HomeMy WebLinkAbout05/02/2023 06.C. Project Completion and Contract Acceptance with Tapani Inc for the North 1st Street Revitalization N Street to SR12 Phase 1 Project 2340 BUSINESS OF THE CITY COUNCIL YAKIMA, WASHINGTON AGENDA STATEMENT Item No. 6.C. For Meeting of: May 2, 2023 ITEM TITLE: Project Completion and Contract Acceptance with Tapani Inc for the North 1st Street Revitalization N Street to S R12 Phase 1 Project 2340 SUBMITTED BY: Scott Schafer, Director of Public Works * Bill Preston, PE, City Engineer(509) 576-6674 SUMMARY EXPLANATION: Tapani Inc completed the North 1st Street Revitalization N Street to SR12 Phase 1 Project 2340. Final inspection for this project was made and the recommendation is that the project be accepted. A final payment of$0 is due from the City to Tapani Inc for the completion of this project. Delayed closure of project due to Department of Labor& Industries review and staff turnover. Contractor: Tapani Inc Contract Awarded on: 02/20/19 Contract Cost: $4,265,791.08 Total Due: $0 The total contract cost is for construction only and does not include engineering and other costs. City Council action is required to accept the project and approve the final construction costs. ITEM BUDGETED: Yes STRATEGIC PRIORITY: Neighborhood and Community Building APPROVED FOR SUBMITTAL BY THE CITY MANAGER RECOMMENDATION: Accept Project ATTACHMENTS: Description Upload Date Type ❑ Completion Letter 2/27/2023 Backup Material , PUBLIC WORKS - Scott Schafer, Director 2 7/4<---- � . Engineering Division 11:7129 North Second Street ;,j';� �. ✓F Yakima, Washington 98901 s'+ • s (509) 575-6111 • Fax (509) 576-6305 +! N'Npir,1 l.o 1- - December 1/3/2020 Mr. Aaron Hailing Tapani, Inc. 1904 SE 6th Place Battle Ground, WA 98604 Re Contract No: C2340 Project Name: North 1st Street Revitalization Project 'NI' St. to SR12 Fed Aid No: STPUS-4579(011) Physical Completion Dear Mr. Hailing: In accordance with Section 1-08.5 of the standard specifications this project is considered physically complete as of Wednesday, December 16, 2019 The contract required the work to be physically complete within One Hundred and sixty (160) working days. Five (5) additional working days were added by change order, for a total of one hundred sixty-five (165) working days. Substantial Completion was granted on working day one hundred sixty-five (165) working days. After which working days ceased to be counted in accordance with Section 1-08.5. Physical Completion was granted on December 12, 2019 once the most of remaining punch-list items had been completed. Within the next 30 days we intend to issue the Final Contract Voucher Certificate(FCVC)for this contract. We will need the following documentation from your office in order to issue the FCVC (list or attach list as needed): ■ Statement(s) Affidavits of Wages Paid Washington State Department of Labor and Industries (L&I) must certify that all Contractors and Subcontractors who performed work on a public works contract are current with payments of their industrial insurance. Should you have any questions, please do not hesitate to contact me at 728-3455. Thank you for your cooperation in this matter. Sincerely, (14 . Robert Desgrosellier Acting Chief Engineer cc: Susie Cutter, Contract Specialist Wendy Harvey, Finance Randy Tabert, Design Engineer File