HomeMy WebLinkAbout07/20/2010 12 2010 2nd Quarter Capital Improvement Projects Report BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. /2,
For Meeting of July 20, 2010
ITEM TITLE: 2010 2nd Quarter Capital Improvement Projects Report
SUBMITTED BY: Michael Morales
Department of Community and Economic Development
CONTACT PERSON /TELEPHONE: Brett Sheffield, PE, Chief Engineer, 576 -6797
SUMMARY EXPLANATION:
Attached is the Engineering Division's 2nd Quarter Capital Improvement Projects Memorandum
and Report which includes Water /Irrigation and Wastewater Capital Improvement Projects.
Also attached is the current project spreadsheet developed by the Sewer, Water, Streets, Traffic
and Engineering Divisions. The current project listing assists in the planning of current and
upcoming projects. It helps the divisions coordinate their work so that, for example, a street is not
rebuilt or seal coated just prior to planned underground work on the same street.
As reported in January con i
p y t Hued and new construction and construction administration
for 2010 is as follows:
Engineering: $25,000,000
Water: $ 3,000,000
Irrigation: $ 2,600,000
WasteWater Collections: $ 1,670,000.
WasteWater Plant: $ 3,600,000
Total: $35,870,000
SEE ATTACHED
MEMORANDUM AND REPORT
Resolution Ordinance Contract _Other (Specify) Memorandum and Report
Funding Source
APPROVED FOR SUBMITTAL: °o
• City Manager
STAFF RECOMMENDATION: Accept Report
ID BOARD /COMMISSION /COMMITTEE RECOMMENDATION:
COUNCIL ACTION:
1 -- July 14, 2010
•
MEMORANDUM .
• July 20, 2010
TO: Mayor,Micah Cawley
Members of City Council
FROM: Michael Morales, Director of CED .
Doug Mayo, PE, City Engineer
SUBJECT: 2010 Capital Improvement Projects: 2nd Quarter
INTRODUCTION
This Quarterly Report information is intended to provide an overview of. the 2nd Quarter
for capital projects scheduled for 2010, including current project status, milestones, and
any new developments that may significantly alter the schedules or costs of the projects.
This narrative report `includes Water /Irrigation Division and Wastewater Division
Capital Improvement Projects along with the Engineering Division.
II CAPITAL IMPROVEMENT PROJECTS
RAILROAD GRADE SEPARATIONS; LINCOLN AVENUE (& MARTIN LUTHER
KING JR. BLVD.) 1ST STREET TO 1ST AVENUE; PHASE 2.
This project consists of re- constructing Lincoln Avenue so the roadway will pass
beneath the existing BNSF railroad tracks. It also includes constructing a bridge for
Front Street that will bridge over Lincoln Avenue. Phase 1 of this project, which
relocated utilities for both underpasses, was completed in the fall of 2007. All of the
right -of -way required for both underpasses has been acquired. Phase 2 of this project,
which constructs the Lincoln Avenue underpass, was awarded to Apollo, Inc. of
Kennewick, on February 3, 2010. Construction began in March and this Phase should be
completed in about 15 months. Lincoln Avenue traffic was detoured onto MLK
(reconfigured for two way traffic) on June 2, 2010; the BNSF shoofly was completed at
the end of June. Partial excavation for the Lincoln Avenue Underpass, along with
construction of the secant pile wall and bottom seal have begun. Design of Phase 3, the
MLK underpass, is 95% complete and, with the favorable bidding environment, the
funding shortfall for this phase is less than $2,000,000. We anticipate getting the
remaining funds and hope to go out to bid on the MLK underpass in late 2010 or early .
2011. With this scenario construction would begin on MLK once the Lincoln Avenue
Underpass is complete.
• ♦. Projected com'"letion date for Lincoln Avenue Underpass: 3 Quarter F 2
p p Q e Y 011 ,
_ . . .
. .
WASHINGTON AVE
0
NUE-BNSF BNSF CROSSING UPGRADE
This project consists of upgrading the signals and improving the track crossing by
installing new concrete crossing pads. The work is to be constructed by BNSF. A Notice
to Proceed was sent to BNSF on August 5, 2009. BNSF has installed the new crossing
signal. They have not yet replaced the track panels. This should be completed during
the next couple of months.
♦ Project completion date: 3 Quarter FY2010
EAST NOB HILL BLVD. & FAIR AVENUE INTERSECTION RECONSTRUCTION
Design for the complete intersection project has been funded by federal STP funds. The
full project will consist of widening the intersection and installing a new mast -arm
signal. The southeast corner frontage improvements were constructed as part of the
Fiesta Foods development, using SIED and REET 2 monies for a portion of the cost. Due
to design demands on the Engineering Division for funded construction projects this
project design will be used as .a filler project for engineering designers.
♦ Project design completion date: This 'filler work' will extend into 2010.
YAKIMA VALLEY TROLLEY BARN & MUSEUM PRESERVATION
Using State Enhancement funds, the City purchased the historic Yakima Valley
Transportation Company Trolley Repair Barn and Substation on January 31, 2008.
Environmental documentation approval has been received to make repairs to the west
and south walls and crane system. Bids to make repairs to the trolley barn were
received on March 12, 2010, with G.M. McClure construction submitting the low bid of
$119,786.88. The majority of the work outlined in the plans has been completed. During
construction, other needed repairs were noted, which have been added to the project. It
is anticipated that construction will be completed in late July. Other rehabilitation items
include repair and upgrade of the barn include masonry repairs and installation of fire
and smoke alarms in the substation and the barn. Depending on funds, the scope
includes restoring portions of the 6 -mile track and overhead wire system that were not
previously done as parts of other projects.
♦ Project completion date: 3rd Quarter FY2010.
O
2
WILLIAM O. DOUGLAS TRAIL, 6TH AVENUE & BRIDGE DECK CROSSING
• This State Enhancement Grant project constructed a 10 -foot wide asphalt pathway along
the west side of 6th Avenue from Hathaway, approximately 0.8 miles in length, which
ties into the Greenway,pathway. This new pathway connects the Fruitvale Boulevard •
area to the Greenway path at the Naches River and will also provide a pedestrian /bike
linkage to the WestTowne Center — Riverside Mall. The 6th Avenue pathway project
was advertised on January 13, 2010 and bids were opened on February 3, 2010. Belsass
and Smith, out.of Ellensburg, submitted the low bid of $259,165. Construction.began on
March 15th and has been completed. We are investigating our limited options for
expending remaining funds.
• Project completion date: 4th Quarter FY2010.
WILLIAM O. DOUGLAS TRAIL BRIDGE RESTORATION AND TRAILHEADS
The purpose of this State Enhancement Grant project was to restore the YVT Naches
River Bridge including cleaning, rust removal and painting, along with filling in
William O. Douglas Trail gaps by acquiring right -of -way adjacent to nineteen private
parcels and to add interpretive signing. The right -of -way plans detailing the needed
property acquisition for the pedestrian /bike pathway have been approved by.WSDOT
® and right of way acquisition nearing completion. Some of the owners of the properties
that were included in the original right -of -way plans are not willing sellers, so we have
modified the location of the trail and right -of -way plans. We have executed an
agreement allowing us to hire Yakima County to help us in the acquisition of the parcels
in the Cowiche Canyon.
Long Painting Co. completed cleaning and painting the YVT Trolley Bridge in October
of 2009.
• Project completion date: 4th Quarter FY2010. .
PUBLIC WORKS PARKING LOT RECONSTRUCTION PROJECT
A 2007 budget policy identified the need for $1,000,000 to complete the three-year
program to replace and restore the subgrade and pavement at the Public Works
Complex using six identified funding sources. $300,000+ was budgeted in each year
from 2007 through 2009. During the fall of 2008, $600,000 of pavement and fencing
improvements were made to the yard, which replaced the asphalt in the worst
condition. The Engineering Division, within the next month, will advertise a project to
repair a sunken concrete slab in the bus barn, install a sanitary sewer line to treat wash •
0 water and upgrade the storm drain facilities on Public Works property.
• Project completion date: 4th Quarter FY2010.
•
3
WEST NOB HILL BLVD., 50th AVENUE TO 64th AVENUE
The City competed for a TIB grant at the end of August, 2008 but was unsuccessful. We
have since selected Huibregtse Louman & Associates (HLA) through competitive
interviews to begin design of the . project in anticipation of Federal.or TIB funding. HLA
is close to design completion. We have completed the right of way acquisition process
with monies acquired as part of the Wal -Mart development agreement. The project
construction remains unfunded at this time. There is potential for $950,000 from a
possible JOBS bill but we continue to pursue other sources of revenue.
o Project completion date: To Be Determined.
WEST NOB HILL BLVD., 64th AVENUE TO 72nd AVENUE
This project received a $950,000 grant from the American Recovery and Reinvestment
Act (ARRA). The project consists of making the frontage improvements on the north
side and portions of the south side of Nob Hill in conjunction with the Wal -Mart
/Walgreens improvements (additional lanes). These improvements consist of curb,
gutter, sidewalk, street lighting and stormwater runoff treatment. Granite Northwest,
Inca began constructing this project on September 1, 2009. This project has been
completed.
o Project completion date: 2 Quarter 2010.
COOLIDGE AVENUE, 80th AVENUE to 88th AVENUE
This roadway reconstruction project was partially funded when it was a County
roadway. With the annexation of this area we received the County's developer
contributions in the amount of $213,388 along with a $150,000 Corridor Mitigation Air
Quality (CMAQ) grant. The City competed for and received another CMAQ grant for
an additional $389,000. The project design is 98% complete and the right of way has
been certified. We are in the process of getting the construction funds obligated, and it is
anticipated that the project will advertise for bids during the week of July 21st.
Construction will include a paved road, curb, gutter and grading for sidewalk on the
north side of Coolidge, along with the installation of a sanitary sewer pipe from 86th
Avenue to 84th Avenue. Sidewalks and streetlights will be completed at the time of
adjacent property development at the developers' expense.
• Project completion date: 3rd Quarter 2010.
4
r SOUTH 16TH AVENUE & WASHINGTON AVENUE INTERSECTION .
- This project consists of widening and realigning the intersection to meet the new
alignment and construction of. Valley Mall Boulevard. Design is approximately 95%
complete. Right -of -Way has been acquired from all but two parcels (Ding Ho
Restaurant and the Airport). We are in the process of receiving possession in use for the
Ding Ho property and are close to resolving the issues with the airport. We anticipate
advertising for bids in August. Funding of $1.1 Million is through a Transportation
Improvement Board (TIB) grant with local match of $300,000 from REET 2 funds.
• Projected completion date: 4th Quarter FY2010.
SUMMITVIEW & NORTH 66TH AVENUE
This project consists of building a new traffic signal and the addition of a left turn lanes
on Summitview Avenue and 66th Avenue. The design of the project is complete and the
needed right of way has been acquired. Overhead utility relocation is .scheduled to
occur in July, and the project advertised for bids on July 14. Funding of $350,000 is
through a 2008 G -0 bond. (A 2009 budget addition added $330,000 for the addition of
0 the left turn lane on Summitview. This changed the project scope and extends the
project duration due to additional survey needs; increased design needs and the
addition of the right -of -way acquisition process.) We have had one public meeting for
the neighborhood and general community.
♦ Projected completion date: 4th Quarter FY2010.
NOB HILL BLVD. OVERPASS REPAIR
This project consists of making necessary maintenance repairs to the overpass structure
through a public works project. In October 2007, HDR Engineers inspected the overpass
and recommended correction of deficiencies found that included, but was not limited to,
repairing several of the concrete wall and column caps; injecting epoxy -grout into
column cracks that were found in several columns; fiberglass wrapping of several
columns; repair all bearing pads; clean, epoxy coat and epoxy grout exposed rebar;
replace the joint membranes between bridge sections; and, repair the worst parts of
damaged hand railings.
Mowat Construction was awarded the project and began working on August 17, 2009.
All of the work has been completed, except for minor cleanup. The project has been
0 completed. .
♦ Projected completion nd
� ompletion date: 2 Quarter FY2010:
•
5 .
CAPITOL THEATRE PRODUCTION CENTER, PAVILION & PLAZA:
PHASE I - Capitol Theatre - Production Center
The Production Center (attached to the back of the Capitol Theatre facility) will facilitate the
unloading and loading of semi- trucks delivering show equipment, upgrad€
required for computerized lighting, staging and sound; address the need for prop and
equipment storage; and parking facilities for production trucks. This also includes a
base layout including all lighting and electrical equipment for a 400 seat, flexible, "Black
Box" theatre on the second floor. This project is approximately 80% completed. Interior
& exterior completion are taking place at this time.
PHASE II — Capitol Theatre - Pavilion
Development of the SE Corner 3 St. & Yakima Ave. This project is pending funding.
PHASE III — Pedestrian Plaza
Development of a pedestrian plaza and lobby extension by closing 3rd Street to
vehicular traffic between Yakima to Chestnut Avenues. This project is pending funding.
TRAHO Architects is the architect for the Project. Leone, Keeble & Moen, a Joint
Venture, is the competitively selected contractor for the project and oversees 29 types of
subcontracted construction. The updated construction budget, including all design,
inspections, fees and construction is set at $6,725,232.
s Projected completion date of Phase I: 3 quarter FY2010
KIWANIS PARK, UPPER PARK
This project consists of building three Little League baseball fields including field
lighting, restroom facilities, a volleyball court, a basketball court and parking lot.
Kiwanis club purchased the property adjacent to the existing Kiwanis Park, cleared the
property and donated the property to the City of Yakima. Funding includes $500,000
from a Recreation in Conservation Office (RCO) grant plus local funding. The Kiwanis
Club has constructed the basketball court and installed new restroom facilities. The
project to construct parking spaces along Maple Street was advertised on July 1, 2010
and bids will be opened on July 22. Design of the remaining facilities is ongoing.
• Projected completion date: To Be Determined
RICHARDSON FIELD CLEANUP AT YAKIMA AIRPORT.
This project consists of removing and replacing approximately 2,250 cubic yards of
contaminated material. This project is 90% funded by a site cleanup grant that the City
received from the Department of Ecology. The project was awarded to Tri- Valley
Construction for $151,269 in late October. The project has been completed.
Projected was completed: 1St quarter FY2010
6
•
• UNDERGROUND STORAGE TANKS AT YAKIMA AIRPORT.
The City received a second site cleanup grant from the Department of Ecology to locate,
assess and develop a plan to remediate, if necessary, contamination remaining from
previously removed underground storage tanks. The project has been completed; wells
are in place for monitoring into 2010.
o Projected assessment completion date: 4th quarter FY2009; (monitoring ongoing)
DOWNTOWN FUTURES INITIATIVE PHASE 4: 8TH STREET and "A" STREET
This project is a continuation of the Yakima Downtown Futures Initiative and was -
funded with $1.5 million of state fund and federal funds ($1 million from a Washington
State Department of Commerce grant and $500,000 of Community. Development Block Grants,
CDBG). The limits of this new project include: Both sides of 8th Street between "A"
Street and Chestnut and the north side of "A" Street from 6th Street to 3 Street. Along
8th Street project construction includes new sidewalk, pedestrian street lighting (historic
style, 13 foot tall lights with dual planter arms), trees and tree grates, tree lighting, an
automatic irrigation system, wheelchair ramps and new curbing as needed. Along the
0 Yakima Convention Center the alignment of 8th Street will curve easterly away from the
Convention Center allowing for an adjacent 7,000 sq. ft. outdoor plaza for facility use.
Bids for the 8th Street project were opened on June 8, 2010, with the low bid of $589,339 • .
being submitted by Belsaas and Smith. Construction began on July 12, 2010.
Along A" Street project construction includes new sidewalk, pedestrian street lighting
(historic style, 13 foot tall lights with dual planter arms), trees and tree grates, tree lighting,
an automatic irrigation system, wheelchair ramps and new curbing as needed. The
Engineering Division is nearing final design for the project. The project was advertised
for bids on June 21, 2010.
o Projected completion date: 3rd quarter FY2010
•
J
0
OTHER TASKS
SERVICE TO OTHER DIVISIONS
Service to other divisions continues to be provided. Miscellaneous work has included:
Sewer extension and restoration projects, legal descriptions for annexations and
vacations; updating irrigation, water and sewer maintenance reference maps; surveying
and mapping; miscellaneous assistance to Police, Planning, Streets, Airport, Public
Works Divisions and Public Works facilities, Yakima Convention Center, Fire
Department, including remodels and miscellaneous projects, and the Capitol Theatre for
capital improvement projects; Purchasing Division, etcetera.
We recently provided engineering assistance for:
• Convention Center: reroofing, partition recovering and stucco repairs.
• Capitol Theatre Remodel: provide design and construction oversight for this
project. Consultant selection for GC /CM has been completed.
• Several small drainage improvement projects.
• Fire Station Remodeling Project: review and coordination.
O
8
Water /Irrigation Division Capital Improvements Projects
• General 308 Irrigation System Phase 3 /Stage 3 Improvements
This project consists of replacing irrigation main and services in the General 308
Irrigation District.: The limits of the project are from South 2nd Street to South Fair
Avenue and from East Pine Street to East Yakima Avenue. Huibregtse, Louman
Associates completed the design and the project was bid on October 7, 2009. A
total of ten bids were received, with the low bid of $804,956.71 being offered by
Apple Tree Construction Co.,` LLC, Yakima. Construction began in November
and has been completed and accepted on June 1, 2010. Final contract price was
$750,570.57. The project replaced approximately 12,000 feet of irrigation main,
along with 325 new services. City Irrigation crews also replaced approximately
4,000 feet of irrigation main and replaced 92 services in the General 308 System
s Project completion date: 2 Quarter FY2010.
Capitol Hill Irrigation System Phase 1 Improvements
0 This project consists of replacing irrigation main and services in the Capitol Hill
Irrigation District. The limits of the project are from South 12th Avenue to South
18th Avenue and from MaClaren Drive to Summitview Avenue. Huibregtse,
Louman Associates, Inc. completed the design and the project was bid on
September 30, 2009. A total of ten bids were received, with the low bid of
$922,348.60 being offered by TTC Construction, LLC, of Yakima, WA. Final '
contract price was $968,837.84. Construction began in November and has been
completed. Project acceptance is scheduled for July 20, 2010. The project
replaced approximately 14,000 feet of irrigation main, along with 314 new
services.
s Project completion date: 2nd Quarter FY2010.
Fruitvale Canal Pipeline Improvements
The project will replace an open ditch irrigation wasteway /canal with a piped irrigation
line along East H Street from North 6 Avenue to North 9 Street. Huibregtse, Louman
Associates, Inc. has completed a preliminary, report providing a preliminary design and
project costs. Project design is underway and is expected to be completed early 2010.
The project will be broken into phases and be bid as funding for construction becomes
0 available, including potential grant or other outside funds.
s Project completion date: On- going.
9
Gardner Park Domestic Well
The project installs a new 3,000 gpm domestic well in Gardner Park, located at
Cornell Avenue and West Pierce Street. Construction on the project began
January 2009. The well was drilled to a depth of 1,328 feet. Well screen and
casing has been installed and pump testing of the well has been completed.
Golder Associates has begun the design for the new pump station for the well site
and is approximately 95% complete. The project report, construction approval
and source approval documents have been submitted to the Department of
Health. The pump station is expected to be competed and the well on line mid -
2010.
♦ Project completion date: 3 Quarter FY2010.
Water System Plan Update
The last Water System Plan was completed in March 2004, an update must be completed
every six years. This project will update the current plan by providing current
information on the existing water system infrastructure, production and consumption
data, future demand forecasting, water use efficiency, operation and maintenance,
future capital improvements, rate structure and revenue forecasting. Thomas Coleman,
PE Consulting Services has been hired to complete the plan update in coordination with
City staff and the Department of Health.
♦ Project completion date: 4th Quarter FY2010.
Water Treatment Plant Backwash Recycle Upgrade
The project will replace the unlined backwash recycle pond with new lined recycle
• • ponds. Huibregtse, Louman Associates is developing a preliminary design
recommendation and report to submit to the Department of, Health for approval. We
also submitted a 2010 Drinking Water State Revolving Fund (DWSRF) Application,
which was not approved. Funding sources will continue to be pursued to complete the
project.
♦ Project completion date: 4th Quarter FY2011.
O
10
0 East Viola Avenue. (I 82.Crossing) Waterline Replacement
The project will replace an undersized, deteriorating waterline crossing under I -82 at
East Viola Avenue, between Rudkin Road and the Wastewater Treatment Plant.
Replacement of the waterline will improve flows and reliability in this part 'of the water
system, as well as replace a sub - standard, direct bury waterline across I -82 with a new
ductile iron waterline in a steel casing within the limits of the interstate highway.
Huibregtse, Louman-Associates has begun the design and is approximately 90%
complete. The project will . be constructed as funding becomes available.
♦ Project completion date: On- going.
General 308 Irrigation System Phase 4 /Stage 1 Improvements
This project consists of replacing irrigation main and services in the General 308
Irrigation District. The limits of the project are from North Naches Avenue to
North 8th Street and from East A Street to East F Street. The project will also
41)
replace a portion of the transmission main located along Hwy 12 west of North
40th Avenue. Huibregtse, Louman Associates completed the design survey and is
currently working on design. Construction is anticipated to begin November,
2010 and be completed by March 2011. City Irrigation crews will also replace
approximately various portions 'of the irrigation main and services in the General
308 System.
• Project completion date: 2nd Quarter FY2011:
Capitol Hill Irrigation System Phase 2 Improvements .
This project consists of replacing irrigation main and services in the Capitol Hill
Irrigation District. The general limits of the project are between South 7th Avenue
and South 12th Avenue, West Yakima Avenue and Tieton Drive. Huibregtse, •
Louman Associates completed ' the design survey and is currently working on
design. Construction is anticipated to begin November, 2010 and be completed
by March 2011.
♦ Project completion date: 2nd Quarter FY2011.
0
1,
. . . . .
Wastewater Division Capital Improvements Projects
Digester Cover Replacement g p ment Project
This project was. contracted in the 1St Quarter of 2009 and construction began in the 2nd
Quarter of 2009. The project includes the replacement of the three secondary digester
covers with new membrane gas holder covers; replacement of secondary cover blowers,
air piping, Motor Control. Centers - (MCCs), local control panel and associated digester
system accessories; improvements to the Secondary Digester Control Room,and
Primary Digester electrical Room; replacement of the existing Dissolved Air Flotation
Thickener (DAFT) mechanical system, improvements to plant SCADA system, sludge
piping improvements; modifications to the plant electrical distribution system and;
dredging of an existing storage lagoon.
The Dredging of the old lagoon is complete and replacement of the existing DAFT has
been completed and was commissioned the second week in April. The digester covers
have been replaced and startup will begin in the 3rd Quarter of 2010.
• Project completion date: 3 Quarter FY2010
Collection System Repairs
410
Engineering designed the repairs and put a package of bid alternates together that went
out to bid the 4 Quarter of 2009. Construction began in and was completed the 1St
Quarter of 2010 completed. The project consisted of the replacement of a sanitary sewer
Man Hole at N 2nd ST and E D ST, repair of a lateral from W D ST to the South side of W
Lincoln Ave, and repair of the lateral from W Nob Hill BLVD (just West of S 16th AVE)
to W Prasch Ave. We are looking at adding a repair to this project for addressing the
Sewer line bottle neck at 3rd and Pierce also.
• Project completion date: 1st Quarter FY2010
Second Phase of the Speedway Race Street Interceptor
The Engineering Division is designing the remainder of the Speedway Interceptor that
will eliminate Race and Beech Street Lift Stations and extend a 36 inch sewer main to the
sewer main at 8 Street and Beech at the Washington Middle School. The exact Route is
being planned and will be determined by the ability to get a Franchise from the Wash.
St. Dept. of Transportation along I -82. Construction will be phased and may begin this
year. We have submitted the Franchise application and are waiting to here if WSDOT
approves this prior to any further design.
• Projected project completion date: 4th Quarter FY2011.
12
Wastewater Facility TMDL (Struvite) Project '
III Initial design concepts ,cepts are being evaluated and Pharmer Engineering has been selected
for this assistance. This project will begin reducing our nutrient concentrations in the
wastewater effluent discharged to the Yakima River as required by the Dept. of Ecology.
Required construction will include the fabrication and installation of a reactor to
harvest phosphorous and the installation of 8 mixers in the aeration basins to augment
nutrient removal through the reactors.
♦ Projected project completion date: 2nd Quarter FY2011.
Wastewater Facility_ and Collection System Plan Update and initial Stormwater
Comprehensive Plan.
The last Water System Plan was completed in February 2004. This project will update
the current facility plan by providing current information on the existing wastewater
facility and collection system infrastructure, regulatory requirements, future loadings,
operation and maintenance, future capital improvements, rate structure and revenue
forecasting.
0 With the adoption of the new Stormwater Regulations a comprehensive Stormwater
system plan is needed and will be implemented along with the Wastewater Facility and
Collection system plan .update.
A consultant will be selected in the 3rd quarter of 2010 to develop these plans.
e Project completion date: 2nd Quarter FY2012.
Levee set back Project and new Wastewater Outfall
Staff continues to be involved in the Gap to Gap project for flood plan restoration which
will include the Wastewater Treatment Plant to relocate or develop a new wastewater
outfall. Alternative will be evaluated to select a new outfall location. Currently the old
Wastewater spray field is being evaluated as a riparian outfall. An engineering report
for alternatives like this will be developed and submitted to Ecology for approval.
♦ Project completion date: 4th Quarter FY2012.
.• . .
. .
13
FY2009/10 PRIVATE PROJECTS
Listing private developer projects shows the amount of private projects that are "on the
books" and pending or under construction with some (not all shown) that go back
several more years. These projects have all been approved since January 2007 and are
either pending construction, under construction, started but not completed or recently
completed. The projects include:
Project Name Location Improvements
Wilson Properties 16th Ave. N. of McKinley Sewer extension
Golden Corral 1901 -1915 S. 1st St. Street improvements
Larry Loveless Short Plat 8100 Tieton Dr, Water, sewer & new street
Hollow Creek Place Short Plat S. 27th Ave. Hollow Creek PI, Street Improvements
WestTowne Center - Riverside Mall 16th Ave., River Rd & 6th Ave Mall Site Development
Rite Aid - Nob Hill BLVD Nob Hill & 24th Avenue Site, Water, Sewer & SD
Washington Mid School Portable Unit 510 S. 9th St. Site Improvements
Franklin Middle School Portable Unit 410 S. 19th Ave. Site Improvements
Hoover Elementary Sewer Extension 400 W. Viola Ave. Site Improvements
Future Fun LLC Drainage . 715 S. 2nd St. Storm Drainage
Advanced Secure Storage Drainage 1913 McKinley Ave. Storm drainage
All Services Parking Lot 715 E. Viola Ave. Parking Lot
Anderson Park Occidental & 64th Ave. Site Improvements
Yakima Bears Executive Viewing Deck Pacific & 12th Ave. Water line alignment
•
14
•
AFFIRMATIVE ACTION GOALS & WIMIDBE PARTICIPATION
W/M /DBE utilization has been included in the past but is not included with this report.
S
The Engineering Division continues to request apparent low bidders of public works
contracts to document their efforts to achieve the City of Yakima's goal of 10% MBE,
WBE or DBE participation goal prior to contract award. However, changes in state law
due to the passage of Initiative 200 prohibit certain practices by contracting agencies (i.e.
the City) for the award of public works projects such . as requiring W/M /DBE
subcontracting. While some contractors have voluntarily reported such information in
the past, we have not received any such reporting this year.
Although we do not receive such information voluntarily, the City must still meet
certain of these federal requirements and each contractor must comply with the
Standard Specifications that are included on each City Public Works Contract. The City
is responsible to:
• Conduct pre- construction conferences during which EEO and City policies are
discussed with the contractor.
• Monitor on -site compliance with the EEO and City policies.
• Ensure our contractors locate, qualify, and increase the skills of minority groups,
women employees, and applicants for employment as required by City policies.
• Ensure the preparation of required EEO and related reports.
110 ..
41)
•
15
Proj Proj. Lead Project Name /Location Description of Work Project Lead • Impacted Constrctn. Status /Schedule Notes
Type .No. Division . Divisions Star bate 7/13/10
Underpass on Lincoln; (MLK Jr. Engineering, Apollo Inc, Kennewick, was low bidder; The 12- • - • -• contractor
• 1818 R/R Grade Separation Phase II; Blvd. late in '10); Front Street Bob Desgrosellier / Water /Irrigation, Phase H, Main
CIP Engineerin month detour is in place on MLK; Rail Bridge will be project is sch -• for completion •
Phase II Lincoln Ave.; 1st St. to 1st Ave. over Lincoln (and,MLK Jr. Brett Sheffield Wastewater, PW, Project, 3/10 1st major work. i Work • - - • n reconstructio
Blvd.. Streets, IS
1818 Grade Separation, . Underpass : Construction proposed starting June 2011; We will be ready to go with the MLK Underpass when
2 CIP Phase - • • • - • • • - Sheffield _ Phase -.Design is at 95% & continuing; _ remainder secured
III • Ave. = • All R/W is in hand ' funding
Streets, IS .
• BNSF will be 3 CIP 2063 - ' ' • - Y cing new Sheffield Bob • BNSF has the new signal in place and is finalizing • • • • - • • - • • - • • ' .+ .. - ' ' ' "' - .. - . - the crossing replacement • • • • •' • - ' • ....- .4 CIP 2153 - . . - - - ... • - ' • Project has been awarded • • _�_d August.
Bob - • - to GM McClure of Yakima; 70% complete
buildings and • - work possible
Avenue Street '' ' Project been Construction has begun and
5 CIP 2166 Engineering : • _ Engineering • • = - - - • - should be completed this summer.
Bridge Deck Crossing _
River; pathway to _ _
work is complete : being closed . More work possible with remaining funds.
Righ t -of -way purchases are under way for property in6 CIP • -- • _,• - -• :•• �_ • _ _ 00' = ••- ' • - • - • '•- • • ' the CowicheCanyon area;
!*'--'
- • - some •urchases have been made
• - & rebuild project is a 3 phase reconstructiqn • - over Phase 3 will include the interior
• B Complex asphalted - _ • rebuild asphalted • • parking garage floor repair in 2010
Public Works Reconstruction _ budgeted . • Phases 1 & 2 completed - ' ' ( & storm drainage improvement? )
Study Fire, • begun.
; ' - • - service • . • Police, ^ $50k approved through 2007 Council Budget
Admin
• ineering_L--- Fueling Station Addition @ 1st St. & Build _ remote fueling station Bob Desgrosellier • Proposed a ARCO . t, lst St. & Lincoln Avenue Demo of the ARCO building is complete;
� ® •
Lincoln Public Works • - • Wonner Works or earl 2011 after Grade Se•aration construction. pump station reconstruction near end of project
Engineering, Traffic Project tied to the Wal -Mart project. There may be Design is 90% complete; Well shelve plans in
• -- •• • • •• -
•- ' - • add :.. • - . . • - R/W was purchased with Wal mart mitigation osome preparation for next funding
on UN- FUNDED, opportunity;
10 CIP 2272
fundin• Count was hired to do some R/W ac• uisition.
Project to • - p' • - • halt Coolidge
We completed R/W acquisition Construction should be completed in 2010;
11 CIP Engineering • Avenues • • • • _ _ • _ - & are awaiting Federal Approval delayed due to extended R/W acquisition.
include
E. . • .: - - • - - . -. - . Engineering
Design only at this time beginning 6/2008; Design only; (Drainage system
12 CIP • -- Intersection Improvements signal Randy _ •. - Design ' Search for funding on -going for this intersection is included.)
Water/Irri•ation
Ave Avenue Widen _ _ ll J 1 j' Design began Fall 2008; TIB Grant of $1.1 Million;
13 . CIP Design Completed & match with $300K REST 2;
6th
intersectio reconstruction , • replace signal Dan • • • rig • R/Way is in final stages with Ding -Ho & Airport _ R/W purchases 78% complete Traffic
• - ., Overlay . .. • : - _ - • Brett • ; - • Project design
funded by REET2 m4�letion 16th & Washingto Avenue project
14 CIP I
.. Avenue : - Brett Sheffield Design & R/W complete, Project will now widen Summitview for a 5th lane at the
15 CIP - Avenue Signal street _ • Utility relocations taking place ' signal; Utility poles are being relocated by the utility
com •anies Repair
____ • farted 8 /20 /09e h At C 2010 ction Co.; Work Pro'ect clean and osin
CIP 2229 • •• • - •. ■ -•. • -- ' ��• q p 1 P 9 Utilities TRAHO is Architect; GC /CM Contractor Leone, Production Center Const. only at this time; Funded
- 17 CIP 2231 Keeble &Moen (Joint Venture); Project is 80% through municipal bonds, Public Facilities District &
• complete; Finish construction in August private donations from Theatre benefactors
RCO grant $500,000 + local funding; RCO grant of $500,000 + local funds - Little League
overall design is approx. 50 %; Fields; lighting; volleyball; restrooms; some parking & •
18 CIP 2212 - • Maple Street parking project out for bids; walking pathway;
Restroom construction starled. playground to be built by volunteers
•
Proj Proj. Lead • Project Name /Location Description of Work Project Lead Impacted Constrctn. Status /Schedule, Notes •
Type No. Division Divisions Start Date 7/13/10
Remove Underground Storage
Underground Storage Tank Removal Doug Mayo / Work is complete; ' DOE grant included locating, assessing and
19 CIP 2274 Engineering Tanks & remove /replace Engineering, Airport 2009
at the airport contaminated soil Brett Sheffield Waiting for DOE review and approval of report; developing a plan to remove unused UST's
Richardson Field Cleanup Remove & Replace 4,000 CY of Doug Mayo / DOE grant included removal and replacement
20 CIP 2145 Engineering at the airport contaminated soil Brett Sheffield Engineering, Airport 2009 Work is substantially complete; of 4,000 CY of contaminated soil
. Realign 8th Street, remove & Realign and reconstruct 8th Street from "A" to
Engineering, Streets Belsaas & Smith of Ellensburg were low bidder of the
Downtown Futures Initiative (DFI), Phase replace sidewalk, place new Yakima Avenue; Rem /Repl. sidewalks north of
Brett Sheffield / & Traffic Eng., 8th St. project; work has started and will be completed
21 CIP 2284 Engineering 4; 8th St:, "A" to Chestnut; & pedestrian lighting, trees, 7/2010 Yakima Ave.; place trees, twinkle lights and ped
Bob Desgrosellier Water /Irrigation, this fall; "A" street is out
"A" St., 3rd to 6th Streets, north side twinkle lights, landscaping lights "A" to Chestnut; Sidewalk & landscaping on .
Wastewater for bids and work will begin in late August.
"A" St., 3rd St. to 6th St., north side only
• Remove & replace sidewalk,
County & City Joint "DFI Styled" Engineering, Streets Granite Northwest is Low Bidder;
new lights, trees, twinkle lights, Brett Sheffield /
Improvements; West - side of 2nd Street, & Traffic Eng., Construction is complete;
22 CIP 2285 Engineering MLK to "4" Street; north side "A" Street landscaping; (New communit Mark Brzoska Water /Irrigation, 10/2009 (Adjacent Performance Park • Project is being closed out
2nd Street westerly to alley; performance park is adjacent) Yakima Count Wastewate Construction is complete)
Place several types of Surface Reconstruct north side of street using porous asphalt,
23 CIP 2291 Engineering J Street LID Demonstration; Water Drainage Materials in Randy Meloy / Engineering, Streets 4/2010 RP &E of Ellensburg has contract; porous concrete and permeable pavers. South side to
"J" Street, 18th to 20th Avenues roadway for drainage study Brett Sheffield project is complete and is being closed out have asphalt pavement with compost- amended
_ roadside ditch.
64th Avenue; Doug Mayo / Surveying completed;
24 CIP ? ? ?? Engineering Roadway and Pathway Engineering, Streets ? ? ?? Wal -Mart is funding part of project as mitigation
Nob Hill to Tieton Drive Brett Sheffield R/W and funding is needed.
Reconstruct intersection, widen
Tieton Drive and 64th Avenue Doug Mayo / Surveying has been completed;
25 CIP 2282 Engineering for additional lane on Tieton . Engineering, Streets ? ? ?? Wal -Mart is funding part of project as mitigation
Intersection Brett Sheffield R/W and funding are needed.
Drive; add signal
Remove trolley tracks from o
S. 2nd Avenue, Doug Mayo / Design is at 57.63%; Remove trolley tracks & rebuild center of roadway;
26 CIP 2286 Engineering Yakima Avenue to Walnut Street roadway; add planters to p art Brett Sheffield Engineering, Streets 2010 Funded with $150,000 REET Funds add planters to portions of roadway center
of center of roadway _ _ _
Remove jail cells, interior walls
E
27 CIP 1783 ngmeermg x City Hall Demolition of & asbestos abatement; Doug Mayo / . Engineering, CED 2010 Wardell Architects demo dac's; Work should be completed by the end of 2010
NE1N,�"f .° interior 3rd and 4th Floors Bob Desgrosellier demolition has started
Rem /Repl windows g
Engineering 8" sanitary sewer Doug Mayo / Engineering, Survey and design started in- house;
28 CIP 2297 : ,,, Swan & Willow, 20th to 24th 2010 Funded through Wastewater
.NEV11 „ ary Brett Sheffield Wastewater easements and /or R/W are needed on Swan
' Engine Reconstruct sewer manholes Doug Mayo / Engineering, Design is Complete;
���
29 - CIP Pierce Avenue at 3rd Avenue Summer 2010 Will be bid through the Small Works Roster
' < and connections Dana Kallevig Wastewater Construct this summer
30 M &O Streets Area 18 - 32nd Ave, Tieton, 40th Chip seal Chris Waarvick Water /Irrigation/WW 1/1/07 chip seal application began mid - August REET2 paying for materials
Ave, Englewood
31 CIP 2055 Wastewater WWTP Phase 1 Facility Wastewater /Facility Max Linden B &V/Water- Irr /Com. 6/1/06 WWTP improvements /upgrades - construction Apollo Inc - 100% complete
Improvements Electronic sec completed .
CIP 2221 Wastewater Final Scada Tip Out Wastewater /Facility MaxLinden Wastewater /B &V 5/1/09. Continued SCADA and wastewater continue tipping out existing communications systems
2222 DAFT Retrofit improvements /upgrades - Project 221, 2222, 2223 replace existing covers/ fix pressure and flow
32 2223 • Dystor Retrofit bid as one contract -Bids opened On April 14- monitoring issue, electrical distribution system
Apollo is apparent low bidder, Apollo awarded upgrades
contract - 30% complete.
CIP 2228 Wastewater Congdon Sewer Main Wastewater /Collection Sys Max Linden /Shelley Engineering/ 10 ? Unknown
33 Willson Wastewater
CIP 2234 Wastewater Neighborhood Wastewater Wastewater /Collection Sys Max Linden /Shelley Engineering/ 10 ? Unknown
34 improvements Willson Wastewater
35 CIP 2264 Wastewater Speedway /Race street Interceptor Wastewater /Collection Sys Max Linden WW /Eng. /PLSA ? 1/1/10 Design for the completion of the 36" sewer line to
Race street LS and demo LS
36 CIP 2254 Waste water Security upgrades Wastewater /Facility MaxLinden Wastewater /B &V 1/1/10 New gate and additional lighting
37 CIP 2255 Wastewater Pretreatment offices Wastewater /Facility MaxLinden Wastewater 6/1/09 Add office space in storage building 09 50% complete
38 CIP 2256 Wastewater Magnesium Tank Relocate Wastewater /Facility MaxLinden Wastewater 1/1/10 New tank and locate within one of the old chemical
buildings
CIP 2293 Wastewater W
" Collection system repairs Wastewater /Collection Sys Max Linden /Shelley W /Eng 11/9/09 Designed
- tom
39 New w Willson
•
i
I
Proj Proj. Lead . Project Name /Location Description of Work Project Lead Impacted Constrctn. Status /Schedule ' Notes
Type No. Division Divisions Start Date 7/13/10
III PWTF Loan approved. Water right transfer
-Water /Irrigation, complete 8/22/06. Golder and Assoc:. completed Worked with Parks Division on siting of new well at
40 CIP 2132 Water /Irrigation D esign and Install a new 3,000 gpm New well at Gardner Park Dave Brown Streets, Eng, Parks, 1/26/09 design. Bid Opened Nov. 6, 2008. Awarded to Gardner Park. Archeological survey complete - no
well at Gardner Park P dgeview School Layne Christensen Company. Drilling started on findings. Drilling operations completed. Golder
Feb.9th. Drilling has been completed as of 3/9/09 working on design of pump station. Plans at 95%
(1,328'). Wellhouse design at 95%
In Progress, lined canal under Hwy 12, completed
Water /Irrigation, study, work needed on diversion and areas of the HLA has completed report and recommendations for
Refurbish the Fruitvale Canal, canal. Enlarged pipe from General System to Fruitvale multi -year piping project from 6th Ave. to 9th St. HLA
Dave Brown /Mike Streets, Stormwater,
41 CIP 2010 Water /Irrigation Fruitvale Canal Diversion and Wasteway on H 2010/2011 Canal. City crews completed connection between working on design of entire project and make ready for
Shane Parks, DOT Yakima
St. General and Fruitvale systems near 16th and Jerome. construction. Working with other Divisions and
County, WDFW Repaired wood gates at Cowiche Creek. Considering agencies on joint project.
a point of diversion change to Nelson Bridge in 2010 .
Water facilities impacted by .
other improvements - DFI, Misc. Mike Shane /James Water /Irrigation, On -going coordination with DFI projects, sidewalk
42 CIP 2288 Water /Irrigation Misc. waterline improvements. sidewalk & transportation Dean Streets, Eng. 2010 projects and misc. Transportation projects Majority of work to be completed by in -house staff.
projects. _
Capital Hill /Loma Vista Irrigation Irrigation System Replacement Water /Irrigation, HLA is consultant. Project design complete. Bid 10 bids received. Low bidder TTC Construction LLC at
43 CIP 2257 Water /Irrigation Mike Shane 11/1/09 Opening was Sept. 30, 2009. Construction approx. $922,348.60. EE - $1,272,599.71. Final contract price
System Refurbish in various neighborhoods Streets 100% complete. $968,837.84
Irrigation System Replacement
in the neighborhoods north of E. HLA is consultant. Project design complete. Bid 10 bids received. Low bidder Apple Tree Construction
44 CIP 2180 Water /Irrigation General Irrigation Pine St., south of Yakima Ave., Mike Shane Water /Irrigation, 11/01/09 Opening on Oct. 7, 2009. Construction is approx. Co. at $804,956/1. EE - $698,043.76. Final contract
Phase 3 Stage 3 east of S. 1st St., west S. 10th Streets 100% complete. price - $750,570.57
St.
Begin preliminary plan, Plan Water /Irrigation Tom Coleman is Consultant. Project kick -off
45 CIP 2258 Water /Irrigation Water System Plan Update due in 2010 Dave Brown Planning N/A meeting with DOH on July 23, 2009
Recycle lagoons and new electrical Design of new recycle lagoons; Dave Brown HLA to provide report to City and DOH on
46 CIP 2259 Water /Irrigation service at the WTP new 800 amp electrical service; Mike Shane Water /Irrigation 2010 recommendations for design.
new generator Jeff Bond .
Internal discussion to began in January to determine
Begin process of determining Dave Brown Water /Irrigation next course of action. G & 0 consultant to provide Inter agency agreement approved by Council, Selah
47 CIP 2261 Water /Irrigation Automated Meter Reading method, materials, process for Mike Shane Wastewater 2009 study and recommendation for Yakima, Selah and and Nob Hill.
automated water meter reading James Dean Utility Billing Nob Hill. Report is being developed to provide
recommendations specific to each agency.
Design the water main Water /Irrigation ° Project will be constructed as funding becomes
48 CIP 2262 Water /Irrigation Replace Main at 1 -82 and Viola replacement at 182 and Viola Mike Shane Wastewater 2009 HLA is consultant. Project design is 95% complete. available.
Irrigation System Replacement
in the neighborhoods north of E.
• General Irrigation Water /Irrigation HLA is consultant. Project design survey underway.
49 CIP 2287 Water /Irrigation A St., south of E. 1 St., east of Mike Shane 2010/2011
Phase 4 - Stage 1 S. 1st St. and west of S. 10th Wastewater, Streets Bid opening fall of 2010
St., SR12 at 40th Ave.
•
Capital Hill /Loma Vista Irrigation Irrigation System Replacement Water /Irrigation HLA is consultant. Project design survey underway.
50 CIP 2257 Water /Irrigation System Refurbish Ph. 2 in various neighborhoods Mike Shane Wastewater, Streets 2010/2012 Bid opening fall of 2010.
.......... ✓s.,.Sie2'.- X.&t ..+_v._ %44.k 1 N49•&aw...... ,.., .,, $ .4 ,F>2 s ?S*, k . _..... .. .Et . ...,+,'... ,. <,-m - ,... r,a.,, ... �. ,. _ ',' , ..a .t.. -. -_. a. , ....t'' a-X. ' ,c , ., . ,. ... , . ... _ > . .<_.. A . ,. �.r2. _, . -. _ .m. .. A.. . . 4,; A
COMPLETED PROJECTS
ffield / — Interest from private partners fell through;
CIP 2241 Engineerin south to Airport and rebuild roadway Bruce Floyd Engineering Cancelled 6/2010 project will be cancelled Project to be deleted from list
Ped signals at 16th & Bonnie Doon; New crossing signals and Brett Sheffield / Low bidder: Knobel's Electric of Yakima
•
CIP 2236 Engineering 4th Street & MLK; Engineering, Traffic 10/2008 Construction 100A.Complete. °
N. 1st St. & N. 16th near Hathaway painted crosswalks Dan Ford. _ 4/2010
• r
. .
• Proj Proj. Lead Project Name /Location Description of Work • Project Lead Impacted Constrctn. Status /Schedule Notes
Type No. Division Divisions Start Date 7/13/10 .
Roadway reconstruction,
•
Jeld -Wen roadway imp's; • Brett Sheffield / Low bidder: Granit NW of Yakima
CIP 2120 Engineering 6th Avenue, River Rd. north 650' pathway addition on west _side Dan Ford Engineering 7/2009 4/2010 Construction 100% Complete.
•
of roadway
CIP 2182 Wastewater UV Disinfection Wastewater /Facility Max Linden B &V/Water- Irr /Com. . 3/1/08 WWTP.improvements /upgrades - ` bid, contract awarded to Apollo Inc. •
Electronic sec 100% complete; closing project out:
CIP 2188 Wastewater 40th & Fruitvale sewer sleeve • Wastewater /Collection Sys MaxLinden B &V /Eng/Water March /April 2007 WSDOT Project- Completed complete, waiting for WSDOT project closure
Widen roadway, add sewer & Brett Sheffield / Engineering, Traffic Project cleanup & closeout is underway;
CIP 2278 Engineering Nob Hill Blvd, 64th to 72nd Avenues 8/2009 Project is 100% complete 4/2010
water utilities Bob Desgrosellier Eng., Wastewater $950K ARRA funding received for City portion
85th Avenue, Kail & Juanita Sewer Neighborhood sewer LID - Al Rose / Brett Engineering, Premier Excavating was low bidder; Project is closed out;
CIP 2208 Engineering Local Improvement District (LID) Approx. 29 parcels Sheffield Wastewater 2/2009 100% complete final assessment hearing went to Council 4/6/10
Simpson Lane Sewer LID; So. 13th, Neighborhood sewer LID - Bob Desgrosellier / Engineering, Scott's Excavating was low bidder;
CIP 2215 Engineering 14th, 15th Streets Approx. 82 parcels Al Rose Wastewater 2/2009 100% complete Council assessment hearing is complete; 4/2010
Realign 16th Ave. south side of Engineering, Streets & °
•
Brett Sheffield / Project is 100% complete; 100% CIP 2213 Engineering 16th Avenue Realignment @ Airport airport tying to future V. Mall Traffic, Wastewater, 7/2009, 100 /o complete. •
Blvd. & 16/Wash Bob Desgrosellier Water /Irrigation Low bidder was: Granite Northwest;
Downtown Futures Initiative (DFI), Phase Remove & replace sidewalk, Engineering, Streets Reconstruct: east side 1st Street; 2nd St. both
3; 1st St., n/o Yakima; 2nd St., "A" to new lights, trees, twinkle lights, Brett Sheffield / & Traffic Eng., sides, 3rd St. both sides, west side Naches all °
CIP 2216 Engineering Chestnut (or Walnut); 3rd St., "A" to landscaping Bob Desgrosellier Water /Irrigation, 7/2008 Yakima Ave to "A" Street; plus both sides • 100 /o complete.
Yakima; (Naches "A" to Yak ?) Wastewater So. 2nd St. Yakima to Chestnut
• Tieton Dr. Pedestrian Project, Update north side sidewalk, Brett Sheffield / Engineering, Traffic, °
CIP 2233 Engineering 16th Ave to 24th Avenues including wheelchair ramps Dan Ford / • Wastewater, 10/2008 Construction is 100 /° complete 100% complete.
•
Joan Davenport Water /Irrigation .
Nob Hill Blvd, Construct sanitary sewer, north Doug Mayo / Engineering,
CIP 1977 Engineering 53rd to 62nd Avenues ( +/) side of roadway Brett Sheffield Wastewater 8/2009 Premier Excavating: Project completed • 100% complete.
Kiwanis Skateboard Park; New concrete Skateboard Park Construction is complete; Parks
CIP 2023 Engineering Fair Ave &Maple Street @ Kiwanis Park Bob Desgrosellier Engineering, Parks 6/2008 Bids opened on 5/15/08 has project funds for a few more amenities
el Grind and Overlay (G &O) Engineering, Traffic,
3rd Ave. Grind & Brett Sheffield / We extended grind and overlay to just north of
CIP 2230 Engineering Mead Avenue to Chestnut roadway & restripe; update Randy Tabert Wastewater, 8/2008 Washington Avenue. Project is complete
wheelchair ramps Water /Irrigation
Engineering, Streets,
•
W. Nob Hill - Grind & Overlay; Grind and Overlay (G &O) of Bob Desgrosellier / Received good bids; grind inside lanes and sealcoat Project is complete;
CIP 2214 Engineering 24th Avenue to 4th Avenue two inside 'through' lanes Wayne Deason Water, Wastewater, 8/2008 entire width in 2008 ($500,000 REET ?) Streets to sealcoat in future as funding is available
Traffic Eng
Streets Poplarview Way Check face of plat Chris Waarvick / Nob Hill Water Graded and dust abatement material applied spring
M &O Randy Meloy Wastewater 2008 2007; new easement in place Project is complete
Rdwy New 3 lane roadway, C /Gutter Engineering, Streets,
River Rd. Improvements, 15th to
1944; & S/Walk, ADA ramping, street Brett Sheffield / Traffic, Water /
CIP Engineering Fruitvale; 27" Sewer trunk 6th Ave to 9/19/06 - This project is closed out Complete
Sew lighting. Replace 8" sewer with Bob Desgrosellier Irrigation, Old Union
•
2128 Fruitvale 27" trunkline Ditch, Wastewater
CIP Engineering Harman's Senior Center Parking Lot Reconstruct & repave parking - Brett Sheffield / Engineering, Parks 4/21/08 contractor done; complete 5/2/08 Project is complete
Reconfiguration - N. 65th Ave. lot to maximize parking
Streets 80th Ave - Zier to Tieton; Zier - 72nd Ave. to Arterial Chip Seal Wayne Deason Mid -June 2008 REET & Street Division Budget
80th Ave.; 72nd Avenue - Nob Hill to Coolidge;
•
• Castlevale -24th Ave to Powerhouse;
M &O Powerhouse - 40th Ave to the West City limits; .
Powerhouse 40th Ave to Lincoln;
ONDS development, was Brett Sheffield / Engineering, ONDS,
CIP 2107 Engineering Marvin Gardens Development private, switched to public Al Rose Wastewater, 10/15/07 This project is complete and being closed out Project is complete
Water /Irrigation
Remove & replace sidewalk, Street & Traffic,
West Yakima Avenue Improvements; Brett Sheffield / Project is complete; Banners are in place; working on
CIP 2165 Engineering Front Street to 7th Avenue new lights, trees, twinkle lights, Bob Desgrosellier Water /Irrigation, • 7/2007 This project is complete getting spring - loaded banner arms'outside of contract
landscaping Wastewater .
Engineering, Westcoast Construction is Prime; Work included
R/R Grade Separation, Phase I; Utilities Relocations Phase I - Utility
1818 Bob Desgrosellier / Water /Irrigation, Front Street and "A" Street bricking /paving in Project is complete;
CIP Phase I Engineering Lincoln Ave. & Martin Luther King Jr. surrounding the Grade Brett Sheffield Wastewater, PW, Relocation work existing right-of-way; includes utility relocation in we soda blasted utility markings as final step
Blvd. vicinity Separation Project Streets, IS began July 23rd area of future underpasses
CIP 2087 Wastewater Speedway Interceptor SR24 phase I- Wastewater /Collection Sys Max Linden • B&V/Engineering 3/19/07 Need to connect at diversion box - completed - work complete waiting for WSDOT project closure and
82 Viola to Speedway on punch list WWTP waiting for rebate of funds from DOT
•
•
■
Proj Proj. Lead Project Name /Location Description of Work Project Lead Impacted Constrctn. Status /Schedule Notes
• Type No. • Division Divisions Start Date 7/13/10. - _
CIP 2087 Wastewater Speedway Interceptor Speedway to Wastewater /Collection Sys Max Linden B &V /Engineering Design /Bid /Construction inspection- Not funded yet
Washington School
Memorial Hospital to "rebuild" Engineering, Streets, Eng has estimate for Streets & Waarvick; awaiting
No. 30th Avenue - Reconstruction; Bob Desgrosellier / •
CIP - Engineering 30th Avenue due to damage Water /Irrigation, ? / 2007 Hospital funding; may have been sealcoated for • Seal Coating completed
Tieton Drive to Walnut during their campus upgrades Bruce Floyd Wastewater temporary measure?
Fruitvale Blvd & 40th Avenue 200' +/ of 42" carrier pipe for Brett Sheffield / Street & Traffic, Superior Paving is prime; Project tied with WSDOT Sewer xing complete; o
• CIP 2188 Engineering Water /Irrigation, Feb /March 2007 construction project of new on -ramps and interchange reconstruction @ 98/0,
Sewer X-ing of WSDOT on ramp future 27" sewer trunk Bob Desgrosellier Wastewater interchange upgrade. signal in & running; trail connection complete
Basalt column placement with lit Brett Sheffield / Bob Engineering, Parks
CIP 2116 Engineering Basalt Art Project, 2nd & E. Yakima Cornucopia & brass Sun Desgrosellier 6/7/07 Art work complete, on time and on budget 6 -20 -07 Project is 100% complete;
2 western medians to be Bid, 2-14-07,
Washington Avenue Median removed for left -turn storage. Bob Desgrosellier / Engineering, Traffic, Columbia is Prime; 100% CIP 2124 Engineering construct spring o 6 -20 -07 Project is 100% complete;
Removal btwn 16th & 24th Ayes Eastern median gets several Randy Tabert Water /Irrig 2007 100% complete
new lights & brick pavers
6th Street S/Walk Replacement, one Remove & Replace one block Bob Desgrosellier / Engineering, Traffic, Tied to Lincoln Avenue Sidewalk Construction 100% • CIP 2169 Engineering Spring 2007 0 6th Street project is 100% complete;
block n/o Race Street of concrete sidewalk Larry Johnston Water /Irrig Project; Block Grant funds 100% complete
New sidewalk on Lincoln, Engineering,
Lincoln Ave. Sidewalk, 25th to 29th Bob Desgrosellier / Columbia is Prime; 100% CIP 2046 Engineering adding 24th to 23rd on Linc. Water /Irrigation, Spring 2007 0 8 -11 -07 Project is 100% complete;
Ave. & r /wa
y purch near 18th Ave. and 40th Ave. near Lincoln Larry Johnston Streets and Traffic Lincoln Sidewalk 100% complete
CIP 2095 Water /Irrigation PRV in 40th Ave. Pump Station Install PRV in 40th Ave. Pump Dave Brown Water /Irrigation, Summer 2007 Old pump removed by City crews. PRV installed by Final Cost - $7,100
Rehab, work in -house Station Streets, Engineering City Crews. Work completed.
CIP / 2131 Water /Irrigation MaClaren Reservoir Rehabilitation Repaired cracks in MaClaren Mike Shane Water /Irrigation 3/1/07 100% Complete Final Cost - $31,216
M &O Reservoir. Replaced ladder &
slide gate. Repaired weir box.
2142 Water /Irrigation Front St. Water Main Replacement water main replacement for Mike Shane Water /Irrigation, and August of 2007 Water main in Front St., Lincoln and MLK installed.
CIP railroad grade separation Engineering All water services transferred to new main in Front ,
project. Streets include Front . from Yakima to MLK.
St., MLK and Lincoln. .
2179 Water /Irrigation Brackett Park Irrigation System Replace the wood irrigation Mike Shane Water /Irrigation, 11/19/07 Bid opening occurred Oct. 3, 2007. Jansen Inc. of Final Cost - $215,705.19
CIP Replacement pipes in the Brackett Park Streets Ferndale, WA is contractor. HLA is consultant. -
•
system Project is 100% complete. Final clean -up and .
_ restoration in spring 2008.
2181 Water /Irrigation Repair /Replace Glenn Drive Replace the pump station and Mike Shane Water /Irrigation 11/01/07 Design complete. Bid opening Oct. 10, 2007. Final Cost - $326,570.45
CIP Reservoir Pump Station and Platform platform in the Glenn Drive POW of Pasco, WA is contractor. Work is
Reservoir underway. HLA is consultant. Project is 100%
_ complete.
Replace Radios and Antennas for Replace Radios & Antennas for
CIP 2185 Water /Irrigation Telemetry System Telemetry System Dave Brown Water Apr -07 Complete Cost $27,755.34
Water - DOT - Yakima Decommission complete, WSDOT hauled fill. Out
CIP 2218 Water /Irrigation Ranney Well Decommission Decommission the Ranney Well Dave Brown Spring of 2008 complete
_ County _ to adv. for hauling rest of spoil material
2096 Water /Irrigation 2nd Level Reservoir Pipe Rehab. /Install new waterlines, Mike Shane Engineering, 1/14/08 Survey and design completed. Bid opening was Final Cost - $147,336.05
CIP Improvements - Ph. 2 drainlines and control valves at Water /Irrigation Dec. 5, 2007. Contractor is TTC of Yakima. HLA is
2nd Level Resv. Site consultant. Project is 100% complete.
Irrigation System Replacement
in the neighborhoods south of
Pacific Ave., north of E. Nob Bid opening occurred Sept. 26, 2007. KRCI of
CIP 2180 Water /Irrigation General Irrigation Hill Blvd„ east of S. Naches Mike Shane Water /Irrigation, Stage 1 11/2007 Wenatchee, WA is contractor. HLA is consultant. Final Cost - $1,329,593.67
Phase 3 Stage 1- Ave., west of Fair Ave. Also, Streets Project is 100% complete.
Custer Ave. between Lincoln •
and W. A Street
110 . .
•
:.,... • .
.,... .
. _
•
• . • .
• •
•
. , .