HomeMy WebLinkAboutR-2024-071 Resolution authorizing a contract with Chervenell Construction Company for the MLK Jr Park Eastside Pool Project 2745 RESOLUTION NO. R-2024-071
A RESOLUTION authorizing an agreement with Chervenell Construction Company for the
MLK Jr Park Eastside Pool Project 2745.
WHEREAS, the City of Yakima previously entered into a contract with NAC Architecture
(R-2023-010) to provide aquatic pool design for the MLK Jr Park Eastside Pool Project 2745
(Project) under original contract number 2023-007, approved by the City Council and executed
on January 4, 2023 by Resolution Number 2023-010; and
WHEREAS, the Project consists of construction of a public swimming pool located in
east Yakima area at 610 South 9' Street; and
WHEREAS, the funding will be provided from a variety of funding sources including state
grants, ARPA, Local Funds, and donations; and
WHEREAS, the City of Yakima used the procedure established by Washington State
law for the bidding and awarding of public capital improvement projects; and
WHEREAS, Chervenell Construction Company was determined to be qualified to
perform the needed construction work; and
WHEREAS, the contract will be null and void if bond, certificate, and required insurance
certificate and endorsement are not received within specified timeframe; and
WHEREAS, the Scope of Work and Budget included in this contract meets the needs
and requirements of the City of Yakima for this Project; and
WHEREAS, the City Council of the City of Yakima finds that entering into the contract
with Chervenell Construction Company for construction of the MLK Jr Park Eastside Pool is in
the best interests of the City and its residents; now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
Section 1. The City Manager is hereby authorized to execute a contract with Chervenell
Construction Company, attached hereto and incorporated herein by this reference, contracted
amount plus Washington State Sales Tax (WSST) for a total not to exceed Ten Million Five
Hundred Eighty Thousand Nine Hundred and Ten Dollars ($10,580,910) to provide construction
services for work outlined in the contract for the MLK Jr Park Eastside Pool Project 2745.
Section 2. The will be null and void if bond, certificate and required insurance is not
received as outlined in the contract.
ADOPTED BY THE CITY COUNCIL this 16th day of A ril, 2024.
�\`'h►► Patricia Byers, Mayor
ATTEST: ,%fl (SEAL
*� •. 4►
*%
• Ili
Rosalinda Ibarra, City Clerk .,%\k\`L`G2�c
$ggAIA DocumentAl 01"- 2017
Standard Form of Agreement Between Owner and Contractor where fhe basis of
payment ls a Sftpu/ated Sum
AGREEMENT made as of the sixteenth day of April in the year 2024
(In words, indicate day, month and year.)
BETWEEN the Owner:
(Name, legal status, address and other information)
City of Yakima
129 North 2nd Street
Yakima, Washington 9890 1
and the Contractor:
Q{ame, legal status, address and other information)
Chervenell Construction Company
107422 E Detrick PR SE
Kennewick, WA 99338
for the following Project:
(Name, location and detailed description)
Martin Luther King Jr. Community Park Pool
610 South 9th Street
Yakima, Washington 9890 I
The Architect:
(Name, legal status, address and other information)
NAC Inc.
1203 West Riverside Avenue
Spokane, Washington 9920 I
(s0e) 838-8240
The Owner and Contractor agree as follows
ADDITIONS AN D DELETIONS:
The author of this document has
added information needed for its
completion. The author maY also
have revised the text of the original
AIA standard form. An Additions and
Deletions Repodthat notes added
information as well as revisions to the
standard form text is available from
the author and should be reviewed. A
vertical line in the left margin of this
document indicates where the author
has added necessary information
and where the author has added to or
deleted from the original AIA text.
This document has important legal
consequences. Consultation with an
attorney is encouraged with respect
to its completion or modification.
The parties should complete
4101@-201 7, Exhibit A, Insurance
and Bonds, contemporaneouslY with
this Agreement. AIA Document
A201@-2017, General Conditions of
the Contract for Construction, is
adopted in this document by
reference. Do not use with other
general conditions unless this
document is modifled.
AIA Docu
reserved.
American
resale, is
e-mail docinfo@aiacontracts.com.
User Notes:
mentA101-2017.CopyrightO1915,191S,1925,1937,1951,1958,1961,1963,1967,1974,1977,1987,1991,1597,2007and2O17'Allrights,,The American lnstitute of-Architects,l' "American institute of Architects," "AlA," the AtA Logo, and "AlA Contract Documents" are trademarks of The
lnstitute of Architects. This documeni was produced at 08:15:01 EI on o4t0312024 under Order No.3104239382 which expires on 1O|1O!2O24' is not for
licensed for one-time use only, and may oniy be used in accordance with the AIA Contract Documents@ Terms of Service. To report copyright violations,
1lnit.
(1 4641 00981 )
2
3
4
5
6
TABLE OF ARTICLES
THE CONTRACT DOCUMENTS
THE WORK OF THIS CONTRACT
DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
CONTRACT SUM
PAYMENTS
DISPUTE RESOLUTION
TERMINATION OR SUSPENSION
MISCELLANEOUS PROVISIONS
ENUMERATION OF CONTRACT DOCUMENTS
EXHIBIT A INSURANCE AND BONDS
ARTICLE 1 THE CONTRACT DOCUMENTS
The Conhact Documents consist of this Agreement, Conditions of the Contract (General, Supplementary, and other
Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed
in this Agreement, and Modifications issued after execution of this Agreement, all of which form the Contract, and are
as fully a part of the Conhact as if attached to this Agreement or repeated herein. The Contract represents the entire
and integrated agreement between the parties hereto and supersedes prior negotiations, representations, or agreements,
either written or oral. An enumeration of the Contract Documents, other than a Modification, appears in Article 9.
ARTICLE 2 THE WORK OF THIS CONTRACT
The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in
the Contract Documents to be the responsibility of others.
ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
$ 3.1 The date of commencement of the Work shall be:
(Check one of thefollowing boxes.)
I I The date of this Agreement.
I X ] A date set forth in a notice to proceed issued by the Owner
Established as follows:
(Insert a date or a means to determine the date of commencement of the Work.)
if a date of commencement of the Work is not selected, then the date of commencement shall be the date of this
Agreement.
$ 3'2 The Contract Time shall be measured from the date of commencement of the Work.
$ 3.3 Substantial Gompletion
$ 3'3'1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall
achieve Substantial Completion of the entire Work:
(Check one of thefollowing boxes and complete the necessaty information.)
AIA Document A1O1 -2017. Copyrighto 1915, 19'18, 1925,1937,1951, 1958, 1961, 1963, 1s67,1974,1977,1987,1991, 1997, 2oo7 and 2017. Ail rights
reserved. "The American lnstitute of Architects," "American lnstituie of Architects," "AlA," the AIA Logo, and "AlA Contract Documents" are trademarks of The
American lnstitute of Architects. This document was produced at 08:15:01 ET on 0410312O24 under Order No.31 04239382 which expires on 1Ol1Ol2O24, is not for
resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents@ Terms of Service. To report copyright violations,
e-mail docinfo@aiacontracts.com.
User Notes: (1464i009S1)
7
I
I
2
lnit.
IX]Not later than thlee-hundred eighty ( 380 ) calendar days from the date of commencement of the
Work.
t I By the following date:
$ 3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are
to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial
Completion of such portions by the following dates:
S 3.3.3If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3, liquidated damages, if
any, shall be assessed as set forth in Section 4.5.
ARTICLE 4 CONTRACT SUM
$ 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor's performance of the
Contract. The Contract Sum shall be Nine Million Seven Hundred Seventy Thousand Dollars ($ 9,770,000.00) plus
Washington State Sales Tax, subject to additions and deductions as provided in the Contract Documents.
$ 4.2 Alternates
$ 4,2,1 Altemates, if any, included in the Contract Sum:
Item Price
Alternate No. 2 Slide Tower & Dual $970,000.00
Runout Slides for Pool B
S 4.2.2 Subject to the conditions noted below, the following altemates may be accepted by the Owner following
execution of this Agreement. Upon acceptance, the Owner shall issue a Modification to this Agreement.
(Insert below each alternate and the conditions that must be metfor the Owner to accept the alternate.)
Item
As allowed under the bidding documents
Conditions for Acceptance
$ 4.3 Allowances, if any, included in the Contract Sum:
(Identifu each allowance,)
Portion of Work
N/A
Item
Not Applicable (1\/A)
Substantial Completion Date
N/A
Price
Price
3
$ 4,4 Unit prices, if any:
(tdenttfy tie item and state the unit price and quantity limitations, if any, to which the unit price will be applicable.)
Item
(N/A)
Units and Limitations Price per Unit ($0.00)
$ 4.5 Liquidated damages, if any:
(Insert terms and conditions for liquidated damages, tf any.)
Liquidated damages are as described in the AIA 201 General Conditions and Specification Section 007300
Supplementary Conditions
The Contractor and Owner agreethat the liquidated damages amount is not a penalty and is a reasonable estimation of
actual damages to the Owner if they are not able to open the outdoor aquatic center for business for the fulI summer
season session.
$ 4.6 Other:
AtADocumentAl}l-2017.Copyright@1S15,1918,1925,1937,1951,1S58,196'1,1963,1967,1974,1977,1587,1991,1997,2007and2017.A11rights
reserved. .The American lnstitute'of-Architects,;' "American lnstitute of Archiiects," "AlA," the AIA Logo, and "AlA Contract Documents" are trademarks of The
American lnstitute of Architects. This documeni was produced at 08:15:01 ET on 04t03t2}24 under Order No.3104239382 which expires on 10/10/2024, is. not for
resale, is licensed for one-time use only, and may oniy be used in accordance with the AIA Contract Documents@ Terms of Service. To report copyright violations'
e-mail docinfo@aiacontracts.com.
user Notes: (1464100981)
lnit.
(Insert provisions for bonus or other incentives, if any, that might result in a change to the Contract Sum.)
N/A
ARTICLE 5 PAYMENTS
$ 5.1 Progress Payments
S 5.1'1 Based upon Applications for Payment submitted to the Architect by the Contractor and Certificates for
Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum to the
Contractor as provided below and elsewhere in the Conh.act Documents.
S 5'1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the
month, or as follows:
I S"ftedule per Contract Documents
$ 5.1.3 The Owner shall make payment of the amount cerlified to the Contractor as provided in the Contract
Documents.
(Federal, state or local laws may require payment within a certain period of time.)
$ 5'1'4 Each Application for Payment shall be based on the most recent schedule of values submitted by the Contractor
in accordance with the Conkact Documents. The schedule of values shall allocate the entire Contract Sum among the
various portions of the Work. The schedule of values shall be prepared in such form, and supported by such data to
substantiate its accuracy, as the Architect may require. This schedule of values shalt be used as a basis for reviewing
the Contractor's Applications for Payment.
$ 5'1'5 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end of
the period covered by the Application for Payment.
$ 5'1'6 In accordance with AIA Document A20lrM-2017, General Conditions of the Contract for Construction, and
subject to other provisions of the Contract Documents, the amount of each pt'ogress payment shall be computed as
follows:
$ 5.1.6.1 The amount of each progress payment shall first include:
.1 That portion of the Contract Sum properly allocable to completed Work;
'2 That portion of the Contract Sum properly allocable to materials and equipment delivered and suitably
stored at the site for subsequent incorporation in the completed construction, or, ifapproved in advance
by the Owner, suitably stored off the site at a location agreed upon in writing; and
'3 That portion of Construction Change Directives that the Architect determines, in the Architect's
professional judgment, to be reasonably justified.
$ 5.1.6.2 The amount of each progress payment shall then be reduced by:
.1 The aggregate of any amounts previously paid by the Owner;
.2 The amount, if any, for Work that remains uncorrected and for which the Architect has previously
withheld a Certificate for Payment as provided in Article 9 of AIA Document A20l--2017;
'3 Any amount for which the Contractor does not intend to pay a Subcontractor or material supplier,
unless the Work has been performed by others the Contractor intends to pay;
.4 For Work performed or defects discovered since the last payment application, any amount for which
the Architect may withhold payment, or nulliS, a Certificate of Payment in whole or in pafi, as provided
in Article 9 of AIA Document A20I-2017; and
,5 Retainage withheld pursuant to Section 5.1.7.
$ 5.1.7 Retainage
$ 5.1'7.1 For each progress payment made prior to Substantial Completion of the Work, the Owner may withhold the
following amount, as retainage, fi'om the payment otherwise due:
(Insert a percentage or amoLrnt to be withheld as retainagefrom each Appticationfor Payment. The amount of
retainage may be limited by governing law.)
AlADocumentAl0l -2017. Copyright@ 1915, 1S18, 1925,1937,1951, 1958, 1961, 1963, 1967,1974,1577,1987,1991, 19S7, 2O07 and 2017. Ail rights
reserved. "The American Institute of Architects," "American lnstitute of Architects," "AlA," the AIA Logo, and "AlA Contract Documents" are trademarks of The
American lnstitute of Architects. This document was produced at 08:'15:01 Ef on 0410312024 under Order No.3104239382 which expires on 1ot1012024, is not for
resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents@ Terms of Service. To report copyrighi violations,
e-mail docinfo@aiaGonlracts.com.
User Notes: (14641009S1)
4
Init.
Statutory retainage of five percent (5%) shall be withheld from all payments, unless the Contractor submits and the
Owner accepts a retainage bond pursuant to RCW 60.28.011(6).
$ 5.1.7.1.1 The following items are not subject to retainage:
(Insert any items not subject to the withhotding of retainage, such as general conditions, insurartce, etc.)
I Nle
S 5.1.7,2 Reduction or limitation of retainage, if any, shall be as follows:
117 th" ,"toinoge established in Section 5. L7.I is to be modified prior to Substantial Completion of the entire Work,
including modificationsfor Substantial Completion of portions of the Work as provided in Section 3'3'2, insert
provisions for such modifications. )
Per statute and the Contract Documents.
S 5.1 .7,3 Except as set forth in this Sectio n 5 .l .7 .3, upon Substantial Cornpletion of the Work, the Contractor may
submit an Application for Payment that includes the retainage withheld from prior Applications for Payment pursuant
to this Sectio i S .t .l . The Application for Payment submitted at Substantial Completion shall not include retainage as
follows:
(Insert any other conditions for release of retainage upon Substantial Completion.)
N/A
S 5,1 .S If final completion of the Work is materially delayed through no fault of the Contractor, the Owner shall pay
the Contractor any additional amounts in accordance with Article 9 of AIA Document A20l-201'l .
$ 5.1.9 Except with the Owner's prior approval, the Contractor shall not make advance payments to suppliers for
materials or equipment which have not been delivered and stored at the site.
$ 5.2 Final Payment
$ S,Z.t Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the
Contractor when
.1 the Contr.actor has fully performed the Contract except for the Conttactor's responsibility to corTect
Work as providedin ArLicle l2of AIA Document A201-2017, and to satisfy otherrequirements, if any,
which extend beyond fina1 payment; and
,2 a final Certificate for Payment has been issued by the Architect.
$ 5.2.2 The Owner's final payment to the Contractor shall be made no later than 30 days after the issuance of the
Architect's final Certificate for Payment, or as follows:
30 days after completion of all requirements for Final Acceptance listed in the A201-2017 General Conditions and
Supplementary Conditions
$ 5.3 lnterest
Fayments due and unpaid under the Contract shall bear interest from the date payment is due at the rate stated below,
or in the absence thereof, at the legal rate prevailing fi'om time to time at the place where the Project is located.
(Insert rate of interest agreed upon, if any.)
(Paragraph deleted)
Per the Contract Documents
ARTICLE 6 DISPUTE RESOLUTION
$ 6.1 lnitialDecision Maker
ihe Architect will serve as the Initial Decision Maker pursuant to Article 15 of AIA Document A20l-20l7,unless the
parties appoint below another individual, not a party to this Agreement, to serye as the Initial Decision Maker.
-(If
the piities mutually agree, insert the name, address and other contact information of the Initial Decision Maker, if
other than the Architect.)
AIA Document A1O1 - 2017. Copyright O 1 91 5, 1 91 B, 1925, 1537, 1 S51, 1 958, 1 961'1963, 1967, 1974,1977,19B7,1991, 1997,2007 and2017. All rights
reserved. "The American lnstitute of Architects," "American lnstitute of Architects," "AlA," the AIA Logo,and "AlA Contract Documents" are trademarks of The .5
TOrAmerican lnstitute of Architects. This document was produced at 08:15:01 ET
resale, is licensed for one-time use only, and may only be used in accordance
e-mail docinfo@aiacontracts.com.
ljser Notes:
on 0410312024 under Order No.3 104239382 which expires on '1
Service. To report
011012024, is not
copyright violations,
lnit.
wiih the AIA Contract Documents@ Terms of
(14641 00981 )
lNa
$ 6.2 Binding Dispute Resolution
For any Claim subject to, but not resolved by, mediation pursuant to Article 15 of AIA Document A201-2017, the
method of binding dispute resolution shall be as follows:
(Check the appropriate box.)
t I Arbitration pursuant to Section 15.4 of AIA Document A20l-2017
t ] Litigation in a court of competent jurisdiction
IX I At*'*er (Spicifyl
Litigation in Superior Court in Yakima County, Washington
If the Owner and Contractor do not select a method of binding dispute resolution, or do not subsequently agree in
writing to a binding dispute resolution method other than litigation, Claims will be resolved by litigation in a court of
competent jurisdiction.
ARTICLE 7 TERMINATION OR SUSPENSION
$ 7'1 The Contract may be terminated by the Owner or the Contractor as provided in Article 14 of AIA Document
A20l--2017.
$ 7'1,1 If the Contract is terminated for the Owner's convenience in accordance with Article 14 of AIA Document
A20l-2011 , then the Owner shall pay the Contractor a termination fee as follows:
(Insert the amount of, or methodfor determining, thefee, if any, payable to the Contractorfollowing a terminationfor
the Owner's convenience.)
N/A
$ 7'2 The Work may be suspended by the Owner as provided in Article 14 of AIA Document A20l--2017.
ARTICLE 8 MISCELLANEOUS PROVISIONS
$ 8'1 Where reference is made in this Agreement to a provision of AIA Document A201-201'7 or another Contract
Document, the reference refers to that provision as amended or supplemented by other provisions of the Contract
Documents.
$ 8.2 The Owner's representative:
Q,{ame, address, email address, and other information)
Ken Wilkinson
230 1 Fruitvale Boulevard
Yakima, WA 98902
(509) 57s,600s
Kenneth. Wilkinson@yakimawa. gov
$ 8.3 The Contractor's representative:
Q,{ame, address, email address, and other information)
Brandon Mayfield, President
Chervenell Construction Cornpany
107422 E. Detrick PR SE
Kennewick, WA 99338
AlADocumentAlOl-2017.Copyright@1915,1918,1925,1937,1951,1958,1961,1363,1967,1974,1977,1987,1991,1997,2007and2017.Ailrights
reserved. "The American lnstitute of Architects," "American lnstitute of Architects," "AlA," the AIA Logo, and "AlA Contract Documents" are trademarks 6f The
AmericanlnstituteofArchitects.Thisdocumentwasproducedat0s:15:01 Ef onO4t03t2o24underOrderNo.3104239382whichexpireson 1}t1ol2024,isnotfor
resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents@ Terms of Service. To report copyright violations,
.e-mail docinfo@aiacontracts.com.
lJser Notes: (14641009S1)
6
lnit.
(s}e) 13s-3377
bmayfi eld@chervenell. com
$ 8.4 Neither the Owner's nor the Contractor's representative shall be changed without ten days' prior notice to the
other party.
$ 8.5 lnsurance and Bonds
S S,5,1 The Owner and the Contractor shall purchase and maintain insurance as set forth in AIA Document
Al0lrIuL-2O17, Standard Form of Agreement Befween Owner and Contractor where the basis of payment is a
Stipulated Sum, Exhibit A, Insurance and Bonds, and elsewhere in the Contract Documents.
$ 8.5,2 The Contractor shall provide bonds as set forth in AIA Document A101rlr-2017 Exhibit A, and elsewhere in
the Conhact Documents.
$ 8.6 Notice in electronic format, pursuant to Article I of AIA Document M0l-2011 , may be given in accordance
with AIA Document E203rI'4-2013, Building Information Modeling and Digital Data Exhibit, if completed, or as
otlerwise set forth below:
(If other than in accordance with AIA Document E203-2013, insert requirements for delivering notice irt electronic
firmat such as name, title, and email address of the recipient and whether and how the system will be required to
generate a read receiptfor the transmission.)
Per the Contract Documents
$ 8.7 Other provisions:
I Nle
ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS
$ 9.1 This Agreement is comprised of the following documents:
,1 AIA Document A101rM-2017, Standard Form of Agreement Between Owner and Contractor, as
modified
.2 AIA Document A101rru2017, Exhibit A, Insurance and Bonds
,3 AIA Document A201rre-2017, General Conditions of the Contract for Construction
(Paragraphs deleted)
as revised by the Owner including Supplementary Conditions. All references to the A201 or to the General
Conditions are to the revised document.
.4 Not used.
.5 Drawings
Number
See attached Index of Drawings
.6 Specifications
Section
See attached Table of Contents
.7 Addenda, if any:
Number
1
Title
Title
Date
February 8,2024
February 75,2024
February 22,2024
February 29,2024
Date
Date
Pages
25
21
36
52
Pages
2
J
4
lnit.AIA Document 4101 -2017. Copyright@ 1915,
reserved. "The American lnstitute of Architects,"
American lnstitute
/ resale, is licensed
e-mail docinfo@aiacontracts.com.
lJser Notes:
1S18, 1925,1937, 1951, 1958,1961, 1963, 1967, 1974,1977,1987, 1991, 1957,2007 and2017. All rights
"American Institute of Architects," "AlA," the AIA Logo, and "AlA Contract Documents" are trademarks of The
of Architects. This document was produced at 08:1 5:01 ET
for one-time use only, and may only be used in accordance
on O4lO3l2O24 under Order No.3 ,l 04239382 which expires on 1011012024, is not for
with the AIA Contract Documents@ Terms of Service. To report copyright violations'
(14641 00981 )
7
Portions of Addenda relating to bidding or proposal requirements are not part of the Contract
Documents unless the bidding or proposal requirements are also enumerated in this Article 9.
Other Exhibits:
(Check all boxes that apply and include appropriate information identifuing the exhibit where
required.)
I X I The Supplementary and other Conditions of the Contract
(Paragraph deleted)
Title Date Pages
(Paragraphs deleted)
.9 Other documents, if any, listed below:
(List here any additional documents that are intended to form part of the Contract Doatments. AIA
Document A20lrNr-2017 provides that the advertisement or invitation to bid, Instructions to Bidders,
samplefonns, the Contractor's bid or proposal, portions ofAddenda relating to bidding or proposal
requirements, and other informationfurnished by the Owner in anticipation of receiving bids or
proposals, are not part of the Contract Documents unless enumerated in this Agreement. Any such
documents should be listed here only if intended to be part of the Contract Documents.)
Department of Labor and Industries Prevailing Wage Rates/
As part of the same Project Manual dated January 19,2024, as stated in Section 9, the following
documents are included as part of tle Contract Documents: Invitation or Advertisement for Bids,
Instructions to Bidders
This Agreement entered into as of the day and year first written above.
Dav e Zab ell. Interim Citv Manager President
(Printed name and title)(Printed name and title)
.8
Document
Project Manual dated January 19,
2024
c rrY c o NrRAcr
"o, .2€{:0&15
RESoLUToN uo, 4-Zoell-O4 1
lnit.AlADocumentAl0l-2017.Copyright@1915,1S18,1925,1937,1951,1958,1961,1963,1967,1974,1977,19S7,1SS1,1S97,2007and2017.Ailrighrs
reserved. "The American lnstitute of Architects," "American lnstitute of Architects," "AlA," the AIA Logo, and "AlA Contract Documents" are trademarks of The
American lnstitute of Architects. This document was produced at 08:15:01 ET on 0410312024 under Order No.3'104239382 which expires on 10t1012024, is not for
resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents@ Terms of Service. To report copyright violations,
e-mail docinfo@aiacontracts.com.
User Notes: (1464i009S1)
I
Additions and Deletions Report for
AIA' Document A101@ - 2017
This Additions and Deletions Report, as defined on page 1 of the associated document, reproduces below all text the author has added
to the standard form AIA document in order to complete it, as well as any text the author may have added to or deleted from the original
AIA text. Added text is shown underlined. Deleted text is indicated with a horizontal line through the original AIA text.
Note: This Additions and Deletions Report is provided for information purposes only and is not incorporated into or constitute any part
of the associated AIA document. This Additions and Deletions Report and its associated document were generated simultaneously by
AIA software at 0B:'15:01 ET on 0410312024.
PAGE 1
AGREEMENT made as of the sixteenth day of April intheyear 2024
Citlr of Yakima
129 North 2nd Street
Yakima. Washineton 98901
Chervenell Construction Company
107422 E Detrick PR SE
Kennewick. WA 99338
Martin Luther King Jr. Communitv Park Pool
610 South 9tl' Street
Yakima. Washington 9890 1
NAC Inc.
1203 West Riverside Avenue
Spokane. Washington 9920 I
(s09) 838-8240
PAGE 2
I L I A date set forth in a notice to proceed issued by the Owner
PAGE 3
ttl Not later than three-hundred eightv ( 3-80j calendar days from the date of commencement of the
Work.
N/A N/A
AdditionsandDeletionsReportforAlADocumentAlOl-2017.CopyrightO1915,1918,1925,1937,1951,1958,'1961,1963,1967,1974'1977, '1987'1991'1997'
trademarks of The American Institute of Architects. This document was produced at 0B:1 5:01 Ef on 0410312O24 under Order No.31 04239382 which expires on
1Ot1Ot2O24, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documentso Terms of Service. To report
copyright violations, e-mail docinfo@aiacontracts.com.
user Notes: - (1464100981)
1
$ 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor's performance of the
Contract. The Contract Sum shall be SNine Million Seven
plus Washington State Sales Tax. subject to additions and deductions as provided in the Contract Documents.
Alternate No. 2 Slide Tower & Dual
Runout Slides for Pool B
$970.000.00
As allowed under the bidding documents
Not Aoplicable fN/A)
Liquidated damages are as described in the AIA 201 General Conditions and Specification Section 007300
Supplementary Conditions
The Contractor and Owner aqree that the liquidated damages amount is not a penaltv and is a reasonable estimation of
actual damages to the Owner if they are not able to open the outdoor aquatic center for business for the fuIl summer
season session.
PAGE 4
N/A
Schedule oer Contract Documents
s 5.1.3
Theownersha11makepaymentoftheamountcertifiedtotheContractor
r\pptieatien fer Paym
PAGE 5
Statutorv retainage of five percent (5olo) shall be withheld from all payments. unless the Contractor submits and the
Owner accepts a retainage bond pursuant to RCW 60.28.011(6).
N/A
Per statute and the Contract Documents.
AdditionsandDeletionsReportforAlADocumentAl0l-2017.Copyright@1915,1918,1925,1937,1951,1958,1961,1963,1967,1574,1977,1987,1991,1997,
trademarks of The American lnstitute of Architects. This document was produced at 0B:15:01 Ef on O4lO3l2O24 under Order No.3104239382 which expires on
1011012024, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documentso Terms of Service. To report
copyright violations, e-mail docinfo@aiacontracts.com.
ljser Notes: (14641009S1)
(N/A)
2
N/A
N/A
30 days after completion of all requirements for Final Acceptance listed in the A20 1 -201 7 General Conditions and
Supolementary Conditions
%
Per the Contract Documents
PAGE 6
N/A
tX I other (Specify)
Litigation in Superior Court in Yakima County. Washington
Ken Wilkinson
2301 Fruitvale Boulevard
Yakima. WA 98902
(509) 57s-6oos
Kerureth. Wilkinson@,vakimawa. gov
Brandon Mavfield" President
Cheruenell Construction Company
107422 E. Detrick PR SE
Kennewick. WA 99338
(s09\ 73s-3377
bmayfi eld@chervenell. com
PAGE 7
Per the Contract Documents
N/A
,l AIA Document A101rL2017, Standard Form of Agreement Between Owner and
@
.3 AIA Document A20lrtQ.017, General Conditions of the Contract for Construction
AdditionsandDeletionsReportforAlADocumentAlOl-2017.Copyright@1915,1918,1925,1937,1951,1958,1961,'1963,1967,1974,1977,1987,139'l'1997'
trademarks of The American lnstitute of Architects. This document was produced at 08:1 5:01 ET on O41O312024 under Order No.31 04239382 which expires on
1Ot1Ot2O24, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documentso Terms of Service. To report
copyright violations, e-mail docinfo@aiacontracts.com.
usir Notes: - (1464100981)
indiea+eebebwr
as revised by the Owner including
Supplementary Conditions. All references to the A20l or to the General Conditions are to the revised
document.
.4 Not used.
See attached lndex of Drawings
See attached Tabie of Contents
February 8^2024
February 15.2024
February 22.2024
February 29.2024
I
I The supolementary and
other Conditions of the Contract
1 25
2t
36
52
z
3
4
PAGE 8
@
+i+lc Da{e Pages
DateTitle PaqesDocument
Project Manual dated January 19.
2024
f--J Stryplementar,v and other eenditiens of the eentraet:
Dseument +itle Pag€s
Department of Labor and Industries Prevailing Wage Rates/
As parl of the same Project Manual dated Januaq/ 19. 2024. as stated in Section 9. the followine
documents are included as part of the Contract Documents: Invitation or Advertisement for Bids.
Instructions to Bidders
Oave ZaUett. tnterim C Brandon Mavfreld.
Additionsand Deletions ReportforAlADocumentAl0l -2017. Copyright@1915, 1918,1925,1937,'1951,1958,'1961,1963, 1967, 1974,19TT,1987, 199.,|,.1997,
trademarks of The American lnstitute of Architects- This document was produced at 08:15:01 Ef on 04tO312024 under Order No.3104239382 which expires on
1011012024, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documentso Terms of Service. To report
copyright violations, e-mail docinfo@aiacontracts.com.
lJser Notes: (14641009S1)
Da+e
4
Cerlif i c ati o n of D o c u m ent' s A uth e nti c ity
AIA@ Document D401rM - 2003
I, , hereby certiff, to the best of my knowledge, information and belief, that I created the attached final document
simultaneously with its associated Additions and Deletions Report and this certification at 08:15:01 ET on 0410312024
under Order N o.3104239382 fromAIA Contract Documents software and that in preparing the attached final
document I made no changes to the original text of AIA@ Document A101rM -2017, Standard Form of Agreement
Between Owner and Contractor where the basis of payment is a Stipulated Sum, other than those additions and
deletions shown in the associated Additions and Deletions Report'
(Signed)
€itle)
(Dated)
AIA Document D401 - 2003. Copyright @ 1992 and 2003. All rights reserved. "The American lnstitute of Architects," "American lnstitute of Architects," "AlA," the AIA
Logo, and "AlA Conlract Documents-" are trademarks of The American lnstitute of Architects. This document was produced at 08:15:01 ET on 0410312024 under
OrderNo.3104239382whichexpireson l}tlot2o24,isnotforresale,islicensedforone-timeuseonly,andmayonlybeusedinaccordancewiththeAlAContract
Documents@ Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.
user Notes: - (1464100981)
1
1
a, .
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 8.
For Meeting of:April 16, 2024
ITEM TITLE: Resolution authorizing a contract with Chervenell Construction
Company for the MLK Jr Park Eastside Pool Project 2745
SUBMITTED BY: Scott Schafer, Director of Public Works
Bill Preston, PE, City Engineer
*Ken Wilkinson, Park and Recreation Manager
SUMMARY EXPLANATION:
The MLK Jr. Park Eastside Pool Project 2745 will provide for a public Aquatic Center located in
east Yakima at MLK Jr. Park.
The City of Yakima (City) used the procedure established by Washington State law for the
bidding and awarding of public capital improvement project with Chervenell Construction
Company being selected to provide construction in the amount of $9,770,000 plus Washington
State Sales Tax(WSST), not to exceed $10,580,910.00.
The Contract has been enclosed for City Council review.
The project is funded by multiple sources, including state grants, ARPA funds, local funds, and private
donations.
As a reminder, as discussed during the April 9 Study Session, donations are timed to come in over
2024, 2025, and 2026, and there remains approximately $500,00 - $600,000 left to raise. From a
spending standpoint (spenddown), the project will be paid out over an approximate 14 month period.
Fundraising efforts, which have been quite successful to date, are expected continue and the goal of
the privately funded portion of the project is expected to be reached. In that money will flow into the
project a bit slower than the construction spenddown, the City will be required to advance City funds to
fill the gap toward the end of the spend down. This will be accomplished utilizing fund balance or an
interfund loan, to be paid back as the remaining are received. The City has sufficient resources to
accomplish this, however, can wait to develop an exact strategy until closer to the time of need when
more information is known.
ITEM BUDGETED: Yes
STRATEGIC PRIORITY: Neighborhood and Community Building
2
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
RECOMMENDATION:
Adopt Resolution awarding the bid to Chervenell Construction Company.
ATTACHMENTS:
Description Upload Date Type
Resolution 4/12/2024 Resolution
a Contract 4/3/2024 Contract
;, Change Order
I ,�1 City of Yakima 01
�a. � r, / Change Order Number
Martin Luther KingJr. CommunityPark Pool Change Order Date 5/28/2024
Project: (Name) 9
(Number) 111-22082 Contract Number lJ -9.D2LI -d(o5
To: (Contractor) r —1 Contract Date 4/16/2024
Chervenell Construction Company
107422 E Detrick PR SE
Kennewick
WA 99338
J
You are directed to make the following changes in this Contract:
01-01 -Construction Change Directive 002(PCO 004)-Pacific Power Service Requirements $1,669.55
01-02-Proposal Request 001-R1 (PCO 002)-City Sewer and DOH Review Comments $52,504.06
01-03-Proposal Request 002(PCO 003)-Delete Lightning Protection ($15,000.00)
01-04-Proposal Request 006(PCO 001)-Remove Unforeseen Pool Structure (2-Day Time Extension) $59,553.98
01-05-Proposal Request 009(PCO 005)-Delete Pool UV System ($60,000.00)
Total $38,727.59
Not valid until signed by both the Approving Authority and Contractor.
Signature of the Contractor indicated agreement herewith,including any adjustment on the Contract Sum or Contract Time.
The original Contract Sum was $ 9770000.00
Net change by previous Change Orders $ 0.00
The Contract Sum prior to this Change Order $ 9770000.00
The Contract Sum will be: El Increased 0 Decreased ❑ Unchanged by this Change Order $ 38727.59
The New Contract Sum including this Change Order will be $ 9808727.59
The Contract Time will be: B Increased 0 Decreased 0 Unchanged by 2 working days
The New Contract Time will be 382 working days
Contractor Ap• •val Reco ended royal m ` ded
ConsW,•v r- Pub Acs or
B By ��i By ' �y�
Title Manny Torrez �/�5 �,
Date 5/29/2024 Date /
Vice President / I
CityEn1inler Approved
�/2 9 al y y\C.l`/ _ (1144,
n/) City
Date_ ni er "l
B G By
Date S(7i / (74 Date _l 3e
Based on Original to: ❑Contractor Copies to: 0 Region 0 Construction Administrator
DOT Form ssiOai EF ❑OSC Accounting 0 City EngineeringRevised (�
CITY CONTRACT NO.'d 1'-'0( C 0l
n
RESOLUTION NO' C( -T
N AC
•
Construction Change Directive
To: Chervenell Costruction CCD#: 002
Attn: Macoy Goulet, PM Project: Aquatic Center at MLK Jr Park
107422 E Detrick PR SE City of Yakima
Kennewick
WA 99338 NAC Project No: Aquatic Center at MLK jr Park Q3I
Date: 05/09/2024 Owner Project No:
In connection with your contract with City of Yakima
dated 4/16/2024 ,you are hereby directed to make the following change(s)in this Contract. Please
submit final costs for Work involved and change in Contract Time(if any)for inclusion in a subsequent Change Order.
Title: Pacific Power Service Requirements
Description: Description continues on Page 2,if following box is checked: 0
Provide additional underground service raceways as noted on Drawing E1.01 and E6.01 -attached.
Attachments: Drawing E1.01 and E6.01 revision date 5/8/24
•
Proposed Adjustments:
1. The proposed basis of adjustment to the Contract Sum or Guaranteed Maximum Price:
O Lump Sum Increase of$ .
Q Unit Price of $ per .
Q Cost,as defined below, plus the following fee:
Time&Materials plus Fee — $ I, 669, 55
Q As follows:
2. The Contract Time is proposed to Be Adjusted .
The proposed adjustment, if any, is an Increase of 0 days.
When signed by qif r . a •rchitect and received by the Contractor,this document becomes effective IMMEDIATELY
as a Construction y=r• ve.(CCD),and the Contractor shall proceed with the change(s)described above.
ARCHITECT �-r DATE 5/23/2024
rialArchitect Name
OWNER A AAWIl�ti DATE 5/25/21-i
Owner Name
CONTRACTOR �� N1o•-coy Gout aDATE S/2I/zo Vf
Contractor Name
Final Adjustments: A document identifying the final approved adjustments, including a breakdown of all related direct
and indirect costs,shall be submitted by the contractor and attached to this form.The adjustments identified there-in shall
be authorized for inclusion in a change order, by the addition of the Architect and Owner signatures below.
Final Cost of Change: $ Final Time Change: days.
ARCHITECT: OWNER:
> 1203 W Riverside Avenue,Spokane,WA,99201-1107
509.838.8240 nacarchitecture.com
Page 1 of 1 Columbus Los Angeles Seattle Spokane
N AC
Proposal Request
To: Chervenell Construction Company PR#: 001-R1
107422 E Detrick PR SE Project: Aquatic Center at MLK Jr Park
Kennewick City of Yakima
WA 99338
NAC Project No: 111-22082
Date: 05/22/2024 Owner Project No:
In connection with your contract with City of Yakima •
dated 4/16/2024 , please furnish an itemized proposal for changes to the Contract Sum and Contract Time
for modifications to the Contract Documents outlined below and/or detailed on the referenced attachments. Submit this
proposal within 14 days of receipt or notify the Architect in writing of the anticipated date of submission.
Title: Change Proposal 01-R1 -City Sewer Revision & Health Dept Comment Revisions
Description: Description continues on Page 2,if following box is checked: ❑✓
See attached description sheets.
Note to Contractor: refer to page 2 for a narrative of changes to the original PR-01. All other clouded changes noted in
the Revision column of the Drawings as both PR-01 and PR 02 apply to this change.
Attachments:
Refer to Conformed Set Drawings for clouded revisions
NOTE: THIS IS NOT A CHANGE ORDER OR A CONSTRUCTION CHANGE DIRECTIVE. DIRECTION TO PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS IS AUTHORIZED ONLY WHEN THE SECTIONS BELOW ARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECT AND OWNER'S SIGNATURES.
Contractor's Proposed Adjustments: Backup documentation from Contractor,showing breakdown of all direct
and indirect costs related to the change,shall be submitted and attached prior to issuance of a Change Order.
Proposed Change in Contract Sum: $ 52,504.06 .
Proposed Change in Contract Time: 0 days.
Submitted by: �� Date: S/Z`j72y
Proposal Review: If the propo . . ce.` •. a Change Order(CO)will follow which indicates the final authorized
Change amount. Billing cannot b�on e change until issuance of the CO.
Architect: ( 1. Date: 5/24/2024
Signa ure above ire ;test at NAC recommends acceptance of the forgoing prroopposal.
Owner: (!ti Date: `—�
gnature above indicates that the Owner accepts the foregoing proposal and authorizes pe orma ce of
he changes specified.
> 1203 W Riverside Avenue,Spokane,WA,99201-1 1 07
509.838-8240 nacarchitecture.com
Columbus Los Angeles Seattle Spokane
N AC
Proposal Request
To: Chervenell Construction Company PR#: 002
107422 E Detrick PR SE Project: Aquatic Center at MLKJr Park
Kennewick City of Yakima
WA 99338
NAC Project No: 111-22082
Date: 04/16/2024 Owner Project No:
In connection with your contract with City of Yakima
dated 5/16/2024 , please furnish an itemized proposal for changes to the Contract Sum and Contract Time
for modifications to the Contract Documents outlined below and/or detailed on the referenced attachments. Submit this
proposal within 14 days of receipt or notify the Architect in writing of the anticipated date of submission.
Title: VE - Delete Lightning Protection
Description: Description continues on Page 2,if following box is checked: El
Specification
Delete:Specification 264113 Lightning Protection System from scope of work.
Attachments:
NOTE: THIS IS NOT A CHANGE ORDER OR A CONSTRUCTION CHANGE DIRECTIVE. DIRECTION TO PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS IS AUTHORIZED ONLY WHEN THE SECTIONS BELOW ARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECT AND OWNER'S SIGNATURES.
Contractor's Proposed Adjustments: Backup documentation from Contractor,showing breakdown of all direct
and indirect costs related to the change,shall be submitted and attached prior to issuance of a Change Order.
Proposed Change in Contract Sum: $ (15,000.00)
Proposed Change in Contract Time: 0 days.
Submitted by: Date: 5710/2_019
Proposal Review: If the propos 's accepte , Change Order(CO)will follow which indicates the final authorized
Change amount. Billing cannot be h for h change until issuance of the CO.
5/10/2024
Architect: Date:
Signature ove indicates t t NAC recommends acceptance of the forgoing proposal.
c ,.
Owner: Date: 5
Sig ture above indicates that the Owner accepts the foregoing proposal and authorizes perform ce of
th hanges specified.
1203 W Riverside Avenue,Spokane,WA,99201-1107
509-838-8240 nacarchitecture.com
Columbus Los Angeles Seattle Spokane
LJUI.u. IyII CI IVCIUpC ILJ. l'JG'ItV1J-/UY0-YD IY-01DJ/1-l..1C0000 I YrLJ/1Y
N AC
Proposal Request
To: Chervenell Construction Company PR #: 006
107422 E Detrick PR SE Project: Aquatic Center at MLK Jr Park
Kennewick City of Yakima
WA 99338
NAC Project No: 1 1 1-22082
Date: 04/29/2024 Owner Project No:
In connection with your contract with City of Yakima
dated 4/16/2024 , please furnish an itemized proposal for changes to the Contract Sum and Contract Time
for modifications to the Contract Documents outlined below and/or detailed on the referenced attachments. Submit this
proposal within 14 days of receipt or notify the Architect in writing of the anticipated date of submission.
Title: Remove Existing Unforeseen Concrete Structure - RFI 01
Description: Description continues on Page 2,if following box is checked: ❑
On 4/26/24 the Owner directed the Contractor to provide a cost proposal to remove in its entirety the buried concrete
structure documented in RFI 01.
Attachments:
RFI 01
NOTE: THIS IS NOT A CHANGE ORDER OR A CONSTRUCTION CHANGE DIRECTIVE. DIRECTION TO PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS IS AUTHORIZED ONLY WHEN THE SECTIONS BELOW ARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECT AND OWNER'S SIGNATURES.
Contractor's Proposed Adjustments: Backup documentation from Contractor,showing breakdown of all direct
and indirect costs related to the change,shall be submitted and attached prior to issuance of a Change Order.
Proposed Change in Contract Sum: $ 59,553.98
Proposed Chan a ii Cpnt1act Time: 2 days.
ocu/'�gne by:
Submitted by: l�u F46D Date: 4/29/2024 I 4:32 PM PDT
4279E5A3DC3F46D
Proposal Review: If the proposal is accepted,a Change Order(CO)will follow which indicates the final authorized
Change amount. Billing cannot Ie hone y.nored for the change until issuance of the CO.
ocu Ig
Architect: Dew mGK Date: 5/2/2024 I 6:50 AM PD—
A Czbove DFEE614
in32
Signa re a cates that NAC recommends acceptance of the forgoing proposal.
Owner: Date: 51 J Siture above indicates that the Owner accepts the foregoing proposal and authorizperform ce of
th changes specified.
> 1203 W Riverside Avenue,Spokane,WA,99201-1107
509-838-8240 nacarchitecture corn
Columbus Los Angeles Seattle Spokane
N AC
Proposal Request
To: Chervenell Construction Company PR#: 009
107422 E Detrick PR SE Project: Aquatic Center at MLKJr Park
Kennewick City of Yakima
WA 99338
NAC Project No: 1 1 1-22082
Date: 05/22/2024 Owner Project No:
In connection with your contract with City of Yakima
dated 4/16/2024 ,please furnish an itemized proposal for changes to the Contract Sum and Contract Time
for modifications to the Contract Documents outlined below and/or detailed on the referenced attachments. Submit this
proposal within 14 days of receipt or notify the Architect in writing of the anticipated date of submission.
Title: Delete Pool A and Pool B UV System
Description: Description continues on Page 2,if following box is checked: n
Drawings:-Ultra Violet(UV)units for each pool have been removed with associated piping and valving.All details
pertaining to the UV are removed from project documents.
Specification:- Remove specification Section 131135 Pool Ultraviolet Disinfection Equipment from project documents.
Attachments:
NOTE:THIS IS NOT A CHANGE ORDER OR A CONSTRUCTION CHANGE DIRECTIVE. DIRECTION TO PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS IS AUTHORIZED ONLY WHEN THE SECTIONS BELOW ARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECT AND OWNER'S SIGNATURES.
Contractor's Proposed Adjustments: Backup documentation from Contractor,showing breakdown of all direct
and indirect costs related to the change,shall be submitted and attached prior to issuance of a Change Order.
Proposed Change in Contract Sum: $ (60,000)
Proposed Change in Contract Time: 0 days.
Submitted by: �/'2 Date: 572 ZOZt)
Proposal Review: If the prop ce o,a Change Order(CO)will follow which indicates the final authorized
Change amount. Billing cannot b: •.= he change until issuance of the CO.
Architect: IP Date: 5/24/2024
Signatu,e above indicates that NAC recommends acceptance of the forgoing proposal.
�il�-
Owner: Date:
Sign:ture above indicates that the Owner accepts the foregoing proposal and authorizes performahce of
the c anges specified.
1203 W Riverside Avenue,Spokane,WA,99201-1107
509-838-8240 nacarchltecture.com
Columbus Los Angeles Seattle Spokane
r, Change Order
,J! ) . City of Yakima
�' or ' 02
Change Order Number
Project: (Name) Martin Luther King Jr. Community Park Pool Change Order Date 6/26/2024
(Number) 111-22082 Contract Number C 2024-065
To: (Contractor) Contract Date 4/16/2024
I Cherveneli Construction Company
107422 E Detrick PR SE
Kennewick
WA 99338
L
You are directed to make the following changes In this Contract:ct
02-01 Proposal Request 04-Delete Locker Room Furring&Plywood Ceilings ($3,000.00)
02-02 Proposal Request 05-Alternate SIP Manufacturer ($5,000.00)
02-03 Proposal Request 08-Pre-Fabricated in lieu of Custom Fences&Gates ($84,962.00)
02-04 Proposal Request 10-Additional Tree Removal $,4089.96
CREDIT ($88,872.04)
Not Including WSST
The contract modifications enumerated above are hereby made a part of the Contract Documents to the same extent as
though they were originally included therein.
Not valid until signed by both the Approving Authority and Contractor.
Signature of the Contractor Indicated agreement herewith,Including any adjustment on the Contract Sum or Contract Time.
The original Contract Sum was $ 9,770,000.00
Net change by previous Change Orders $ 38,727.59
The Contract Sum prior to this Change Order $ 9,808,727.59
The Contract Sum will be: 0 Increased M Decreased 0 Unchanged by this Change Order $ (88,872.04)
The New Contract Sum including this Change Order will be $ 9,719,855.55
The Contract Time will be: 0 Increased 0 Decreased IN Unchanged by 0 working days
The New Contract Time will be working days
Conti a �-4�..,.._0 rovat R mended ro a l mmended
C+ Pu ' orks
By
/
�j By S AP
Tits r- Q S.isn {.a Pt NAC Areh%eoure
r Date 6/26 2024 Date 7 s2(/
oZ 7 / City en e r Approved
Date 7" N : -
oatefBy
4/ t(Z' j Date lL/ OI27 1 wW
Based on Original to: i3 Contractor Copies to: B Region IN Construction Administrator CITY CONTRACT Na `1 co#oa
DOT Form 570-001 EF B OSC AccountingEl CityEngineeringvD �
Revised 08/2021
RESOLUTION NO: 1
N AC
Proposal Request
To: Chervenell Construction Company PR #: 004
107422 E Detrick PR SE Project: Aquatic Center at MLKJr Park
Kennewick City of Yakima
WA 99338
NAC Project No: 1 1 1-22082
Date: 04/16/2024 Owner Project No: C-2024-065
In connection with your contract with City of Yakima
dated 4/16/2024 ,please furnish an itemized proposal for changes to the Contract Sum and Contract Time
for modifications to the Contract Documents outlined below and/or detailed on the referenced attachments. Submit this
proposal within 14 days of receipt or notify the Architect in writing of the anticipated date of submission.
Title: Delete Locker Room Plywood Ceilings
Description: Description continues on Page 2,!Hollowing box is checked: 111
In Locker Room 110 and 111, delete plywood ceiling and furring system. Provide finish paint(6.1)on the exposed SIP
system in these rooms.
This change is issued as a value engineering cost savings.
Attachments:
Drawing A9.01 revision date 6/5/2024
NOTE: THIS IS NOTA CHANGE ORDER OR A CONSTRUCTION CHANGE DIRECTIVE. DIRECTION TO PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS IS AUTHORIZED ONLY WHEN THE SECTIONS BELOW ARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECT AND OWNER'S SIGNATURES.
Contractor's Proposed Adjustments: Backup documentation from Contractor,showing breakdown of all direct
and indirect costs related to the change,shall be submitted and attached prior to issuance of a Change Order.
Proposed Change in Contract Sum: $ (3,000)
Proposed Change in Contract Time: 0 days.
Submitted by: 4 Date: WI '/20 aq
Proposal Review: If the proposal'y'""• --• : Change Order(CO)will follow which indicates the final authorized
Change amount. Billing cannot be nored for ' - hange until issuance of the CO.
6/20/2024
Architect: ( Date:
Signature bove indicates tha NAC recommends acceptance of the forgoing proposal.
Owner: Date: 6 �� 2
Sig re above indicates that the ner accepts the foregoing proposal and aut orizes performanc of
the anges specified.
> 1203 W Riverside Avenue,Spokane,WA,99201-1107
509-838-8240 nacarchitecture.com
Columbus Los Angeles Seattle Spokane
N AC
Proposal Request
To: Chervenell Construction Company PR#: 005
107422 E Detrick PR SE Project: Aquatic Center at MLK Jr Park
Kennewick City of Yakima
WA 99338
NAC Project No: 111-22082
Date: 06/04/2024 Owner Project No:
In connection with your contract with City of Yakima
dated 4/16/2024 ,please furnish an itemized proposal for changes to the Contract Sum and Contract Time
for modifications to the Contract Documents outlined below and/or detailed on the referenced attachments. Submit this
proposal within 14 days of receipt or notify the Architect in writing of the anticipated date of submission.
Title: Alternative SIP Manufacturer
Description: Description continues on Page 2,if following box is checked: El
Section 06 12 00-STRUCTURAL INSULATED PANELS, Part 2.1.A
Add: Part 2.1.A.2 Insulspan,www.insulspan.com
DRAWINGS:S3.02-ROOF FRAMING PLAN
Revise:Coded Note#7
Note:Submit manufacturer's literature and engineering calculations stamped by a professional engineer showing the
Insulspan SIP system meets all project contract documents requirements.
Attachments:
Drawing S3.02 revision date 5/6/2024
NOTE: THIS IS NOT A CHANGE ORDER OR A CONSTRUCTION CHANGE DIRECTIVE. DIRECTION TO PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS IS AUTHORIZED ONLY WHEN THE SECTIONS BELOW ARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECT AND OWNER'S SIGNATURES.
Contractor's Proposed Adjustments: Backup documentation from Contractor,showing breakdown of all direct
and indirect costs related to the change,shall be submitted and attached prior to Issuance of a Change Order.
Proposed Change in Contract Sum: $ (5,000) .
Proposed Change in Contract Time: 0 days.
It 114 r /
Submitted by: Date: C; IZ Zo24
Proposal Review: If the prig'sal is ac, • ed,a Change Order(CO)will follow which indicates the final authorized
Change amount. Billing can no ,.! •snore# •r the change until issuance of the CO.
6/14/2024
Architect: Date:
Sign re above i icates that NAC recommends acceptance of the forgoing proposal.
r
Owner: /Alt Date: ZD
ignature above indicates that the Owner accepts the foregoing proposal and utho izes performa ce of
the changes specified.
> 1203 W Riverside Avenue,Spokane,WA,99201-1107 A
509.838.8240 nacarchitecture.com
Columbus Los Angeles Seattle Spokane
N AC
Proposal Request
To: Chervenell Construction Company PR#: 008
107422 E Detrick PR SE Project: Aquatic Center at MLK Jr Park
Kennewick City of Yakima
WA 99338
NAC Project No: 111-22082
Date: 04/16/2024 Owner Project No: C-2024-065
In connection with your contract with City of Yakima
dated 4/16/2024 ,please furnish an itemized proposal for changes to the Contract Sum and Contract Time
for modifications to the Contract Documents outlined below and/or detailed on the referenced attachments. Submit this
proposal within 14 days of receipt or notify the Architect in writing of the anticipated date of submission.
Title: Pre-Fabricated Metal Fencing&Gates
Description: Description continues on Page 2,if following box is checked: �✓
The following value engineering change has been accepted by the Owner:
Please refer to Section 323119"Decorative Metal Fences and Gates":
1.Change acceptable manufacturer to Ameristar;(https://www.ameristarperimeter.com/).
Attachments:
Drawing A4.01 and A4.10 revision date 5/20/24
NOTE: THIS IS NOT A CHANGE ORDER OR A CONSTRUCTION CHANGE DIRECTIVE. DIRECTION TO PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS IS AUTHORIZED ONLY WHEN THE SECTIONS BELOW ARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECT AND OWNER'S SIGNATURES.
Contractor's Proposed Adjustments: Backup documentation from Contractor,showing breakdown of all direct
and indirect costs related to the change,shall be submitted and attached prior to issuance of a Change Order.
Proposed Change in Contract Sum: $ (84,962)
Proposed Change in Contract Time: 0 days. /
Submitted by: Date: G( i9/Zoz4
Proposal Review: If the propos d t': - Change Order(CO)will follow which indicates the final authorized
Change amount. Billing cannot be .orr for.
- change until issuance of the CO.'111111111_
Architect: �� Date: 6/20/2024
Signature above Indicate tha NAC recommends acceptance of the forgoing proposal.
z�
Owner: -I A Date: / /I
Sign ture above indicates that the Owner accepts the foregoing proposal and authorizes perfo mance of
the hanger specified.
> 1203 W Riverside Avenue,Spokane,WA,99201-1 1 07
509-838-8240 nacarchitecture.com
Columbus Los Angeles Seattle Spokane
N AC
Proposal Request
To: Chervenell Construction Company PR#: 010
107422 E Detrick PR SE Project: Aquatic Center at MLK Jr Park
Kennewick City of Yakima
WA 99338
NAC Project No: 111-22082
Date: 05/15/2024 Owner Project No:
In connection with your contract with City of Yakima
dated 4/16/2024 ,please furnish an itemized proposal for changes to the Contract Sum and Contract Time
for modifications to the Contract Documents outlined below and/or detailed on the referenced attachments. Submit this
proposal within 14 days of receipt or notify the Architect in writing of the anticipated date of submission.
Title: Additional Tree Removal
Description: Description continues on Page 2,if following box is checked: El
At the request of the Owner provide a cost/time proposal to remove two existing trees that have been deemed by the City
of Yakima's arborist to be in poor condition and in need of removal especially considering they could be compromised by
pending deep sanitary sewer line installation.
Attachments:
None
NOTE: THIS IS NOT A CHANGE ORDER OR A CONSTRUCTION CHANGE DIRECTIVE. DIRECTION TO PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS IS AUTHORIZED ONLY WHEN THE SECTIONS BELOW ARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECT AND OWNER'S SIGNATURES.
Contractor's Proposed Adjustments: Backup documentation from Contractor,showing breakdown of all direct
and indirect costs related to the change,shall be submitted and attached prior to issuance of a Change Order.
Proposed Change in Contract Sum: $ 4,089.96
Proposed Change in Contract Time: 0 days.
Submitted by:
Date: G/3/zoZ.j
Proposal Review: I propo a ' accepted,a Change Order(CO)will follow which indicates the final authorized
Change amount. Billin nnot be o ored for the change until issuance of the CO.
6/3/2024
Architect: Date:
Signa re above indicates hat NAC recommends acceptance of the forgoing proposal.
Owner:
(/L (A4/ Date: 4 (9)riak
Si nature above indi tes that the Owner accepts the foregoing proposal and authorizes performance of
t ip changes specified.
> 1203 W Riverside Avenue,Spokane,WA,99201-1107
509-838-8240 nacarchitecture.com
Columbus Los Angeles Seattle Spokane
'_1, , Change Order
401„,,1; City of Yakima 03
" Change Order Number
Martin Luther KingJr. CommunityPark Pool Change Order Date 8/09/2024
Project: (Name) g
(Number) 111-22082 Contract Number C-2024-065
To: (Contractor) �— Contract Date 4/16/2024
I Chervenell Construction Company
107422 E Detrick PR SE
Kennewick
L
WA 99338
You are directed to make the following changes in this Contract:
03-01 Proposal Request 11 -Future Play Structure Piping Connection $1,670.09
03-02 Construction Change Directive 03-Relocate Pool B Drains $5,630.62
03-03 Proposal Request 13-Rebar Rework @ Waterstop $613.17
03-04 Proposal Request 03-Revise Dual Slide and Stair Tower credit($225,000.00)
TOTAL CREDIT($217,086.12)
Not Including WSST
The contract modifications enumerated above are hereby made a part of the Contract Documents to the same extent as
though they were originally included therein.
Not valid until signed by both the Approving Authority and Contractor.
Signature of the Contractor indicated agreement herewith,including any adjustment on the Contract Sum or Contract Time.
The original Contract Sum was $ 9,770,000.00
Net change by previous Change Orders $ 50,144.45
The Contract Sum prior to this Change Order $ 9,719,855.55
The Contract Sum will be: 0 Increased M Decreased 0 Unchanged by this Change Order $ -217,086.12
The New Contract Sum including this Change Order will be $ 9,502,769.43
The Contract Time will be: 0 Increased 0 Decreased E Unchanged by 0 working days
The New Contract Time will be working days
Contr . .royal R- •mmended r va c mended
C. N . - .e 0
By /
By ` By �//
Tit �c�z i )N-t NAc Date Architecture 8/9/ 024 Date 'b/�d 2 <„,_
a
p/ / ity Engl er V Oft 1 2' 2 �/) � City City a r
By /� ; v:
Dat SI / ate a. .ai ' WA. ��
Based on Original to: 9 Contractor Copies to: IN Region B Construction Administrator
DOT Form 570-001 EF IN OSC Accounting IN City Engineering a,dxi--0(6 0,y3
Revised 08/2021 CITY CONTRACT NO-
RESOLUTION
l�+�t�3
RESOLUTION NO. Z a1 1.1 1
N AC
Proposal Request
To: Chervenell Construction Company PR #: 01 1
107422 E Detrick PR SE Project: Aquatic Center at MLKJr Park
Kennewick City of Yakima
WA 99338
NAC Project No: 111-22082
Date: 06/19/2024 Owner Project No: C-2024-065
In connection with your contract with City of Yakima
dated 4/16/2024 , please furnish an itemized proposal for changes to the Contract Sum and Contract Time
for modifications to the Contract Documents outlined below and/or detailed on the referenced attachments. Submit this
proposal within 14 days of receipt or notify the Architect in writing of the anticipated date of submission.
Title: Piping Connection for Future Play Structure- RFI 26
Description: Description continues on Page 2,if following box is checked: El
The Owner and A/E in response to RFI 26 directed the Contractor to proceed with a piping connection sump to terminate
piping for a future Pool A play structure. Specifically the Contractor was directed to provide the capped piping with the
12x12x12 sump with a grate on top.Grating is to be installed flat and secured,and to provide waterstop at the piping
penetration to prevent leaking.
Attachments:
RFI 26 w/A/E response dated 6/19/24
NOTE: THIS IS NOT A CHANGE ORDER OR A CONSTRUCTION CHANGE DIRECTIVE. DIRECTION TO PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS IS AUTHORIZED ONLY WHEN THE SECTIONS BELOW ARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECT AND OWNER'S SIGNATURES.
Contractor's Proposed Adjustments: Backup documentation from Contractor,showing breakdown of all direct
and indirect costs related to the change,shall be submitted and attached prior to issuance of a Change Order.
Proposed Change in Contract Sum: $ 1,670.09
Proposed Change in Contract Time: 0 days.
Submitted by: Date: 7/ 9/1024
Proposal Review: If the proymac -. -d,a Change Order(CO)will follow which indicates the final authorized
Change amount. Billing canno V.-- h� . the change until issuance of the CO.
Architect: _A" Date: 7/09/2024
Signature ..ove indicate that ilAC recommends acceptance of the forgoing proposal.
Owner: it L, (Ai
C . Date: z
Signa_re above indicates that the Owner accepts the foregoing proposal and au orizes p ormance of
the anges specified.
> 1203 W Riverside Avenue,Spokane,WA,99201-1107
509-838-8240 nacarchitecture.com
Columbus Los Angeles Seattle Spokane
N AC
Construction Change Directive
To: Chervenell Costruction CCD#: 003
Attn: Macoy Goulet, PM Project: Aquatic Center at MLK Jr Park
107422 E Detrick PR SE City of Yakima
Kennewick
WA 99338 NAC Project No: Aquatic Center at MLK jr Park(181
Date: Owner Project No: C-2024-065
In connection with your contract with City of Yakima
dated 4/16/2024 ,you are hereby directed to make the following change(s)in this Contract. Please
submit final costs for Work involved and change in Contract Time(if any)for inclusion in a subsequent Change Order.
Title: Relocate Pool B Drains
Description: Description continues on Page 2,if following box is checked: ❑
As follow up to the Owner's 6/14/2024 email-the Contractor is directed to proceed with the relocation of the main drains
assemblies at Pool B to the position indicated in the attached 6/17/24 email from WTI. Backfill and compact existing
drain locations and salvage the existing piping to extent possible. Additional information of piping reconfiguration is
forthcoming.
Attachments: 6/14/24 KW email;6/17/24 WTI Pool Pipe email
Proposed Adjustments:
1. The proposed basis of adjustment to the Contract Sum or Guaranteed Maximum Price:
O Lump Sum Increase of$
Q Unit Price of $ per
Q Cost, as defined below, plus the following fee:
Time and Materials
O As follows:
2. The Contract Time is proposed to Be Adjusted
The proposed adjustment, if any, is an Increase of days.
When signed by the er and c 'tect and received by the Contractor,this document becomes effective IMMEDIATELY
as a Construction Cha irecti ( CD), and the Contractor shall proceed with the change(s)described above.
ARCHITECT Don McKinney DATE 06/17/2024
Architect Name
OWNER � 1 ttiiI k(06(1 DATE � /2'/
Ow er ame
CONTRACTOR Nto-coY 6ou(ct DATE C/z9/2dZ9
Contractor Name
Final Adjustments: A document identifying the final approved adjustments, including a breakdown of all related direct
and indirect costs,shall be submitted by the contractor and attached to this form.The adjustments identified there-in shall
be authorized for inclusion' der, by the addition of the Architect and Owner signatures below.
Final Cost of Ch ,630.62 Final Time Change: 0 days.
ARCHITECT: OWNER:
> 1203 W Riverside Avenue,Spokane,WA,99201-1 1 07
509-838-8240 nacarchitecture.com
Page 1 of 1 Columbus Los Angeles Seattle Spokane
N AC
Proposal Request
To: Chervenell Construction Company PR #: 013
107422 E Detrick PR SE Project: Aquatic Center at MLK Jr Park
Kennewick City of Yakima
WA 99338
NAC Project No: 111-22082
Date: 7/12/2024 Owner Project No: C-2024-065
In connection with your contract with City of Yakima
dated 4/16/2024 , please furnish an itemized proposal for changes to the Contract Sum and Contract Time
for modifications to the Contract Documents outlined below and/or detailed on the referenced attachments. Submit this
proposal within 14 days of receipt or notify the Architect in writing of the anticipated date of submission.
Title: Rebar Rework for Waterstop Installation
Description: Description continues on Page 2,if following box is checked: Ei
The A/E in response to RFI 18 directed the Contractor to revise rebar layout to accommodate required waterstop
installation.
Attachments:
Chervenell PCO 011 -RFI 18 w/A/E response dated 6/10/24
NOTE: THIS IS NOT A CHANGE ORDER OR A CONSTRUCTION CHANGE DIRECTIVE. DIRECTION TO PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS IS AUTHORIZED ONLY WHEN THE SECTIONS BELOW ARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECT AND OWNER'S SIGNATURES.
Contractor's Proposed Adjustments: Backup documentation from Contractor,showing breakdown of all direct
and indirect costs related to the change,shall be submitted and attached prior to issuance of a Change Order.
Proposed Change in Contract Sum: $ $613.17
Proposed Change in Contract Time: 0 days.
Submitted by: Date: 7/2Z/z0a4
Proposal Review: If ty- . opos' .ccepted,a Change Order(CO)will follow which indicates the final authorized
Change amount. Billing,:ano�, .red for the change until issuance of the CO.
7/22/2024
Architect: Date:
Signatu e above i dicate that NAC recommends acceptance of the forgoing proposal.
iOwner: (�,., Yr\-- Date:
Si ature above indicates that the Owner accepts the foregoing proposal and au orizes perform nce of
t - changes specified.
> 1203 W Riverside Avenue,Spokane,WA,99201-1107
509-838-8240 nacarchitecture.com
Columbus Los Angeles Seattle Spokane
N AC
Proposal Request
To: Chervenell Construction Company PR#: 003
107422 E Detrick PR SE Project: Aquatic Center at MLK Jr Park
Kennewick City of Yakima
WA 99338
NAC Project No: 1 1 1-22082
Date: 04/26/2024 Owner Project No: C-2024-065
In connection with your contract with City of Yakima
dated 4/16/2024 ,please furnish an itemized proposal for changes to the Contract Sum and Contract Time
for modifications to the Contract Documents outlined below and/or detailed on the referenced attachments. Submit this
proposal within 14 days of receipt or notify the Architect in writing of the anticipated date of submission.
Title: Revise Pool B Dual Waterslides &Tower
Description: Description continues on Page 2,if following box is checked:
Revise Pool B dual waterslides and tower per attached"Splashtacular"proposed slide layout information.
Attachments:
Splashtacular Proposed Slide Layout SLD5 1 of 1,dated 6/17/2024
NOTE: THIS IS NOT A CHANGE ORDER OR A CONSTRUCTION CHANGE DIRECTIVE. DIRECTION TO PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS IS AUTHORIZED ONLY WHEN THE SECTIONS BELOW ARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECT AND OWNER'S SIGNATURES.
Contractor's Proposed Adjustments: Backup documentation from Contractor,showing breakdown of all direct
and indirect costs related to the change,shall be submitted and attached prior to issuance of a Change Order.
Proposed Change in Contract Sum: $ (225,000)
Proposed Change in Contract Time: 0 days.
Submitted by: Date:
Proposal Review: If the pr...sa is c-.ted,a Change Order(CO)will follow which indicates the final authorized
Change amount. Billing canna .e hono -d or the change until issuance of the CO.
Architect: Date: 7/01/2024
Signature ove
indicatesat th NAC recommends acceptance of the forgoing proposal.
in �l �
Owner: V"" 1- Date: 7 /(/z
Sig ature above indicates that the Owner accepts the foregoing proposal and authorizes performance of
the changes specified.
> 1203 W Riverside Avenue,Spokane,WA,99201-1107
509-838-8240 nacarchitecture.com
Columbus Los Angeles Seattle Spokane
'�` Change Order
k 1 } City of Yakima
- \or Change Order Number 04
Project: (Name) Martin Luther King Jr. Community Park Pool Change Order Date
9/20/2024
(Number) 111-22082 Contract Number C-2024-065
To: (Contractor) - Contract Date 4/16/2024
FChervenell Construction Company
107422 E Detrick PR SE
Kennewick
WA
99338
You are directed to make the following changes in this Contract:
04-01 Proposal Request 12-Pool Amenities Site Changes $11,322.76
04-02 Proposal Request 16-Intrusion Detection @ Admissions $1,181.16
$12,503.92
Not Including WSST
The contract modifications enumerated above are hereby made a part of the Contract Documents to the same extent as
though they were originally included therein.
Not valid until signed by both the Approving Authority and Contractor.
Signature of the Contractor indicated agreement herewith,including any adjustment on the Contract Sum or Contract Time.
The original Contract Sum was $ 9,770,000.00
Net change by previous Change Orders $ -166,941.67
The Contract Sum prior to this Change Order $ 9,502,769.43
The Contract Sum will be: Er Increased Decreased ❑ Unchanged by this Change Order $ 12,503.92
The New Contract Sum including this Change Order will be $ 9,515,273.35
The Contract Time will be: 0 Increased 0 Decreased 17 Unchanged by 0 working days
The New Contract Time will be working days
\
Contra royal R c mmended va Re ded
C ruc a Isar Public s Dir
By
randon Mayfield By By
Y
Tit NDa Architectur
e 9/20 2024 Date
President
Date A-3/72 l9 City EngAe Appr
ity M aiJ1V ----
B
Da ?/Z (?&i Date a ) aaa
Based on Original to: 9 Contractor opies to: B Region B Construction Administrator ' -0t
DOT Form 570.001 EF 8 OSC AccountingB CityEngineering CITY CONTRACT NO.
Revised 08/2021 n .�,^''
RESOLUTION NO' F- -In
`' ' '` Change Order
l; City of Yakima
\`� Change Order Number 05
Martin Luther KingJr. CommunityPark Pool Change Order Date 10/25/2024
Project: (Name) 9
(Number) 111-22082 Contract Number C-2024-065
To: (Contractor) �— � Contract Date
4/16/2024
I Chervenell Construction Company
107422 E Detrick PR SE
Kennewick
LWA 99338
You are directed to make the following changes in this Contract:
05-01 Proposal Request 17-Toilet Flush Sensor Power $1,056.38
05-02 Construction Change Directive 04-Middle School Side Sewer $43,077.06
05-03 Proposal Request 18-Additional Tree Removal $2,133.19
TOTAL $46,266.63
Not Including WSST
The contract modifications enumerated above are hereby made a part of the Contract Documents to the same extent as
though they were originally included therein.
Not valid until signed by both the Approving Authority and Contractor.
Signature of the Contractor indicated agreement herewith,including any adjustment on the Contract Sum or Contract Time.
The original Contract Sum was $ 9,770,000.00
Net change by previous Change Orders $ -254.726.65
The Contract Sum prior to this Change Order $ 9,515,273.35
The Contract Sum will be: E Increased ❑Decreased ❑ Unchanged by this Change Order $ 46,266.63
The New Contract Sum including this Change Order will be $ 9,561,539.98
The Contract Time will be: ❑ Increased 0 Decreased III Unchanged by 0 working days
The New Contract Time will be working days
Contra • •royal R- •mmended \ rov a ded
c• al • _ • Pub 74,•rk Di r
By
BY ( BY J
Tt ' '
'Pre t 4 ttit NAC Architecture
Date 10/2 /2024 Date /0 30 elr
%City E i eer Appr v
Date / r a S%OZ SA 'A /� City a
By �/ '" l
Date, I000 Date Nov I av
Bated o„ original to: 9 Contractor Copies to: El Region B Construction Administrator n 5
DOT Form S70-001 EF 8 OSC Accounting8 CityEngineering W .�
Re�sed08/2021 g g CITY CONTRACT N0
RESOLUTION NO:fi -61 1
%.s Change Order
k 1;5 City of Yakima
06
�!�� Change Order Number
Project: (Name) Martin Luther King Jr.Community Park Pool Change Order Date
12/09/2024
(Number) 111-22082 Contract Number C-2024-065
To: (Contractor) r Contract Date 4/16/2024
Chervenell Construction Company
107422 E Detrick PR SE
Kennewick
WA 99338
You are directed to make the following changes in this Contract:
06-01 Proposal Request 19-Concrete Paving Fiber Reinforcement $5,125.80
06-02 Construction Change Directive 05-Column Revision @ Grid 3/B $1,671.34
TOTAL $6,797.14
Not Including WSST
The contract modifications enumerated above are hereby made a part of the Contract Documents to the same extent as
though they were originally included therein.
Not valid until signed by both the Approving Authority and Contractor.
Signature of the Contractor indicated agreement herewith,including any adjustment on the Contract Sum or Contract Time.
The original Contract Sum was $ 9,770,000.00
Net change by previous Change Orders $ -208,460.02
The Contract Sum prior to this Change Order $ 9,561,539.98
The Contract Sum will be: ® Increased 0 Decreased 0 Unchanged by this Change Order $ 6,797.14
The New Contract Sum including this Change Order will be $ 9,568,337.12
The Contract Time will be: 0 Increased 0 Decreased a Unchanged by 0 working days
The New Contract Time will be working days
Contr royal Rpc mmended ro al m ded
C ruc er Isor Pu ' drs or
By / t
By ( , By
Title 17r t s I i t rt. NAC Architecture
Date 12/0 /2024 Date
G� `City Engineer ApprI, :rf 001 /
Date / ( /-7t/ wL CityM;:.
By :' /'
Date tl46 (n) z-5 Date j • * �
✓
Based on Original to: 9 Contractor Copies to: I3 Region 13 Construction Administrator
DOT Form 570.001 EF B OSC Accounting B City Engineering
Revised 0e12021 - i �°C �
CITY CONTRACT NOQQ /T4/�/_-��►/(_J�'�)
RESOLUTION NO -J-�. -U7I
City of Yakima
Project: (Name) Martin. Luther King Jr.CommunityPark Pool
(Number) 111-22082
To: (Contractor)
—1
|Chenmmd|Construction Company /
1O7432EDetrick PR8E
Kennewick
VVA9O338
|
L -�
'You are directed to make the following changes In this Contract:
07-01 PRU2U-POOO24 Building Signage Changes
07-02 PR21-PCOO23'Cold Weather TPO
07-03 PR22'Structural Insulated Panel Reconciliation
:07-04 PR024R1-Plumbing Shrouds
'07-05 PRU25'Plywood Ceilings
Change Order
07
Change Order Number
Change Order Date 02/17/202
C-2024-06
Contract Number '
Contract Date
4/16/2024
credit
$%,925.UO
$10.102.21
$3,501.23
TOTAL $23.628.02
Not Including VVSST
'The contract modifications enumerated above are hereby made mpart of the Contract Documents to the same extent as
though they were originally included therein.
—ot valid until signed by boththe roving Authority and Cunbactor.
Signature of the Contractor indicatiagreement herewith, Including any adjustment on the Contract Sum or Contract Time.
The original Contract Sum was ~~~...... ~.~...~~.^........................... ...~_~.~~~. $ _
Net change byprevious Change Orders ._.~....~~...~-.~................ .~~~..`~.~... ... $ _-201,662.88
The Contract Sum prior hothis Change Order ................... ........... .......... .._.~............ $ _ 12
The Contract Sum will be: 9 Increased ODecreased OUnchanged by this Change Order $ 23,628.02
The New Contract Sum including this Change Order will be ~....~_........... .~.,~~~~^~~^ $
9,591,965.14
0
�e�n�a�T�ewiUbe: O��a�d OD��a�d ��U�h�Q� by working days
The New Contract Time will bo working days
`
IContractor
K
I By AMP
� ����
' ~-~ ~, �~_---.
rm��u�.� r"�v�`°" wm�mmu=m=
nu `. - u�r:m�5
Dat
e
^ �
Based on
DOT Form 570-001 EF
Revised OB/202L
Original to: 19Contrauor Copies to 19 Region 19 Construction Administrat%rr, coNTRAo
MoScAccnumino nm����oneennv
- � - - RESOLUTION NO.'
Proposal Request
To: Chervenell Construction Company
107422 E Detrick PR SE
Kennewick
WA 99338
Date: 12/11/2024
PR #: 020
Project:
Aquatic Center at MLK Jr Park
City of Yakima
NAC Project No:
Owner Project No:
111-22082
C-2024-065
In connection with your contract with City of Yakima
dated 4/16/2024 , please furnish an itemized proposal for changes to the Contract Sum and Contract Time
for modifications to the Contract Documents outlined below and/or detailed on the referenced attachments. Submit this
proposal within 14 days of receipt or notify the Architect in writing of the anticipated date of submission
Title: Building Signage Change
Description: Description continues on Page 2, if following box is checked:
1) Refer to Drawing A4.10, Detail 2,
ADD: 6" high cast metal letters to read: MLK JR PARK
These tester shall be installed below the 15" letters reading AQUATIC CENTER (no changes), Left justify both sets,
2) Refer to Drawing A4.10, Details 1 and 4; Drawing A4.01 Detail 9,
DELETE: three sets of 15" cast metal letters reading: COMMUNITY ROOM
Attachments:
None
NOTE: THIS IS NOT A CHANGE ORDER OR A CONSTRUCTION CHANGE DIRECTIVE. DIRECTION TO PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS IS AUTHORIZED ONLY WHEN THE SECTIONS BELOW ARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECT AND OWNER'S SIGNATURES.
Contractor's Proposed Adjustments: Backup documentation from Contractor, showing breakdown of ail direct
and indirect costs related to the change, shall be submitted and attached prior to issuance of a Change Order.
Proposed Change in Contract Sum: $
Proposed Change in Contract Time:
Submitted by:
Proposal Review: If the
Change amount. Billing cann
Architect:
Owner:
osal is c
ono d
(5,964.60)
0
days.
Date: 12 /11 /1 2-0-2-1-1
ted, a Change Order (CO) will follow which indicates the final authorized
cc the change until issuance of the CO,
Date: 1 2/19/2024
above indicates that NAC recommends acceptance of the forgoing propolal.
Date: I
Sign, are above in iCa es that the Owner accepts the foregoing proposal and a hori.es performance of
the flanges specified,
> 1203 W Riverside Avenue, Spokane, WA, 99201-1107
509-838-824o nacarchitecture.com
Columbus Los Angeles Seattle Spokane
Proposal Request
To [hemene|Construction Company
1O74l2EDetrick PR5s
Kennewick
WA 99338
Date: 12/11/2024
.-_-..�...��."".,m����m��m��m�
"'"^"""`""'~^~'y~~' contract with nd[ontrac T—kn_e
dated 4/16/2024 please furnish anitemized proposal for dhanges tothe Contract �u� a
for modifications tothe Contract Documents outlinedbelow and/or detailed onthe referenced attachments. Submit this
the Auh�ctinwh�ngo[the andUpa�dd�eofsubm��«»'
proposal within 14 daysufrece|p�ornonTy e
Title: TPO Roofing Cold Weather Installation
Description; Description continues onpnge2, iffoxwmsbox ischecked: El
To accommodate scheduled installation of the fully adhered roofing`
d i andcipatedcold weather
conditions the owner � c�|d��a�herodhe�ive�re�ommended
and o thecostco��orusmgcu
~ ``~^--- �� ..=��8edin�ectiunO75423�/dde2'3�D
bythe Y�anu��u,�`mlieu o�the ��od��adm��e . .
Product Data submittal for Cold Weather Adhesive have been previously approved see attached
PR *: 021
Aquatic [enter at MLK]rPark
City of Yakima
NACProject NO:
Owner Project No'.
111-2zo82
Attachments:
Submittal O754Zs'z
NOT&THIS 8NOT xCHANGE ORDER ORuDONSTRUCTION CHANGE DIRECTIVE. DIRECTION TO PROCEED WITH THE
WORK DESCRIBED /NTHE PROPOSED MODIFICATIONS IsAUTHORIZED ONLY WHEN THE SECTIONS BELON/AHE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECT AND OWNER'S SIGNATURES.
,_�
k documentation �um[on�ac,ocshowing beakdmmnofall direct
/.Con�rocto�sp�mposedAdju»tnments |e«c uPda�achedphnr*nissuance ofaChange Ord«r
andindirec�cns��re|a�ed�o�hecxanXc.s�a/oesuom/u�uu/.
�
� 2,123.50�'. Proposed Change inContract Sum: $
�
� Proposed Change inContract Time: �,^^ O'��° _ days.
Date:
� Submitted �_
s acce te , a Change Order (CO) will follow which indicates the final authorized
Proposal Review: if the
�Change amount. Billing cannot change until issuance "."."`°
12/13/2O24
Signature a/o�e F-dicate'sfIat NAC recommends acceptance of the forgoing proposal
—�Jeabmein �cate, that the owner ausFtthe s—foegoing proposal and a��'horiksperformance or
Columbus Los Angeles Seattle Spokane
Proposal Request
To: [hcmend|Construction Company
1O74I2EDetrick pRSE
Kennewick
NN9933D
Date: 04/16/2024
PR#t 022
Project: Aquatic Center atMU<]rPark
City ufYakima
NACProject No:
owner Project No:
111-2ZO8Z
In connection with your ,
dated 4/16/2024 . please furnish anitemized proposal for changes mthe Contract Sum and "~^^'.`^^^'`
for modifications to the Contract Documents outlined below and/or detailed on the referenced attachments. Submit this
proposal within 14 days of receipt or notify the Architect in writing of the anticipated date of submission.
Title: Structural Insulation Panel (S|P)System Reconciliation
Description: Description continues onPage ziffollowongbox ischecked:
Asfull and complete consideration for additional Contractor isseeking inp[OOZU Structural Revisions for SIP
System the Owner and Contractor have agreed to increase the Contract Sum bythe one half ofthe value ofPco2o.
Attachments
'NOTE. THIS IS NO7A CHANGE ORDER ORACONSTRUCTION CHANGE DIRECTIVE. DIRECTION TO PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS IS AUTHORIZED ONLY WHEN THE SECTIONS BELOWARE
COMPLETED WiTH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECTAND OWNER'S SIGNATURES.
'-- Backup documentation homContractor,howingbreakdownofaU�,e�
�Cmntrac�o��propoaedAdju�tn�em�s aac p ucum�n,a n�s
�and indirect costs related oothe change, shall besubmitted and attached prior tnissuance ofaChange Order.Proposed Change in Contract Sum; $ $3,1925.00_ _
-
|'
Proposed Change inContract Time:
Submitted by:
Proposal Review: If the
`Change amount. Billing ca
^
/0
._—aChange Order (CO) will follow which indicates the final authorized
e* for the change until issuance of the CO.
Date: 12/13/2024_
recommends acceptance of the forgoing p
Date �
that the owner accepts the foregoing proposal an&a performance of
the �,hanges specified,
, /20awRiverside Avenue, Spokane, wx 9e201-1107
509-838-824v oocann/teoum/om
Columbus Los Angeles Seattle Spokane
Proposal Request
To
Chemnel|[onstruction Company
1O74zzEDetrick PRSs
Kennewick
VVA9g]3O
Date 01/24/2025
PR #: 074_R1
Project: Aquatic Center atMU<}rPark
City ofYakima
NACProject No:
Owner Project No:
111-2208Z
In connection with your contract with Citv of Yakima tract Time
dated 4116/2024 , please furnish an itemized proposal for changes to the Contract sum and Con
for modifications to the Contract Documents outlined below and/or detailed on the referenced attachments. Submit this
proposal within 14 days of receipt or notify the Architect in writing of the anticipated date of submission.
Title: Plumbing Chase Shrouds
Description: Description continues onPage zyfolmw»ngbox ischecked: L�
Provide pressure treated wood framed plywood sheathed shroud to conceal horizontal runs of copper plumbing piping in
MensChanging 110and WomensChanging 111. Slope the tupofthe shroud oodrain,
Provide similar shroud to conceal verl:[cal piping in the northeast corner of L ifegua rd /Storage 1 00A (refer to Drawing
Ps.O1).
Paint all shrouds to match surrounding wall surfaces.
Attachments:'
None
NOTE. THIS IS NO7ACHANGE ORDER OR A CONSTRUCTION CHANGE DIRECTIVE. DIRECTION TO PROCEED WITH THE
WORK DESCRIBED VVTHE PROPOSED /moDK7CAzIoNS IYAUTHORIZED ONLY WHEN THE SECTIONS BELom/ARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THEARCHITECTAND OWNER'S SIGNATURES.
Contractor's Proposed Adjustments: Backup documentation from Contractor, showing breakdown ofall direct
and indirect costs relatedm thechange,dha||besubmittedandattachedphor»oisauanoeofa[hange0mer.
Proposed Change |ncontract sum: $ 10
~_.162_21
� Proposed Change |nContract Time: �~,_`0 days.
Submitted by:
Proposal Review: If the p d, a Change Order ([[) will follow which indicates the final authorized
Change amount. Billing cannZbe�h=nore�)Zr the change until issuance of the CO.
Owner
Date: -2/6/2025
NAC recommends acceptance of the forgoing proposal.
Date: -z,,l q -zo z-
S404ture above indicates that the Owner accepts the foregoing pmposa)and authorizes performance uf
t*4 changes specified.
> 120awRiverside Avenue, Spokane, WA,yyzo1-11ur
509'838-824o nausnn/tecm,e,mm
Columbus Los Angeles Seattle Spokane
Pro
To:
a
osaK
�
equest
[hemeneUConstruction Company
1O74Z2EDetrick PRSE
Kennewick
VVA993sO
Date: 01/15/2025
PR#: 025
Project: Aquatic Center at MLKJr Park
City ofYakima
NACProject NO:
Owner Project No:
111-22O82
|nconnection with your contract with CitvofYakima
dated p/easemm�.
/snon/m/z�"p."p"==.~changes ~ the Contract _—_—Sum an
�'r—`'Ducumen�oudinedb�mwand/ord�ai|edonthe re�renadattachments.
Submit this
dContractTime
proposal within /4 ""
'~ modifications~�—--Contract
"' receipt the Architect wr
iting
Title: Locker Room Ceilings
Description: Description continues onPage Z iffo«owog box ischecked. LJ
The Owner wishes mrescind previously executed PR04which deleted the Type ['4plywood ceiling system in in the
mensand wmmenslocker rooms.
Attachments:
NOTE. THIS 8;NOT4CHANGE ORDER ORACONSTRUCTION CHANGE DIRECTIVE. DIRECTION nJPROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS IS AUTHORIZED ONLY WHEN THE SECTIONS BELOW ARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECTA*mOWNER'S SIGNATURES.
--= Contractor's
"—
�opooed Adjustments: eadmpdocumemadnn�omcon�au�
nshowing ���o��aUd��
;and indirect related to the change, shall be submitted and attached prior to issuance of a Change Order.
� Proposed Change inContract Sum: $_�,$3.501.23_
Proposed Change inContract Time:
Submitted by:
-,Proposal Review: ifthe gr�
: Change amount. Billing canno
days.
|/_�)/ZoZ�
Date .�-°'''I � . ` ~^=-_
�:�«�aChange order (CO)will follow which indicates the final authorized
_~ he change until issuance of the CO.
1/21/2O25
--�_______
_
___�
�
wxcmmmm����ar��t�saL
- - - forgoing propo
' --
ae� �"
rg,a'ture above indicates that the — owner accepts the foregoing proposal and authorizes performance of
he changes specified.
�12nWRiverside Avenue, Spokane, WA, 99201-1107
mm*m*mmn nacanh|tectumcnm
Columbus u,,Angeles Seattle Spokane
. . ... . . .���
Proposal Request
To:
[hemewd|Construction Company
1D74ZZEDetrick PRSE
Kennewick
YVA99]38
Date: 01/24/2025
PR#t ()76
Project: Aquatic Center at MU(]rPark
City ofYakima
WACPnoject No:
Owner Project NO:
111-2ZO82
|nconnection with your contract with citv of'Yakima,
dated 4/lh/�24 '�easefvmishani�mizedpmpo�|for �engesmthe Contract Sum and Cnn�� actme
hrmodiMcutionsfothe Contract Documents outlined below and/or detailed onthe referenced attachments. Submit this
proposal within 14 days of receipt or notify the Architect in writing of the anticipated date of submission.
Title: Umbrella Clarifications
Description: Description continues onPage Z07mlo*inobox ischecked: L�
A1.UZ'SITE PLAN,
ADD: Umbrella located inthe south landscape area see coded note aD.
Note: Color selections for each of the five umbrella locations have been identified in coded note 23 and 28.
Attachments
Drawing A1.02 - SITE PLAN revision date 1/17/25
/ymT&THIS/smmrACHANGE ORDER oRACONSTRUCTION CHANGE DIRECTIVE. DIRECTION TOPROCEED WITH THE
mOwKofSCRIBEDVxTHE PROPOSED MODIFICATIONS /SAUTHORIZED ONLY WHEN THE SECTIONS af1OWARE
COMPLETED WITH THE CONTRACTORS PROPOSAL AND WITH BOTH THE ARCHITECTAND OWNER'S SIGNATURES.
'Contractor's Proposed Adjustments: Backup documentation from Contractor, showing breakdown urall direct
and indirect costs related to the change, shall be submitted and attached prior to issuance of a Change Order,
\ Proposed Change inContract Sum: $�9.880.88_
Proposed Change in Contract Time: 0 days
Submitted by:
Proposal Review: if the propo �f
Change amount. Billing cannot bi
—:aiccep
fo.- tfechange until issuance ofthe CO.
wZ S
2/6/225
— e�ba�ep���ufuem�omm
s�mam�amo�indicates N*C recommends ''~�`~~'.
Owner accepts the foregoing PMPOSS� and performance of
"ttu'r'a ve
th changes specified.
s 1203wRiverside Avenue, Spokane, WA, syzo -1/07
ooy'8,9*o24v noonmtecture.'om
Columbus Los Angeles Seattle Spokane
Project: (Name)
(Number)
To: (Contractor)
City of Yakima
Martin Luther King Jr. Community Park Pool
111-22082
I Chervenell Construction Company
107422 E Detrick PR SE
Kennewick
WA 99338
L
1
Change Order
Change Order Number
Change Order Date 03/31/2025
Contract Number C 2024 065
Contract Date .. 4/16/2024
08
You are directed to make the following changes in this Contract:
08-01 PR 27R1 — Casework Locks
08-02 PR 28 - Louver Revisions
08-03 PR 29 - Changing Room Soffit Lids
08-04 PR 32 - Surge Tank Vent Fan
08-05 PR 33 - Pool Heater & Control Panel Electrical Requirements
08-06 PR 34 - Mini -Split Shrouds
$5,287.05
$2,572.86
$1,564.94
$5,002.20
$1,241.40
$2,408.03
TOTAL $18,076.48
Not Including WSST
The Contract modifications enumerated above are hereby made a part of the Contract Documents to the same extent as
though they were originally included therein.
Not valid
a of until the Con
signed by both the Approving Authority and Contractor.
Si
gnature tractor indicated agreement herewith, including any adjustment on the Contract Sum or Contract Time.
The original Contract Sum was
Net change by previous Change Orders $
-The Contract Sum prior to this Change Order $
The Contract Sum will be: 8 Increased ❑ Decreased ❑ Unchanged by this Change Order $
The New Contract Sum including this Change Order will be ..............»...>.,..............««._..<.. $
9,770,000.00
-178,034.86
9,591,965.14
18,076.48
9,610,041.62
The Contract Time will be: ❑ Increased ❑ Decreased M Unchanged by 0 working days
The New Contract Time will be working days
f 9e-c- plw10-9er
©ate
3/z9(zo2S
Based on
DOT Form 570-001 EF
Revised 08/2021
original to: El Contractor
By
NAC Architecture
Date
Copies to: El Region El Construction Administrator
9 OSC Accounting El City Engineering
CITY CONTRACT N
RESOLUTION NO:
Proposal Request
To:
[hemeneUConstruction Company
l07422EDetrick PR5E
Kennewick
vvA9933O
Date: 02/20/2025
PR*: 027-R1
Project: Aquatic Center at IVILx]rpark
City ofYakima
N4CProject No:
Owner Project No:
111-22O82
mconnection with your contract with ritvofYaNma--
dated 4/16/2024^ . please furnish anitemized proposal for changes tuthe Contract Sum and Contract Time
for modifications to the Contract Documents outlined below and/or detailed on the referenced attachments. Submit this
proposal within 14 days of receipt or notify the Archit(tct in writing of the anticipated date of submission.
Title Casework Locks
Description: Description continues on Page 2, iffbimwingbox * checked:
�]
Refer mannotated DRAWINGS A7uz INTERIOR ELEVATIONS:
ADD: Cabinet Locks atdesignated cabinet doors and drawers.
Attachments:
Drawing A7.02 annotated, Lock Product Data
NOTE. THIS s0O7ACHANGE ORDER DRACONSTRUCTION CHANGE DIRECTIVE. DIRECTION TOPROCEED WITH THE
WORK DESCRIBED 0VTHE PROPOSED MODIFICATIONS 8AUTHORIZED ONLY WHEN THE SECTIONS BELOW ARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECTAND OWNERS SIGNATURES.
Contractor's Proposed Adjustments: Backup documentation from Contractor, showing breakdown ofall direct
and indirect costs related to the change, shall be submitted and attached prior to issuance of a Change Order.
Proposed Change in Contract Sum: $
Proposed Change in Contract Time: U days.
Submitted by:
oaS
Proposal Review: |fthe proposal is accepted, aChange Order ([O)will follow which indicates the final authorized
Change amount. Billing cannot be honored for the change until issuance of the CO.
Architect �� _ _ oate
Owner
Signat ,^ above indicates tPatmAcrecommends acceptance wrthe forgoing
'
above indicates that the Owner accepts the foregoing proposal and aUhorizes performance of
changes specified.
^ 120awRiverside Avenue, Spokane, WA, 99201-1107
509-838-8240 nao,nh/tectue.mm
Pro
To:
I
osaU
[hcmeneUConstruction Company
1D7422EDetrick PRS[
Kennewick
VYA99338
Date: 02/18/2025
in connection with your contract with City of Yakima
dated please furnish anitemized proposal for changes to the Contract Sum and Contract Time
for modifications nfthe `Contract Documents outlined below and/or detailed onthe referenced attachments. Submit this
proposal within 14 days ofreceipt ornotify the Archit�ccinwriting ofthe anticipated date ofsubmission,
PR *: 028
Project: Aquatic Center at MLK1rPark
City ofYakima
NACProject No:
Owner Project No:
111-22082
Title: Louver 14and 16Revisions _
�
Description: Description continues cmp�e 2.iffoVowogbox is�»omed. F�-I
Refer coElevation 1 onDrawing A4.Dl'and Drawing A4.1V Louver Types,
CHANGE: the dimensions of Louver l4and Louver 16such that the slope of the top side matches the slope ofthe roof
and the adjacent louvers #13and #15respectively. Field dimension openings uoverify.
Attachments:
2/17/25 email notification and photo provided by Chervenell Construction,
)VOTE, THIS IS NOT ACHANGE ORDER ORA CONSTRUCTION CHANGE DIRECTIVE. DIRECTION TO PROCEED WITH THE
WORK -DESCRIBED IN THE PROPOSED MODIFICATIONS 0AUTHORIZED ONLY WHEN THE SECTIONS BELOWARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECTAND OWNER'S SIGNATURES.
'Contractor's Proposed Adjustments: Backup documentation from Contractor, showing breakdown orall direct
and indirect costs related to the change, shall be submitted and attached prior to issuance of a Change Order,
�
Proposed Change in Contract Sum: $
Proposed Change inContrTim
e: O days
Submitted by:
Proposal Review: If the --
' ~
Change amount. Billing camooi7
I-S'al is ac-*
Date:~
p'�,,�cl, a Change Order (CO) will follow which indicates the final authorized
for the change until issuance of the CO.
Architect _-_ __ Date:^
Sign4,'Iure above indicat,�,w
3-19-2025
that mAcrecommends acceptance o/the forgoing proposal,
that the owner accepts the foregoing proposal and authorizes performance of
changes specified,
" izo3wRiverside Avenue, Spokane, WA, yyzo -1107
e*83e'624n ^ocan».u,mre^u,m
Columbus Los Angeles Scao|eSpokane
Pro
To:
osal
•
e
uest
Chervenell Construction Company
107422 E Detrick PR SE
Kennewick
WA 99338
Date: 03/24/2025
In connection with your contract with City of Yakima
dated 4/16/2024 , please furnish an itemized proposal for changes to the Contract Sum and Contract Time
for modifications to the Contract Documents outlined below and/or detailed on the referenced attachments. Submit this
proposal within 14 days of receipt or notify the Architect in writing of the anticipated date of submission.
Title: Plywood Lids @ Changing Room Entry Soffits
Description: Description continues on Page 2, i f following box is checked: D
Provide wood framed plywood sheathed lid above changing room entries with hinged access panel to prevent debris
from being thrown into the entry ceiling cavity.
PR #: 029
Project: Aquatic Center at MLK Jr Park
City of Yakima
Attachments:
Chervenell PCO 033 R1 dated 3/20/25
NAC Project No:
Owner Project No:
111-22082
C-2024-065
NOTE: THIS IS NOT A CHANGE ORDER OR A CONSTRUCTION CHANGE DIRECTIVE. DIRECTION TO PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS IS AUTHORIZED ONLY WHEN THE SECTIONS BELOW ARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECT AND OWNER'S SIGNATURES.
Contractor's Proposed Adjustments: Backup documentation from Contractor, showing breakdown of all direct
and indirect costs related to the change, shall be submitted and attached prior to issuance of a Change Order.
Proposed Change in Contract Sum: $ $1,564.94
Proposed Change in Contract Time: 0 days.
iza-(
Submitted by:
Proposal Review: If the pro
Change amount. Billing canno
Architect:
Owner:
0. 4f, ar
e nurture
Date:
d, a Change Order (CO) will follow which indicates the final authorized
fo the change until issuance of the CO.
Date:
3/25/2025
Signatur a ove Indicate that NAC recommends acceptance of the forgoing proposal.
Date: -5 (z-Viznas—
Sig tore above indicates that the Owner accepts the foregoing proposal and authorizes performance of
th changes specified.
> 1203 W Riverside Avenue, Spokane, WA, 99201-1107
509-838.8240 nacarchitecture.com
Columbus Los Angeles Seattle Spokane
Proposal Request
To:
[herveneU{unstruction Company
107422EDetrick pe5E
Kennewick
WA99338
Date: 03/18/2025
pR#h 032
pn4ecc Aquatic Center a*MLK]rPark
City cfYakima
mAcp,ojec No:
Owner Project No:
l`1-22O82
mconnectionwiMhyou,contraccvmth�OtvufYakbma
—
dated 4U6/2024 . please furnish unitemized proposal for changes cnthe Contract Sum and Contract Time
for modifications to the Contract Documents outlined below and/or detailed on the referenced attachments. Submit this
pmposa|with|n 14 days vfreceipt nrnotify the x,�h|,��tinwMungofthe ant|Upateddate nfsuunni,sion.
Title: Surge Tank Vent -Fan RF|O68 _
Description: Description continues vnpoge 2, ifm0owogbox ischecked: �]
In the A/E response to RFI 068 the mechanical engineer determined the need to provide a vent fan serving the surge tank
area. The Contractor provided associated pricing inpcoo31 which has approved inthe amount uf$s'ooz.z0
Attachments:
NOTE: THIS 8No7ACHANGE ORDER O0ACONSTRUCTION CHANGE DIRECTIVE. DIRECTION T0PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS IS AUTHORIZED ONLY WHEN THE SECTIONS BELOWARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THEARCHITECTAND OWNER'S SIGNATURES.
Contractor's Proposed Adjustments: Backup documentation from Contractor, showing breakdown ufall direct
and indirect costs related to the change, shall be submitted and attached prior to issuance of a Change Order,
Proposed Change in Contract Sum: $ $5,002.20
Proposed Change inContract Time:
submitted by:
Proposal Review: If the proposal is accepted, a Change Order (CO) will follow which indicates the final authorized
Change amount. Billing cannot be honored for the change until issuance of the CO.
Signature *ove indicates that NAC recommends acceptance of the forgoing proposal.
Da
5il �-ature above indicates that the Owner accepts the foregoing proposal
(,,-, changes specified.
,1203 Wmveoide Avenue, Spokane, WA, ezm-1nn
509-833-B240 nacanch/tectum.mm
Columbus Los Angeles Seattle Spokane
Prososal e•uest
To: Chervenell Construction Company PR #: 033
107422 E Detrick PR SE Project: Aquatic Center at MLK Jr Park
Kennewick City of Yakima
WA 99338
Date: 03/19/2025
NAC Project No:
Owner Project No:
111-22082
C-2024-065
In connection with your contract with City of Yakima
dated 4/16/2024 , please furnish an itemized proposal for changes to the Contract Sum and Contract Time
for modifications to the Contract Documents outlined below and/or detailed on the referenced attachments. Submit this
proposal within 14 days of receipt or notify the Architect in writing of the anticipated date of submission.
Title: Pool Heater & Control Panel Electrical Requirements - RFI 070
Description: Description continues on Page 2, if following box is checked: El
As follow up to A/E response to RFI 070 the Contractor submitted PCO 034 for the amount of $1,241.40 as documentation
of the related cost impacts which have been determined by the A/E to reflective of the additional scope of work.
Attachments:
Chervenell PCO 034 dated 3/13/2025
NOTE: THIS IS NOT A CHANGE ORDER OR A CONSTRUCTION CHANGE DIRECTIVE. DIRECTION TO PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS IS AUTHORIZED ONLY WHEN THE SECTIONS BELOW ARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECT AND OWNER'S SIGNATURES.
,Contractor's Proposed Adjustments: Backup documentation from Contractor, showing breakdown of all direct
and indirect costs related to the change, shall be submitted and attached prior to issuance of a Change Order.
Proposed Change in Contract Sum: $ $1.241,40,
Proposed Change in Cq
Submitted by:
Proposal Review: If the prop
Change amount. Billing cannot
Architect:
Owner:
Date:
a Change Order (CO) will follow which indicates the final authorized
e change until issuance of the CO.
Date: 3/24/2025
AC recommends acceptance of the forgoing proposal.
Date:
cure above indicates that the Owner accepts the foregoing proposal and authorizes performance of
e changes specified.
> 1203 W Riverside Avenue, Spokane, WA, 99201-1107
509-838-8240 nacarchitecture.com
Columbus Los Angeles Seattle Spokane
Pro
To:
osal
e
uest
Chervenell Construction Company
107422 E Detrick PR SE
Kennewick
WA 99338
Date: 03/24/2024
PR #: 034
Project: Aquatic Center at MLKJr Park
City of Yakima
NAC Project No:
Owner Project No:
111-22082
C-2024-065
In connection with your contract with City of Yakima
dated 4/16/2024 , please furnish an itemized proposal for changes to the Contract Sum and Contract Time
for modifications to the Contract Documents outlined below and/or detailed on the referenced attachments. Submit this
proposal within 14 days of receipt or notify the Architect in writing of the anticipated date of submission.
Title: Mini -Split System Piping Shroud
Description: Description continues on Page 2, i f following box is checked:
Provide utility service line set shrouds to conceal piping/raceways serving split system units SS-1 a, 55I-1b, and SSI-2c, and
SSI 2c. Paint to march existing wall surface.
Attachments:
Cherevenell PCO 035 dated 3/20/25
NOTE: THIS IS NOT A CHANGE ORDER OR A CONSTRUCTION CHANGE DIRECTIVE. DIRECTION TO PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS IS AUTHORIZED ONLY WHEN THE SECTIONS BELOW ARE
COMPLETED WITH THE CONTRACTOR'S PROPOSAL AND WITH BOTH THE ARCHITECT AND OWNER'S SIGNATURES.
Contractor's Proposed Adjustments: Backup documentation from Contractor, showing breakdown of all direct
and indirect costs related to the change, shall be submitted and attached prior to issuance of a Change Order.
Proposed Change in Contract Sum: $ S2,408.03
Proposed Change in Contract Time:
4
:
0 days.
Submitted by: Date
Proposal Review: If the
Change amount. Billing cant
Architect:
Owner:
osal is
e host°
/25/Z0 a5
pted, a Change Order (CO) will follow which indicates the final authorized
for the change until issuance of the CO.
3/25/2025
Date:
S' re above indicat s that NAC recommends acceptance of the forgoing proposal.
Date: -2 2
Sig ature above indicates that the Owner accepts the foregoing proposal and authorizes performance of
the changes specified.