HomeMy WebLinkAbout06/21/2016 09 2017-2022 Six-Year Transportation Improvement Program AmendmentBUSINESS OF THE CITY COUNCIL YAKIMA, WASHINGTON AGENDASTATEMENT Item No. 9. For Meeting of: June 21, 2016 ITEM TITLE: Public Hearing to consider resolutions: A) Adoption of the Six-Year Transportation Improvement Program for the years 2017 to 2022, and to amend the Metropolitan Transportation Plan; and B) Amend the Yakima Urban Area Comprehensive Plan Capital Facilities Element SUBMITTED BY: Brett Sheffield, Chief Engineer, 576 -6797 SUMMARY EXPLANATION: Attached is the 2017 — 2022 Six-year Transportation Improvement Program (TIP), along with an explanation sheet that describes the information contained on the various columns of the Six-Year TIP. The following six projects have been added: • #18 16th Avenue and Tieton Drive Intersection Improvements • #20 64th Avenue and Ahtanum Road Intersection Improvements • #21 South 16th Avenue Sidewalks • #22 McClure Elementary School Safety Improvements • #23 McKinley Elementary School Safety Improvements • #24 6th Avenue Roadway Improvements Projects removed from the 2016 — 2021 TIP, as they were completed or the funds were obligated are: • #1 Yakima Railroad Grade Separations, Phase 4 • #47 Lincoln Avenue Corridor Safety Improvements A) Each year the City is required by RCW 35.77.010 and RCW 36.81.121 to update its Six-year Transportation Improvement Program (TIP) for submittal to the Washington State Department of Transportation. This plan must include all transportation projects for which state gas tax revenue of federal revenue will be used. The current plan for 2017 — 2022 includes thirteen projects that are funded. Funding for the remainder of the projects will continue to be sought. The funded projects are: #1 — North 1St Street Revitalization, `N' Street to SR 12 #2 — North 1St Street Revitalization, MLK to `N' Street #3 — Powerhouse Road Sidewalk #4 —Adams Elementary/Washington Middle School Sidewalk Improvements #5 — Garfield Elementary Safety Improvements #6 — Yakima Valley Transportation Company Preservation #7 — Spring Creek Road Reconstruction #8 — South 36th Avenue Reconstruction #9 — Sorenson Road Reconstruction #10 — Bravo Company Boulevard #12 — Northside Alley Pavers #16 — S. 80th Avenue Bridge #17 —Wide Hollow Bridge Six -year Transportation Improvement Program (TIP) Background On August 10, 2005, the President signed into law the Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA -LU). This act is the next authorization after the prior Transportation Equity Act of 1998 for the 21St Century (TEA-21) and previous Intermodal Surface Transportation Efficiency Act (ISTEA) of 1991. The current act again specifies the systems on which certain funds can be used and activities for which funds can be used and promotes the role of the Metropolitan Planning Organizations (MPO) in the planning and programming of projects. SAFETEA -LU requires each designated MPO to develop a Transportation Improvement Program (TIP), and the state to develop a Statewide Transportation Improvement Program (STIP) as a condition to securing federal funds for the transportation projects. Projects listed in the STIP are the only projects that can be approved by the Federal Highway Administration (FHWA) and the Federal Transit Administration (FTA) to utilize federal fund of by the State of Washington for approved State funding agencies. The STIP is a prioritized program of transportation projects, complied from local and regional plans, along with the Washington Transportation System Plan (WTP), which provides a backbone for developing projects for the intermodal transportation network in the State of Washington. The STIP contains federally funded projects plus state and local projects that are regionally significant. These projects have been identified through the planning process as the highest priority for the available funding to the state's transportation program. Planning activities of state and local governments are essential parts of integrated regional planning processes. Long range transportation planning is a part of the comprehensive land use planning carried out by local governments. Citizen participation is an integral part of the planning process at all levels. Local Agencies are required to develop and adopt a six-year transportation program. All local agencies are required to hold at least one public hearing during the development of the six-year transportation program. B) The City needs to amend the Yakima Urban Area Comprehensive Plan Capital Facilities Element to incorporate the adopted six-year TIP for 2017 to 2022. This will ensure that we are in compliance with the Growth Management Act and that we are consistent with the Comprehensive Plan as required. The amendment is limited to incorporate only those projects that adopted in the STIP and is not subject to the "once a year" change required under the laws of the Growth Management Act. ITEM BUDGETED: STRATEGIC PRIORITY: APPROVED FOR SUBMITTAL: Interim City Manager STAFF RECOMMENDATION: Adopt the Six-Year TIP and amend the regional Metropolitan Transportation Plan and Comprehensive Plan Capital Facilities Element. BOARD/COMMITTEE RECOMMENDATION: ATTACHMENTS: Description Upload Date Type D six-year program 6110/2016 Cmer Memo D six-year appendices 6110/2016 Coxer Memo D Resolutions 6/1012016 Co%er Memo Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 co. Name: Yakima Co. From 2017 to 2022 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/7/16 & 6/21/16, Adoption Date: 6/21/2016 Amend Date: Resolution No.., Project Costs in Thousands of Dollars Federally Furtded Expenditure Schedule — 0 Project identification v Fund Source Information (Local Agency) Projects Only _ A. PINJFederal Aid No. B. Bridge No, c s m Federal Funding R /W c z C. Project Title E E m c v a -c a Phase Federal State State Local Total - Envir. Required q u D. Street /Road Name or Number N a " ' J u u °' Start Federal Fund Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date c o E. Beginning MP or Road MP Or Road 6 g g a s � m .. a'.: T.. 'o Code m m F. Describe .Work toBeDone Phase (MMfYY) 1 2 3 4_ 5 6 7 8 9 10 11 12 13" 14 15 16 17 18 19 20 21 14 1 North 1st Street Revitalization 3 " S 0.42 P Cls : 1/1/2018 STP(U) 2,718 424 3,142 3,142 CE No '. worth 1st Street 06 T from: 'N' Street to: SR 12 0 Improve North 1st Street by rehabilitating the pavement C and lane markings, removing on- street parking, W enhancing street and pedestrian lighting, constructing 5 median islands and installing various pedestrian and decorative elements.. Totals 2,718 424 3,142 3,142 14 2 North 1st Street Revitalization 06 5 0.98 P CN 1J1J2Q17 EASTLANE 8 «5po TIC 1.5{jD 1Ci, ' 6,SKt 3,500 CE Yes N 1st Street 12 T from: MLK Blvd;.:, to: 'N'Street G 12/31/2415 Improve North 1st Street by rehabilitating the pavement C and lane markings, removing on- street parking, W enhancing street and pedestrian lighting, constructing S median islands and installing various pedestrian and 0 decorative elements, Totals 8,500 10,000 6,500 3,500 17 3 Powerhouse Road Sidewalk 05 S 0,6 O CN 1/1/2017" TAP 245 i5 245 CE No Powerhouse Road 12 C from: Cowiche Canyon Rd to: Mobile Home Park T Widen westbound lane to provide a 14 -foot wide shared bike lane and construct curb, gutter and sidewalk on the north side of the road; Totals 245 245 245 19 4 Adams Elem.jiNashington M.S, Sidewalk Improvements 12 5 N/A P' CN '5/1/2017 '' SRTS 282 282 282 CE Yes Various Streets T from: to: 0 1 1 5/1/2017 This project will make various pedestrian safety improvements in the vicinity of Adams Elementary School and Washington Middle School, such as, constructing sidewalks, improving roadway crossings, installing flashers and installing fencing. Totals 282 282 282 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co. From 2017 to 2022 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/7/16 & 6/21/16 Adoption Date; 6/21/2416 Amend Date: Resolution No.: Pfoject Costs in Thousands of Dollars Federally Funded � o Protect Identification � Fund Source Information Expenditure Schedule Projects Clnly v C A PIN /federal Aid No B. Bridge No, c r m Federal Fundin (Local Agency) RjW c z °— c,: Project Tdle DatreetjRoad NameorNumber E E m J U a u Phase Start Federal Fund Federal State State Local Total ----' Envic Required c F, BeginningmPOrROad - EndingMPOrRoad a v a IS `} 2` 6 Code Cost by', Fund Code ' Funds Funds 'Funds 1st 2nd 3rd 4th Type Date ai F. Describe Work to Be Done E. ;n ,. Phase (iYa M /YY) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16" 17 18 19 24 21 19 5 Garfield Elementary Safety Improvements 12 5 N/A P CN 5/1/2017 ° SRTS' 1$1 141 141 CE Yes Various Streets T from: to: 0 1/1/2017 This project will make various pedestrian safety improvements in the vicinity of Garfield Elementary School, such as, constructing sidewalk, improving roadway crossings, installing flashers. Totals 141 141 141 14 6 Yakima Valley Transportation Company Preservation 03 S ®.02 0 CN - 111/2017 STP(E) '52 52 52 CE No Yakima Avenue from: Yakima Avenue to: 6th Avenue This project will remove and replace a portion of the existing trolley rail in the vicinity of the intersection of 6th Avenue and Yakima Avenue, Totals' 52 52 52 17 7 Spring Creek Rood Reconstruction 03 S 0.85 S Cls 3/1/2017 SIED 1,100 8211 1, 2Ci 1, 2{} SEPA Yes Spring Creek Road W rom: Washington Ave, to: 36th Avenue 311J2o17 Widen roadway to three lanes, install curb, gutter, sidewalk and street lights. 1JOO 820 1,920 1,920 17 8 36th Avenue Reconstruction 03 0.40 S CN 3J1/2017 SIED 520 385 905 405 SERA Yes 36th Avenue W from.' Spring Creek Rd, to: Sorenson Rd. 3/1(2017 Widen roadway to three lanes, install curb, gutter, sidewalk and street lights. 520 385 905 905 Agency: Yakima Co. No.: 39 Co. Name: Yakima Co. City No.: 1485 MPO/RTPC: YVCOG M3MM3MM =7 From 2017 to 2022 Hearing Date: 6/7/16&6/21J16 Adoption Date: 6/21/2016 Amend Date: Resolution No.. Project Costs in Thousands of Dollars Federally Funded 1, Project Identification Fund Source Information Expenditure Schedule Projects Call E A. PIN/Federal Aid Na. 8- Bridge Na. Federal Funding (Local Agency) R/W Ri C. Project Title E 0 U 0- Phase Federal State State Local Total Envir. Required D. Street/Road Name or Number Start Federal Fund E. Beginning MP or Road - Ending MP or Road ro 15 0 Cost by Fund Code Code Funds Funds Funds 1st 2nd 3rd 4th Type Date Z F. Describe Work to Be Done Phase (MM/YY) 1 2 3 4 5 6 7 8 , 9 10 21 12 13 14 15 16 17 18 19 19 20 21 --17 9 Sarenjon Road Reconstruction 03 S 014 S N7 SIED 0 32i7 Yes Sorenson Road W 7 frarm 36th Avenue to: 38th Avenue 3/112017 Widen roadway, install curb, gutter, sidewalk and street lights. Totals 180 140 320 320 —T6 10 Bravo Company Boutevard 01 S 7 .65 P R 1/1/2017 U FT 1 i aw CE Yes North 10th Street 06 T CN 1/1/2018 LIFT 4„480i 1,1201 S'Rvof S'SAO from: 'H' Street to: Lincoln Ave. W 1/1/2018 Construct new roadway including water, sewer, curb, S gutter, sidewalk, street lighting and storm drainage 0 system, Totals --F-1 5,280 1,320 6,600 LORD 5,600 =6 — 11 E. 'H'Street Extension, Ph. 1 01 P 1-10 P N i�17 SOO 11) Soo CE Yes E- 'H' Street 08 T CN 1/l/2019 '19 TIB I B 1,500 3,1001 4,60() )F 4,600 F] 4,6]00 from: 1st Street to: 10th Street W 1211/2018 Construct new roadway including water, sewer, curb, S gutter, sidewalk, street lighting and storm drainage 0 system. Totals 3,600 5,100 500 4,600 CO 12 Northside Alley Paver 07 S 3,5 p C'l 1/112017 Ci V i 353 57 410 410 CE No Alleys between Folsom Ave, and Frurtvale Blvd, T from: 16th Avenue to: 6th Avenue C Pave the east/west gravel alleys between Folsom 0 Avenue and Frurvale Boulevard from 16th Avenue to 6th Avenue Totals 353 57 410 410 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co-. From 2017 to 2022 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6 /7/16 & 6/21/16 Adoption Date: 6 /21/2016 Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded � y Project Identification � Fund Source Information Expenditure Schedule Projects OrrIT A. PIN /Federal Aid Noa B. Bridge No. c Y a Federal Funding (Local Agency) R/W = Z CProject Title E m a .c a Phase .. o D. street /Road Name or Number v > y w J 0 Start Federal Fund Federal State State Local Total 4th Envir. Required E, Beginning MP or Road Ending MP or Road a n ��, ® o Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd Thru Type Date E. Describe Work to Be Done a� va r- '''' = a 'Phase ...6th. jt'v7 /yY} 1 2 3 4 "' S 6 7 8 9 10 11 12- 13 14 15 16 17 18" 19 20 21 16 13 E 'H'StreetExtension, Ph.2 01 P 0.55 P RW 1/1/2019' STP t1� 432 8 5tM1 Stj{} CE Yes E.'H'Street 08 T CN ',1/112021 STP(U) 2,1621 3381 2,5001 2,500 from: 10th Street to: 1 -82 W 11112018 Construct new roadway including water, sewer, curb, 5 gutter, sidewalk, street lighting and storm drainage system. Totals 2,584 406 3,000 500 2,500 QO 14 Cowiche Canyon Trail 28 P 2.0O RW 7J1J2O19 CWA 105 105 105 Cowiche Canyon CN 1/112021) CWA 1,695 1,695 1,695 from: Powerhouse Road to: Trainead 1/1/2020 Construct a 10 -foot wide pathway, including two bridges over Cowiche Creek. Totals 1„800 105 1,605 14 15 E. Nob Hrtt BPvd. &Fair Ave, 1/5 improvements 03 P N/A P RW 1%SJ2O17 STP(U) 187 29 216 236 CE Yes Nob Hill Boulevard 04 T CN 6/1J2019 STP(:: 1,457 227 1,684' 1,684 from: E. Nob Hill Blvd. to: Fair Ave. 31 W 1/1/2019 Widen Nob Hill Boulevard through the intersection, C construct left -turn lane, curb, gutter, sidewalk, street 0 lighting and drainage.. Upgrade signal by installing mast arm structures; Totals 1...644 256 1,�t1€1 216 1,6$4 17 " `16 5. 80th Avenue Bridge 09 S 0.05 P PE 1/1/2017 DOE 0 25 25 CE No S. 80th Avenue T CN 1j1J2018 ROE 725 0 75 75 from: Wide Hollow Rd. to: PlothAve. 0 Replace existing two -lane bridge over Wide Hollow Creek with three -lane bridge. The City's involvement is only to pass through of an Ecology grant in conjunction with the County's flood plain management project. Totals 100 75 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co. From 2017 to 2022 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/7/16 & 6/21/16 Adoption Date: 6/21/2016 Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded ro v Project Identification v Fund Source Information Expenditure Schedule Projects Only � 'E A... PIN/Federal Aid No. B. Bridge No,. '. c s ^ w � Federal Fundin g (Local Agency) R W / c ° as C, Project Title E V. a u° sy Phase r° Federal State State Local Total Envir. Required — _r D. Street /Road Name or Number a u Start Federal Fund e, Beg7nn7ngMPorRoad- EndingMPOrRoad t°u n $ m Y ° Cade Cost by Fund Code Funds Funds Funds 1St 2nd 3rd 4th Type Date s.i F. Describe work to Be Done E I? H h ;— = a Phase7irl' /YY) 1 "2 3. 4 5 1 6 7 8 9 10 11" 12 13 14 15 16 17 18 19 20 21 17 17 Wide Hallow Road Bridge 9 S 0-65 P PE 1/1/2017 DOE 25 25 ZS CE No Wide Hollow Road T CN 1/1/2018'- DOE 75 35 ' 75 from: 89th Avenue to: 88th Avenue O Replace existing two -lane bridge over Wide Hollow Creek with three -lane bridge. The City's involvement is only to pass through of an Ecology grant in conjunction with the County's flood plain management project. Totals 100 100 25 75 14 18 loth Ave. & Tieton Jr. Intersection improvements S P 0.40 P PE ' STP {U) 26t1 40 340 300 CE Yes 16th Avenue 7 T RW STP {U} 3460 5u0 4,000 3,460 rom: 16th Ave. to: Tieton Dr. G CN STP {U} 1,3001 200 1,500 1SOD 4/1/2021 O Reconstruct and widen 16th Avenue and Tieton Drive C S by adding left -turn lanes for all movements at the W intersection. Upgrade the traffic signal; Totals 5x020 780 500 300 3,460 1,5770 14 19 18th Street Underpass 12 P 0.02 P PE do1f1J2018 BRAG Z40 300 3�1 CE No Yakima Avenue T CN '1 /1/2019 BRAG 2,288 �57221&50 2,69 f from: Yakima Ave.- to: 18th Street 0 S Replace the bridge on E Yakima Avenue that crosses IN over 18th Street. Totals 2,528 632 3,160 300 2,960 17 20 64th Ave. &Ahtanum Intersection improvements 12 P N {A P PE 111/?t717 CMAQ 56 9 65 65 CE Yes 64th Avenue T RW ,1/1/2018 CMAQ 43 7 so 50" frta € 64th Ave; Yo: Ahtanum Rd. C CN 5(1/2018 CMAQ 43 67 SE70 500 5J112018 Improve the Bath Avenue and Ahtanum Road intersection by constructing a westbound right -turn lane on Ahtanum and installing a traffic signal. Totals 532 83 615 65 550 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co. From 2017 to 2022 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/7/16 & 6/21/16 Adoption Date: 6/21/2016 Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded ID Project Identification Fund Source Information Expenditure Schedule Project @g only V E A, PIN /Federal Aid No. B. Bridge No. c W s v Federal Funding " ILOCaI Agency) R/W z C. Project Title E m v a Phase ..—.._ . °_ > '0. Street /Road Name or Number a v u Start Federal Fund Federal State State Local Total Envir, Required '.. E. Beginning MP or Road - Ending MP or Road n n ,°., m m ' r Code Cost by Fund Code'. Funds Funds Funds 1St 2nd 3rd 4th Type bate L F. Describe Work to Be Done E = M a Phase CM1 j 1 2 3'' 4 5 6 7 8 9 10 11 12 13 14 15 1 16 17 18 19 20 21 14 21 Sot th 16th Avenue Sidewalks 12 P 0.88 P PE 111/2017 PBP 4 6 60 60 CE Yes 16th Avenue T RW 6/1/2017 '' PER 234' 26 260' 260 rom, Washington Ave. to: Nab Hill Blvd. C CN 6/1/2018 PEP 1 3691 41 410 410 6/1/2018 Install 7 -foot sidewalk on the west side of 16th 0 Avenue. Totals 657 73 730 320 410 19 22 McClure Elementary School Safety Improvements 12 P NJA P PE 1%11 1, SRTS 46 46 46 CE Yes Various locations T RW 6/1/2017 SRTS 65 S 65 from: to: C CN ,6/1/2018 SRTS 380' 384 3807 611/2018 0 This project will make various pedestrian safety improvements in the vicinity of McClure Elementary School, such as, constructing sidewalk, ADA ramps and improving crosswalks. Totals 491 491 111 380 19 23 McKinley Elementary School Safety Improvements 12 P NJA P' PE !1/1%2017' SRTS 5i3' SO 50 CE No Various locations T CA '6j1120JS SR TS 430} 430 430 from: to: C 0 This project will make various pedestrian safety improvements in the vicinity of McKinley Elementary School, such as, replacing delapitated sidewalk, constructing ADA ramps, and installing a HAWK pedestrian crossing system. Totals 480 0 480 50 430 19 __iT 6th Avenue Roodwoy Improvements 03" P 1.51 0 PE 1/1f2019 OTHER 201{1 2110 4170 400 CE No 6th Avenue 07 P CN 1/1/2020 OTHER =01 2,000 4,000 4;07001 from: Walnut Street to: River Road T Reconstruct the existing trolley rail and impacted roadway, grind and overlay the remaining width of 6th Avenue. Totals 0 2,200 4,400 0 400 U00 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: yakima Co. From 2017 to 2022 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/7/16 & 6/21/16 Adoption Date: 6/21/2016 Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded y Project Identification Fund Source Information Expenditure Schedule groJecCx Only V E A. PIN /Federal Aid No,. B. Bridge No..., s N @c Federal Funding " {Local Agency) R/W ° z s e, :Project Title, i}`StroetfRoadNameorNUmber E N on v ro v a Phase Start Federal Fund Fe:era State State Local Total Envir, Required o €, Beginning MP or Road Ending MP or Road m a — = 'ty Code CoFund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date YP F. Describe Work to Be Done E.F ,� P ', (MM /YY) 1 _2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 12 25 SR 12 & 16th Avenue Interchange 03 P N/A 0 PE 11jf2018 STP(U) 86 14 11DO 100 CE No Westbound ramps of SR 12 06 CN 1/1/2019 STP(U) 775 1..:21 900' fronn. 16th Aveeue to: SR 12 Construct a roundabout where the westbound ramps intersect with N. 16th Avenue. Totals 855 135 1'OM 100 900 14 26 S. 1s[ Si. & E. Washington Ave. tj5 Improvements 03 P NJA P PE 1(1/2018 STP {U} 260 40 300 300 CE Yes South 1sY Street 06 W RWj11201 STP(U) 250 40' 300 300 " from: S. 1st Street to: E. Washington Ave. S CRI 1/1,12020 STP(U) 1,211: 189 1,400 1.,400" 1/112020 Realign intersection, widen E. Washington Avenue to T accommodate an additional lane, replace curb, gutter 0 and sidewalk, and install a new traffic signalization system. , Totals 1,731 269 2,000 300 300 1,401) 14 27 Washington Ave, &Longfiber Rd.lntersection 03 P N/A C PE '1/1/2018 STP(U) Sf70 14 114 CE Yes Washington Avenue OS T RW `Sj1/2019 STP(U) 1110' i4 < 7795 7795 from: Washington Ave. to: Longfiber Rd'. 06 W CN ',1/1/2020' STP(U) 6$8' 107 1/8/2020 S Improve the Washington Avenue and Longfiber Road 0 intersection by constructing an eastboung left -turn lane on Washington and a northbound left -turn lane on Longfiber, install or replace curb, gutter, sidewalk, street lighting, storm drainage and safety flashing signal Totals 888 135 1,023 114 114 795 14 28 E. Nob Hitt Boulevard Reconstruction 03 P 0 =85 C PE 1/1 {2018 STP( 11 545 85 630 630 CE Yes E. Nob Hill Boulevard 04 T RW '3J1j2019 STP(U) 1,090 120 11280'' 1,260 from: S. 6th Street to: S. 18th Street 06 W CN 1/1/2020 STP(Lf 6,532 1,021} 7,552 7,552 1/112020 S Reconstruct and widen roadway to S lanes with 0 intersection improvements, curb, gutter, sidewalk, P street lighting and drainage system G Tota(s 8.167 1,275 9,442 630 1,260 7,552 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co„ From 217 to 222 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/7/16 & 6/21/16 Adoption Date: 6/21/2016 Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded Project Identification m Fund Source Information Expenditure Schedule projects Only u E A. PIN /Federal Aid No. B. Bridge No c t a Federal Funding Local { Agency) / c z C. Project Title E 50 °o a Phase r Q.Street /Road Name or Number '. a a c° .� u Start Federal Fund Federal State State Local Total Envir, Required c o E. Beginning MP OrROad - Ending MP Or Road c o. '«� : ® m o Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date .` u- o- F. Describe Work to Be Done , :. � � � � .Y _, a. .phase (F4I� ) 1 2 3 4 1 5 1 6 7 8 9 1 10 11 12 13. 14 15 16 17 18 19 1 20 21 14 29 N.'40thAve. &Summitview Ave Intersection 12 P MIA P PE 1/1/2018! STP(U) 126 17 143 163 CE Yes N. 40th Avenue T RW ',1 /1 /2019' STP(U) 130 20 150 , 55{7I from: N. 40th Ave. to: Summitview Dr, W CN 1(1 /2020 STP(U} 692 108 Soo ' 800 1/1/2020 Improve the intersection by constructing larger 5 corner radii, lengthening the turn lanes, and O upgrading the traffic signal system. Totals 948 145 1,093 143 150 800 14 30 N. 15th Avenue & Fruitvate Blvd, tJS 12 P N/A P PE 1(1/2018 STP(U} 126 18 144 144 CE Yes N. 16th Avenue T RW 1(1J2019 STP(U} 173 27 200 200' from: N, 16th Ave. to: Fruitvale Blvd. 0 CN 1 /1/2020 STP(U) 450 62 462 A62 1J112020 Improve the intersection by constructing larger curb S radii, installing ADA ramps, and upgrading the traffic W signal system. Totals 699 107 806 144 200 462 16 31 F. Mead Avenue Reconstruction 03 P 0.76 P PE STP(S} 122 TPP 23 152 152 CE No E. Mead Avenue 06 T 11/1/20191 CN '1/1/2020 STP(S) 1,730 TPP 206 �702,1006 2170 from: Rudkin Rd. to: Fair Ave. 5 Partner with Union Gap to reconstruct E. Mead C Avenue, install curb, gutter, sidewalk and storm G :drainage system. O Totals 7.,$52 77 2,158 152 21006 17 32 S. 48th Avenue Reconstruction 03 P 1 00 P PE '1/1/2018 STP(U) 223 35 258 25$ CE Yes South 48th Avenue 05 T RW 1/1/2019 STP(U} 1, i 518 1 81 600 600 from: Summitview Ave. to: Nob Hill Blvd. W CN 1/1/2020 STP(U} 1,d$5 232 1,717 1,717' 1/112020 S Reconstruct and widen 48th Avenue, install curb, 0 gutter, sidewalk, street lighting and drainage system. Totals 2,227 348 21575 258 600 1,717 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co. From 2017 to 2022 City No.: 1485 MPOJRTPO: YVCOG Hearing Date: _ 6/7116 & 6/21/16 Adoption Date: 6/21/2016 Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded y Project Identification 1 Fund Source Information Expenditure Schedule Prtzjeetx Only A. PIN/Federal Aid No. B. Bridge No. c v w N Federal Funding ( Local Agency) P/W c N C. Project Title DStreetJROadNameorNUmber E a do ; v u s a U Phase Start Federal Fund Federal State State Local Total --�-- 4th Envir: Required 15 `o E. Beginning MP or Road Ending MP or Road n a m Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd Thru Type Date u. n: F. Describe work to Be Done E '? 6 = a Phase 6th (MM /Y1*) 1 2 3 4 5 " 6 7.. 8 9 10 " 11 12 13 14 15 16 17 18 19 20 21 17 33 Powerhouse Rd. & Englewood Ave. tjS 12` P N/A P PE 111/2019 STP(S) 43 7 50 50 CE Yes Powerhouse Rd, T RW 1/1(2020 STP(S) 87' 13 100 100' ram: Powerhouse Rd. to: Englewood Ave; C CN 1/1/2021' STP(S) 500' 528'' 578 1J1J2021 Realign intersection, install curb, gutter, sidewalk and S safety flashing signal. Possibly construct a O roundabout. W Totals 630 98 728 50 678 14 34 W. Lincoln Ave. & MLK Blvd. Realignment 01 P 0.50 C PE 1J1j2018 STP(E) 42 t ? 491 491 CE Yes W. Lincoln Avenue 12 T RW '1/1/2019' STP {E) j,ia47' 163 1,2'ji1' 1,210 from: N. 5th Ave. to: Custer St. W CN '1/1/2020' STP (E) 1,801 281 2,082 2,082' 1/112020 5 0 Realign W. Lincoln Avenue, install curb, gutter, P sidewalks, street lighting, drainage. G Totals 3,272 511 3,783 491 1,210 2,082 14 35 N. 34th Ave, & Fruitvale Blvd. lj5 Improvements 12' P NJA P PE 1/1/2019 5TP {U) 63 5 6£S 68 CE Yes Fruitvale Boulevard T RW 11/2020 STP {U) 87' 13 0) 100 from: Fruitvale Blvd. to: N, 34th Ave. O CN 1/1/2021 5TP (U) 556 1 87 d ! 643 1/1/2021 S Improve intersection by installing a traffic signal W system, curb, gutter and sidewalk. Widen leg south of Fruitvale to inlcude a left -turn lane Totals 706 105 811 68 743 16 36 Tinton Dr. & S. 5th Ave. 1jS improvements 12 P N/A P PE 11112018 STP(U) 65 11 80 CE Yes Tieton Drive W RW 1/1/2019 STP(U) j(11' 16 120 120 T from: Tieton Dr. to: S. 5th Ave. S CN 5/1/2020' STP(U) 85 " 135 1,000 1,000 5!112020 Remove existing traffic signal and construct a T roundabout, remove and replace curb, gutter, 0 sidewalk, street lighting and drainage Totals 1,[}88 162 1.200 80 120 1,000 Agency: Yakima Six Year Transportation improvement Program Co. No.: 39 Co. Name: Yakima Co, From 2017 to 2022 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/7/16 & 6/21/16 Adoption Date: 6/21/2016 Amend Date: Resolution II Project Costs in Thousands of Dollars Federally Funded Project Identification Fund Source information Expenditure Schedule Pro Only Ci A. PIN /Federal Aid No. B. Bridge No. c Y y Federal Funding (Local Agency) RJW . °2 Z C. Project Title D. Street/Road Name or Number E a — m J m u +- Phase Start Federal Fund Federal State 'Fund State '. Local Total ---' At EnVlr, Required E. Beginning MP or Road - Ending MP or Road c > «'� ® o Code Cost by Code' Funds Funds Funds let 2nd 3rd Thru Type Date a, F. Describe Work to Be Done... F- N j d Phase ...6th (MMpaily) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17' 18 19 20 21 17 37 Y mmo Downtown Future initiatives, Phase 5 06 P N/A P PE ajlJ2f}18 OTHER 500 500 500 CE No 12 T CN $ /1f ME OTHER 5,500 '' 5,500' 5,500 from: 1st Street to: 9th Street C Install historic lighting, sidewalk modifications and S other improvements. Exact improvement area(s) to be determined Totals 61 Blow 500 5,500 14 38 F. Nob Hill Blvd. & S. 18th Street I/S Improvements 01 P 0,10 C PE 11112018 STP {U)' S0 8 58 58 CE Yes E. Nab Hill Boulevard 04 T RW 11/1/20201 1/1f2019' STP {U} 50 8 * 58! from: E. Nob Hill Blvd, to: S. 18th Street W CN STP(U) 346 ' 54 400'- 400! 1/1/2020 Widen south leg for double left turn from westbound S Nob Hill, install curb, gutter, sidewalk, upgrade traffic signal system Totals 446 70 516 58 58 400 14 39 S. 48th Ave.& Summitview Ave.Signalization 12 P N/A P' PE '1/112019 ST1 11 2T-FF-. 4 29 29 CE Yes Summitview Avenue T PW ',6J1f219 STP {S} 2 4' 29 29 from: Summitview Ave. to: S. 48th Ave. CN 1 /1/2020 STP(S) 55 1 6 35 635 1/5)2024 Install traffic signal at the intersection of Summitview Avenue and 48th Avenue, Totals 604 89 693 58 635 14 40 S. 72nd Ave. & W. Washington Ave. !j5 12 P N/A P PE 1/112018 5TP(C} 91 14 Ifts 105 CE Yes S. 72nd Avenue 06 T RAN [CN 1/1/2019 STP(C) 91 1A 10 105 from: s. 72nd Ave. to: W. Washington Ave. 0 111 /2020 STP (C) 544 86 630 630 11112620 Improve intersection by installing a traffic signal 5 system or roundabout. W Totals "726 114 840 105 105 630 Agency: Yakima Six Year Transportation Improvement Program Co. No.: a-9 Co. Name: yak!MjcD. From 2017 to 2022 City No.: 1485 MPO/RTPO: YVCOG Hearing Date: 6/7/16 & 6/21/16 Adoption Date: 6/21/2016 Amend Date: Resolution No.: Project Costs in Th"sarn IS of Dollars Federally Funded Project Identification Fund Source information Expenditure Schedule Projects Only E A. PIN/Federal Aid No. B.:. Bridge No. 16 Federal Funding (Local Agency) A/W .2 C. Project Title D. Street/Road Name or Number E .1 a U t Phase Start Federal Federal Fund Federal r Federal State State Local Total 4th Envir, Required S� fC'o d Code TFun Cost by Fund Code Funds Cost by Funds Funds 1st Sod Sid Thru Type Date 8: F. Describe Work to Be Done 6; :3 Phase P he s a 6th (MMIYY) 1 2 3 4 5 6 7 8 9 10 10 11 11 12 13 14 15 16 17 18 19 20 21 -174- 41 N. Aid-th Ave. & Englewood Ave intersection 12 p CNA P PE STp(U)---F43 7 50 CE No N. 40th Avenue T 11/1/26191 CN 6/1/2019 STPHJ) 260 401 300 300 from: N. 40th Ave. to: Englewood Replace traffic signal poles and upgrade controller. Totals 303 47 350 350 -74 -'Z Nab Hill Boulevard Sidewalk Improvements 12 P 50 RE 1/1/2020 1 11:� 9 63 —63 CE Yes Nab Hill Boulevard T �YW1/1/2021 STI:'(:; 19 '126 126 from: S. 16th Ave. to: S. 6th Street S ED 1/1/2022 STP(S) 327 51[ 378 378 1/112022 Construct sidewalk in locations where it doesn't exist So on the south side of Nab Hill Totals 489 78 567 567 14 A3 E, Yakima Ave. & Fair Ave. Signalization 12 P NW Is I:il I i I f T 1 86 I4 10Q 100 CE No Yakima Avenue T CN 6/1/20201 STP(U) 519 81 600 from: E. Yakima Ave, to.- Fair Ave. By Install traffic signal at the intersection of Yakima S Avenue and Fair Avenue. 0 Totals 605 95 700 100 600 16 44 S, 3rd Avenue & W Washington Ave. Signal 12 P W, P RE -F-F-T-]-TT210 4/1/2018 20 20720 20 SO 20 CE No S. Sail Avenue T CN 9/ 1/2018 210 21B 210 2101 10 from: S< 3rd Ave, to: W. Washington Ave. Upgrade the traffic signalization system 230 230 230 I Totals 230 230 230 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co. From 2017 to 2022 City No.: 1485 MPO/RTPO: YVCOG Hearing Date: 6/7/16 & 6/21/16 Adoption Date: 6121/2016 Amend Date: Resolution No.; Project Costs in Thousands of Dollars Federally For find Project Identification Fund Source Information Expenditure Schedule Protects Only U g A, PIN/Federal Aid No. B. Bridge No. c Federal Funding (Local Agency) R/W at C. Project Title D. Street/Road Name or Number E a. t Phase Start Federal Fund Federal State State Local Total 4th Envir, Required F. Beginning NIP or Road - Ending MP or Road Q) Code Cost by Fund Code Funds Funds Funds 1st Sun 3rd Thru Type Date F. Describe Work to Be Done 2 Phase 6th jBiRapy) 2 3 1 4 5 1 6 7 1 8 1 9 10 11 12 13 14 15 16 17 18 19 1 20 21 19 45 7&HlAvenue Improvements 61 --- -- — P 0,50 P PE 1/1/20191 STOIC) 87 )0 R 0 — 11101 CE Yes 75th Avenue 08 As RW 1/1/2020 STP(U) 173 27 0 00 0 200 from: Mead Ave. to: Nab Hill Blvd, S CHI 11112021 5TP(U) 1x0391 162 1,22DO 1,200 1/1/2021 T Construct a new two-lane roadway and widen 0 portions of existing roadway, install curb, gutter, sidewalk, street lighting and storm drainage system. _17 Totals 11298 202 1,500 100 1,400 6 S. With Avenue improvements 03 P 76 P PT' PE 1/1/2018 "/' 018 S T P Ul 6 14 100 100 CE Yes 66th Avenue 04 T BAR 1/1/2019 019 STZ) 1873 27 200 200 from: Summitview Ave. to: Scenic Dr. AS CN C, 1/1/2020 1/7 STP(U) 1,096 164 1,260 1,260 111j2020 Reconstruct and widen roadway to three lanes, install S curb, gutter, sidewalk, storm drainage system and 0 utilities. Totals 1,355 205 1,560 100 200 L260 — 77 �7 Bodkin Road Reconstruction 03 P 7— 76 P RE 1/1/2018 "C' STP(C} STP(C) 271 —7 C E N o Bodkin Road 06 T CN 1/9/1900 STP(C) STP(C) 945 TPA? 94's 106 1,1361 996 71991. from: E, Visslis Ave. to: Rainier PI, AS S Reconstruct roadway, install curb, gutter, sidewalk and storm drainage. Partner with Union Gap to install additional sewer force main. Totals 1,054 945 133 2,132 136 1,996 -7— 8 Englewood Avenue Improvements 05 P 00 P RE RE 0 STP(C) — 272 43 43 315 -315 31 315 CE Yes Englewood Avenue 06 T PAR F11112020 2 21 STP(C) 349 1 1 55 5 5 404 404 40 404 from: N. 40th Ave. to: N. SIBS Ave, AS CRI 1/1/20221 STP(C) 2,329r 363 2�692 2�692J 1/1/2022 S Widen roadway to three lanes, install curb, gutter, 0 sidewalk, street lighting and storm drainage system.,I C ITotals 2,950 461 3,411 3,411 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima_ . Co. From 2017 to 2022 City No.: 1485 MPO/RTPO: YVCOG Hearing Date: 6/7/16 & 6/21/16 Adoption Date: 6/21/2016 Amend Date: Resolution No.; Project Costs in Thousands of Dollars Federally Funded Project Identification Fund Source Information Expenditure Schedule of0jo IS Only A. PIN/Federal Aid No, B. Bridge No. Federal Funding (Local Agency) R/W C. Project Title D. Street/Road Name or Number E m V 0 Phase Start Federal Federal State State Local Total 4t Envir, Required E. Beginning MP or Road - Ending MP or Road Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd Thm Type Date L F. Describe Work to Be Done Phase 6th (MM/YY) 1 1 2 1 3 4 5 6 7 8 1 9 1 10 11 12 13 14 15 1-6 1-7 1S 19 20 21 17 49 Englewood Avenue Improvements 65 P 0.50 P PE STP'U' STP(U) 136 136 21 205(7 157 CE Yes Englewood Avenue 06 T RW rl/1/2026� 1/1,12021 1/j/ STP(U) STP(U) 173 173 27 2 I 200 from: N. 16th Ave- to: N. 24th Ave. W CN 1/1/2022 1/j/ STP(U) STP(U)] 1, 1, 4 17 54 11, 182 1,3461 1,346 111/2022 Widen roadway to three lanes, install curb, gutter, S sidewalk, street lighting and storm drainage system, water and sewer lines. Totals 1,473 230 1,703 1.703 17 50 S. ROM Avenue Improvements 04 P 30 P RE 1/1/2020 131 0 20 '6 1511 151 CE Yes S. 80th Avenue T RW 111/2021 T �38 2 59 5 90 72 441 441 1 from: Tieton Drive to: Ear Road 0 C C�N 1/l/2002021 1/j/ 0 TIB 1 667 1,68 1, 927 1,927 1/1/2022 S Widen roadway to three lanes, install curb, gutter, W sidewalk, street lighting and storm drainage system. C Totals 2,180 339 2,519 2,519 17 51 Englewood Avenue Improvements 03 P 00 P PE P ' 0 � P STP(U) 1' 2181 341 2,581 252 CE Yes Englewood Avenue 05 T RW WNJ 71/1/2020 1/,/ 0 1 1/1/2021 STP(U) STP U) 327 3 1 51 37 378 from: N. 24th Ave. to: N, 40th Ave. 06 W C C 1/1/2002 2 STTP((UU7)2,789 435 3,224 3,224 1/1/2022 Reconstruct and widen roadway to three lanes, install S curb, gutter, sidewalk, street lighting and storm 0 drainage system, Install sewer and water lines, Totals 3,334 520 3,854 3,854 17 52 88th Avenue improvements 06 P .48 - P PE P E PE 19 1/1/2019 1/1/20 STP(U STP(U) A3 -f 50 Yes 88th Avenue 12 T RW RW 1/1/2020 1/ 1/2020 STP(U STP(U) 7 52 8 6( 60 from: Tieton Dr. to: Surnmitview Ave, C 6/1,12020 STP(U) 285 4751 330 330 611/2020 G Construct curb, gutter, sidewalk and storm drainage system on the east side of 88th Avenue. T;ials 380 60 440 50 390 Agency: Yakima Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima CO. From 2 017 to 2022 City No.: 1485 MPO %RTPO: YVCOG Hearing Date: 6/7/16&6/21/16 Adoption Date: 6/21/2016 Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded @ v Project Identification v Fund Source Information Expenditure Schedule Frtaects O(�iy v E A. PIN/Federal Rid No. B. Bridge No. c W "' Federal Funding (Local Agency) R/W c � C. Project rule � m '°o a Phase , -- ° 'o. Street/Road orNUmber > N w v J v u Start Federal Fund Federal State State Local Total 4th Envir. Required c E. Beginning MP or Road- Ending MP or Road n n ? Q Code Cost by Fund Code' Funds Funds Funds 1st 2nd 3rd Thou Type Date LL a` F. Describe Work to Be Done E - M j.. a Phase .6th (MM/Yy). 1 2 3 4 5 6 7 8 9 10 '' 11 12 13 14 15 1 16 17 18 19 20 21 17 53 64th Avenue improvements 03 P 1,00 P PE 1/1/2019 STP(U} 2t7d7 32 232 232 CE No 64th Avenue 04 " T CN 111f2ft2f�' STP(U) is 249 1,849 -- 13849 from: Washington Ave. to: Nob Hill Blvd. 06 W C Widen roadway to three lanes, install curb, gutter, G sidewalk, street lighting and storm drainage system„ ' 0 O 1,800 281 21083 232 1,849 16 54 1 -82 & Lincoln Avenue Interchange 01 P NIA 0' PE 1/1/2018 STP {U} 2601 4It 3L ADO CE Yes Lincoln Avenue P RW 1/1/2019 STP(U) 173 27 20 72oo from: E.'G'Street to: 1 -82 G CIS 6(1/2020 STP(U) 1,730 27p 2.; 2,000 6/112020 Reconstruct /extend off -ramp from existing 1 -82 off ramp for Lincoln Avenue to E. 'G' Street. 2.,163 337 2500 300 200 2,000 14 55 26th Avenue Corridor Improvement 04 P 3.50 P PE 1/1/2019 STP {U }' 12D 16th Avenue T 77-7-F-77 from: SR 12 to: Washington Ave. W C G Study to determine strategies for improving the 16th 0 Avenue corridor S 120 17 137 137 14 "56 40th Avenue Corridor Improvements 04 P 3 „20 P PE 3 /aJ2id191 STP {U} 120 17 .1.:37 137 40th Avenue T from: SR 12 to: Washington Ave. W C G Study to determine strategies for improving the 40th 0 Avenue corridor, 5 Totals 120 17 137 137 Agency: Yakima Six Year Transportation Improvement Program Co. No.: 39 Co. Name: Yakima Co. From 2017 to 2022 City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/7/16 & 6/21/16 Adoption Date: 6/21/2016 Amend Date: Resolution No.: Project Costs in Thousands of Dollars Federally Funded Project Identification Fund Source Information Expenditure Schedule projects Only V A. PIN/Federal Aid NO,r' B. Bridge No. c y Federal Fu nd ing (Loco! Agency} R/W c C. Project Title m 'o c- Phase ° h o.streetlROadNameorNumber E — m a Start Federal Fund Federal State State Local Total 4th Envir, Required E. Beginning MP or Road - Ending MP or Road n a r r '0 o Code Cost b Fund Code Funds Y Funds Funds 1st 2nd 3rd Than Type Date yp I f. Describe work to Be Done �.. w o Y : = y Phase 6th (7t m } 1 2 3 4' S 6 7' 8 9 10 11 12 13 14 15 16 17 18 19 20 21 14 57 Nob Hill Boulevard Corridor Improvements 03 P 2.70 P PE STP(Ul 20 17 137 137 Nob Hill Boulevard 04 T 11,11,12019 from: 1 -82 to: 16th Ave, 0 S W Study to determine strategies for improving the Nob C Hill Boulevard corridor. G 120 17 137 137 14 58 NorthjSouth Connector to West Valley 01 P "' 6.00 P PE ,'1/1/2019 STP(U) 432 68 500 Soo CE Yes Unknown Road 04 T from: Ahtanum Rd. to: Summitview Ext. 06 W S Corridor study to determine the best location for a C north /south limited access route in West Valley. City G and County joint project. 0 432 68 500 500 14 59 S. 1st Street /Main Street CorridorImprovements 01 P 2.00 P PE 1/1/2019 STP(U) 120 17 137 137 No S, 1st Street /Main Street T from: Nob Hill Blvd. to: Barker Mill Bridge 0 S Joint project with Union Gap. Stacy to determine W strategies for improving the 1st Street /Main Street C corridor. G 120 17 137 137 I I 14� M= Agency Enter name of the sponsoring agency. County Number Enter the OFM assigned number (see LAG Appendix City Number Enter the OFM assigned number (see LAG Appendix 21.45). MPO/RTPO Enter the name of the associated MPO (if located within urbanized area) or - Major Collector RT•• (if located in a rural area). Hearing Date Enter the date of the public hearing. Adoption Date Enter the date this program was adopted by council or commission. Resolution Number Enter Legislative Authority resolution number (if applicable.) Amendment Date Enter the date this program was amended • council or commission. m7mr,=01032 Description 00- No Classification Rural (Under 5000 pop.) 01 - Interstate 02 - Principal Arterials 06 - Minor Arterials 07 - Major Collector 08 - Minor Collector 09 - Local Access Urban (Over 5000 pop.) 11- Interstate 12- Freeways & Expressways 14- Other Principal Arterials 16- Minor Arterial 17- Collector 19- Local Access 01- It construction o s'ru c" on o new alignment 02- Relocation Project 03- Reconstruction 04- Major WiJJdening g 05- Minor Widenino Mi- hm -F--t _ 1 111111111 111 Description 07 - Resurfacing 14 - Bridge Program-Speci 08 - New Bridge Construction 21 - Transit Capital Project 09- Bridge Replacement 22- Transit Operation] 10 - Bridge Rehabilitation 11 - Minor Bridge Rehabilitation 12 - Safety/Traffic Operation/TSM 13 - Environmentally Related N9 23 - Transit Planning 24 - Transit Training/Admin. 31- Non Capital Improvement 32 - Non Motor Vehicle Project 5. Funding Status. Enter the funding status for the entire project which describes t current status. I S - Project is selected by the appropriate selection body and funding has been secured by the lead agency. P - Project is subject to selection by an agency other than the lead and is listed for planning purposes. (Funding has not been determined.) k. Total Length. Enter project length to the nearest hundredth (or code "00" if not VU411WI "Z�L Eel III, C -Cable TV G - Gas CJ -Othe[ F» -Power S - SeVVer(DtherthaAageOcV-oVVAed) T -Telephone PE - Preliminary Engineering only (or Planning) RW - Right of Way or land acquisition only (or equipment purchase) CN - Construction only (or transit operating) ALL - All Phases- from Preliminary Engineering through Construction 41 NMMRREI��i BLA - Bureau of Indian Affairs Bm Bridge Replacement nrRehab. CDBG Community Development Fixed Guideways Block Grant (HUD) CMAO - Congestion Mitigation Air Quality DEMO Demo Project (Selected) Discretionary - FerryBootDiaoetiunary. Public - Rural Economic Vitality Program Lands Highways, or Scenic Byways DOD Dept. ofDefense |c Interstate Construction |K0 Interstate Maintenance NHS - National Highway System 11. Federal Funds. Enter the total federal cost (in thousands) of the phase regardless of when the funds will be spent. 12. State Fund Code. Enter the appropriate code for any of the listed state funds to be used on this project. go FTA Discretionary for Capital Expenditures 5307 - FTAUdbunAneao 5309(Bum)- Bus 5309(FG) Fixed Guideways 5309(N8) New Starts 5310 FTA Elderly/Disabled 5311 FTA Rural Areas REV - Rural Economic Vitality Program STP(C) - STP Statewide Competitive Program STP(E) STP Transportation Enhancements STP(S) STP Safety Including Hazard and RR STP(R) STP Rural Regionally Selected STP(U) STP Urban Regionally Selected STP UVSDOT use only 11. Federal Funds. Enter the total federal cost (in thousands) of the phase regardless of when the funds will be spent. 12. State Fund Code. Enter the appropriate code for any of the listed state funds to be used on this project. go CAPP - County Arterial Preservation Program PWTF Public Works Trust CHAP - City Hardship Assistance Program RAP Rural Arterial Program IPP - Transportation Partnershis Program SCP - Small City Program AIP - Arterial Improvement Program WSDOT - WSIDOT funding 20. Environmental Data Type. Enter the type of environmental assessment that will be required for this project. (This is "required" forfOdbra& fund6dpM&C � but may be filled in for state or locally funded projects.) EIS - Environmental Impact Statemenl EA - Environmental Assessment C E - Categorical Exclusion MQ a I I I [W. I I to] a 0 W., I oil 111 0 0 W] RESOLUTION NO. R — 2016 - A RESOLUTION adopting the Six -Year Transportation Improvement Program for the period of 2017 through 2022 for the construction of streets and arterials streets in the City of Yakima and amending the Metropolitan Transportation Plan. WHEREAS, the City of Yakima annually prepares, reviews and adopts a Six Year Program for the construction of streets and arterial streets in the City of Yakima for the ensuing six year period, all as contemplated and required by State RCW 35.77.010 and applicable Federal law; and WHEREAS, the City of Yakima desires to amend the Metropolitan Transportation Plan to ensure compliance with the Growth Management Act and the regional transportation plan for the construction of streets and arterial streets in the City of Yakima, all as contemplated and required by State and Federal law, and WHEREAS, after public hearings on the matter, held at the regular meeting of the Yakima City Council on June 7, 2016 and June 21, 2016, with proper public notice as required by RCW 35.77.010, the City Council finds that the plan attached hereto should be adopted as the Six -Year Transportation Improvement Program for the period of 2017 through 2022 for the construction of streets and arterial streets in the City of Yakima, now, therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA: The Six -Year Construction Program for the period of 2017 through 2022, a copy of which is attached hereto and by this reference made a part hereof, is hereby adopted as the official Six -Year Transportation Improvement Program for the City of Yakima, including proposed amendments to the Metropolitan Transportation Plan along with Street Improvements, which are also approved. ADOPTED BY THE CITY COUNCIL this 21st day of June, 2016. Avina Gutierrez, Mayor ATTEST: City Clerk RESOLUTION NO. R — 2016 - A RESOLUTION to amend the Yakima Urban Area Comprehensive Plan Capital Facilities Element to incorporate the Six -year Transportation Improvement Program (TIP) for the period of 2017 through 2022. WHEREAS, the City of Yakima annually prepares, reviews and adopts a Six — Year Transportation Improvement Program for the construction of streets and arterial streets in the City of Yakima for the ensuing six year period, all as contemplated and required by State RCW 35.77.010 and applicable Federal law; and WHEREAS, the City of Yakima desires to amend the Yakima Urban Area Comprehensive Plan Capital Facilities Element to reflect the adoption of the Six -year TIP, as contemplated and required by RCW 36.70A.070(6) to ensure compliance with the Growth Management Act and consistency of the Comprehensive Plan and the Six -year TIP; and, WHEREAS, this amendment is limited to incorporation of the projects listed in the Six -year Transportation Improvement Plan for the period of 2017 to 2022 to the Capital Facilities Element of the Yakima Urban Area Comprehensive Plan, which is contemplated and provided under RCW 36.70A.130(213) and RCW 35.77.010; and, WHEREAS, public hearings were held by the Yakima City Council on the Six -year TIP on June 7, 2016 and June 21, 2016, with proper public notice as required by RCW 35.77.010; now, therefore BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA: The adopted Six -Year Transportation Improvement Program for the period of 2017 through 2022 for the City of Yakima shall be incorporated as an amendment to the Capital facilities Element of the Yakima Urban Area Comprehensive Plan. ADOPTED BY THE CITY COUNCIL this 21st day of June, 2016. Avina Gutierrez, Mayor ATTEST: City Clerk