotel
21 S. 18th St.
Eng -Site -Imp
in review
Borton Fruit - Ahtanum Rd.
2602 Ahtanum Rd.
Eng -Site -Imp
in review
Washington Heights Ph. 4
78th/Whatcom
Eng -Site -Imp
in review
Denny's Restaurant
3704 Fruitvale Blvd.
Eng -Site -Imp
in review
Pentecostal Church Sewer Extension
808 W. Mead Ave.
Eng -Site -Imp
apprvd for const.
Gregg Marrs Sewer Extension
1605 E. Mead Ave.
Eng -Site -Imp
apprvd for const.
Longfibre Rd. Frontage Improvements
2020 Longfibre Rd.
Eng -Site -Imp
apprvd for const.
Hogback Rainier East Lot 2
2406 W. Nob Hill Blvd.
Eng -Site -Imp
completed
Powerhouse Villas Ph. 2 & 3
3201 Powerhouse Rd.
Eng -Site -Imp
in construction
Vista Ridge Subdivision
2155 S. 72nd Ave.
Eng -Site -Imp
in review
SOZO Sports Complex Sewer
2210 S. 38th Ave
Eng -Site -Imp
completed
Rainier Court Subdivision
8909 Summitview Ave
Eng -Site -Imp
apprvd for const.
5k sf Commercial Bldg.
27 S. Front St.
Eng -Site -Imp
on hold
Hogback Rainier East Lot 1
2410 W. Nob Hill Blvd.
Eng -Site -Imp
completed
Skeel Subdivision
8110 Tieton Dr.
Eng -Site -Imp
in construction
Summit Crest Subdivision
8805 Summitview Ave.
Eng -Site -Imp
in construction
N. 16th Ave. Commercial Building
916 N. 16th Ave.
Eng -Site -Imp
completed
Catalyss
4200 Castlevale Rd.
Eng -Site -Imp
completed
Powerhouse Villas Ph. 1
3201 Powerhouse Rd.
Eng -Site -Imp
in construction
YVMH Energy Plant Expansion
2811 Tieton Dr.
Eng -Site -Imp
in construction
Cubcrafters
2400-2500 Airport Ln
Eng -Site -Imp
completed
2015
North Acres MH Relocation
320 E. N St.
Sewer
completed
Cas cadia -Pear Tree Assisted Living
4130 Englewood Ave.
Eng -Site -Imp
completed
Tri-Plex
1110 ST Johns St.
Eng -Site -Imp
completed
Howard Maggard Duplex's
1706 Grant Ave.
Eng -Site -Imp
completed
Tahoma Square Ph. 2
1829 S. 1st St.
Eng -Site -Imp
in construction
Audio King
703 E. Nob Hill Blvd.
Eng -Site -Imp
completed
D. Martinez Comm. Bldgs
506-508 W. Nob Hill Blv
Eng -Site -Imp
completed
Bainter Sewer Extension
502 S. 90th Ave.
Sewer
in review
E. Lee Sewer Force Main
7706 Occidental Rd.
Sewer
apprvd for const.
YVMH Parking Lot Expansion
212 S. 29th Ave.
Site Improvements
completed
YVCC Ops and Admin. Bldgs
1211 W. Prasch Ave.
Eng -Site -Imp
completed
47 Hops Offic Bldg.
2516 S. 23rd Ave.
Site Improvements
completed
Ziad Awwad Conv. Store
801 S. Fair Ave.
Eng -Site -Imp
in construction
11
13
AFFIRMATIVE ACTION GOALS & WIM/DBE PARTICIPATION
W/M/DBE utilization has been included in the past but is not included with this report.
The Engineering Division continues to request apparent low bidders of public works contracts to
document their efforts to achieve the City of Yakima's goal of 10% MBE, WBE or DBE
participation goal prior to contract award. However, changes in state law due to the passage of
Initiative 200 prohibit certain practices by contracting agencies (i.e. the City) for the award of
public works projects such as requiring W/M/DBE subcontracting. While some contractors have
voluntarily reported such information in the past, we have not received any such reporting last
year.
Although we do not receive such information voluntarily, the City must still meet certain of these
federal requirements and each contractor must comply with the Standard Specifications that are
included on each City Public Works Contract. The City is responsible to:
• Conduct pre -construction conferences during which EEO and City policies are discussed
with the contractor.
• Monitor on-site compliance with the EEO and City policies.
• Ensure our contractors locate, qualify, and increase the skills of minority groups, women
employees, and applicants for employment as required by City policies.
• Ensure the preparation of required EEO and related reports.
12
Proj
Proj.Impacted
Lead Division
Project Name/Location
Description of Work
Proj1�ct Lead
Constrctn.
Status/Schedule
Notes
Type
No.
Divisions
Start Date
4/5/2017
1818
Engineering
Lincoln Avenue Underpass;
Raised Sidewalk &
Engineering,
Sidewalk was finished in December;
1
CIP
Phase
UPDATED
Phase IV
Bins of Light
Brett Sheffield
Traffic Engineering,
2016
Artwork construction begins early April;
Project awarded to KRCI, LLC of Wenatchee
IV
Raised Sidewalk & Bins of Light
Streets
Ribbon -cutting set for mid -Ma
New rights of way, public
Engineering, Streets
Bravo Company Blvd. will be a Blvd. style street that
2
CIP
2337
Special Projects
Cascade Millsite Parkway
utilities, roads, lighting,
Joan Davenport/
& Traffic Eng.,
? ? ?
Bravo Company Blvd. extension
includes 2 more roundabouts. Design work includes
& Engineering)
( 9� 9)
roundabouts, sidewalks,
Brett Sheffield
Water/Irrigation, ation,
9
is being designed
9 9
road design & realignment in vicinity of East-West
9 9 Y
pathway, infrastructure
Wastewater/Storm
corridor to respond to BNSF rail concern
Phase 1: Entire Site
Engineering, Streets
Consultant, Landau Assoc's, will gather data for
3
CIP
2355
Engineering &
Cascade Mil/site Parkway
Brett Sheffield /
& Traffic Eng.,
tbd
evaluation of landfill area and plywood plant site in
Current data effort in coordination with
S ecial Projects)
� p > >
continued
� �
Phase 2: Southern portion
Joan Davenport
( P )
Water/Irrigation,
response to DOE concerns about groundwater
P g
DOE Voluntary Compliance Program
Y P g
Wastewater/Storm
and contaminants. Excludes landfill area
East-West Connector;
"H"
New rights of way, public
Engineering, Streets
Consultant (H.W. Lochner) hired for
4
CIP
2336
Special Projects
St. alignment from 1 st St.
utilities, roads, lighting,
Brett Sheffield /
& Traffic Eng.,
2017?
NEPA review underway.
creation of design alternatives and
& Engineering)
( 9 9)
to Terrace Heights;
9
signal(s),sidewalks, pathway,
p Y.
Joan Davenport
( p )
Water/Irrigation, ation,
9
Yakima Count is project lead
Y P �
NEPA review (environmental)
Through Yakima Resources prop.
infrastructure
Wastewater/Storm
Interchange Justification Report
Working with WSDOT for
City and County developing a plan to implement
5
CIP
2356
Special Projects
(I.J.R.) for modification of
modification of Yakima Ave /
Brett Sheffield /
Engineering, Streets
tbd
portions of the improvements in a phased manner
WSDOT & FHWA have given approval the IJR
& En
(gineerin g)
I-82 and Yakima Avenue
I-82 Interchange
Joan Davenport&Traffic
( )
En g.'
in order to defer WSDOT changes to I-82 and
g
construction interchange portion early.
Special Projects
North 1st Street Corridor
Design and construction of
Brett Sheffield /
Engineering, Streets
& Traffic Eng.,
Federal funding of $2.7 M deferred for Phase 1.
Engineering design for this Phase ("N" St. to I-82) is on
6
CIP
2340
(& Engineering)
Revitalization;
sidewalk, landscape and utility
( Joan Davenport)
Water/Irrigation,
2018?
In September we submitted for a TIGER Federal
hold due to delay in identified Federal Funding. This
Phase 1: I-82 to 'N' St.
upgrades
Wastewater/Storm
Grant for both phases, MLK to "N" & "N" to I-82
section is anticipated for construction in 2017.
Design & construction of
Engineering, Streets
Huibregtse, Louman Associates, (HLA) of Yakima
Special Projects
North 1 st Street Corridor
sidewalk, landscape and utility
& Traffic Eng.,
was awarded the design contract;
Both phases of this work were included in a 2017
7
CIP
2390
(& Engineering)
Revitalization;
upgrades; adding bike lanes
Brett Sheffield
Water/Irrigation,
2018?
In September we submitted for a TIGER Federal
FASTLANE federal grant application.
Phase 2: MLK to'N' St.
removing parking; relocating
Wastewater/Storm,
Grant for both phases, MLK to "N" & "N" to I-82,
Grant selection has not yet been made.
overhead utilities
Private Utilities
but were not successful
Paving Gravel Alleys:
Engineering,
Funded by
8
CIP
??�
Engineering
Area bound by: Fruitvale to Lincoln &
Grade and chip -seal
Bob Desgrosellier
Streets,
2017
Design has started;
Congestion Mitigation &Air Quality funding
5th to 16th Avenues
existing gravel alleys
Water/Irrigation,
will be publicly bid this year
(CMAQ)
Wastewater
Powerhouse Road Sidewalk;
Construct curb &gutter,
Engineering,
Summer
Funded by $275,000 grant from
9
CIP
����
Engineering
800' west of Pecks Canyon Road
sidewalk and storm drainage
Bob Desgrosellier
Streets,
2017
o
Surveying is complete, design is at 60%
Transportation Alternatives Program (TAP)
to Cowiche Canyon Road
Storm
10
CIP
2153
Engineering
YVT System Restoration
Remove and repair approx.
Bob Desgrosellier
Engineering,
2016
leaving approx. $60K for track repair; Prior CarBarn and other work was completed,
We have to amend existing federal submittals to
( 6th Ave. vicinity Yakima Ave.)
100 feet of trolley track
Streets
Parking lot paving has been completed
include the proposed work within federal regulations
E. Nob Hill Blvd &Fair Avenue,
Widen intersection all 4 legs;
Brett Sheffield /
Engineering, Traffic,
Design only at this time beginning 6/2008;
Current funding for design only;
11
CIP
2143
Engineering
Intersection Improvements
purchase r/waY. new signal
(Randy Tabert)
Wastewater,
Design only
Search for construction funding on-going
(Drainage improvement slated for this intersection)
Water/Irrigation
We applied for STP funding
Capitol Theatre
Engineering,
Several items completed; Carpeting completed in
Replaced aisle lighting; added overhead cable runs;
12
CIP
2354
Engineering
Safety Improvements
Safety Improvements
Bob Desgrosellier
Capitol Theatre
2015 & 2016
summer 2016; other work is forthcoming
Replaced main lobby, mezzanine lobby and Robertson
Room carpeting
Tiger Oil Properties Remediation:
Work with DOE to test theseBrett
Sheffield /
13th & E. Nob Hill and 56th & Summitview
13
CIP
2389
Engineering
East Nob Hill Blvd; North 1st St.;
City properties, remediate soils
Joan Davenport /
Engineering,
2015
Work with DOE and our consulting firm continues;
may have sales pending;
West Nob Hill Blvd
and water as needed and then
Bob Desgrosellier
CED
24th & Nob Hill: monitor 4 more quarters.
N. 1st Street property is pending remediation
sell to developers
Work with to release City
Brett Sheffield /
The project is the approximate 2,000 feet of creek
Discussions have anticipated work occurring
14
CIP
����
Engineering
Lower Cowiche Creek Project
property for Cowiche Creek
Rich Sanislo
Engineering
2018 or later
from SR -12 downstream to the Naches River
after any modification to
Conservancy
Nelson Bridge Irrigation Intake Modification
Economic
Council authorized design team to proceed with
Gustafson Guthrie Nichol (GGN) preparing
Increase the existing Plaza and
Sean Hawkins /
Development,
thru 2017
project plans after projected costs were reduced.
construction doc's; to provide construction admin.
15
CIP
����
Engineering
Downtown Yakima Central Plaza
surroundings into a world-class
Brett Sheffield
Engineering,
and beyond
GGN is finishing plans in 2016;
services as City Council chooses to proceed.
event center
Streets,
SEPA checklist nearly complete.
Pledges are at $5.3M. Council wants over $9M
Planning,
Working with utilities for their relocation
in pledges before bonding the project
58 acre site; Fields: 17
Economic®
Work continues on the collaboration of design,
Multi -Sport Complex with
soccer/multi-sport; 14 FIFA
Sean Hawkins /
Development,
Design plans are at 8010+ for the improvements
development and operation of a world-class Yakima
16
CIP
????
Engineering
SOZO Sports of Central WA,
sized grass; 3 FIFA sized
Brett Sheffield
Engineering,
? ? ?
to Spring Creek, Sorenson Road
Sports Complex consisting of soccer/multi-sport fields
S. 38th Avenue just north of Ahtanum
lighted synthetic turf; Sports
Streets,
and 36th Avenue.
and an indoor sports facility
Campus & other facilities
Planning,
Proj
Proj.
Lead Division
Project Name/Location
Description of Work
Proj1e5ct Lead
Impacted
Constrctn.
Status/Schedule
Notes
Type
No.
Divisions
Start Date
4/5/2017
Safe Routes to School Sidewalks:
Install new sidewalk in the
This project was awarded through the
Design is at 80%; R/Way funds have been obligated
17
CIP
????
Engineering
Adams Elementary School &
vicinity of the schools.
Bob Desgrosellier
Engineering
2017
Safe Routes To School Program
so we can start to negotiate r/way strip purchases
Washington Middle School
Locations forthcoming)
Safe Routes to School Sidewalks:
Install new sidewalk in the
This project was awarded through the
Design is at 80%; RNVay funds have been obligated
18
CIP
����
Engineering
Garfield Elementary School
vicinity of the school.
Bob Desgrosellier
Engineering
2017
Safe Routes To School Program
so we can start to negotiate r/way strip purchases
Locations forthcoming)
NEW!!!
64th & Ahtanum
Widen the intersection adding a
Brett Sheffield
Application for this project was successful for
Project has been selected,
19
CIP
����
Engineering
widening and signalization
westbound RTO lane
Randy Tabert
Engineering
2018
Congestion Mitigation & Air Quality funding
but funding is not available until 2018
and adding a signal
CMAQ
NEW!!!
Heritage Capitol Project Grant for
g p
Restore arts of the YVT
p
Engineering,Work
will proceed as the contract with Washington
p g
$50,000 from Heritage Capitol Projects is matched
20
CIP
????
Engineering
YVTrolley Improvements
facilities and trolley system
Bob Desgrosellier
Streets
2017
Heritage Capitol Projects is final
against Trolley volunteers labor & improvements &
$90,000 in matching City construction funds
21
CIP
????
NEW!!!
Safe Routes to School Sidewalks:
Install new sidewalk in the
vicinity of the schools.
Bob Desgrosellier
Engineering
2018?
This project was awarded through the
Project was selected, however,
Engineering
McKinley Elementary School
Locations forthcomin
Safe Routes To School Program
award by State Legislature is pending
NEW!!!
Safe Routes to School Sidewalks:
Install new sidewalk in the
This project was awarded through the
Project was selected
22
CIP
????
Engineering
McClure Elementary School
vicinity of the schools.
Bob Desgrosellier
Engineering
2018?
Safe Routes To School Program
but pending award by State Legislature
Locations forthcomin
RH2 has been selected as the Design Engineer.
The improvements are identified as part of the long
Slipline existing interceptor with
The contract has been signed. Initial assessments
term master plan. They are needed to address
21
CIP
2416
Wastewater
Speedway/Race street Interceptor
new force mains, refit of Rudkin
Engineering/
Wastewater
3rd / 4th Quarter
of the Rudkin Road lift station improvements have
adverse flow conditions and reroute the flows from the
Phase II
Road lift station and new lift
Dana Kallevig
2016
been made. Survey work for the Beech street line
Fair Ave basin as well as parts of the 2nd Ave. basin
station on Beech.
and Race Street lift station has been performed.
and allow for inclusion of the flows associated with the
redevelopment of the sawmill area.
City's working w/USBR & HDR on fish screen
Applied to DOE for point of diversion change to Nelson
Water/Irrigation,
/intake project options. Assessment received 6/13
Dam. Point of
Move Point of Diversion
Rich Sanislo /
USBR, Yakima
w/design alt's & recommendations. HDR finalized
Diversion change on public notice
22
CIP
2010
Water/Irrigation
Nelson Dam Replacement/ Fruitvale
(Improving Nelson Dam fish
Dave Brown /
County, WDFW,
2017
report & options; we met stakeholders 9/13 to
7/13/12 and 7/20/2012.
Canal Diversion Improvements
screen for additional water)
Mike Shane
North Yakima
discuss options. Final HDR report based on
USBR project is out of funding.
Conservation District
comments. Stakeholder review on-going. Working
Water Division budgeted $8M in 2017
with Yakima County to review coordination with
for project infrastructure
flood plan restoration project.
23
CIP
2288
Water/Irrigation
Misc. waterline improvements.
Water facilities impacted
Mike Shane /
Water/Irrigation,by
2016/17
On-going coordination with other projects
Majority of work to be completed by in-house staff.
misc. projects
Emilio Lopez
Streets, Eng.
Working with Golder & Assoc. for Hydrotech Eng
Support Services for design, permitting, funding,
construction bid & inspection support of new intake
Modification of river intake;
& floodplain stabilization structures. Conceptual
Naches River WTP Intake
Possible improvements in river
Dave Brown,
design for new river structures provided 12/13; final
Ecology has issued a Watershed grant for $250,000
24
CIP
2335
Water/Irrigation
Improvements
to maintain existing location
Mike Shane
Water/Irrigation
2017
design underway. Additional stakeholder (TAG)
for this project.
and flows to intake
meetings to determine final design criteria. Yakima
County to survey area & water levels at intake to
provide additional information to stakeholders
regarding design. Modified design proposed
provided to stakholders.
DID #29 Reroute -
Reroute section of DID #29 that
Project awarded to Tri -Valley Construction in
Construction primarily completed in December 2016. A
25
CIP
2445
Stormwater
Lincoln Ave. and N. 29th Ave.
collapsed under a residence.
Randy Meloy
Stormwater
2016
November 2016.
small amount of grass restoration work to be
completed in Spring 2017.
Construct curb & gutter on
26
CIP
2447
Stormwater
N. 49th Ave. Drainage Imprvm'ts
Englewood Ave.; increasing
Randy Meloy
Stormwater
2016
Survey work completed.
Project's primary purpose is to alleviate damage from
Englewood Ave. to Gilbert Park
storm drain pipe sizes on
Design plans are at 80%.
heavy rainfalls that cause localized flooding.
Englewood and N. 49th Aves
Removal and replacement of
27
CIP
???
Stormwater /
N. 66th Ave. Reconstruction - Scenic
road bed and asphalt
Randy Meloy
Stormwater/Streets
2017
Emergency project.
Entire street to be reconstructed after sustaining
Streets
Drive to Englewood Ave.
pavement. Installation of
Construction set to start in April 2017.
severe damage during winter of 2016-2017.
drainage system.