HomeMy WebLinkAbout12/01/2015 05B 3rd Quarter 2015 Capital Improvement Projects ReportBUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. S.B.
For Meeting of. December 1, 2015
ITEM TITLE: 3rd Quarter 2015 Capital Improvement Projects Report
SUBMITTED BY: Debbie Cook, PE, Director Utilities & Engineering
SUMMARY EXPLANATION:
Attached is the Engineering Division's 3rd Quarter Capital Improvement Projects Memorandum and Report
which includes Water /Irrigation and Wastewater Capital Improvement Projects.
Also attached is the current project spreadsheet developed by the Sewer, Water, Irrigation, Streets, Traffic
and Engineering Divisions. The current project listing assists in the planning of current and upcoming
projects. It helps the divisions coordinate their work so that, for example, a street is not rebuilt or seal coated
prior to planned underground work on the same street.
Resolution:
Other (Specify):
Contract:
Start Date:
Item Budgeted:
Funding Source/Fiscal Impact:
Strategic Priority:
Insurance Required? No
Mail to:
Phone:
APPROVED FOR
SUBMITTAL:
RECOMMENDATION:
Accept the report
ATTACHMENTS:
Ordinance:
Contract Term:
End Date:
Amount:
City Manager
Description
QUairtedy [: �ejrxxt mairraum?..
Clajpi�al IPir¢ kxts Spreods1ha.A
Upload Date
11/23/2015
11501M
Type
Bac,IkLJjP IMa eirii aII
Bac,IkLJjP IMa eirii aII
MEMORANDUM
November 23, 2015
TO: Mayor Micah Cawley
Members of City Council
FROM. • Debbie Cook, PE, Director of Utilities & Engineering
Robert Desgrosellier, Senior Engineer
SUBJECT. • 2015 Capital Improvement Projects: Yd Quarter
INTRODUCTION
This Quarterly Report is intended to provide an overview of the City's capital improvement
projects for the 3r Quarter of 2015, including current project status, milestones, and any new
developments that may significantly alter the schedules or costs of the projects. This narrative
discusses Water /Irrigation Division, Wastewater /Stormwater Division and Engineering Division
proj ects.
Railroad Grade Separations, Phase 4: Proiect Aesthetics
This project consists of constructing the "Bins of Light" art piece on Lincoln Avenue just east of
the Front Street Bridge, and constructing an elevated sidewalk on the south side of Lincoln from
1st Avenue to 1st Street. As an agreement has been reached with the Millennial Arts Foundation
and an agreement is in place with the artists, final design is underway. The plans and
specifications for the project should be completed in December, and the project is scheduled to
be advertised in early January The estimated cost for this project is around $600,000.
♦ Projected completion: 3rd Quarter FY2016
Yakima Valley Trolley Barn & Museum Preservation
Using State Enhancement funds, the City purchased the historic YVT Trolley Repair Barn and
Substation on January 31, 2008. Funding also allowed for repairs to the west and south walls and
the crane system. That work has been completed. Some funding still remains and will be used to
remove and replace approximately 120 feet of bad track starting at the intersection of Yakima
Avenue and 6th Avenue, and continue southerly along 6th Avenue. Paperwork for environmental
clearance has to be submitted specifically for this deficient crossing.
♦ Projected completion: mid -year FY2016
Tieton and 64th Avenue Intersection Improvements
This project will improve the intersection of Tieton Drive and 64th Avenue by adding a left -turn
lane for westbound Tieton Drive traffic and install a traffic signal. Funds for this project come
from a Transportation Improvement Board (TIB) grant ($783,600) and the Wal -Mart
development agreement ($200,000). The right of way needed for this project has been acquired
and the design has been completed. Bids were opened on September 24th, with Granite
Construction Company submitting the low bid of $582,900. Construction is scheduled to begin
in early spring next year.
♦ Projected completion date: 3rd Quarter FY2016
Cascade Mill Redevelopment Proiect
This project includes multiple tasks to redevelop the former 225 -acre Boise Cascade Mill.
Yakima was awarded $25 million in LIFT funding (Local Infrastructure Financing Tool) from
the State of Washington to create a Revenue Development Area that will assist in the transition
from the former mill to a mixed use economic catalyst including an estimated 4500
light manufacturing, office park, commercial, retail and entertainment jobs..
The current status of the project includes:
1. Interchange Justification Report Study (IJR), (approved by FHWA in May of 2013) is
underway to improve freeway access to I -82 and the Cascade Mill site as well as to
connect to the future "East -West Corridor Road" - Yakima County project lead. NEPA
review is currently under preparation. City of Yakima and Yakima County are proposing
to modify the IJR approach to construct ramps and bridges related to the East -West
Corridor as a first phase using local and LIFT funds. A bridge over the Yakima River and
the widening of I -82 would occur in a later phase.
2. Design of the Cascade Mill Parkway (a North to South City Boulevard -type Street that
will provide access to the mill site). City of Yakima is project lead. The project to
construct the southernmost 500 feet of the Cascade Mill Parkway, along with the
roundabout will connect Fair Avenue, Lincoln Avenue, MLK Boulevard and Cascade
Mill Parkway is currently under construction and is scheduled for completion in
November. Granite Construction Company is the prime contractor for this project. Their
submitted bid to do the work was $2,424,581.15.
3. Preliminary Design and alignment of "East -West Corridor Road" — Yakima County
project lead. The existing `H' Street corridor will be improved from North 1st Street to
7th Street as part of this project. NEPA review currently under preparation.
4. Grant funding research, permitting and options for clean -up and remediation of former
City of Yakima municipal landfill has begun with Department of Ecology. DOE has
included $20 Million in the proposed State Capital Budget for landfill cleanup.
♦ Projected completion date: Fair Avenue Roundabout completion date: 4th Quarter 2015.
Landfill cleanup, wood waste removal, right of way acquisition are pending.
North I st Street Corridor Revitalization — `N' Street to SR -12 (Phase 1)
North 1 sc Street Corridor Revitalization — `N' Street to MLK Jr. BlvtL (Phase 2)
In 2010, the City received a $25,000 planning grant through Yakima County SIED funding for
the first segment of this project; a comprehensive approach to planning for future improvements
to North First Street from "A" Street to the US- 12/I -82 Interchange. The North First Street
Improvement Study took place last year to develop a design and action plan to address potential
arterial street design alternates including an analysis of resulting traffic flow, streetscape and
2
landscape improvements, and required utility upgrades. The final study document was adopted
by City Council on October 11, 2011.
The City applied for, and received a $250,000 Surface Transportation Program (STP) federal
grant for preliminary engineering on August 23, 2012. In January of 2013, the City was awarded
$2,718,000 for the construction of Phase 1. A professional services agreement was entered into
with HDJ Design Group to develop the engineering plans and construction specifications. The
engineering plans and construction specifications have been completed. Approval of the
environmental documentation is ongoing. Originally, it was anticipated that the project would
bid in the spring of 2015. We have since been informed that the STP construction funds will not
be available in 2015, so project construction will be delayed. Emphasis will be placed on
relocating /under - grounding of overhead utilities, as well as safety and improving the appearance
of the corridor.
• Phase 2: `N' Street to MLK Jr. Blvd., construction is estimated to be $8,000,000 and will
be funded by a City of Yakima bond. We interviewed consulting firms to perform the
design and Huibregtse Louman and Associates (HLA) has been selected to perform the
design for us. They have started their work and should be completed around the end of
2015, with construction to begin in 2016. Due to the amount of work included in phase 2,
and the amount of impacts that it will have to traffic, businesses and private utilities, it
has been determined to split phase 2 into two phase. Phase 2a will perform the
construction from MLK Boulevard to `I' Street, and will be constructed in 2016. Phase
2b will perform the construction from `I' Street to `N' Street and will be constructed in
2017. It is anticipated that phase 2a will be advertised for bids in January.
Both phases of this work were included in a 2015 TIGER Grant submittal for Federal funds. The
City was not selected to receive a 2015 TIGER Grant
♦ Projected completion dates: FY2016 (and later)
2012 C
Improvements, & Lincoln Ave. Corridor Safety -
This project is funded by a 100% federal Highway Safety Improvement Program grant of
$840,000 and is divided into two pieces: Citywide Safety Improvements; and, Lincoln Avenue
Corridor Safety - N. 32nd Avenue to N. 5th Avenue.
The Citywide Safety Improvements ($400,000) will upgrade signal heads throughout the city
from 8 -inch diameter to 12 -inch diameter, as well as constructing ADA ramps along 16th Avenue
between Nob Hill Boulevard and River Road. The Citywide Safety Improvements portion of the
project has been completed/
The Lincoln Avenue Corridor Safety project will upgrade signal heads to 12 -inch diameter at 5th
Avenue, 6th Avenue and 16th Avenue, construct ADA ramps at many of the crossroads, install
sidewalk and replace sidewalk, remove trees blocking the sight distance at several intersections
and install two overhead school flashers at the crosswalk for Robertson Elementary School.
The right of way acquisitions for the Lincoln Avenue Corridor Safety has been certified by
FHWA. We are in the process of obligating the construction funds and are scheduled to go to bid
in December.
♦ Projected completion date: 3rd Quarter 2016
3
Ist/Main & Nob Hill Corridor Safe
This project is funded by a 100% federal Highway Safety Improvement Program grant of
$400,000. It is being done in conjunction with education and enforcement programs to reduce
the number of severe accidents that occur in these two corridors.
The improvements that will be made to the roadway include low cost fixes, such as, upgrading
signal heads, installing "prepare to stop" when flashing signal system, install median curbs,
upgrade /install sidewalk sections and upgrade ADA ramps, install countdown pedestrian signal
heads, install speed radar signs, upgrade illumination, improve driveway ingress and egress, and
upgrade the signal heads and illumination at Main Street and Ahtanum in Union Gap.
Bids for this project were opened on April 17, 2015. The low bid submitted by Columbia
Asphalt and Gravel was $305,290. Construction has been completed, except for some additional
work to paint the dual -faced curb and install traffic candles.
♦ Projected completion date: 4t' Quarter FY2015
West Valley Middle School Improvements
This project is funded by a federal "Safe Routes to School" grant. It includes an educational and
enforcement portion in the project as well. The improvements include installing a traffic signal
at the intersection of S. 72n Avenue and Mead Avenue, and constructing sidewalk on the south
side of Zier Road from S. 72nd to 75th Avenues. Bids for the project were opened on July 29tH
with Columbia Asphalt and Gravel submitting the low bid of $530,496.50. We have delayed
construction until the spring of 2016; or possibly during the summer after the school year.
♦ Projected completion date: 3rd Quarter FY2016
Alley Pavers
This project is funded by a federal "Congestion Mitigation /Air Quality" (CMAQ) grant. It will
pave the alleys located within the following limits: Fruitvale Boulevard (north boundary),
Lincoln Avenue (south boundary), 5th Avenue (east boundary) and 16th Avenue (west boundary).
Design should begin this spring; it is anticipated that construction will occur in 2016.
♦ Projected completion date: 3rd Quarter FY2016
Powerhouse Road Sidewalk
This project will widen the westbound lane to 14 feet, so that it will be able of function as a
shared bicycle /vehicle lane. The project will also construct curb, gutter and sidewalk on the
north side of the road. This project is funded with a $275,000 TAP Grant. Design of this project
should begin this fall with construction scheduled for the summer of 2016.
• Projected completion date: 3rd Quarter FY 2016
4
Water /Irrigation Division Capital Improvements Projects
Water Treatment Plant Intake Improvements
The project will evaluate the river and WTP intake structure for potential modifications and
improvements to maintain the existing river location and flows to into the intake. We are
currently working with Golder & Assoc. for Hydro- technical Engineering Support Services for
design, permitting, funding, construction bid and inspection support of a new intake and flood
plain stabilization structures. Ecology has issued a Watershed grant for $250,000 for this project.
Bonneville Power Authority has issues a $69,000 grant to see if the city's and the Gleed Canal
Company's diversion could be consolidated. A couple of stakeholder meetings were held;
comments from those meetings were incorporated into the design and another meeting is being
scheduled to review suggested modifications to the design and to determine the next steps to
move forward.
♦ Projected completion date: 4th Quarter FY2016
Fruitvale Canal - Nelson Dam Improvements
This project will consolidate the river diversions for Fruitvale Canal with the existing diversions
at the Nelson Dam. We are working on fish screen /intake project options. Discussions are
continuing with the Bureau of Reclamation, Washington Department of Fish and Wildlife,
Yakima County, National Marine Fisheries Service, Yakama Nation and North Yakima
Conservation District on project design and options. A water right change in point of diversion is
being approved by Ecology. Discussions with Yakima County are on -going to see how the
project fits with their flood plain restoration projects. Additional stakeholders meetings are being
scheduled.
♦ Projected completion date: On -going
Kissel Park Well Pump and Motor Replacement
The project will install a new 300 -hp submersible motor, pump and cable at the existing Kissel
Park Well site.
Competitive quotes were solicited from five (5) contractors off of the MRSC Small Works Roster
— Layne of Washington, Inc., Foremost Pump & Well Services LLC, Picatti Brothers, Inc.,
Schneider Water Services and PumpTech Inc. Two sealed quotes were received on February 23,
2015 with the low quote of $194,760.00 being offered by Schneider Water Services of Saint
Paul, OR. Pump and motor are currently on order and expected to be installed November 2015.
♦ Project completion date: 4th Quarter FY2015
5
Wastewater Division Capital Improvements Projects
Industrial Wastewater Line Extension
Wastewater division continues to actively pursue the separation of high strength food process
water (industrial waste) from the domestic sanitary sewer collection and treatment process. To
serve existing food processing businesses this project extended the existing Industrial Waste (IW)
line to Noel Canning and Jewel Fruit. This new line is also available to future food processing
businesses. Huibregtse Louman Associates (HLA) provided construction administration, design,
and inspection. Construction began on March 2014 and was timed with Noel Canning's
installation of the private side service to the new main. POW was awarded the project &
construction is complete except final paperwork. With this project we also relined four (4)
sections of domestic sewer main adding structural stability to the deteriorated pipe. The project is
complete.
♦ Projected completion date: Completed
Pipe Rehabilitation — General
The Wastewater Division will be identifying pipeline segments that may be rehabilitated through
manhole to manhole cured -in -place pipe repair. Eight lines have been identified to date as
candidates. The project timing and size will be dependent on funding available for the project.
Wastewater has identified pipelines for cured -in -place point repairs and has begun project
specifications and descriptions for the pipe repairs. Final scope of the project will be determined
after a cost evaluation. Budget has been approved to start a pipeline rehabilitation program to
address the old and deteriorating wastewater collection system. The program will consist of pipe
and manhole rehabilitation and replacement along with addressing access issues throughout the
city. Scoping activities are under way. Construction will be ongoing starting in 3rd quarter 2015
until the system conditions are addressed. The project will stabilize current conditions of the
pipe system and reduce infiltration of groundwater which will save treatment costs in the future
and limit the need for upgrades to the Wastewater Treatment Plant.
♦ Projected completion date: on -going
Collection System Plan Update & Initial Stormwater Comp Plan, Wastewater Facility Plan
With the adoption of the new stormwater regulations a comprehensive Stormwater System Plan
is needed and will be implemented along with the Wastewater Facility and Collection System
Plan Update.
Akel Engineering Group, Inc. has completed capacity models for both systems and completed a
capital projects priority projection based upon the capacity model.
Design of stormwater improvements for N. 1st Street and Randall Park projects are under way
The FCS Group completed a Wastewater and Stormwater rate structure and a wholesale
customer billing model that meets the specifications of the 3 -Party Wholesale Service
Agreement.
6
The last Wastewater Facility Plan was completed in February 2004. This project updates the
current facility plan by providing current information on the existing wastewater facility and
collection system infrastructure, regulatory requirements, future loadings, operation and
maintenance, future capital improvements, rate structure and revenue forecasting. The updated
facility plan will incorporate the completed Akel collection system and stormwater system
documents.
CDM Smith (consultants) has been selected to prepare the Wastewater Facility Plan. Contract
negotiations for the Professional Service Agreement are in progress. A completed Professional
Service Agreement is anticipated during the 4th quarter of 2015.
♦ Projected completion date: FY2016
Levee set back Proiect, Greenway Trail Re -route and new Wastewater Outfall
The Gap to Gap project for flood plain restoration included the relocation of the Wastewater
Treatment Plant outfall. Yakima County selected a consulting team to conduct NEPA/SEPA
review of overall Gap to Gap project. Design plans from the Corps. of Engineers are in progress.
♦ Phase I construction completed: 4th Quarter FY2013
♦ Phase II: Floodplain Restoration Outfall Alternative: The project is physically complete
and in service. As -built drawings have been provided and accepted. Quarterly progress
reports have been submitted to both DOE and RCO for the 2015 reporting periods. Pay
requests from the eligible grants have been submitted. Final reports as well as stewardship
plans are in progress. Construction was completed during the second quarter of FY2015.
♦ Projected completion date: Completed
♦ Phase III: Outfall Channel Piping: The interim, open channels installed under Phase II
will be retrofitted with enclosed piping between the existing discharge structures and the
Riparian area southeast of the treatment plant. Consultant interviews have been completed
and the project is pending contract negotiations
♦ Projected completion date: FY2017
Fine Screen PMiect:
This project enables the plant to comply with new biosolids regulations requiring a maximum of
3/8 aperture screens to reduce manufactured inerts in the biosolids generated at the facility. The
project design was halted due to funding limitations. An alternative to meet the regulations is
being pursued. This approach includes replacing the existing 1 /z" aperture bars in the screens
with 3/8" and rebuilding the drive units and washer compactors.
Washer compactors have been rebuilt by Wastewater Maintenance personnel. Bar racks have
been procured and scheduled for installation early February 2015. For additional savings, the
installation of the new bar racks will be directed through professional services and conducted by
Wastewater Maintenance personnel. Bar screens have been installed, project is complete.
♦ Projected completion date: Completed
7
Speedway Interceptor and Beech Street Lift Station PMiect:
The existing 36 inch gravity sewer interceptor located between Beech Street and Nob Hill on the
west side of I -82 is currently experiencing excessive sedimentation due to flat and adverse pipe
slopes with slow fluid speeds and intermittent reverse flows. As part of the 2013 wastewater
Master Plan, improvements to that interceptor were identified. The improvements include
insertion of two different sized, parallel force mains inside the existing pipe as well as the
construction of a new lift station on Beech Street south of Kiwanis Park. Flows currently
reaching the Race Street lift station will be intercepted at Beech and 15th and be redirected into
the new lift station. The Race Street lift station will be decommissioned. The parallel pipe
system will allow for conveyance of existing flows at higher speeds as well as provide a
mechanism for expanding service to the Boise Cascade Mill Site region without increasing the
sedimentation problem as flows from that area develop. It will also allow for future phased
construction of improvements that will eliminate existing bottlenecks in the sewer interceptor
system west of Washington Middle School.
Included in this project will be minor upgrades to the electrical elements of the Rudkin Road lift
station and installation of an emergency bypass connection along with modifications to the
existing junction box at the intersection of Rudkin Road and East Viola Ave.
RI-12 Engineering has been selected as the design consultant. The professional services contract
has been completed and designs are currently under way. Initial design submittals are anticipated
during the 4th quarter of 2015.
Stormwater Capital Improvements Projects
None
E:3
PRIVATE PROJECTS (Current Listing)
Listing private developer projects shows the amount of private projects that are "on the books"
and pending or under construction with some (not all shown) that go back several more years.
These projects have all been approved since February 2008 and are either pending construction,
under construction, started but not completed or recently completed. The projects, most recent at
top, include:
Project Name Address Permit Type Status
2015
Cascadia -Pear Tree Assisted Living
4130 Englewood Ave.
Eng- Site -Imp
a pprvd for const.
Tri -Plex
1110 ST Johns St.
Eng- Site -Imp
apprvd for const.
Howard Maggard Duplex's
1706 Grant Ave.
Eng- Site -Imp
a pprvd for const.
Tahoma Square Ph. 2
1829 S. 1st St.
Eng- Site -Imp
in review
Audio King
703 E. Nob Hill Blvd.
Eng- Site -Imp
in construction
D. Martinez Comm. Bldgs
506 -508 W. Nob Hill Blv
Eng- Site -Imp
in review
Baiter Sewer Extension
502 S. 90th Ave.
Sewer
in review
E. Lee Sewer Force Main
7706 Occidental Rd.
Sewer
in review
YVMH Parking Lot Expansion
212 S. 29th Ave.
Site Improvements
in review
YVCC Ops and Admin. Bldgs
1211 W. Prasch Ave.
Eng- Site -Imp
in construction
47 Hops Offic Bldg.
2516 S. 23rd Ave.
Site Improvements
in construction
Ziad Awwad Conv. Store
801 S. Fair Ave.
Eng- Site -Imp
apprvd for const.
Washington Fruit Waterline Relocate
1007 River Rd.
Eng- Site -Imp
in review
Habitat for Humanity
1009 N. 2nd St.
Eng- Site -Imp
apprvd for const.
Hollingbery Site
212 N. 1st Ave.
Eng- Site -Imp
apprvd for const.
Viola Improvements
2008 W. Viola Ave.
Eng- Site -Imp
apprvd for const.
Rainier Square
2706 W. Nob Hill Blvd
Eng- Site -Imp
in construction
Murrang Short Plat
80th / Midvale
Eng- Site -Imp
apprvd for const.
Scenic Estates
80th / Scenic
Eng- Site -Imp
apprvd for const.
Meadow View Ph. 2
83rd / Westbrook
Eng- Site -Imp
apprvd for const.
Ahtanum Crossing
64th / Ahtanum
Eng- Site -Imp
in review
Autobody Shop
807 S. 3rd St.
Eng- Site -Imp
apprvd for const.
Tahoma Square Ph. 1
1903 S. 1st St.
Eng- Site -Imp
in construction
DMF Investments
3201 Powerhouse Rd.
Eng- Site -Imp
apprvd forconst.
Gravbrot Short Plat 3700 Fairbanks Ave. Eng- Site -Imp apprvd for const.
2014
Washington Fruit - Office
1007 River Rd.
Site Improvements
in construction
Washington Fruit - Apple facility
1007 River Rd.
Site Improvements
in construction
Washington Fruit - N. 6th Ave.
1007 River Rd.
Eng- Site -Imp
in construction
Frosty Pack
2820 River Rd.
Site Improvements
in construction
Walmart Retail Strip
6410 W. Nob Hill Blvd
Site Improvements
in construction
9
AFFIRMATIVE ACTION GOALS & WIM /DBE PARTICIPATION
W/M/DBE utilization has been included in the past but is not included with this report.
The Engineering Division continues to request apparent low bidders of public works contracts to
document their efforts to achieve the City of Yakima's goal of 10% MBE, WBE or DBE
participation goal prior to contract award. However, changes in state law due to the passage of
Initiative 200 prohibit certain practices by contracting agencies (i.e. the City) for the award of
public works projects such as requiring W/M/DBE subcontracting. While some contractors have
voluntarily reported such information in the past, we have not received any such reporting last
year.
Although we do not receive such information voluntarily, the City must still meet certain of these
federal requirements and each contractor must comply with the Standard Specifications that are
included on each City Public Works Contract. The City is responsible to:
• Conduct pre - construction conferences during which EEO and City policies are discussed
with the contractor.
• Monitor on -site compliance with the EEO and City policies.
• Ensure our contractors locate, qualify, and increase the skills of minority groups, women
employees, and applicants for employment as required by City policies.
• Ensure the preparation of required EEO and related reports.
10
Proj
Proj.
Impacted
Constrctn.
Notes
Type
No.
Lead Division
Project Name /Location
Description of Work
Project Lead
Divisions
Start Date
StatustSchedule
1112312015
1818
Engineering
Lincoln Avenue Underpass;
Raised Sidewalk &
Engineering,
2015 - sidewalk
Sidewalk design underway;
Project back in queue, plans are at 95 °k;
1
CIP
Phase
UPDATED
Phase IV
Bins of Light
Brett Sheffield
Traffic Engineering,
2016 - bins of light
Bins of Light Design and manufacture of
Work to be started spring of 2016
IV
Raised Sidewalk & Bins of Li ht
Streets
Bins of Light Panels also underway
New rights of way,
g y, public
Engineering, Streets
1st Roundabout (at Fair Ave. & 10th St.)
'15;
This north -south Blvd. style street includes
Special Projects
utilities, roads, lighting,
Joan Davenport/
& Traffic Eng.,
Roundabout -
completion is 96 °k &should be completed in
3 roundabouts. Design work includes road design
2
CIP
2337
(& Engineering)
Cascade Millsite Parkway
roundabouts, sidewalks,
Brett Sheffield
Water /Irrigation,
Fair/ 10th St.
Ribbon cutting was on 11/17/15
and realignment in vicinity of East -West corridor
pathway,
p y, infrastmcture
Wastewater /Storm
Started in May
Granite Construction, Yakima, E contractor.
in response to BNSF concerns.
Funded w /LIFT funds & 50 /50 SIED Grant /Loan
Phase 1: Entire Site
Engineering, Streets
Consultant, Landau Assoc's, will gather data for
3
CIP
2355
Engineering &
Brett Sheffield /
& Traffic Eng.,
tbd
evaluation of landfill area and plywood plant site in
Current data effort in coordination with
(Special Projects)
Phase 2: Southern portion
(Joan Davenport )
Water /Irrigation,
response to DOE concerns about groundwater and
DOE Voluntary Compliance Program
Wastewater /Storm
contaminants. Excludes landfill area
East -West Connector;
"H"
New rights ofway, public
Engineering, Streets
Consultant (H.W. Lochner) hired for
4
CIP
2336
Special Projects
St. alignment from 1st St.
utilities, roads, lighting,
Brett Sheffield /
& Traffic Eng.,
2017?
NEPA review underway.
creation of design alternatives and
& Engineering)
( g g)
to Terrace Heights;
g
signal(s), sidewalks, pathway,
p y,
(Joan Davenport)
Water /Irrigation,
Yakima County is project lead
NEPA review (environmental)
Through Yakima Resources prop.
infrastructure
Wastewater /Storm
Interchange Justification Report
Working with WSDOT for
City and County developing a plan to implement
WSDOT and FHWA have given
5
CIP
2356
Special Projects
modification of
modification of Yakima Ave /
Brett Sheffield /
Engineering, Streets
portions of the improvements in a phased manner
preliminary approval to this concept.
& Engineering)
( g 9)
-82 and Yakima Avenue
-82 and
-82 Interchange
Joan Davenport
( P )
& Traffic Eng.,
9 ,
in ocon tr defer WSDOT changes and
Still working through the approval process
n earl
construction interchange portion early.
Engineering, Streets
Federal funding of $2.7 M deferred for Phase 1.
"N"
Special Projects
North 1st Street Corridor
Design and construction of
Brett Sheffield /
&Traffic Eng.,
City will proceed with Phase 2 using City bond.
Engineering design for this Phase ( St. to -82) is
6
CIP
2340
(& Engineering)
Revitalization;
sidewalk, landscape and utility
(Joan Davenport )
Water /Irrigation,
2017?
In June we submitted for TIGER Federal Grant for
on hold due to delay in identified Federal Funding.
Phase 1: I -82 to St.
upgrades
Wastewater /Storm
both phases, MILK to "N" & "N" to I -82
This section is anticipated for construction in 2017.
Design and construction of
Engineering, Streets
Huibregtse, Louman Associates, (HLA) of Yakima
Special Projects
North 1 st Street Corridor
sidewalk, landscape and utility
& Traffic Eng.,
was awarded the design contract;
Engineering design for Phase 2 (MILK to "N" St.)
7
CIP
2390
(& Engineering)
Revitalization;
upgrades; adding bike lanes
Brett Sheffield
Water /Irrigation,
2016
In June we submitted for a TIGER Federal Grant for
is underway, will be completed this year, be bid over
phase 2: MLK to'N' St.
removing parking; relocating
Wastewater /Storm,
both phases, MILK to "N" & "N" to I -82,
winter with construction starting in spring of 2016.
overhead utilities
Private Utilities
I but were not successful
Tieton Drive and 64th Avenue
Reconstruct intersection, widen
Project was bid; Granite Construction is low bidder
8
CIP
2282
Engineering
Intersection
for additional lane on Tieton
Drive; add signal
Randy Talbert
Engineering, Streets
2015
at $582,900. Funded by TIB grant for $784K
plus $200K of Wal -Mart mitigation;
Construction will start in the spring of 2016
Lincoln Ave Corridor Safety-
Sidewalk, ADA Ramps,
Design at 82%
9
CIP
2344
Engineering
N. 32nd Ave. to N. 16th Ave.
overhead school zone crossing
Brett Sheffield
Engineering, Traffic
2015
RANay has been acquired;
Funded by a 100% Federal Grant
flashers& other safety imp's
advertise over winter /construct in 2016
1st Street &Nob Hill Corridor
Median barriers, signal
Brett Sheffield
Work is 98% complete. Working through final
Federal Grant includes: ped. countdown timers;
10
CIP
2357
Engineering
Safety Improvement Project
upgrades; sidewalk &ADA
Randy Talbert
Engineering, Traffic
2015
punchlist items to complete the work.
Usignal signal
ramps at various locations
Changed out signal heads to make them LED
to
Paving Gravel Alleys:
ngmeenng,
Funded by
11
CIP
? ?�
Engineering
Area bound by: Fruitvale to Lincoln &
Grade and chip -seal
Brett Sheffield
Streets,
2016
Design to start in winter 2015/16
Congestion Mitigation &Air Quality funding
5th to 6th Avenues
existing gravel alleys
Water /Irrigation,
Wastewater
(CMAQ)
Construct Traffic Signal on
Engineering,
Project awarded to Columbia Asphalt;
12
CIP
2380
Engineering
West Valley Middle School
72nd Ave. & Mead;
Brett Sheffield
Streets,
2015
work to start in June 2016 after school is out.
Safe Routes to School funding ($544,000 grant)
Vicinity Improvements Project
Sidewalk on south side of
Traffic Eng.,
Signal to be constructed using mostly surplus signal
Project total: $604,000
Zier Road, 72nd to 75th Ave
Wastewater
equipment
Powerhouse Road Sidewalk;
curb & gutter,
Engineering,
Need to start with surveying project area.
Funded by $275,000 grant from
13
CIP
Engineering
Canyon
800' west of Pecks Can on Road
sidewalk and storm drainage
Brett Sheffield
Streets,
2016
Design to start over winter 2015/16
Transportation Alternatives Program (TAP)
to Cowiche Canyon Road
Storm
14
CIP
2153
Engineering
YVi System Restoration
Remove and repair approx. 100
Bob Desgrosellier
Engineering,
2016
Prior Car Bam and other work was completed,
We have to amend existing federal submittals to
( 6th Ave. vicinity Yakima Ave. )
feet oftrolley track
Streets
leaving approx. $60K for track repair
include the proposed work within federal regulations
E. Nob Hill Blvd & Fair Avenue,
Widen intersection all 4 legs;
Brett Sheffield /
Engineering, Traffic,
Design only at this time beginning 6/2008;
Current funding for design only;
15
CIP
2143
Engineering
Intersection Improvements
purchaser /way; newsignal
(Randy Tabert)
Wastewater,
Design only
Search for funding on -going
(Drainage improvement slated for this intersection)
Wastewa ation
Weapplied for STP funding
16
CIP
? ? ??
Engineering
Kissel Park
Resurfacing Tennis Courts
Randy Talbert /
Engineering,
20151
Possible tennis court surface rehabilitation
Will pursue design / construction
Tenn is Court Resurfacing
Ken Wilkinson
Parks
by city forces
after receiving direction
17
CIP
2354
Engineering
Capitol Theatre
Safety Improvements
Bob Desgrosellier
Engineering,
2015
Aisle lights are being ordered; cable brackets are
Replace aisle lighting; add overhead cable runs;
Safety ra rovements
Y P
Capitol Theatre
P
otherwork is forthcoming
pending, 9
Replace main lobby & mezzanine lobby carpeting
P Y Y P 9
Relocating Visitor Center from
Relocate Visit or Center from
Joan Davenport/
Engineering,
Design complete. Will rebid over the winter;
Bid twice in 2015 with no results;
18
CIP
2403
Engineering
Fair Ave. to 9th St. &Yakima
Fair Ave. to 9th St. &Yakima
Brett Sheffield
Convention Center
2016
Work slated for completion prior to Memorial Day
We rebuilt the bid package and will rebid.
onto existin Cit roe
Visitor Info Center
Tiger Oil Properties Remediation:
Work with DOE to test these
Brett Sheffield /
Work Work with DOE and our consulting firm continues;
The property at 24th & Nob Hill Blvd.
19
CIP
2389
Engineering
East Nob Hill Blvd; North 1st St.;
City properties, remediate soils
Joan Davenport /
CED
2015
24th & Nob Hill location has been completed.
is waiting to be cleared for public sale
West Nob Hill Blvd
and water as needed
Bob Desgrosellier
Three more locations to be completed in the future
YPAL Building Remodel
Remodel interior of
Engineering ,
Phase 1: Done (windows, siding, exterior paint)
Planning to start the interior work in December,
20
CIP
����
Engineering
North 4th Street
YPAL Building
Brett Sheffield
�,PD
December 2015
Phase 2: interior paint, new drop ceiling, carpeting
running through March 2016
in SW and NW areas of the building)
Proj
Proj.
Impacted
Constrctn.
Notes
Type
No.
Lead Division
Project Name /Location
Description of Work
Project Lead
Divisions
Start Date
StatuslSchedule
1112312015
NEW!!!
Work
Work with — to release City
Brett Sheffield /
The project is the approximate 2,000 feet of creek
Discussions has anticipated work occurring after
21
CIP
vvvv
Engineering
Lower Cowiche Creek Project
property for Cowiche Creek
Rich Sanislo
Engineering
2017 or later
from SR -12 downstream to the Naches River
any modification to Nelson Bridge Irrigation Intake
Conservancy
Modification
Increase the existing Plaza and
Sean Hawkins /
Economic
April 2015 Council authorized a professional
Gustafson Guthrie Nichol (GGN) will prepare design &
22
CIP
? ? ??
Engineering
Downtown Yakima Central Plaza
surroundings into a world -class
Debbie Cook /
Development,
2016 -
services contract for engineering and design.
construction doc's; and to provide construction
event center
Brett Sheffield
Engineering,
thru 2017
Design is to be completed by Spring 2016;
administration services at such time as the City
Streets, Planning,
Bidding and start of construction: 2016
Council chooses to proceed with the construction
58 acre site; Fields: 17
Economic
The intent is to collaborate in the design, development
NEW!!!
Multi -Sport Complex with
soccer /multi -sport; 14 FIFA
Sean Hawkins /
Development,
On 4/7/15 City Council authorized a professional
and operation of a world -class Yakima Sports
23
CIP
? ? ??
Engineering
SOZO Sports Central
sized grass; ti FIFA sized
Debbie Cook
Engineering,
? ? ?
services contract for engineering and design work.
Complex consisting of soccer /multi -sport fields and an
t hta
S. 38th Avenue just north of Ahtanum
lighted synthetic turf; Sports
Streets, Planning,
indoor sports facility
Campus & other facilities
Downtown Parking Lot Lighting;
Economic
Pkg lot on 2nd St. at YCTV has been upgraded with
Lighting was upgraded by City Lighting Crew;
NEW!!!
Barrel House parking lot;
Installing and upgrading parking
Sean Hawkins /
Development,
new LED lights; Pkg Lot north of Probation Building
Pole placement and underground wiring
24
CIP
? ? ??
Engineering
YCTV parking lot;
lot lights
Bob Desgrosellier
Engineering,
2015 Summer
has six new LED pole- mounted lights. Pkg Lot at
at Barrel House was be contracted out.
Probation pkg lot
Traffic
Barrel House received 4 new LED pole- mounted
Work was completed for approximately one -half ofthe
lights plus new LED wall -packs
cost of budgeted amount.
NEW!!!
Safe Routes to School Sidewalks:
Install new sidewalk in the
Summer 2016
This project was recently awarded through the Safe
25
CIP
....
Engineering
Adams Elementary School &
vicinity ofthe schools.
Brett Sheffield
Engineering
at the earliest
Routes To School Program
Washington Middle School
(Locations forthcoming)
NEW!!!
Safe Routes to School Sidewalks:
Install new sidewalk in the
Summer 2016
This project was recently awarded through the Safe
26
CIP
����
Engineering
Garfield Elementary School
vicinity ofthe school.
Brett Sheffield
Engineering
at the earliest
Routes To School Program
(Locations forthcoming)
The improvements are identified as part ofthe long
Slipline existing interceptor with
RH2 has been selected as the Design Engineer.
term master plan. They are needed to address
27
CIP
2416
Wastewater
Speedway /Race street Interceptor
newforce mains and new lift
Engineering/
Wastewater
2015/2016
The contract has been signed. Designs are
adverse flow conditions and reroute the flows from the
Phase II
station.
Jeremy Hoover
anticipated to be complete in the 2nd quarter 2016
Fair Ave basin as well as parts ofthe 2nd Ave. basin
with construction to begin in the 3rd quarter.
and allowfor inclusion ofthe flows associated with the
redevelopment ofthe sawmill area.
wanewaeencoleman
Jeremy Hoover/
eng meenng /COrney
update of plan to account for recently constructed
28
CIP
2268
Wastewater
WW Facility plan update
Wastewater /Facility
W
Debbie Cook
Engineering /Pha .m
Engineering /Br , and
NA
CDM Consulting was selected for design
elements and planned improvements
Caldwell /Kennedy Jenks
29
CIP
Wastewater
Riparian Outfall Project 1
Wastewater /Facility
Marc Cawley Dana
Wastewater
7/1/13
Work is complete;
Kallevig
Dana is working on closeout of project.
Marc Cawley/
Identify and prioritize pipe segments.
30
CIP
Wastewater
Pipe rehabilitation /various
pipe re -line
Jeremy Hoover
WastewaterNVater
2014 March
Bid awarded to POW Construction.
Project complete.
Pipeline has been re- lined.
installation of underground piping to enclose the
31
CIP
2327
Wastewater
Outfall Channel Piping
Wastewater /Facility
Jeremy Hoover
Wastewater
Late 2016
Consultant interviews scheduled for 10/21/15
existing approximately 1,100 foot long effluent
channels to include inlet and outlet structures
City's working w /USBR & HDR on fish screen
Water /Irrigation,
/intake project options. Assessment received 6/13
Applied to DOE for point of diversion change to Nelson
Move Point of Diversion
Rich Sanislo /
USBR, Yakima
w /design alt's & recommendations. HDR finalized
Dam. Point of
32
CIP
2010
Water /Irrigation
FruitvIm Canal Diversion
(Improving Nelson Dam fish
Dave Brown /
County, WDFW,
2015
report & options; met stakeholders 9/13
Diversion change on public notice
Improvements
screen for additional water)
Mike Shane
North Yakima
Fi n
discuss options. Final H D R report based on
7/13/12 and 7/20/2012.
Conservation District
comp review on- going. Working
US BR project is out offunding.
Yaki a Couolder
with Yakima County to review coordination with
flood plan restoration project.
33
CIP
2288
Water /Irrigation
Misc. waterline improvements.
Water facilities impacted
Mike Shane /
Water /Irrigation,
2014/15
On -going coordination with other projects
Majority ofwork to be completed by in -house staff.
by mist. projects
Emilio Lopez
Streets, En g.
Proj
Type
Proj.
No.
Lead Division
Project Name /Location
Description of Work
Project Lead
Impacted
Divisions
Constrctn.
Start Date
StatustSchedule
Notes
1112312015
Working with Golder & Assoc. for Hydrotechnical
Engineering Support Services for design,
permitting, funding, construction bid and inspection
Modification of river intake;
support of new intake and floodplain stabilization
Naches River WTP Intake
Possible improvements in river
Dave Brown,
structures. Conceptual design for new river
Ecology has issued a Watershed grant for $250,000
34
CIP
2335
Water /Irrigation
Improvements
to maintain existing location
Mike Shane
Water /Irrigation
2014/15
structures was provided and foal design is
for this project.
and flows to intake
underway. Additional stakeholder (TAG) meetings
to be scheduled determine final design criteria.
Yakima County to survey area and water levels
around intake to provide additional information to
stakeholders regarding design.
Solicited quotes from 5 contractors for removal and
Replacement
t of a
of existing rebuilt
replacement of motor Feb. 2015. Received two
35
CIP
2350
Water /Irrigation
Kissel Park Well Repair
pump and motor with
Dave Brown, Jets
Water /Irrigation
2015
quotes. Project awarded to Schneider Water
Schneider Water Services low bidder at $194,760.00
new pump and motor
Bond, Mike Shane
Services. Pump and motor on orderwith expected
delivery fall 2015. Installation completed 11/16/15.
Processing project acceptance.