HomeMy WebLinkAbout07/20/2010 12 2010 2nd Quarter Capital Improvement Projects Report BUSINESS OF THE CITY COUNCIL YAKIMA, WASHINGTON AGENDA STATEMENT Item No. /2, For Meeting of July 20, 2010 ITEM TITLE: 2010 2nd Quarter Capital Improvement Projects Report SUBMITTED BY: Michael Morales Department of Community and Economic Development CONTACT PERSON /TELEPHONE: Brett Sheffield, PE, Chief Engineer, 576 -6797 SUMMARY EXPLANATION: Attached is the Engineering Division's 2nd Quarter Capital Improvement Projects Memorandum and Report which includes Water /Irrigation and Wastewater Capital Improvement Projects. Also attached is the current project spreadsheet developed by the Sewer, Water, Streets, Traffic and Engineering Divisions. The current project listing assists in the planning of current and upcoming projects. It helps the divisions coordinate their work so that, for example, a street is not rebuilt or seal coated just prior to planned underground work on the same street. As reported in January con i p y t Hued and new construction and construction administration for 2010 is as follows: Engineering: $25,000,000 Water: $ 3,000,000 Irrigation: $ 2,600,000 WasteWater Collections: $ 1,670,000. WasteWater Plant: $ 3,600,000 Total: $35,870,000 SEE ATTACHED MEMORANDUM AND REPORT Resolution Ordinance Contract _Other (Specify) Memorandum and Report Funding Source APPROVED FOR SUBMITTAL: °o • City Manager STAFF RECOMMENDATION: Accept Report ID BOARD /COMMISSION /COMMITTEE RECOMMENDATION: COUNCIL ACTION: 1 -- July 14, 2010 • MEMORANDUM . • July 20, 2010 TO: Mayor,Micah Cawley Members of City Council FROM: Michael Morales, Director of CED . Doug Mayo, PE, City Engineer SUBJECT: 2010 Capital Improvement Projects: 2nd Quarter INTRODUCTION This Quarterly Report information is intended to provide an overview of. the 2nd Quarter for capital projects scheduled for 2010, including current project status, milestones, and any new developments that may significantly alter the schedules or costs of the projects. This narrative report `includes Water /Irrigation Division and Wastewater Division Capital Improvement Projects along with the Engineering Division. II CAPITAL IMPROVEMENT PROJECTS RAILROAD GRADE SEPARATIONS; LINCOLN AVENUE (& MARTIN LUTHER KING JR. BLVD.) 1ST STREET TO 1ST AVENUE; PHASE 2. This project consists of re- constructing Lincoln Avenue so the roadway will pass beneath the existing BNSF railroad tracks. It also includes constructing a bridge for Front Street that will bridge over Lincoln Avenue. Phase 1 of this project, which relocated utilities for both underpasses, was completed in the fall of 2007. All of the right -of -way required for both underpasses has been acquired. Phase 2 of this project, which constructs the Lincoln Avenue underpass, was awarded to Apollo, Inc. of Kennewick, on February 3, 2010. Construction began in March and this Phase should be completed in about 15 months. Lincoln Avenue traffic was detoured onto MLK (reconfigured for two way traffic) on June 2, 2010; the BNSF shoofly was completed at the end of June. Partial excavation for the Lincoln Avenue Underpass, along with construction of the secant pile wall and bottom seal have begun. Design of Phase 3, the MLK underpass, is 95% complete and, with the favorable bidding environment, the funding shortfall for this phase is less than $2,000,000. We anticipate getting the remaining funds and hope to go out to bid on the MLK underpass in late 2010 or early . 2011. With this scenario construction would begin on MLK once the Lincoln Avenue Underpass is complete. • ♦. Projected com'"letion date for Lincoln Avenue Underpass: 3 Quarter F 2 p p Q e Y 011 , _ . . . . . WASHINGTON AVE 0 NUE-BNSF BNSF CROSSING UPGRADE This project consists of upgrading the signals and improving the track crossing by installing new concrete crossing pads. The work is to be constructed by BNSF. A Notice to Proceed was sent to BNSF on August 5, 2009. BNSF has installed the new crossing signal. They have not yet replaced the track panels. This should be completed during the next couple of months. ♦ Project completion date: 3 Quarter FY2010 EAST NOB HILL BLVD. & FAIR AVENUE INTERSECTION RECONSTRUCTION Design for the complete intersection project has been funded by federal STP funds. The full project will consist of widening the intersection and installing a new mast -arm signal. The southeast corner frontage improvements were constructed as part of the Fiesta Foods development, using SIED and REET 2 monies for a portion of the cost. Due to design demands on the Engineering Division for funded construction projects this project design will be used as .a filler project for engineering designers. ♦ Project design completion date: This 'filler work' will extend into 2010. YAKIMA VALLEY TROLLEY BARN & MUSEUM PRESERVATION Using State Enhancement funds, the City purchased the historic Yakima Valley Transportation Company Trolley Repair Barn and Substation on January 31, 2008. Environmental documentation approval has been received to make repairs to the west and south walls and crane system. Bids to make repairs to the trolley barn were received on March 12, 2010, with G.M. McClure construction submitting the low bid of $119,786.88. The majority of the work outlined in the plans has been completed. During construction, other needed repairs were noted, which have been added to the project. It is anticipated that construction will be completed in late July. Other rehabilitation items include repair and upgrade of the barn include masonry repairs and installation of fire and smoke alarms in the substation and the barn. Depending on funds, the scope includes restoring portions of the 6 -mile track and overhead wire system that were not previously done as parts of other projects. ♦ Project completion date: 3rd Quarter FY2010. O 2 WILLIAM O. DOUGLAS TRAIL, 6TH AVENUE & BRIDGE DECK CROSSING • This State Enhancement Grant project constructed a 10 -foot wide asphalt pathway along the west side of 6th Avenue from Hathaway, approximately 0.8 miles in length, which ties into the Greenway,pathway. This new pathway connects the Fruitvale Boulevard • area to the Greenway path at the Naches River and will also provide a pedestrian /bike linkage to the WestTowne Center — Riverside Mall. The 6th Avenue pathway project was advertised on January 13, 2010 and bids were opened on February 3, 2010. Belsass and Smith, out.of Ellensburg, submitted the low bid of $259,165. Construction.began on March 15th and has been completed. We are investigating our limited options for expending remaining funds. • Project completion date: 4th Quarter FY2010. WILLIAM O. DOUGLAS TRAIL BRIDGE RESTORATION AND TRAILHEADS The purpose of this State Enhancement Grant project was to restore the YVT Naches River Bridge including cleaning, rust removal and painting, along with filling in William O. Douglas Trail gaps by acquiring right -of -way adjacent to nineteen private parcels and to add interpretive signing. The right -of -way plans detailing the needed property acquisition for the pedestrian /bike pathway have been approved by.WSDOT ® and right of way acquisition nearing completion. Some of the owners of the properties that were included in the original right -of -way plans are not willing sellers, so we have modified the location of the trail and right -of -way plans. We have executed an agreement allowing us to hire Yakima County to help us in the acquisition of the parcels in the Cowiche Canyon. Long Painting Co. completed cleaning and painting the YVT Trolley Bridge in October of 2009. • Project completion date: 4th Quarter FY2010. . PUBLIC WORKS PARKING LOT RECONSTRUCTION PROJECT A 2007 budget policy identified the need for $1,000,000 to complete the three-year program to replace and restore the subgrade and pavement at the Public Works Complex using six identified funding sources. $300,000+ was budgeted in each year from 2007 through 2009. During the fall of 2008, $600,000 of pavement and fencing improvements were made to the yard, which replaced the asphalt in the worst condition. The Engineering Division, within the next month, will advertise a project to repair a sunken concrete slab in the bus barn, install a sanitary sewer line to treat wash • 0 water and upgrade the storm drain facilities on Public Works property. • Project completion date: 4th Quarter FY2010. • 3 WEST NOB HILL BLVD., 50th AVENUE TO 64th AVENUE The City competed for a TIB grant at the end of August, 2008 but was unsuccessful. We have since selected Huibregtse Louman & Associates (HLA) through competitive interviews to begin design of the . project in anticipation of Federal.or TIB funding. HLA is close to design completion. We have completed the right of way acquisition process with monies acquired as part of the Wal -Mart development agreement. The project construction remains unfunded at this time. There is potential for $950,000 from a possible JOBS bill but we continue to pursue other sources of revenue. o Project completion date: To Be Determined. WEST NOB HILL BLVD., 64th AVENUE TO 72nd AVENUE This project received a $950,000 grant from the American Recovery and Reinvestment Act (ARRA). The project consists of making the frontage improvements on the north side and portions of the south side of Nob Hill in conjunction with the Wal -Mart /Walgreens improvements (additional lanes). These improvements consist of curb, gutter, sidewalk, street lighting and stormwater runoff treatment. Granite Northwest, Inca began constructing this project on September 1, 2009. This project has been completed. o Project completion date: 2 Quarter 2010. COOLIDGE AVENUE, 80th AVENUE to 88th AVENUE This roadway reconstruction project was partially funded when it was a County roadway. With the annexation of this area we received the County's developer contributions in the amount of $213,388 along with a $150,000 Corridor Mitigation Air Quality (CMAQ) grant. The City competed for and received another CMAQ grant for an additional $389,000. The project design is 98% complete and the right of way has been certified. We are in the process of getting the construction funds obligated, and it is anticipated that the project will advertise for bids during the week of July 21st. Construction will include a paved road, curb, gutter and grading for sidewalk on the north side of Coolidge, along with the installation of a sanitary sewer pipe from 86th Avenue to 84th Avenue. Sidewalks and streetlights will be completed at the time of adjacent property development at the developers' expense. • Project completion date: 3rd Quarter 2010. 4 r SOUTH 16TH AVENUE & WASHINGTON AVENUE INTERSECTION . - This project consists of widening and realigning the intersection to meet the new alignment and construction of. Valley Mall Boulevard. Design is approximately 95% complete. Right -of -Way has been acquired from all but two parcels (Ding Ho Restaurant and the Airport). We are in the process of receiving possession in use for the Ding Ho property and are close to resolving the issues with the airport. We anticipate advertising for bids in August. Funding of $1.1 Million is through a Transportation Improvement Board (TIB) grant with local match of $300,000 from REET 2 funds. • Projected completion date: 4th Quarter FY2010. SUMMITVIEW & NORTH 66TH AVENUE This project consists of building a new traffic signal and the addition of a left turn lanes on Summitview Avenue and 66th Avenue. The design of the project is complete and the needed right of way has been acquired. Overhead utility relocation is .scheduled to occur in July, and the project advertised for bids on July 14. Funding of $350,000 is through a 2008 G -0 bond. (A 2009 budget addition added $330,000 for the addition of 0 the left turn lane on Summitview. This changed the project scope and extends the project duration due to additional survey needs; increased design needs and the addition of the right -of -way acquisition process.) We have had one public meeting for the neighborhood and general community. ♦ Projected completion date: 4th Quarter FY2010. NOB HILL BLVD. OVERPASS REPAIR This project consists of making necessary maintenance repairs to the overpass structure through a public works project. In October 2007, HDR Engineers inspected the overpass and recommended correction of deficiencies found that included, but was not limited to, repairing several of the concrete wall and column caps; injecting epoxy -grout into column cracks that were found in several columns; fiberglass wrapping of several columns; repair all bearing pads; clean, epoxy coat and epoxy grout exposed rebar; replace the joint membranes between bridge sections; and, repair the worst parts of damaged hand railings. Mowat Construction was awarded the project and began working on August 17, 2009. All of the work has been completed, except for minor cleanup. The project has been 0 completed. . ♦ Projected completion nd � ompletion date: 2 Quarter FY2010: • 5 . CAPITOL THEATRE PRODUCTION CENTER, PAVILION & PLAZA: PHASE I - Capitol Theatre - Production Center The Production Center (attached to the back of the Capitol Theatre facility) will facilitate the unloading and loading of semi- trucks delivering show equipment, upgrad€ required for computerized lighting, staging and sound; address the need for prop and equipment storage; and parking facilities for production trucks. This also includes a base layout including all lighting and electrical equipment for a 400 seat, flexible, "Black Box" theatre on the second floor. This project is approximately 80% completed. Interior & exterior completion are taking place at this time. PHASE II — Capitol Theatre - Pavilion Development of the SE Corner 3 St. & Yakima Ave. This project is pending funding. PHASE III — Pedestrian Plaza Development of a pedestrian plaza and lobby extension by closing 3rd Street to vehicular traffic between Yakima to Chestnut Avenues. This project is pending funding. TRAHO Architects is the architect for the Project. Leone, Keeble & Moen, a Joint Venture, is the competitively selected contractor for the project and oversees 29 types of subcontracted construction. The updated construction budget, including all design, inspections, fees and construction is set at $6,725,232. s Projected completion date of Phase I: 3 quarter FY2010 KIWANIS PARK, UPPER PARK This project consists of building three Little League baseball fields including field lighting, restroom facilities, a volleyball court, a basketball court and parking lot. Kiwanis club purchased the property adjacent to the existing Kiwanis Park, cleared the property and donated the property to the City of Yakima. Funding includes $500,000 from a Recreation in Conservation Office (RCO) grant plus local funding. The Kiwanis Club has constructed the basketball court and installed new restroom facilities. The project to construct parking spaces along Maple Street was advertised on July 1, 2010 and bids will be opened on July 22. Design of the remaining facilities is ongoing. • Projected completion date: To Be Determined RICHARDSON FIELD CLEANUP AT YAKIMA AIRPORT. This project consists of removing and replacing approximately 2,250 cubic yards of contaminated material. This project is 90% funded by a site cleanup grant that the City received from the Department of Ecology. The project was awarded to Tri- Valley Construction for $151,269 in late October. The project has been completed. Projected was completed: 1St quarter FY2010 6 • • UNDERGROUND STORAGE TANKS AT YAKIMA AIRPORT. The City received a second site cleanup grant from the Department of Ecology to locate, assess and develop a plan to remediate, if necessary, contamination remaining from previously removed underground storage tanks. The project has been completed; wells are in place for monitoring into 2010. o Projected assessment completion date: 4th quarter FY2009; (monitoring ongoing) DOWNTOWN FUTURES INITIATIVE PHASE 4: 8TH STREET and "A" STREET This project is a continuation of the Yakima Downtown Futures Initiative and was - funded with $1.5 million of state fund and federal funds ($1 million from a Washington State Department of Commerce grant and $500,000 of Community. Development Block Grants, CDBG). The limits of this new project include: Both sides of 8th Street between "A" Street and Chestnut and the north side of "A" Street from 6th Street to 3 Street. Along 8th Street project construction includes new sidewalk, pedestrian street lighting (historic style, 13 foot tall lights with dual planter arms), trees and tree grates, tree lighting, an automatic irrigation system, wheelchair ramps and new curbing as needed. Along the 0 Yakima Convention Center the alignment of 8th Street will curve easterly away from the Convention Center allowing for an adjacent 7,000 sq. ft. outdoor plaza for facility use. Bids for the 8th Street project were opened on June 8, 2010, with the low bid of $589,339 • . being submitted by Belsaas and Smith. Construction began on July 12, 2010. Along A" Street project construction includes new sidewalk, pedestrian street lighting (historic style, 13 foot tall lights with dual planter arms), trees and tree grates, tree lighting, an automatic irrigation system, wheelchair ramps and new curbing as needed. The Engineering Division is nearing final design for the project. The project was advertised for bids on June 21, 2010. o Projected completion date: 3rd quarter FY2010 • J 0 OTHER TASKS SERVICE TO OTHER DIVISIONS Service to other divisions continues to be provided. Miscellaneous work has included: Sewer extension and restoration projects, legal descriptions for annexations and vacations; updating irrigation, water and sewer maintenance reference maps; surveying and mapping; miscellaneous assistance to Police, Planning, Streets, Airport, Public Works Divisions and Public Works facilities, Yakima Convention Center, Fire Department, including remodels and miscellaneous projects, and the Capitol Theatre for capital improvement projects; Purchasing Division, etcetera. We recently provided engineering assistance for: • Convention Center: reroofing, partition recovering and stucco repairs. • Capitol Theatre Remodel: provide design and construction oversight for this project. Consultant selection for GC /CM has been completed. • Several small drainage improvement projects. • Fire Station Remodeling Project: review and coordination. O 8 Water /Irrigation Division Capital Improvements Projects • General 308 Irrigation System Phase 3 /Stage 3 Improvements This project consists of replacing irrigation main and services in the General 308 Irrigation District.: The limits of the project are from South 2nd Street to South Fair Avenue and from East Pine Street to East Yakima Avenue. Huibregtse, Louman Associates completed the design and the project was bid on October 7, 2009. A total of ten bids were received, with the low bid of $804,956.71 being offered by Apple Tree Construction Co.,` LLC, Yakima. Construction began in November and has been completed and accepted on June 1, 2010. Final contract price was $750,570.57. The project replaced approximately 12,000 feet of irrigation main, along with 325 new services. City Irrigation crews also replaced approximately 4,000 feet of irrigation main and replaced 92 services in the General 308 System s Project completion date: 2 Quarter FY2010. Capitol Hill Irrigation System Phase 1 Improvements 0 This project consists of replacing irrigation main and services in the Capitol Hill Irrigation District. The limits of the project are from South 12th Avenue to South 18th Avenue and from MaClaren Drive to Summitview Avenue. Huibregtse, Louman Associates, Inc. completed the design and the project was bid on September 30, 2009. A total of ten bids were received, with the low bid of $922,348.60 being offered by TTC Construction, LLC, of Yakima, WA. Final ' contract price was $968,837.84. Construction began in November and has been completed. Project acceptance is scheduled for July 20, 2010. The project replaced approximately 14,000 feet of irrigation main, along with 314 new services. s Project completion date: 2nd Quarter FY2010. Fruitvale Canal Pipeline Improvements The project will replace an open ditch irrigation wasteway /canal with a piped irrigation line along East H Street from North 6 Avenue to North 9 Street. Huibregtse, Louman Associates, Inc. has completed a preliminary, report providing a preliminary design and project costs. Project design is underway and is expected to be completed early 2010. The project will be broken into phases and be bid as funding for construction becomes 0 available, including potential grant or other outside funds. s Project completion date: On- going. 9 Gardner Park Domestic Well The project installs a new 3,000 gpm domestic well in Gardner Park, located at Cornell Avenue and West Pierce Street. Construction on the project began January 2009. The well was drilled to a depth of 1,328 feet. Well screen and casing has been installed and pump testing of the well has been completed. Golder Associates has begun the design for the new pump station for the well site and is approximately 95% complete. The project report, construction approval and source approval documents have been submitted to the Department of Health. The pump station is expected to be competed and the well on line mid - 2010. ♦ Project completion date: 3 Quarter FY2010. Water System Plan Update The last Water System Plan was completed in March 2004, an update must be completed every six years. This project will update the current plan by providing current information on the existing water system infrastructure, production and consumption data, future demand forecasting, water use efficiency, operation and maintenance, future capital improvements, rate structure and revenue forecasting. Thomas Coleman, PE Consulting Services has been hired to complete the plan update in coordination with City staff and the Department of Health. ♦ Project completion date: 4th Quarter FY2010. Water Treatment Plant Backwash Recycle Upgrade The project will replace the unlined backwash recycle pond with new lined recycle • • ponds. Huibregtse, Louman Associates is developing a preliminary design recommendation and report to submit to the Department of, Health for approval. We also submitted a 2010 Drinking Water State Revolving Fund (DWSRF) Application, which was not approved. Funding sources will continue to be pursued to complete the project. ♦ Project completion date: 4th Quarter FY2011. O 10 0 East Viola Avenue. (I 82.Crossing) Waterline Replacement The project will replace an undersized, deteriorating waterline crossing under I -82 at East Viola Avenue, between Rudkin Road and the Wastewater Treatment Plant. Replacement of the waterline will improve flows and reliability in this part 'of the water system, as well as replace a sub - standard, direct bury waterline across I -82 with a new ductile iron waterline in a steel casing within the limits of the interstate highway. Huibregtse, Louman-Associates has begun the design and is approximately 90% complete. The project will . be constructed as funding becomes available. ♦ Project completion date: On- going. General 308 Irrigation System Phase 4 /Stage 1 Improvements This project consists of replacing irrigation main and services in the General 308 Irrigation District. The limits of the project are from North Naches Avenue to North 8th Street and from East A Street to East F Street. The project will also 41) replace a portion of the transmission main located along Hwy 12 west of North 40th Avenue. Huibregtse, Louman Associates completed the design survey and is currently working on design. Construction is anticipated to begin November, 2010 and be completed by March 2011. City Irrigation crews will also replace approximately various portions 'of the irrigation main and services in the General 308 System. • Project completion date: 2nd Quarter FY2011: Capitol Hill Irrigation System Phase 2 Improvements . This project consists of replacing irrigation main and services in the Capitol Hill Irrigation District. The general limits of the project are between South 7th Avenue and South 12th Avenue, West Yakima Avenue and Tieton Drive. Huibregtse, • Louman Associates completed ' the design survey and is currently working on design. Construction is anticipated to begin November, 2010 and be completed by March 2011. ♦ Project completion date: 2nd Quarter FY2011. 0 1, . . . . . Wastewater Division Capital Improvements Projects Digester Cover Replacement g p ment Project This project was. contracted in the 1St Quarter of 2009 and construction began in the 2nd Quarter of 2009. The project includes the replacement of the three secondary digester covers with new membrane gas holder covers; replacement of secondary cover blowers, air piping, Motor Control. Centers - (MCCs), local control panel and associated digester system accessories; improvements to the Secondary Digester Control Room,and Primary Digester electrical Room; replacement of the existing Dissolved Air Flotation Thickener (DAFT) mechanical system, improvements to plant SCADA system, sludge piping improvements; modifications to the plant electrical distribution system and; dredging of an existing storage lagoon. The Dredging of the old lagoon is complete and replacement of the existing DAFT has been completed and was commissioned the second week in April. The digester covers have been replaced and startup will begin in the 3rd Quarter of 2010. • Project completion date: 3 Quarter FY2010 Collection System Repairs 410 Engineering designed the repairs and put a package of bid alternates together that went out to bid the 4 Quarter of 2009. Construction began in and was completed the 1St Quarter of 2010 completed. The project consisted of the replacement of a sanitary sewer Man Hole at N 2nd ST and E D ST, repair of a lateral from W D ST to the South side of W Lincoln Ave, and repair of the lateral from W Nob Hill BLVD (just West of S 16th AVE) to W Prasch Ave. We are looking at adding a repair to this project for addressing the Sewer line bottle neck at 3rd and Pierce also. • Project completion date: 1st Quarter FY2010 Second Phase of the Speedway Race Street Interceptor The Engineering Division is designing the remainder of the Speedway Interceptor that will eliminate Race and Beech Street Lift Stations and extend a 36 inch sewer main to the sewer main at 8 Street and Beech at the Washington Middle School. The exact Route is being planned and will be determined by the ability to get a Franchise from the Wash. St. Dept. of Transportation along I -82. Construction will be phased and may begin this year. We have submitted the Franchise application and are waiting to here if WSDOT approves this prior to any further design. • Projected project completion date: 4th Quarter FY2011. 12 Wastewater Facility TMDL (Struvite) Project ' III Initial design concepts ,cepts are being evaluated and Pharmer Engineering has been selected for this assistance. This project will begin reducing our nutrient concentrations in the wastewater effluent discharged to the Yakima River as required by the Dept. of Ecology. Required construction will include the fabrication and installation of a reactor to harvest phosphorous and the installation of 8 mixers in the aeration basins to augment nutrient removal through the reactors. ♦ Projected project completion date: 2nd Quarter FY2011. Wastewater Facility_ and Collection System Plan Update and initial Stormwater Comprehensive Plan. The last Water System Plan was completed in February 2004. This project will update the current facility plan by providing current information on the existing wastewater facility and collection system infrastructure, regulatory requirements, future loadings, operation and maintenance, future capital improvements, rate structure and revenue forecasting. 0 With the adoption of the new Stormwater Regulations a comprehensive Stormwater system plan is needed and will be implemented along with the Wastewater Facility and Collection system plan .update. A consultant will be selected in the 3rd quarter of 2010 to develop these plans. e Project completion date: 2nd Quarter FY2012. Levee set back Project and new Wastewater Outfall Staff continues to be involved in the Gap to Gap project for flood plan restoration which will include the Wastewater Treatment Plant to relocate or develop a new wastewater outfall. Alternative will be evaluated to select a new outfall location. Currently the old Wastewater spray field is being evaluated as a riparian outfall. An engineering report for alternatives like this will be developed and submitted to Ecology for approval. ♦ Project completion date: 4th Quarter FY2012. .• . . . . 13 FY2009/10 PRIVATE PROJECTS Listing private developer projects shows the amount of private projects that are "on the books" and pending or under construction with some (not all shown) that go back several more years. These projects have all been approved since January 2007 and are either pending construction, under construction, started but not completed or recently completed. The projects include: Project Name Location Improvements Wilson Properties 16th Ave. N. of McKinley Sewer extension Golden Corral 1901 -1915 S. 1st St. Street improvements Larry Loveless Short Plat 8100 Tieton Dr, Water, sewer & new street Hollow Creek Place Short Plat S. 27th Ave. Hollow Creek PI, Street Improvements WestTowne Center - Riverside Mall 16th Ave., River Rd & 6th Ave Mall Site Development Rite Aid - Nob Hill BLVD Nob Hill & 24th Avenue Site, Water, Sewer & SD Washington Mid School Portable Unit 510 S. 9th St. Site Improvements Franklin Middle School Portable Unit 410 S. 19th Ave. Site Improvements Hoover Elementary Sewer Extension 400 W. Viola Ave. Site Improvements Future Fun LLC Drainage . 715 S. 2nd St. Storm Drainage Advanced Secure Storage Drainage 1913 McKinley Ave. Storm drainage All Services Parking Lot 715 E. Viola Ave. Parking Lot Anderson Park Occidental & 64th Ave. Site Improvements Yakima Bears Executive Viewing Deck Pacific & 12th Ave. Water line alignment • 14 • AFFIRMATIVE ACTION GOALS & WIMIDBE PARTICIPATION W/M /DBE utilization has been included in the past but is not included with this report. S The Engineering Division continues to request apparent low bidders of public works contracts to document their efforts to achieve the City of Yakima's goal of 10% MBE, WBE or DBE participation goal prior to contract award. However, changes in state law due to the passage of Initiative 200 prohibit certain practices by contracting agencies (i.e. the City) for the award of public works projects such . as requiring W/M /DBE subcontracting. While some contractors have voluntarily reported such information in the past, we have not received any such reporting this year. Although we do not receive such information voluntarily, the City must still meet certain of these federal requirements and each contractor must comply with the Standard Specifications that are included on each City Public Works Contract. The City is responsible to: • Conduct pre- construction conferences during which EEO and City policies are discussed with the contractor. • Monitor on -site compliance with the EEO and City policies. • Ensure our contractors locate, qualify, and increase the skills of minority groups, women employees, and applicants for employment as required by City policies. • Ensure the preparation of required EEO and related reports. 110 .. 41) • 15 Proj Proj. Lead Project Name /Location Description of Work Project Lead • Impacted Constrctn. Status /Schedule Notes Type .No. Division . Divisions Star bate 7/13/10 Underpass on Lincoln; (MLK Jr. Engineering, Apollo Inc, Kennewick, was low bidder; The 12- • - • -• contractor • 1818 R/R Grade Separation Phase II; Blvd. late in '10); Front Street Bob Desgrosellier / Water /Irrigation, Phase H, Main CIP Engineerin month detour is in place on MLK; Rail Bridge will be project is sch -• for completion • Phase II Lincoln Ave.; 1st St. to 1st Ave. over Lincoln (and,MLK Jr. Brett Sheffield Wastewater, PW, Project, 3/10 1st major work. i Work • - - • n reconstructio Blvd.. Streets, IS 1818 Grade Separation, . Underpass : Construction proposed starting June 2011; We will be ready to go with the MLK Underpass when 2 CIP Phase - • • • - • • • - Sheffield _ Phase -.Design is at 95% & continuing; _ remainder secured III • Ave. = • All R/W is in hand ' funding Streets, IS . • BNSF will be 3 CIP 2063 - ' ' • - Y cing new Sheffield Bob • BNSF has the new signal in place and is finalizing • • • • - • • - • • - • • ' .+ .. - ' ' ' "' - .. - . - the crossing replacement • • • • •' • - ' • ....- .4 CIP 2153 - . . - - - ... • - ' • Project has been awarded • • _�_d August. Bob - • - to GM McClure of Yakima; 70% complete buildings and • - work possible Avenue Street '' ' Project been Construction has begun and 5 CIP 2166 Engineering : • _ Engineering • • = - - - • - should be completed this summer. Bridge Deck Crossing _ River; pathway to _ _ work is complete : being closed . More work possible with remaining funds. Righ t -of -way purchases are under way for property in6 CIP • -- • _,• - -• :•• �_ • _ _ 00' = ••- ' • - • - • '•- • • ' the CowicheCanyon area; !*'--' - • - some •urchases have been made • - & rebuild project is a 3 phase reconstructiqn • - over Phase 3 will include the interior • B Complex asphalted - _ • rebuild asphalted • • parking garage floor repair in 2010 Public Works Reconstruction _ budgeted . • Phases 1 & 2 completed - ' ' ( & storm drainage improvement? ) Study Fire, • begun. ; ' - • - service • . • Police, ^ $50k approved through 2007 Council Budget Admin • ineering_L--- Fueling Station Addition @ 1st St. & Build _ remote fueling station Bob Desgrosellier • Proposed a ARCO . t, lst St. & Lincoln Avenue Demo of the ARCO building is complete; � ® • Lincoln Public Works • - • Wonner Works or earl 2011 after Grade Se•aration construction. pump station reconstruction near end of project Engineering, Traffic Project tied to the Wal -Mart project. There may be Design is 90% complete; Well shelve plans in • -- •• • • •• - •- ' - • add :.. • - . . • - R/W was purchased with Wal mart mitigation osome preparation for next funding on UN- FUNDED, opportunity; 10 CIP 2272 fundin• Count was hired to do some R/W ac• uisition. Project to • - p' • - • halt Coolidge We completed R/W acquisition Construction should be completed in 2010; 11 CIP Engineering • Avenues • • • • _ _ • _ - & are awaiting Federal Approval delayed due to extended R/W acquisition. include E. . • .: - - • - - . -. - . Engineering Design only at this time beginning 6/2008; Design only; (Drainage system 12 CIP • -- Intersection Improvements signal Randy _ •. - Design ' Search for funding on -going for this intersection is included.) Water/Irri•ation Ave Avenue Widen _ _ ll J 1 j' Design began Fall 2008; TIB Grant of $1.1 Million; 13 . CIP Design Completed & match with $300K REST 2; 6th intersectio reconstruction , • replace signal Dan • • • rig • R/Way is in final stages with Ding -Ho & Airport _ R/W purchases 78% complete Traffic • - ., Overlay . .. • : - _ - • Brett • ; - • Project design funded by REET2 m4�letion 16th & Washingto Avenue project 14 CIP I .. Avenue : - Brett Sheffield Design & R/W complete, Project will now widen Summitview for a 5th lane at the 15 CIP - Avenue Signal street _ • Utility relocations taking place ' signal; Utility poles are being relocated by the utility com •anies Repair ____ • farted 8 /20 /09e h At C 2010 ction Co.; Work Pro'ect clean and osin CIP 2229 • •• • - •. ■ -•. • -- ' ��• q p 1 P 9 Utilities TRAHO is Architect; GC /CM Contractor Leone, Production Center Const. only at this time; Funded - 17 CIP 2231 Keeble &Moen (Joint Venture); Project is 80% through municipal bonds, Public Facilities District & • complete; Finish construction in August private donations from Theatre benefactors RCO grant $500,000 + local funding; RCO grant of $500,000 + local funds - Little League overall design is approx. 50 %; Fields; lighting; volleyball; restrooms; some parking & • 18 CIP 2212 - • Maple Street parking project out for bids; walking pathway; Restroom construction starled. playground to be built by volunteers • Proj Proj. Lead • Project Name /Location Description of Work Project Lead Impacted Constrctn. Status /Schedule, Notes • Type No. Division Divisions Start Date 7/13/10 Remove Underground Storage Underground Storage Tank Removal Doug Mayo / Work is complete; ' DOE grant included locating, assessing and 19 CIP 2274 Engineering Tanks & remove /replace Engineering, Airport 2009 at the airport contaminated soil Brett Sheffield Waiting for DOE review and approval of report; developing a plan to remove unused UST's Richardson Field Cleanup Remove & Replace 4,000 CY of Doug Mayo / DOE grant included removal and replacement 20 CIP 2145 Engineering at the airport contaminated soil Brett Sheffield Engineering, Airport 2009 Work is substantially complete; of 4,000 CY of contaminated soil . Realign 8th Street, remove & Realign and reconstruct 8th Street from "A" to Engineering, Streets Belsaas & Smith of Ellensburg were low bidder of the Downtown Futures Initiative (DFI), Phase replace sidewalk, place new Yakima Avenue; Rem /Repl. sidewalks north of Brett Sheffield / & Traffic Eng., 8th St. project; work has started and will be completed 21 CIP 2284 Engineering 4; 8th St:, "A" to Chestnut; & pedestrian lighting, trees, 7/2010 Yakima Ave.; place trees, twinkle lights and ped Bob Desgrosellier Water /Irrigation, this fall; "A" street is out "A" St., 3rd to 6th Streets, north side twinkle lights, landscaping lights "A" to Chestnut; Sidewalk & landscaping on . Wastewater for bids and work will begin in late August. "A" St., 3rd St. to 6th St., north side only • Remove & replace sidewalk, County & City Joint "DFI Styled" Engineering, Streets Granite Northwest is Low Bidder; new lights, trees, twinkle lights, Brett Sheffield / Improvements; West - side of 2nd Street, & Traffic Eng., Construction is complete; 22 CIP 2285 Engineering MLK to "4" Street; north side "A" Street landscaping; (New communit Mark Brzoska Water /Irrigation, 10/2009 (Adjacent Performance Park • Project is being closed out 2nd Street westerly to alley; performance park is adjacent) Yakima Count Wastewate Construction is complete) Place several types of Surface Reconstruct north side of street using porous asphalt, 23 CIP 2291 Engineering J Street LID Demonstration; Water Drainage Materials in Randy Meloy / Engineering, Streets 4/2010 RP &E of Ellensburg has contract; porous concrete and permeable pavers. South side to "J" Street, 18th to 20th Avenues roadway for drainage study Brett Sheffield project is complete and is being closed out have asphalt pavement with compost- amended _ roadside ditch. 64th Avenue; Doug Mayo / Surveying completed; 24 CIP ? ? ?? Engineering Roadway and Pathway Engineering, Streets ? ? ?? Wal -Mart is funding part of project as mitigation Nob Hill to Tieton Drive Brett Sheffield R/W and funding is needed. Reconstruct intersection, widen Tieton Drive and 64th Avenue Doug Mayo / Surveying has been completed; 25 CIP 2282 Engineering for additional lane on Tieton . Engineering, Streets ? ? ?? Wal -Mart is funding part of project as mitigation Intersection Brett Sheffield R/W and funding are needed. Drive; add signal Remove trolley tracks from o S. 2nd Avenue, Doug Mayo / Design is at 57.63%; Remove trolley tracks & rebuild center of roadway; 26 CIP 2286 Engineering Yakima Avenue to Walnut Street roadway; add planters to p art Brett Sheffield Engineering, Streets 2010 Funded with $150,000 REET Funds add planters to portions of roadway center of center of roadway _ _ _ Remove jail cells, interior walls E 27 CIP 1783 ngmeermg x City Hall Demolition of & asbestos abatement; Doug Mayo / . Engineering, CED 2010 Wardell Architects demo dac's; Work should be completed by the end of 2010 NE1N,�"f .° interior 3rd and 4th Floors Bob Desgrosellier demolition has started Rem /Repl windows g Engineering 8" sanitary sewer Doug Mayo / Engineering, Survey and design started in- house; 28 CIP 2297 : ,,, Swan & Willow, 20th to 24th 2010 Funded through Wastewater .NEV11 „ ary Brett Sheffield Wastewater easements and /or R/W are needed on Swan ' Engine Reconstruct sewer manholes Doug Mayo / Engineering, Design is Complete; ��� 29 - CIP Pierce Avenue at 3rd Avenue Summer 2010 Will be bid through the Small Works Roster ' < and connections Dana Kallevig Wastewater Construct this summer 30 M &O Streets Area 18 - 32nd Ave, Tieton, 40th Chip seal Chris Waarvick Water /Irrigation/WW 1/1/07 chip seal application began mid - August REET2 paying for materials Ave, Englewood 31 CIP 2055 Wastewater WWTP Phase 1 Facility Wastewater /Facility Max Linden B &V/Water- Irr /Com. 6/1/06 WWTP improvements /upgrades - construction Apollo Inc - 100% complete Improvements Electronic sec completed . CIP 2221 Wastewater Final Scada Tip Out Wastewater /Facility MaxLinden Wastewater /B &V 5/1/09. Continued SCADA and wastewater continue tipping out existing communications systems 2222 DAFT Retrofit improvements /upgrades - Project 221, 2222, 2223 replace existing covers/ fix pressure and flow 32 2223 • Dystor Retrofit bid as one contract -Bids opened On April 14- monitoring issue, electrical distribution system Apollo is apparent low bidder, Apollo awarded upgrades contract - 30% complete. CIP 2228 Wastewater Congdon Sewer Main Wastewater /Collection Sys Max Linden /Shelley Engineering/ 10 ? Unknown 33 Willson Wastewater CIP 2234 Wastewater Neighborhood Wastewater Wastewater /Collection Sys Max Linden /Shelley Engineering/ 10 ? Unknown 34 improvements Willson Wastewater 35 CIP 2264 Wastewater Speedway /Race street Interceptor Wastewater /Collection Sys Max Linden WW /Eng. /PLSA ? 1/1/10 Design for the completion of the 36" sewer line to Race street LS and demo LS 36 CIP 2254 Waste water Security upgrades Wastewater /Facility MaxLinden Wastewater /B &V 1/1/10 New gate and additional lighting 37 CIP 2255 Wastewater Pretreatment offices Wastewater /Facility MaxLinden Wastewater 6/1/09 Add office space in storage building 09 50% complete 38 CIP 2256 Wastewater Magnesium Tank Relocate Wastewater /Facility MaxLinden Wastewater 1/1/10 New tank and locate within one of the old chemical buildings CIP 2293 Wastewater W " Collection system repairs Wastewater /Collection Sys Max Linden /Shelley W /Eng 11/9/09 Designed - tom 39 New w Willson • i I Proj Proj. Lead . Project Name /Location Description of Work Project Lead Impacted Constrctn. Status /Schedule ' Notes Type No. Division Divisions Start Date 7/13/10 III PWTF Loan approved. Water right transfer -Water /Irrigation, complete 8/22/06. Golder and Assoc:. completed Worked with Parks Division on siting of new well at 40 CIP 2132 Water /Irrigation D esign and Install a new 3,000 gpm New well at Gardner Park Dave Brown Streets, Eng, Parks, 1/26/09 design. Bid Opened Nov. 6, 2008. Awarded to Gardner Park. Archeological survey complete - no well at Gardner Park P dgeview School Layne Christensen Company. Drilling started on findings. Drilling operations completed. Golder Feb.9th. Drilling has been completed as of 3/9/09 working on design of pump station. Plans at 95% (1,328'). Wellhouse design at 95% In Progress, lined canal under Hwy 12, completed Water /Irrigation, study, work needed on diversion and areas of the HLA has completed report and recommendations for Refurbish the Fruitvale Canal, canal. Enlarged pipe from General System to Fruitvale multi -year piping project from 6th Ave. to 9th St. HLA Dave Brown /Mike Streets, Stormwater, 41 CIP 2010 Water /Irrigation Fruitvale Canal Diversion and Wasteway on H 2010/2011 Canal. City crews completed connection between working on design of entire project and make ready for Shane Parks, DOT Yakima St. General and Fruitvale systems near 16th and Jerome. construction. Working with other Divisions and County, WDFW Repaired wood gates at Cowiche Creek. Considering agencies on joint project. a point of diversion change to Nelson Bridge in 2010 . Water facilities impacted by . other improvements - DFI, Misc. Mike Shane /James Water /Irrigation, On -going coordination with DFI projects, sidewalk 42 CIP 2288 Water /Irrigation Misc. waterline improvements. sidewalk & transportation Dean Streets, Eng. 2010 projects and misc. Transportation projects Majority of work to be completed by in -house staff. projects. _ Capital Hill /Loma Vista Irrigation Irrigation System Replacement Water /Irrigation, HLA is consultant. Project design complete. Bid 10 bids received. Low bidder TTC Construction LLC at 43 CIP 2257 Water /Irrigation Mike Shane 11/1/09 Opening was Sept. 30, 2009. Construction approx. $922,348.60. EE - $1,272,599.71. Final contract price System Refurbish in various neighborhoods Streets 100% complete. $968,837.84 Irrigation System Replacement in the neighborhoods north of E. HLA is consultant. Project design complete. Bid 10 bids received. Low bidder Apple Tree Construction 44 CIP 2180 Water /Irrigation General Irrigation Pine St., south of Yakima Ave., Mike Shane Water /Irrigation, 11/01/09 Opening on Oct. 7, 2009. Construction is approx. Co. at $804,956/1. EE - $698,043.76. Final contract Phase 3 Stage 3 east of S. 1st St., west S. 10th Streets 100% complete. price - $750,570.57 St. Begin preliminary plan, Plan Water /Irrigation Tom Coleman is Consultant. Project kick -off 45 CIP 2258 Water /Irrigation Water System Plan Update due in 2010 Dave Brown Planning N/A meeting with DOH on July 23, 2009 Recycle lagoons and new electrical Design of new recycle lagoons; Dave Brown HLA to provide report to City and DOH on 46 CIP 2259 Water /Irrigation service at the WTP new 800 amp electrical service; Mike Shane Water /Irrigation 2010 recommendations for design. new generator Jeff Bond . Internal discussion to began in January to determine Begin process of determining Dave Brown Water /Irrigation next course of action. G & 0 consultant to provide Inter agency agreement approved by Council, Selah 47 CIP 2261 Water /Irrigation Automated Meter Reading method, materials, process for Mike Shane Wastewater 2009 study and recommendation for Yakima, Selah and and Nob Hill. automated water meter reading James Dean Utility Billing Nob Hill. Report is being developed to provide recommendations specific to each agency. Design the water main Water /Irrigation ° Project will be constructed as funding becomes 48 CIP 2262 Water /Irrigation Replace Main at 1 -82 and Viola replacement at 182 and Viola Mike Shane Wastewater 2009 HLA is consultant. Project design is 95% complete. available. Irrigation System Replacement in the neighborhoods north of E. • General Irrigation Water /Irrigation HLA is consultant. Project design survey underway. 49 CIP 2287 Water /Irrigation A St., south of E. 1 St., east of Mike Shane 2010/2011 Phase 4 - Stage 1 S. 1st St. and west of S. 10th Wastewater, Streets Bid opening fall of 2010 St., SR12 at 40th Ave. • Capital Hill /Loma Vista Irrigation Irrigation System Replacement Water /Irrigation HLA is consultant. Project design survey underway. 50 CIP 2257 Water /Irrigation System Refurbish Ph. 2 in various neighborhoods Mike Shane Wastewater, Streets 2010/2012 Bid opening fall of 2010. .......... ✓s.,.Sie2'.- X.&t ..+_v._ %44.k 1 N49•&aw...... ,.., .,, $ .4 ,F>2 s ?S*, k . _..... .. .Et . ...,+,'... ,. <,-m - ,... r,a.,, ... �. ,. _ ',' , ..a .t.. -. -_. a. , ....t'' a-X. ' ,c , ., . ,. ... , . ... _ > . .<_.. A . ,. �.r2. _, . -. _ .m. .. A.. . . 4,; A COMPLETED PROJECTS ffield / — Interest from private partners fell through; CIP 2241 Engineerin south to Airport and rebuild roadway Bruce Floyd Engineering Cancelled 6/2010 project will be cancelled Project to be deleted from list Ped signals at 16th & Bonnie Doon; New crossing signals and Brett Sheffield / Low bidder: Knobel's Electric of Yakima • CIP 2236 Engineering 4th Street & MLK; Engineering, Traffic 10/2008 Construction 100A.Complete. ° N. 1st St. & N. 16th near Hathaway painted crosswalks Dan Ford. _ 4/2010 • r . . • Proj Proj. Lead Project Name /Location Description of Work • Project Lead Impacted Constrctn. Status /Schedule Notes Type No. Division Divisions Start Date 7/13/10 . Roadway reconstruction, • Jeld -Wen roadway imp's; • Brett Sheffield / Low bidder: Granit NW of Yakima CIP 2120 Engineering 6th Avenue, River Rd. north 650' pathway addition on west _side Dan Ford Engineering 7/2009 4/2010 Construction 100% Complete. • of roadway CIP 2182 Wastewater UV Disinfection Wastewater /Facility Max Linden B &V/Water- Irr /Com. . 3/1/08 WWTP.improvements /upgrades - ` bid, contract awarded to Apollo Inc. • Electronic sec 100% complete; closing project out: CIP 2188 Wastewater 40th & Fruitvale sewer sleeve • Wastewater /Collection Sys MaxLinden B &V /Eng/Water March /April 2007 WSDOT Project- Completed complete, waiting for WSDOT project closure Widen roadway, add sewer & Brett Sheffield / Engineering, Traffic Project cleanup & closeout is underway; CIP 2278 Engineering Nob Hill Blvd, 64th to 72nd Avenues 8/2009 Project is 100% complete 4/2010 water utilities Bob Desgrosellier Eng., Wastewater $950K ARRA funding received for City portion 85th Avenue, Kail & Juanita Sewer Neighborhood sewer LID - Al Rose / Brett Engineering, Premier Excavating was low bidder; Project is closed out; CIP 2208 Engineering Local Improvement District (LID) Approx. 29 parcels Sheffield Wastewater 2/2009 100% complete final assessment hearing went to Council 4/6/10 Simpson Lane Sewer LID; So. 13th, Neighborhood sewer LID - Bob Desgrosellier / Engineering, Scott's Excavating was low bidder; CIP 2215 Engineering 14th, 15th Streets Approx. 82 parcels Al Rose Wastewater 2/2009 100% complete Council assessment hearing is complete; 4/2010 Realign 16th Ave. south side of Engineering, Streets & ° • Brett Sheffield / Project is 100% complete; 100% CIP 2213 Engineering 16th Avenue Realignment @ Airport airport tying to future V. Mall Traffic, Wastewater, 7/2009, 100 /o complete. • Blvd. & 16/Wash Bob Desgrosellier Water /Irrigation Low bidder was: Granite Northwest; Downtown Futures Initiative (DFI), Phase Remove & replace sidewalk, Engineering, Streets Reconstruct: east side 1st Street; 2nd St. both 3; 1st St., n/o Yakima; 2nd St., "A" to new lights, trees, twinkle lights, Brett Sheffield / & Traffic Eng., sides, 3rd St. both sides, west side Naches all ° CIP 2216 Engineering Chestnut (or Walnut); 3rd St., "A" to landscaping Bob Desgrosellier Water /Irrigation, 7/2008 Yakima Ave to "A" Street; plus both sides • 100 /o complete. Yakima; (Naches "A" to Yak ?) Wastewater So. 2nd St. Yakima to Chestnut • Tieton Dr. Pedestrian Project, Update north side sidewalk, Brett Sheffield / Engineering, Traffic, ° CIP 2233 Engineering 16th Ave to 24th Avenues including wheelchair ramps Dan Ford / • Wastewater, 10/2008 Construction is 100 /° complete 100% complete. • Joan Davenport Water /Irrigation . Nob Hill Blvd, Construct sanitary sewer, north Doug Mayo / Engineering, CIP 1977 Engineering 53rd to 62nd Avenues ( +/) side of roadway Brett Sheffield Wastewater 8/2009 Premier Excavating: Project completed • 100% complete. Kiwanis Skateboard Park; New concrete Skateboard Park Construction is complete; Parks CIP 2023 Engineering Fair Ave &Maple Street @ Kiwanis Park Bob Desgrosellier Engineering, Parks 6/2008 Bids opened on 5/15/08 has project funds for a few more amenities el Grind and Overlay (G &O) Engineering, Traffic, 3rd Ave. Grind & Brett Sheffield / We extended grind and overlay to just north of CIP 2230 Engineering Mead Avenue to Chestnut roadway & restripe; update Randy Tabert Wastewater, 8/2008 Washington Avenue. Project is complete wheelchair ramps Water /Irrigation Engineering, Streets, • W. Nob Hill - Grind & Overlay; Grind and Overlay (G &O) of Bob Desgrosellier / Received good bids; grind inside lanes and sealcoat Project is complete; CIP 2214 Engineering 24th Avenue to 4th Avenue two inside 'through' lanes Wayne Deason Water, Wastewater, 8/2008 entire width in 2008 ($500,000 REET ?) Streets to sealcoat in future as funding is available Traffic Eng Streets Poplarview Way Check face of plat Chris Waarvick / Nob Hill Water Graded and dust abatement material applied spring M &O Randy Meloy Wastewater 2008 2007; new easement in place Project is complete Rdwy New 3 lane roadway, C /Gutter Engineering, Streets, River Rd. Improvements, 15th to 1944; & S/Walk, ADA ramping, street Brett Sheffield / Traffic, Water / CIP Engineering Fruitvale; 27" Sewer trunk 6th Ave to 9/19/06 - This project is closed out Complete Sew lighting. Replace 8" sewer with Bob Desgrosellier Irrigation, Old Union • 2128 Fruitvale 27" trunkline Ditch, Wastewater CIP Engineering Harman's Senior Center Parking Lot Reconstruct & repave parking - Brett Sheffield / Engineering, Parks 4/21/08 contractor done; complete 5/2/08 Project is complete Reconfiguration - N. 65th Ave. lot to maximize parking Streets 80th Ave - Zier to Tieton; Zier - 72nd Ave. to Arterial Chip Seal Wayne Deason Mid -June 2008 REET & Street Division Budget 80th Ave.; 72nd Avenue - Nob Hill to Coolidge; • • Castlevale -24th Ave to Powerhouse; M &O Powerhouse - 40th Ave to the West City limits; . Powerhouse 40th Ave to Lincoln; ONDS development, was Brett Sheffield / Engineering, ONDS, CIP 2107 Engineering Marvin Gardens Development private, switched to public Al Rose Wastewater, 10/15/07 This project is complete and being closed out Project is complete Water /Irrigation Remove & replace sidewalk, Street & Traffic, West Yakima Avenue Improvements; Brett Sheffield / Project is complete; Banners are in place; working on CIP 2165 Engineering Front Street to 7th Avenue new lights, trees, twinkle lights, Bob Desgrosellier Water /Irrigation, • 7/2007 This project is complete getting spring - loaded banner arms'outside of contract landscaping Wastewater . Engineering, Westcoast Construction is Prime; Work included R/R Grade Separation, Phase I; Utilities Relocations Phase I - Utility 1818 Bob Desgrosellier / Water /Irrigation, Front Street and "A" Street bricking /paving in Project is complete; CIP Phase I Engineering Lincoln Ave. & Martin Luther King Jr. surrounding the Grade Brett Sheffield Wastewater, PW, Relocation work existing right-of-way; includes utility relocation in we soda blasted utility markings as final step Blvd. vicinity Separation Project Streets, IS began July 23rd area of future underpasses CIP 2087 Wastewater Speedway Interceptor SR24 phase I- Wastewater /Collection Sys Max Linden • B&V/Engineering 3/19/07 Need to connect at diversion box - completed - work complete waiting for WSDOT project closure and 82 Viola to Speedway on punch list WWTP waiting for rebate of funds from DOT • • ■ Proj Proj. Lead Project Name /Location Description of Work Project Lead Impacted Constrctn. Status /Schedule Notes • Type No. • Division Divisions Start Date 7/13/10. - _ CIP 2087 Wastewater Speedway Interceptor Speedway to Wastewater /Collection Sys Max Linden B &V /Engineering Design /Bid /Construction inspection- Not funded yet Washington School Memorial Hospital to "rebuild" Engineering, Streets, Eng has estimate for Streets & Waarvick; awaiting No. 30th Avenue - Reconstruction; Bob Desgrosellier / • CIP - Engineering 30th Avenue due to damage Water /Irrigation, ? / 2007 Hospital funding; may have been sealcoated for • Seal Coating completed Tieton Drive to Walnut during their campus upgrades Bruce Floyd Wastewater temporary measure? Fruitvale Blvd & 40th Avenue 200' +/ of 42" carrier pipe for Brett Sheffield / Street & Traffic, Superior Paving is prime; Project tied with WSDOT Sewer xing complete; o • CIP 2188 Engineering Water /Irrigation, Feb /March 2007 construction project of new on -ramps and interchange reconstruction @ 98/0, Sewer X-ing of WSDOT on ramp future 27" sewer trunk Bob Desgrosellier Wastewater interchange upgrade. signal in & running; trail connection complete Basalt column placement with lit Brett Sheffield / Bob Engineering, Parks CIP 2116 Engineering Basalt Art Project, 2nd & E. Yakima Cornucopia & brass Sun Desgrosellier 6/7/07 Art work complete, on time and on budget 6 -20 -07 Project is 100% complete; 2 western medians to be Bid, 2-14-07, Washington Avenue Median removed for left -turn storage. Bob Desgrosellier / Engineering, Traffic, Columbia is Prime; 100% CIP 2124 Engineering construct spring o 6 -20 -07 Project is 100% complete; Removal btwn 16th & 24th Ayes Eastern median gets several Randy Tabert Water /Irrig 2007 100% complete new lights & brick pavers 6th Street S/Walk Replacement, one Remove & Replace one block Bob Desgrosellier / Engineering, Traffic, Tied to Lincoln Avenue Sidewalk Construction 100% • CIP 2169 Engineering Spring 2007 0 6th Street project is 100% complete; block n/o Race Street of concrete sidewalk Larry Johnston Water /Irrig Project; Block Grant funds 100% complete New sidewalk on Lincoln, Engineering, Lincoln Ave. Sidewalk, 25th to 29th Bob Desgrosellier / Columbia is Prime; 100% CIP 2046 Engineering adding 24th to 23rd on Linc. Water /Irrigation, Spring 2007 0 8 -11 -07 Project is 100% complete; Ave. & r /wa y purch near 18th Ave. and 40th Ave. near Lincoln Larry Johnston Streets and Traffic Lincoln Sidewalk 100% complete CIP 2095 Water /Irrigation PRV in 40th Ave. Pump Station Install PRV in 40th Ave. Pump Dave Brown Water /Irrigation, Summer 2007 Old pump removed by City crews. PRV installed by Final Cost - $7,100 Rehab, work in -house Station Streets, Engineering City Crews. Work completed. CIP / 2131 Water /Irrigation MaClaren Reservoir Rehabilitation Repaired cracks in MaClaren Mike Shane Water /Irrigation 3/1/07 100% Complete Final Cost - $31,216 M &O Reservoir. Replaced ladder & slide gate. Repaired weir box. 2142 Water /Irrigation Front St. Water Main Replacement water main replacement for Mike Shane Water /Irrigation, and August of 2007 Water main in Front St., Lincoln and MLK installed. CIP railroad grade separation Engineering All water services transferred to new main in Front , project. Streets include Front . from Yakima to MLK. St., MLK and Lincoln. . 2179 Water /Irrigation Brackett Park Irrigation System Replace the wood irrigation Mike Shane Water /Irrigation, 11/19/07 Bid opening occurred Oct. 3, 2007. Jansen Inc. of Final Cost - $215,705.19 CIP Replacement pipes in the Brackett Park Streets Ferndale, WA is contractor. HLA is consultant. - • system Project is 100% complete. Final clean -up and . _ restoration in spring 2008. 2181 Water /Irrigation Repair /Replace Glenn Drive Replace the pump station and Mike Shane Water /Irrigation 11/01/07 Design complete. Bid opening Oct. 10, 2007. Final Cost - $326,570.45 CIP Reservoir Pump Station and Platform platform in the Glenn Drive POW of Pasco, WA is contractor. Work is Reservoir underway. HLA is consultant. Project is 100% _ complete. Replace Radios and Antennas for Replace Radios & Antennas for CIP 2185 Water /Irrigation Telemetry System Telemetry System Dave Brown Water Apr -07 Complete Cost $27,755.34 Water - DOT - Yakima Decommission complete, WSDOT hauled fill. Out CIP 2218 Water /Irrigation Ranney Well Decommission Decommission the Ranney Well Dave Brown Spring of 2008 complete _ County _ to adv. for hauling rest of spoil material 2096 Water /Irrigation 2nd Level Reservoir Pipe Rehab. /Install new waterlines, Mike Shane Engineering, 1/14/08 Survey and design completed. Bid opening was Final Cost - $147,336.05 CIP Improvements - Ph. 2 drainlines and control valves at Water /Irrigation Dec. 5, 2007. Contractor is TTC of Yakima. HLA is 2nd Level Resv. Site consultant. Project is 100% complete. Irrigation System Replacement in the neighborhoods south of Pacific Ave., north of E. Nob Bid opening occurred Sept. 26, 2007. KRCI of CIP 2180 Water /Irrigation General Irrigation Hill Blvd„ east of S. Naches Mike Shane Water /Irrigation, Stage 1 11/2007 Wenatchee, WA is contractor. HLA is consultant. Final Cost - $1,329,593.67 Phase 3 Stage 1- Ave., west of Fair Ave. Also, Streets Project is 100% complete. Custer Ave. between Lincoln • and W. A Street 110 . . • :.,... • . .,... . . _ • • . • . • • • . , .