HomeMy WebLinkAbout04/18/2023 06.N. Resolution authorizing an agreement with HLA Engineering and Land Surveying, Inc to provide Professional Construction Management, Observation and Administration Services for the Nob Hill Boulevard Resurfacing and Pacific Avenue Sidewalk I Y�'1114'+
�0�
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 6.N.
For Meeting of:April 18, 2023
ITEM TITLE: Resolution authorizing an agreement with HLA Engineering and
Land Surveying, Inc to provide Professional Construction
Management, Observation and Administration Services for the Nob
Hill Boulevard Resurfacing and Pacific Avenue Sidewalk
Improvements Projects 2619 and 2612
SUBMITTED BY: Scott Schafer, Director of Public Works
* Bill Preston, City Engineer- (509) 576-6754
SUMMARY EXPLANATION:
The City of Yakima's Nob Hill Boulevard Resurfacing project includes resurfacing from 15th Ave
to 28th Ave. Pacific Ave. Sidewalk Improvements constructs missing sidewalk segments along
Pacific Ave. The City used the procedure established by Washington State law for the bidding
and awarding of public capital improvement projects with HLA Engineering and Land Surveying,
Inc. being selected to provide professional services for construction engineering and
administration services on the projects in the amount not to exceed $230,900.00. The two
projects will be combined into one construction project for ease of administration and reduction of
construction costs. The Agreement has been attached for City Council review.
The Nob Hill Resurfacing project is being state funded with a Transportation Improvement Board
(TI B)Award of$1,335,000 requiring a 20% local match and the Pacific Ave. Sidewalk
Improvements project, is being funded by a $250,000 Award for Complete Street with no local
match required.
ITEM BUDGETED: Yes
STRATEGIC PRIORITY: Public Safety
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
RECOMMENDATION:
Adopt Resolution
ATTACHMENTS:
2
Description Upload Date Type
D Resolution HLA Projects 4/5/2023 Resolution
D Consultant Agreement 3/31/2023 Contract
3
RESOLUTION NO. R-2022-
A RESOLUTION authorizing an Agreement with HLA Engineering and Land Surveying, Inc.
to provide Professional Construction Management, Observation and
Administration Services for the Nob Hill Boulevard Resurfacing and
Pacific Avenue Sidewalk Improvements Projects 2619 and 2612.
WHEREAS, the Nob Hill Boulevard Resurfacing project received $1,335,000 from the
Transportation Improvement Board (TIB) for design and construction with a minimum 20% local
match required; and
WHEREAS, the Pacific Avenue Sidewalk Improvements project received $250,000 from
TIB for Complete Streets requiring no local match; and
WHEREAS, the Nob Hill Boulevard Resurfacing and Pacific Avenue Sidewalk
Improvements projects will be combined into one construction project for ease of administration
and reduced construction costs; and
WHEREAS, the City of Yakima (City) has the need to perform construction management
on the Nob Hill Boulevard Resurfacing and Pacific Avenue Sidewalk Improvements Projects;
and
WHEREAS, the City used the procedure established by Washington State law for the
bidding and awarding of public capital improvement projects; and
WHEREAS, HLA was determined to be qualified to perform the needed professional
construction management work and was selected to provide professional construction
management, observation and administration services; and
WHEREAS, the City Council of the City of Yakima finds that entering into the
Professional Services Agreement with HLA Engineering and Land Surveying, Inc., for
construction management on the Nob Hill Boulevard Resurfacing and Pacific Avenue Sidewalk
Improvements projects is in the best interests of the City and its residents; now, therefore
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
The City Manager is hereby authorized to execute a Professional Services Agreement
with HLA Engineering and Land Surveying, Inc., attached hereto and incorporated herein by this
reference, not to exceed Two Hundred Thirty Thousand Nine Hundred Dollars ($230,900) to
provide construction management services and services outlined in the Professional Services
Agreement.
ADOPTED BY THE CITY COUNCIL this 18th day of April, 2023.
ATTEST: Janice Deccio, Mayor
Sonya Clear Tee, City Clerk
4
Contract Supplemental Agreement
Supplemental Agreement Organization and Address:
Number: 1 HLA Engineering and Land Surveying, Inc.
2803 River Road
Yakima, WA 98902
Original Contract Number: Execution Date of Supplement:
2022-192
City Project Number: Completion Date of Supplement:
AT 2612/2619 December 31, 2024
Project Title: Original Amount Payable:
Nob Hill Boulevard Resurfacing and Pacific $306,710
Avenue Sidewalk Improvements
HLA Project No. 22145C
Revised Amount Payable this Supplement: $537,610 (Increase of$230,900)
Supplemental Agreement No. 1
The City of Yakima (CITY),Washington desires to supplement the Original Contract No. 2022-192 entered
into with HLA Engineering and Land Surveying, Inc. on October 19, 2022, by Resolution No. 2022-141.
All provisions in the basic contract remain in effect except as expressly modified by this supplement. The
changes to the Agreement are described as follows:
Exhibit A: Scope of Services
The attached Exhibit A-Scope of Services for additional tasks to be performed as part of this Supplemental
Agreement include Construction Engineering services associated with eighty (80) contract days.
Exhibit B: Construction Fees
Payment for this supplemental work, as shown on Exhibit B is not to exceed $230,900, bringing the total
amount of the Agreement to $537,610 (Original Task Order Amount of$306,710 plus Supplement No. 1
amount of$230,900).
Exhibit C: Schedule of Rates
Exhibit C shall be supplemented with the attached 2023 calendar year schedule of rates for the completion
of the Agreement for Professional Services.
If you concur with this supplement and agree to the changes as stated above, please sign the appropriate
spaces below and return to this office for final action.
By: By:
Consultant Signature City Manager Signature
Date
VAts02VGeneralAContracts&Task Orders V Yakima A2022\Nob Hill Blvd.Resurfacing&Pacific Ave.Sidewalk ImpACN Agreement\2023-03-24 Contract No.2022-192 Supplement
1 docx
5
EXHIBIT A
Scope of Services
Nob Hill Boulevard Resurfacing and Pacific Avenue Sidewalk Improvements Project
Project Management
1. Provide monthly status reports and invoices for work performed.
2. Maintain project files for Agency review.
Assumptions:
1. City will prepare funding reimbursements.
Construction Engineering and Administration
(The construction contract duration is eighty (80) working days. The fee estimate assumes each working
day consists of twelve (12) hours per day.)
Coordinate and facilitate preconstruction meeting, including preconstruction agenda and meeting record.
Prepare and issue Notice to Proceed to Contractor.
Furnish the field survey crew to set horizontal and vertical control for the project.
Provide staking for construction, including but not limited to structures, curb and gutter, sidewalk, subgrade
elevations, signing, and pavement markings.
Provide submittal review for project materials as provided by the Contractor per the specifications. Maintain
submittals list for duration of project.
Respond to Contractor Request for Information (RFI).
Administer construction meetings anticipated once per week during the duration of improvements.
Furnish a qualified resident engineer (inspector) to observe construction and be at the project site during
all significant work. The resident engineer shall provide surveillance of construction for substantial
compliance with plans and specifications. It is anticipated the Contractor may perform asphalt paving work
at night and concrete curb/sidewalk work during the day, requiring two shifts to observe construction.
Prepare daily progress reports.
Prepare weekly statements of working days.
Consult and advise the Agency during construction and report of the completed work with Agency
representatives.
Review acceptance sampling and testing for construction materials.
Perform measurement and computation of pay items.
Recommend progress payments for the Contractor to the Agency.
Prepare proposed contract change orders and/or force account computations as required.
Conduct final inspection with the Contractor, Agency, and HLA, and prepare punchlist of items to be
addressed by the Contractor and provide to the Agency.
VAts02VGeneralAContracts&Task Orders V Yakima A2022\Nob Hill Blvd.Resurfacing&Pacific Ave.Sidewalk ImpACN Agreement\2023-03-24 Contract No.2022-192 Supplement
1 docx
6
Prepare and furnish reproducible record drawings and field notes of completed work in accordance with
project field records.
Prepare administrative documents to the appropriate agencies which have jurisdiction over funding, design,
and construction of this project.
Monitor the Contractor and Subcontractor's compliance with State labor standards during the construction
phase of this project, including requests to sublet, intents to pay prevailing wages, affidavits of wages paid,
employee wage interviews, and issuing letters of non-compliance and/or missing documentation.
All project communications including owner, Contractor, utilities, and others shall be directed through HLA.
Prepare and submit recommendation of project acceptance and Notice of Completion of Public Works
Contract (NOC) for Agency review and processing.
VAts02VGeneralAContracts&Task Orders V Yakima A2022\Nob Hill Blvd.Resurfacing&Pacific Ave.Sidewalk ImpACN Agreement\2023-03-24 Contract No.2022-192 Supplement
1 docx
7
EXHIBIT B
Construction Fees
The following spreadsheet shows the estimated time and expenses to perform said services. The maximum
amount of compensation to the ENGINEER shall not exceed the amount indicated, but the ENGINEER
reserves the right to move fee and hours between tasks as necessary to complete the PROJECT.
Project Title: Nob H.II Boulevard Resurfacing and Pacific Avenue Sidewalk Improvements
Client: City of Yakima
Date: March 21.2023 ENGINEERS HOURLY ESTIMATE
Senior Proect Project Licensed Two Men Resident Contract Engineering
Task Task Description Principal Engineer Engineer I Land Sure, Engneerr Administrator Technician Total Task Direct
No. Engineer II Surveyor Crew Inspector III I Hours Costs
5250 1 5184 5165 $181 5256 1 5136 1 $151 1 597
1 Prepare and Issue Notice of Award 0 1 0 0 0 0 2 0 3 5486
2 Conduct PreConstruction Meei.ng 2 2 2 0 0 2 2 0 10 $1.772
3 Prepare and Issue Notice to Proceed 1 1 0 0 0 0 I 0 3 5585
4 Field Survey Crew for Horan/en Contrd 0 1 0 10 60 0 0 2 73 517.518
5 Materials Submiltol Review 2 8 2 0 0 4 2 4 22 53,536
6 Weekly Construction Meetings(1Xl16orc) 4 16 8 0 0 16 16 0 60 59.856
7 Construction Observation(BOdI 4 80 8 0 0 960 0 4 1056 5147.988
8 Field Inspection Reports 0 8 0 0 0 80 30 0 118 516.882
9 Weekly Statement or Wong,Days 2 2 0 0 0 8 8 8 28 $3,940
10 Materials on Hand 0 4 2 0 0 4 4 0 14 52.214
11 Prepare Monthly Progress Pay Estimates 4 8 4 0 0 0 20 0 36 56.152
12 Review Materials Testing Results for Complienue with Contract 0 8 2 0 0 2 2 0 14 $2.376
13 Prepare and Submit Change Orders 2 4 2 0 0 0 4 0 12 52.170
14 Review State Labor Standards Compeartce 0 2 0 0 0 0 4 8 14 51.748
15 Conduct Final Wark•Throu9hPrepare Punehi.1 2 4 2 0 0 4 8 0 20 53 318
16 Project Closeout 2 8 4 0 0 8 16 0 38 56.136
17 Record Drawings 0 2 1 0 0 8 4 0 15 52,225
Labor Subtotal 25 159 37 10 60 1096 123 26 1536 $228.932
SUBCONSULTANTS
Subconsullents Fee Mark-us
SO
Subtotal Subconsullants SO
EXPENSES
Expenses: Cost/Unit Ground Days Days Miles Units
Mileage $0,66 3000 51.970
Subtotal Expanses $1.970
TOTAL $230,900
1Vs021General\Contracts&Task OrderslYakima120221Nob Hill Blvd.Resurfacing&Pacific Ave.Sidewalk Imp1CN Agreement12023-03-24 Contract No.2022-192 Supplement
1.docx
8
EXHIBIT C
SCHEDULE OF RATES
FOR
HLA Engineering and Land Surveying, Inc.
Effective January 1, 2023, through December 31, 2023
Senior Principal Engineer $250.00 per hour
Licensed Principal Engineer $223.00 per hour
Licensed Principal Land Surveyor $223.00 per hour
Licensed Professional Engineer $201.00 per hour
Other Licensed Professional $201.00 per hour
Project Engineer II $184.00 per hour
Licensed Professional Land Surveyor $181.00 per hour
Project Engineer I $165.00 per hour
Contract Administrator III $151.00 per hour
Senior Planner $149.00 per hour
CAD Technician $145.00 per hour
Engineering Technician III $136.00 per hour
Planner $136.00 per hour
Resident Engineer $136.00 per hour
Surveyor $134.00 per hour
Surveyor on Two Man Crew $128.00 per hour
Contract Administrator II $126.00 per hour
Engineering Technician II $117.00 per hour
Surveyor on Three Man Crew $112.00 per hour
Contract Administrator I $97.00 per hour
Engineering Technician I $97.00 per hour
Administrative/Clerical $97.00 per hour
Vehicle Mileage Federal Rate