HomeMy WebLinkAbout07/05/2023 06.B. Project Completion and Contract Acceptance with Superior Walls LLC for the 2nd St Landscaping Renovation Project 2441BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 6.8.
For Meeting of: July 5, 2023
ITEM TITLE: Project Completion and Contract Acceptance with Superior Walls
LLC for the 2nd St Landscaping Renovation Project 2441
SUBMITTED BY: Scott Schafer, Director of Public Works
* Bill Preston, PE, City Engineer 509-576-6754
SUMMARY EXPLANATION:
City Project #2441 provided for the 2nd Street Landscaping Renovation. In 2018 the City
contracted with Superior Walls LLC to provide for site preparation, grading, irrigation system
installation, and landscaping for N 2nd Street.
Final inspection for this project was made and the recommendation is that the project be
accepted. Project completion is subject to issuance of Certificate of Payment by the Department
of Revenue and authorizations from state agencies allowing final payment. A final payment of $0
is due from the City to Superior Walls LLC for the completion of the work.
Project Manager: Randy Tabert
Contractor: Superior Walls LLC
Contract Awarded: 02/01 /18
Contract Cost: $ 65,324.25
Retainage Due: $ 2,970.85
The total contract cost is for construction only and does not include engineering and other costs.
City Council action is required to accept the project and approve the final construction costs.
ITEM BUDGETED: Yes
STRATEGIC PRIORITY: Public Safety
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
RECOMMENDATION:
Accept Project
F-A A CITII : I M 1:4 z k I&I
Description Upload Date Type
Compleflon Note 6/14/2023 Backup Material
Engineering Division
129 North Second Street
Yakima, Washington 98901
1'575-6111
RE: City of Yakima 2017 2nd St Landscaping Renovation
Project No. 2441with Superior Walls
Date: June 14, 2023
Note to file: Project Completion
The above referenced project was considered complete on 6/25/18. A physically
complete letter could not be found.