HomeMy WebLinkAboutR-2024-143 Resolution authorizing Task Order 2024-01 with HLA Engineering and Land Surveying, Inc. to provide engineering services for City of Yakima Project No. SC2819 -2025 Wastewater CIPP Rehabilitation of Rudkin Road Trunk Sewer Main RESOLUTION NO. R-2024-143
A RESOLUTION authorizing Task Order 2024-01 with HLA Engineering and Land
Surveying, Inc. to provide engineering services for City of Yakima Project
No. SC2819—2025 Wastewater CIPP Rehabilitation of Rudkin Road Trunk
Sewer Main.
WHEREAS, the City of Yakima owns and maintains the Wastewater Collections System
in accordance with applicable Federal, State and Local regulations; and
WHEREAS, the Wastewater Division has identified the need to rehabilitate approximately
3,350 linear feet of sanitary sewer collection pipeline and seven manholes from S.18th Street at
Rainier Place to the Rudkin Road lift station at Lilac Lane and Rudkin Road, to improve the
longevity, maintenance and operation of the existing sewer main; and
WHEREAS,the City of Yakima Wastewater Division requires engineering design, bidding,
and construction services for the sanitary sewer system improvements; and
WHEREAS, the City previously entered into City of Yakima Contract No. 2023-139 with
HLA Engineering and Land Surveying, Inc. to develop Task Orders at the direction of the City to
provide engineering services for sewer system improvements; and
WHEREAS, at the direction of the City, HLA developed Task Order 2024-01 for the
engineering services required for the improvements identified in Project No. SC2819, and
WHEREAS, the City Council has determined that it is in the best interest of the City of
Yakima and its residents to approve Task Order 2024-01 with HLA Engineering and Land
Surveying, Inc., to perform the required engineering services; now, therefore
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
The City Manager is hereby authorized and directed to execute Task Order 2024-01 under
Contract No. 2023-139 between the City of Yakima and HLA Engineering and Land Surveying,
Inc., in an amount not to exceed Two Hundred Sixteen Thousand Seven Hundred and Sixty-Two
Dollars ($216,762) to provide engineering services for Project No. SC2819 — 2025 Wastewater
CIPP Rehabilitation of Rudkin Road Trunk Sewer Main; a copy of Task Order 2024-01 with
EXHIBIT 1— PROFESSIONAL SERVICES is attached hereto and by this reference made a part
hereof.
ADOPTED BY THE CITY COUNCIL this 5th day of August, 2024.
.7
ATTEST: = YAtt/4 Patricia•Aht Byers, Mayor
BEAU= ,
Rosalinda Ibarra, City Clerk /NiG c0.
TASK ORDER NO. 2024-01
(CITY CONTRACT NO 2023-137, RESOLUTION NO. R-2024-143)
AGREEMENT REGARDING TASK ORDER UNDER CITY CONTRACT 2023-139 AND
RESOLUTION R-2023-107 BETWEEN
CITY OF YAKIMA
AND
HLA ENGINEERING AND LAND SURVEYING, INC. (HLA)
WHEREAS, CITY and ENGINEER entered into City Contract No. 2023-139 ("the contract") as
authorized by City Resolution No. R-2023-107; and
WHEREAS, the parties agreed in the contract, Section 2.1 that ENGINEER shall be expected to
perform the work required by each task or group of tasks as assigned by the City for completion as
required by the City and approved by Yakima City Council;
THEREFORE, the parties agree ENGINEER shall complete the following tasks as part of the
Basic Services as defined in Section 2.1 of the contract subject to all the terms and conditions contained
in the contract, which is incorporated by reference.
PROJECT DESCRIPTION:
2025 Wastewater CIPP Rehabilitation - Rudkin Road Trunk Sewer Main
City Project No. SC2819
HLA Project No. 24128E
The CITY of Yakima (CITY) desires to rehabilitate approximately 3,350 linear feet (LF) of sanitary sewer
collection pipeline and seven (7) manholes from S.18th Street at Rainier Place to the Rudkin Road lift
station at Lilac Lane and Rudkin Road, necessary to properly maintain and operate the existing sewer
main. Rehabilitation pipeline segments include the following.
1. Rudkin Road
Segments 5548, 5549, 5550, 5673, 5674, and 5678.
Manhole numbers E56MH33, E62MH1, E62MH2, E62MH3, E63MH1, E63MH2, and
E63MH4.
SCOPE OF SERVICES:
At the direction of the CITY, HLA shall provide professional engineering services for the 2025 Wastewater
CIPP Rehabilitation - Rudkin Road Trunk Sewer Main (PROJECT). HLA services shall include the
following
1.0 Design Engineering
1.1 Provide complete PROJECT management to deliver the PROJECT within mutually
determined expectations.
1.2 Conduct a topographic survey of the PROJECT area as required to complete design, plans,
and specifications, including call for utility locates.
1.3 Perform field investigations necessary to design the identified improvements including
measuring inverts within manholes, field checking topographic survey, and all associated
traffic control for field investigations.
G\Contracts&Task Orders\Yakima\2024\Wastewater Collections\2024-07-15 24128E Task Order No 2024-01 2025 Wastewater CIPP Rehab-
Rudkin Rd Trunk Sewer Main docx Page 1 of 8
1.4 Attend up to two (2) PROJECT meetings with CITY staff at 60% and 90% plan completion to
fully review all elements of the PROJECT
1.5 Assist with PROJECT updates and related administrative documents to the appropriate
agencies that have jurisdiction over design and construction of this PROJECT
1.6 Review video inspection of the sewer main as provided by the CITY and identify existing side
sewer locations, and any obstruction removal needs
1 7 Notify private utilities of pending improvements.
1 8 Perform the preliminary design and submit 60% preliminary plans and preliminary estimate to
the CITY.
1.9 Meet with CITY to review 60% submittal. CITY to confirm removal or addition of any pipeline
segments within five working days following 60% review meeting.
1 10 Following receipt of 60% plan review comments by the CITY, prepare 90% design plans and
submit to the CITY for review
1 11 Review and discuss 90% design plans with CITY staff.
1.12 Following receipt of 90% plan review comments by the CITY, perform the final design, and
prepare complete plans and specifications for publicly bid improvements, as authorized by
the CITY
1.13 Perform quality control and assurance review of all final documents.
1.14 Prepare Engineer's construction cost estimate
1.15 Provide final plans and specifications to the CITY in electronic format suitable for printing and
use at time of bid advertisement It is anticipated HLA will prepare one (1) complete set of
plans and specifications for one (1) bid call; additional bid packages will be considered
additional services.
1.16 Following receipt of authorization from CITY, prepare advertisement for bids and provide to
the CITY for use and implementation All advertising fees to be paid by the CITY.
1.17 Submit bid advertisement to the Yakima Herald Republic.
1 18 Post documents to HLA website and notify potential bidders, utility companies, and plan
centers of PROJECT posting, and maintain planholder list.
1 19 Answer and supply information as requested by prospective bidders
1.20 Prepare and issue addenda to contract documents, if necessary.
1.21 Attend the bid opening and participate in the evaluation process.
1 22 Prepare summary of bids received and review bidder's qualifications and responsiveness.
1 23 Make recommendation of award to the CITY for construction contract.
1.24 Prepare administrative documents to the appropriate agencies which have jurisdiction over
funding, design, and construction of the PROJECT
G\Contracts&Task Orders\Yakima\2024\Wastewater Collections\2024-07-15 24128E Task Order No 2024-01 2025 Wastewater CIPP Rehab-
Rudkin Rd Trunk Sewer Main docx Page 2 of 8
2.0 Construction Engineering
2.1 Following City Manager intent to award authorization, prepare notice of intent to award to the
Contractor, assemble construction contract documents, and coordinate contract execution
with the CITY and Contractor.
2.2 Review Contractor's submission of certificate of insurance and contract bond.
2.3 Coordinate and facilitate preconstruction meeting with the CITY, Contractor, private utilities,
and affected agencies, including preconstruction agenda and meeting record.
2.4 Prepare and transmit notice to proceed to Contractor.
2.5 Furnish a field survey crew to provide geometric control, including construction staking, if
necessary
2.6 Furnish a qualified resident engineer(inspector) to observe construction for substantial
compliance with plans and specifications and CITY Construction Standards
2.7 Review Contractor's submission of samples and shop drawings.
2.8 Maintain record of materials (ROM) for duration of PROJECT.
2.9 Respond to Contractor requests for information (RFI).
2.10 Interpret plans and specifications when necessary.
2.11 Prepare daily progress reports.
2.12 Prepare weekly statements of working days.
2 13 Create and maintain accurate construction documentation for the life of the PROJECT
2.14 Ensure the CITY has all necessary files for potential audits.
2.15 Consult and advise the CITY during construction and make final review and report of the
completed work with CITY representatives.
2.16 Coordinate testing scheduling with the Contractor's materials testing firm and review
acceptance sampling and testing for construction materials.
2.17 Coordinate and attend construction meetings anticipated once per week during the duration
of improvements
2.18 Perform measurement and computation of pay items
2 19 Prepare and provide monthly progress estimates to the CITY and recommend progress
payments for the Contractor.
2.20 Prepare proposed contract change orders and/or force account computations as required
2.21 Review post-installation video inspection of the sewer main as provided by the Contractor
and identify any deficiencies.
2.22 Conduct final walkthrough inspection with the Contractor and CITY Prepare and transmit
punchlist to Contractor.
G\Contracts&Task Orders\Yakima\2024\Wastewater Collections\2024-07-15 24128E Task Order No 2024-01 2025 Wastewater CIPP Rehab-
Rudkin Rd Trunk Sewer Main docx Page 3 of 8
2.23 Prepare and furnish record drawings and field notes of completed work in accordance with
PROJECT field records provided by the resident engineer and those submitted by the
Contractor.
2.24 Prepare administrative documents to the appropriate agencies which have jurisdiction over
funding, design, and construction of this PROJECT
2.25 Monitor the Contractor's compliance with state labor standards.
2 26 Prepare and submit recommendation of PROJECT acceptance
2.27 Notify CITY when retainage may be released.
2.28 Ensure the PROJECT is completed as designed and contract specifications are adhered to
during construction
3.0 Additional Services
Provide professional engineering services for additional work requested by the CITY that is not included
in this Task Order.
4.0 Items to be Furnished and Responsibility of the CITY
The CITY will provide or perform the following
4.1 Provide full information as to CITY requirements for the PROJECT.
4.2 Provide all available information pertinent to the PROJECT relative to completion of design
and construction of the PROJECT.
4 3 Provide video inspection files of all PROJECT pipeline segments.
4 4 Contact property owners affected by the PROJECT and gain necessary access to property
for field investigation, design, and construction of improvements. Entry to private property will
not be made until a CITY approved agreement is obtained.
4 5 Examine all documents presented by HLA and provide written decisions within a reasonable
time so as not to delay the work of HLA.
4.6 Obtain approval of all governmental authorities for the PROJECT, and approvals and
consents from other individuals as necessary for completion of the PROJECT
4.7 Pay for advertising, notices, or other publications as may be required.
4.8 Pay for all necessary permits and testing fees not paid by the Contractor.
4 9 The CITY will prepare and submit Notice of Completion of Public Works Contract (NOC) and
monitor lien releases from state agencies
TIME OF PERFORMANCE:
HLA will diligently pursue completion of the PROJECT as follows:
1.0 Design Engineering
1.1 HLA will provide 60% draft plans, 60% draft specifications, and 60% cost estimate for CITY
review within sixty (60) working days from receipt of signed Task Order.
G\Contracts&Task Orders\Yakima\2024\Wastewater Collections\2024-07-15 24128E Task Order No 2024-01 2025 Wastewater CIPP Rehab-
Rudkin Rd Trunk Sewer Main docx Page 4 of 8
1.2 Each successive plan review set(90% and final) shall be completed within thirty (30) working
days of comment receipt from that previously submitted set.
1.3 The bid advertisement will be scheduled for a Thursday publication in the Yakima Herald
Republic.
1.4 The bid opening will be two (2)weeks following the bid advertisement
1 5 A bid summary and recommendation of award will be prepared within two (2) working days of
the bid opening.
1.6 Following award concurrence by the CITY, contracts will be prepared and provided to the
Contractor within three (3) working days
2.0 Construction Engineering
2.1 Construction engineering services shall begin upon construction contract award by the CITY
to the lowest responsible bidder and extend through the completion of construction, and
completion of as-constructed drawings and labor documentation closeout, as requested and
directed by the CITY.
2 2 A maximum of forty (40) working days has been assumed for the construction of the
improvements and the construction observation estimate is based on twelve (12) working
hours per day.
2 3 Should the Contractor be granted time extensions for construction completion due to
recognized delays, requested additional work, and/or change orders, services during
construction beyond the forty (40)working days shall be considered additional services.
3.0 Additional Services
Time for completion of work directed by the CITY under additional services shall be negotiated and
mutually agreed upon at the time service is requested by the CITY.
FEE FOR SERVICES:
For the services furnished by HLA as described within this Task Order, the CITY agrees to pay HLA the
fees as set forth herein. The amounts listed below may be revised only by written agreement of both
parties
1.0 Design Engineering
All work directed by the CITY for design engineering shall be performed on a time-spent basis at the
hourly billing rates in affect at time of this Task Order, provided in EXHIBIT B of the Agreement(City
Contract No 2023-139, Resolution No. R-2023-107), plus reimbursement for direct non-salary expenses
as described in section 6.1.1.1. An estimate of time and expenses for services is provided in EXHIBIT 1
below. The estimated maximum fee for this work is $90,320.00.
2.0 Construction Engineering
Construction is anticipated to occur during the winter of 2024-2025 All work for construction engineering
services shall be performed on a time-spent basis at the affect at time of this Task Order, provided in
EXHIBIT B of the Agreement(City Contract No 2023-139, Resolution No. R-2023-107), plus
reimbursement for direct non-salary expenses as described in section 6.1.1.1. An estimate of time and
expenses for services is provided in EXHIBIT 1 below. The estimated maximum fee for this work is
$126,440 00
G.\Contracts&Task Orders\Yakima\2024\Wastewater Collections\2024-07-15 24128E Task Order No 2024-01 2025 Wastewater CIPP Rehab-
Rudkin Rd Trunk Sewer Main docx Page 5 of 8
3.0 Additional Services
Additional work requested by the CITY not included in this Task Order shall be authorized by the CITY
and agreed upon by HLA in writing prior to proceeding with services. HLA will perform additional services
as directed/authorized by the CITY on a time-spent basis at the hourly rates in affect at the time of this
Task Order, provided in EXHIBIT B of the Agreement (City Contract No. 2023-139, Resolution No R-
2023-107), plus reimbursement for direct non-salary expenses as described in section 6.1 1.1
Proposed: y'. 1111r AXCL.. _ /i6 /zz
HLA Engineering an' and S -ying, Inc. Da
Michael T. Battle, P , ' - •ent
Approved: Ifs]
Ci y of Yakima / Date
Dave Zabell, City nager
CITY CONTRACT N/O� do 93 139ID.2 0
RESOLUTION NO. aoL(jL3
G\Contracts&Task Orders\Yakima\2024\Wastewater Collections\2024-07-15 24128E Task Order No 2024-01 2025 Wastewater CIPP Rehab-
Rudkin Rd Trunk Sewer Maln.docx Page 6 of 8
EXHIBIT 1 — PROFESSIONAL SERVICES
During the term of this Task Order, HLA Engineering and Land Surveying, Inc. (HLA), shall perform
professional services in connection with the following project
2025 Wastewater CIPP Rehabilitation - Rudkin Road Trunk Sewer Main
Task Order No. 2024-01
City Project No. SC2819
HLA Project No. 24128E
For the services described in Task Order No 2024-01, compensation shall be paid per Section 6 of the
Agreement(City Contract No. 2023-139, Resolution No. R-2023-107). The following spreadsheets show
the estimated time and expenses to perform said services.
Project Title 2025 Wastewater CIPP Rehabilitation-Rudkin Road Trunk Sewer Main
Client. City of Yakima
City Contract Number: 2024-01
Date June 6,2024 ENGINEERS HOURLY ESTIMATE
Senior Licensed Project Licensed Surveyor on CAD Administrative+
Task Principal Principal Engineer Land Two Man Technician Clerical Total Task Direct
Project Task Hours Coss
No Engineer Engineer II Surveyor Crew
$263 $235 $194 S191 $135 $153 $102
1.0 DESIGN ENGINEERING
1 Protect Management2 4 4 0 0 0 0 10 $2,242
2 Protect Meetings 4 8 8 C 0 6 0 20 54.484
3 Field investigations and field surveying 0 4 10 12 20 C 0 48 $7,872
4 Pipeline evaluation,review video inspection 0 6 16 C 0 0 0 22 $4.514
5 Preliminary design 4 18 40 8 0 24 16 108 $19,404
6 In-house project review,quality control 3 4 16 8 0 10 12 53 $9,115
7 Incorporate Agency review comments 1 8 16 C 0 10 10 45 57,797
8 Final design,plans.and specifications 4 18 16 2 0 10 24 72 512,276
9 Prepare estimate of construction cost 1 4 12 0 3 8 0 25 54.755
10 Manage and administer bid process 1 8 8 C 0 0 16 33 55,327
11 Answer bidder questions 0 8 8 C 0 0 2 18 53.636
12 Prepare and issue addenda 0 6 a C 3 6 4 24 54,288
13 Attend bid opening 0 _ 2 C 0 0 0 4 $858
14 Prepare tabulation of bids 0 2 4 6 0 C 4 10 51,654
15 Make recommendation of contract award 1 2 4 C 0 C 4 11 51,917
Labor Subtotal 21 98 172 30 20 68 92 501 500,135
EXPENSES:
Travel" CostiUnit Ground Days Days Miles
Mileage 56 87 100 567 00
Meals+Lodging $C.00
Misc.Expenses:
Advertisement
Telephone
Postage
•
Printing 3 copies pianslspecs 5114 00
Sub-Consultants
None Anticipated I 50 001 I I I (Multiplier I 1.11 I $0.00
Subtotal-Labor $00,138 00
Subtotal-Expenses 5181.00
Total-DESIGN ENGINEERING 500,320 00
G\Contracts&Task Orders\Yakima\2024\Wastewater Collections\2024-07-15 24128E Task Order No 2024-01 2025 Wastewater CIPP Rehab-
Rudkin Rd Trunk Sewer Main docx Page 7 of 8
EXHIBIT 1 —PROFESSIONAL SERVICES (Continued)
2025 Wastewater CIPP Rehabilitation - Rudkin Road Trunk Sewer Main
Task Order No. 2024-01
City Project No. SC2819
HLA Project No. 24128E
Project Title: 2025 Wastewater CIPP Rehabilitation-Rudkin Road Trunk Sewer Main
Client: City of Yakima
City Contract Number 2024-01
Date: June 6,2024 ENGINEERS HOURLY ESTIMATE
Licensed Construction Project Resident Contract
Task Pnncipal Supervisor Engineer Engineer/ Administrator Task Direct
No Project Task Total Flours
Engineer ii Inspector III Costs
$274 $202 $202 $149 S166
2.0 CONSTRUCTION ENGINEERING
1 Assist City with Review/Contract Prep. 2 0 2 0 8 12 $2,280
2 Conduct Pre-Construction Meeting 2 2 2 2 2 10 $1.986
3 Construction Observation 0 8 0 480 0 488 $73,136
4 Field Inspection Reports 0 8 8 16 8 40 $6,944
5 Construction Administration 0 6 0 4 60 70 S11,768
6 Construction Meetings 2 4 2 4 4 16 $3,020
7 Submittal Review 0 4 0 8 8 20 $3,328
8 State Labor Standards Compliance 0 0 0 0 16 16 $2,656
9 Progress Payments 2 2 8 4 16 32 $5,820
10 Change Orders _ 2 6 8 16 36 $6,416
11 Final Walk-ThroughlPunchlist 1 4 2 2 4 13 $2,448
12 Project Closeout 2 4 2 2 16 26 $4,714
13 Record Drawings 1 2 2 2 2 9 $1,712
Labor Subtotal 14 46 36 532 160 788 $126,228
EXPENSES:
Travel. Cost/Unit Ground Days Miles
Mileage $0.67 320 S214.40
Meals/Lodging $0 00
T Misc.Expenses:
Advertisement
Telephone
Postage
Misc
Sub-Consultants:
None Anticipated $0.00 Multiplier 1 1 $0 00
Subtotal-Labor $126,228 00
Subtotal-Expenses $214.40
Total-CONSTRUCTION ENGINEERING $126,442 40
G\Contracts&Task Orders\Yakima\2024\Wastewater Collections\2024-07-15 24128E Task Order No.2024-01 2025 Wastewater CIPP Rehab-
Rudkin Rd Trunk Sewer Main docx Page 8 of 8
(---
;:, • • r'''
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 7.G.
For Meeting of: August 5, 2024
ITEM TITLE: Resolution authorizing Task Order 2024-01 with HLA Engineering and
Land Surveying, Inc. to provide engineering services for City of
Yakima Project No. SC2819 - 2025 Wastewater CIPP Rehabilitation
of Rudkin Road Trunk Sewer Main
SUBMITTED BY: Scott Schafer, Director of Public Works
* Mike Price, Wastewater/Stormwater Manager
SUMMARY EXPLANATION:
City of Yakima (City) project SC2560 will rehabilitate approximately 3,350 linear feet of concrete sanitary
sewer trunk line and seven manholes from S.18th Street at Rainier Place to the Rudkin Road lift station
at Lilac Lane and Rudkin Road. The Project will utilize cured-in-place pipe (CIPP) lining technology that
minimizes trenching and other surface disturbances. The improvements restore pipeline reliability and
maintainability, and conserve wastewater treatment plant hydraulic capacity by reducing groundwater
infiltration into the pipeline.
Task Order 2024-01 under existing City contract 2023-139 with HLA, is for engineering design, bidding,
and construction services required for the project in an amount not to exceed $216,762. The Task Order
with EXHIBIT 1 - PROFESSIONAL SERVICES is attached for Council review. Funds are budgeted from
Sewer Construction Fund 476.
ITEM BUDGETED: Yes
STRATEGIC PRIORITY: Investment In Infrastructure
RECOMMENDATION: Adopt Resolution.
ATTACHMENTS: