Loading...
HomeMy WebLinkAbout07/21/2009 07 Six-Year TIP for 2010 to 2015 and Amendment to Metropolitan Transportation Plan and Yakima UAC Plan BUSINESS OF THE CITY COUNCIL • YAKIMA, WASHINGTON AGENDA STATEMENT Item No. 1 1 For Meeting of July 21, 2009 ITEM TITLE: Public Hearing to consider: A) Adoption of the Six -year Transportation Improvement Program for the years 2010 to 2015, and to amend the Metropolitan Transportation Plan; and • B) Amend the Yakima Urban Area Comprehensive Plan Capital Facilities Element to incorporate the adopted Six -year Transportation Improvement Program. SUBMITTED BY: William Cook, Director of Community and Economic Development - CONTACT PERSON/TELEPHONE: Brett Sheffield, Chief Engineer, 576 -6797. SUMMARY EXPLANATION: ® Attached is the 2010 - 2015 Six -year TIP, along with an explanation sheet that describes the information contained on the various columns of the Six -year TIP. Two transit projects have been added to the six -year TIP. These projects are: • '#8 Expanded transit service to Terrace Heights • #18 Fixed route bus service to Moxee along the SR 24 corridor. Continued on Page Two Resolutions X Ordinance Contract Other (Specify) Six -Year TIP Funding Source APPROVED FOR SUBMITTAL: \ ""�...r- City Manager STAFF RECOMMENDATION: 1. Hold the Public Hearing to consider adoption of Resolution approving the Six -year TIP and amending the regional Metropolitan Transportation Plan and the Comprehensive Plan Capital Facilities Element. 4110 2. Adopt the plan. BOARD /COMMISSION /COMMITTEE RECOMMENDATION: COUNCIL ACTION: Page Two Projects that that have been deleted from the 2009 — 2014 TIP as they were completed or the funds were obligated include: • #3 16 Avenue Realignment • #5 Purchase five new transit buses • #6 Purchase three new paratransit vehicles • #13 Nob Hill Boulevard Improvements from 64 Avenue to 72 " Avenue • #68 Nob Hill Boulevard Improvements from 68 Avenue to 72n Avenue • #77 Nob Hill Boulevard Overpass Repairs Council and the public are welcome to add other arterial system projects to the list. The six -year TIP project listing will, .be finalized at today's hearing and sent to the Yakima Valley Conference of Governments (YVCOG) after approval. City and County staff, together with the Council Intergovernmental Committee, are working toward , common standards and coordinated planning for public projects that impact both the city and surrounding county areas. Agreement on these issues will be the first step the goal of a seamless transportation planning process between the City and County. A) Each year the City is required by RCW 35.77.010 and RCW 36.81.121 to update its Six -year Transportation Improvement Program (TIP) for submittal to the Washington State Department of Transportation. This plan must include all transportation projects for which state gas tax revenue . of federal revenue will be used. • The current plan for 2010 — 2015 includes fifteen projects that are funded. Funding for the remainder of the projects will continue to be sought. • �. Six -year Transportation Improvement Program (TIP) Background I , • , On August 10, 2005, the President signed into law the Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA -LU). This act is the next authorization after the prior Transportation Equity Act of 1998 for the 21S Century (TEA -21) and previous Intermodal Surface Transportation Efficiency Act (ISTEA) of 1991. The current act again .specifies . the systems on which certain funds can be used, and activities for which funds can be used and promotes the role of the Metropolitan Planning Organizations (MPO) in the planning and programming of projects: SAFETEA -LU requires each designated MPO, to develop a Transportation Improvement Program (TIP), and the state to develop a, Statewide Transportation Improvement Program (STIP) as a condition to securing federal funds for the transportation projects. Projects listed in the STIP are_ the only projects that can be approved by the Federal Highway Administration (FHWA) and the Federal Transit Administration (FTA) to utilize federal fund of by , the State of Washington for approved State funding agencies. The STIP is a prioritized program of transportation projects, complied from local - and regional plans, along with the Washington Transportation System Plan (WTP), which 'provides a backbone for developing projects for the intermodal transportation network in the State of Washington. - The STIP contains federally funded projects plus state and local projects that are regionally® < significant. These projects have been identified through the planning process as the highest priority for the available funding to the state's transportation program. ' 2 - July 15, 2009 Planning activities of state and local governments are essential parts of integrated regional • planning processes. Long range transportation planning is a part of the comprehensive land use planning carried out by local governments. Citizen participation is an integral part of the planning process at all levels. Local Agencies are required to develop and adopt a six -year transportation program. All local agencies are required to hold at least one public . hearing during the development of the six -year transportation program. Project ranking has been performed utilizing data supplied by the Street and Traffic Division. The ranking will be integrated with other project needs and the total list will be reviewed and adjusted to the particular need of the City of Yakima. B) The City needs to amend the Yakima Urban Area Comprehensive Plan Capital Facilities Element to incorporate the adopted six -year TIP for 2010 to 2015. This will ensure that we are in compliance with the Growth Management Act and that we are consistent with the Comprehensive Plan as required: The amendment is limited to incorporate only those projects that adopted in the STIP and is not subject to the "once a year" change required under the laws of the Growth Management Act. III _... . , • III • RESOLUTION NO. R —2009 - • A RESOLUTION adopting a Six -Year Transportation Improvement Program for the period of 2010 through 2015 for the construction of streets and arterials streets in the City of Yakima and amending the Metropolitan Transportation Plan. WHEREAS, the City of Yakima annually prepares, reviews and adopts a Six Year Program for the construction of streets and arterial streets in the City of Yakima for the ensuing six year period, all as contemplated and required by State RCW 35.77.010 and applicable Federal . law; and WHEREAS, the City of Yakima desires to amend the Metropolitan Transportation Plan to ensure compliance with the Growth Management Act and the regional transportation plan for the construction of streets and arterial streets in the City of Yakima, all as contemplated and required by State and Federal law, and 411 WHEREAS, after a public hearings on the matter, held at the regular meeting of the Yakima City Council on July 21, 2009, with proper public notice as required by RCW 35.77.010, the City Council finds that the plan attached hereto should be adopted as the Six -Year Transportation Improvement Program for the period of 2010 through 2015 for the construction of streets and arterial streets in the City of Yakima, now, therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA: The Six -Year Construction Program for the period of 2010 through 2015, a copy of which is attached hereto and by this reference made a part hereof, is hereby adopted as the official Six -Year Transportation Improvement Program for the City of Yakima, including proposed amendments to the Metropolitan Transportation Plan along with Street Improvements, which are also approved. ADOPTED BY THE CITY COUNCIL this 21 day of July, 2009. • David Edler, Mayor ATTEST: City Clerk • RESOLUTION NO. R — 2009 - A RESOLUTION to amend the Yakima Urban Area Comprehensive Plan Capital Facilities Element to incorporate the Six -year Transportation Improvement Program (TIP) for the period of 2010 through 2015 WHEREAS, the City of Yakima annually prepares, reviews and adopts a Six — Year Transportation Improvement Program for the construction of streets and arterial streets in the City of Yakima for the ensuing six year period, all as contemplated and required by State RCW 35.77.010 and applicable Federal law; and WHEREAS, the City of Yakima desires to amend the Yakima Urban Area Comprehensive Plan Capital Facilities Element to reflect the adoption of the Six -year TIP, as contemplated and required by RCW 36.70A.070(6) to ensure compliance with the Growth Management Act and consistency of the Comprehensive Plan and the Six -year TIP; and, WHEREAS, this amendment is limited to incorporation of the projects listed in the Six -year Transportation Improvement Plan for the period. of 2010 to 2015 to the Capital Facilities Element of the Yakima Urban Area Comprehensive Plan, which is contemplated and provided under RCW 36.70A.130(2B) and RCW 35.77.010; and WHEREAS, a public hearing was held by the Yakima City Council on the Six -year TIP on July 21, 2009, with proper public notice as required by RCW 35.77.010; now,. therefore BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA: The adopted Six -Year Transportation Improvement Program for the period of 2010 through 2015 for the City of Yakima shall be incorporated as an amendment to the Capital facilities Element of the Yakima Urban Area Comprehensive Plan. ADOPTED BY THE CITY COUNCIL this 21 day of July, 2009. David Edler, Mayor ATTEST: IIII City Clerk • 9. Appendices A. Six Year Form Instructions Heading Agency Enter name of the sponsoring agency. County No. Enter the assigned number (see LAG Appendix 21.44). City No. Enter the assigned number (see LAG Appendix 21.45). MPO /RTPO Enter the name of the associated MPO (if located within urbanized area) or RTPO (if located in a rural area). Hearing Date Enter the date of the public hearing: Adoption Date Enter the date this program was adopted by council or commission. - Resolution No. Enter Legislative Authority resolution number (if applicable.) Amendment Date Enter the date this program was amended by council or commission. Column Number 1. Functional Classification. Enter the appropriate 2 -digit code denoting the Federal Functional Classification. (Note: The Federal Functional Classification must be one approved by FHWA.) • Description 00 = No Classification Rural (< 5000 pop.) • Urban (> 5000 pop.) 01 - Interstate 11 - Interstate 02 - Principal Arterials 12 - Freeways & Expressways 06 - Minor Arterials 14 - Other Principal Arterials 07 - Major Collector 16 - Minor Arterial 08 - Minor Collector 17 - Collector 09 - Local Access 19 - Local Access 2. Priority Numbers. Enter local agency number identifying agency project priority (optional). 3. Project Identification. • Enter (a) Federal Aid Number if previously assigned; (b) Bridge Number; (c) Project Title; (d) Street/Road Name or Number /Federal Route Number; (e) Beginning and Ending Termini (milepost or street names); and (f) Describe the Work to be Completed. 4. Type Codes. Enter the appropriate federal code' number. Description 01 - New construction on 07 - Resurfacing 14 - Bridge Program - Special new alignment 08 - New Bridge Construction 21 - Transit Capital Project 02 - Relocation 09 - Bridge Replacement 22 - Transit Operational Project 03 - Reconstruction 10 - Bridge Rehabilitation 23 - Transit Planning 04 - Major Widening 11 - Minor Bridge Rehabilitation 24 - Transit Training /Admin. • 05 - Minor Widening 06 - Other Enhancements 12 - Safety/Traffic Operation/TSM 31 - Non Capital Improvement 13 - Environmentally Related 32 - Non Motor Vehicle Project 26 5. Funding Status. Enter the funding status for the entire project or phase that describes the current status. S - Project is `selected' by the appropriate selection body and funding has been secured by the lead agency. P - Project is subject to selection by an agency other than the lead and is listed for planning purposes. (Funding has not been determined.) 6. Total Length. Enter project length to the nearest hundredth (or code "00" if not applicable). 7. Utility Code(s). Enter the appropriate code letter(s) for the utilities that need to be relocated or are impacted by the construction project. C - Cable TV G - Gas O :Other P - Power S - Sewer (other than agency-owned) T - Telephone W - Water 8. Project Phase. Select the appropriate phase code of the project. PE - Preliminary Engineering, including Design (or Planning) RW - Right of Way or land acquisition CN - Construction only (or transit planning or equipment purchase) ALL - All Phases: from Preliminary Engineering through Construction (Use only in Years 4, 5, & 6) 411 • 9. Phase Start Date. Enter the month /day /year MM /DD/YY format that the selected phase of the project is actually expected to start. 10. Federal Fund Code. Enter the Federal Fund code from the table. • FTA Discretionary for Capital Expenditures BIA - Bureau of Indian Affairs 5307 - FTA Urban Areas BR - Bridge Replacement or Rehab. 5309(Bus) - Bus CDBG - Community Development 5309(FG) - Fixed Guideways Block Grant (HUD) 5309(NS) - New Starts CMAQ - Congestion Mitigation Air Quality 5310 - FTA Elderly /Disabled DEMO .. - ISTEA Demo Project (Selected) . 5311 - FTA Rural Areas Discretionary - Ferry Boat Discretionary, Public - REV - Rural Economic Vitality Program 'Lands Highways, or Scenic Byways, etc. STP(C) - STP Statewide Competitive Program DOD - Dept. of Defense STP(E) - STP Transportation Enhancements IC - Interstate Construction STP(S) - STP Safety Including Hazard and RR IM - Interstate Maintenance STP(R) - STP Rural Regionally Selected NHS - National Highway System STP(U) - STP Urban Regionally Selected 3037 - FTA Job Access /Reverse Commute STP - WSDOT use only 27 • • 11. Federal Funds. Enter the total federal cost (in thousands) of the phase regardless of when the funds will be spent. 12. State Fund Code. Enter the appropriate code for any of the listed state funds to be used on this project. LAPP - County Arterial Preservation Program PWTF - Public Works Trust Fund CHAP - City Hardship Assistance Program RAP - Rural Arterial Program TPP - Transportation Partnership Program SCP - Small City Program AIP - Urban Arterial Program SCPP - Small City Pavement Program (formerly Arterial Improvement Program) PSMP - Pedestrian Safety & Mobility Program FMSIB - Freight Mobility Strategic Investment Board PTSP - Public Transportation Systems Program WSDOT - WSDOT provided funding OTHER - Any other unlisted state fund codes 13. State Funds. Enter all funds from the State Agencies (in thousands) of the phase regardless of when the funds will be spent. 14. Local Funds. Enter all the funds from Local Agencies (in thousands) of the phase regardless of when the funds will be spent. 410 15. Total Funds. Enter the sum of columns 10, 12, and 14. (Auto- calculation in the "STIP Too" program.) 16 -19. Expenditure Schedule - (1st, 2nd, 3rd, 4th thru 6th years). Enter the estimated expenditures (in thousands) of dollars by year. (For Local Agency use.) 20. Environmental Data Type. Enter the type of environmental assessment that will be required for this project. (This is "required "for Federally funded projects, but may be filled in for state or locally funded projects.) EIS - Environmental Impact Statement EA - EnvironmentaIAssessment CE - Categorical Exclusion 21. R/W Certification. Click Y if Right of Way acquisition is or will be required. If yes, enter R/W Certification Date, if known. (This is "required" for Federally funded projects.) e 28 Wash' tate Department of Transportation • Six Yea T Transportation Improvement Pr am Agency: Y III From 2010 to • Co. No.: 39 Co. Name: Yakima Co. Hearing. Date: 7-21-2009 Adoption Date: City No.: 1485 MPO /RTPO: YVCOG - Amend Date: Resolution No.: . Project Identification Project Costs In Thousands of Dollars Federally Funded A. PIN/Federal AId No. B. Bridge No. n re F Source information Expenditure Schedule Projects Only E C. Protect Title = r Federal Funding . (Local Agency R/W c cc ' v t c 3 D. Street/Road Name or Number 2 y Phase Federa Federal State 4lh Required Z E. Beginn M or R • E MP or Roa E ~ 1° - 2 Start Fund • Cost by Fun State Local Total 1st 2nd 3rd Thru T vie Date F. Describe Work to be Done n (mMdd/my) Code Phase Code Funds Funds Funds 6th yp (M�Y� 1 2 3 • 4 5 8 7 8 9 10 11 12 13 14 • 15 16 17 18 19 20 21 • CN 1/1/2010 STP(U) 2668 FMSIB 2200 2000 6888 8868 EA 14 1 01 S 0.20 T CN 1/1/2010 DEMO 8270 • AIP 3000 11270 11270 Yes Yakima Railroad Grade Separations - Phase 2 06 Lincoln Ave. 07 G from: N 1st St to: N 1st Ave 08 0 9/1/09 Construct Grade Separations and adjacent roadway reconstructor, s including realignment of Front Street. • ' Totals 10,938 5200 2000 18138 18138 14 2 01 P CN 8/1/2010 STP(U) 650 FMSIB 2000 3768 6418 6418 EA 0.2 T CN 8/1/2010 ARRA- 8000 AIP 1500 • 9500 9500 Yes Yakima Railroad Grade Separations- Phase 3 06 - Martin Luther King, Jr. Blvd 07 G from: N. 1st Sreet to: N. 1st Ave 0 Construct Grade Separation and adjacent roadway reconstruction including 0 8 - 9/1/2009 Front Street . Totals 8,650 3500 3768 15918 15918 00 3 12 S N/A ALLI 1/1/2010 5307 1 1601 I 1601 32021 3202 I CE Transit Operating Expenditures 22 No Various fixed rates and locations 23 from: N/A to: N/A 24 - Annual operating assistance from the FTA in support of our transit system; • 31 fixed conte, paratransit Dial -A -Ride and vanpool program Totals 1,601 1601 3202 3202 . 00 4 03 S N/A C CN 1/1/2010 I STP(E) 1 255 2551 255 CE YVT Trolley Barn/Powerhouse Rehabilitation • G Yes • S 3rd Ave O ' from: to: S 06/01/07 Minor car bam and powerhouse restoration Including property purchase T W Totals . 255 255 255 ' Report Date: June 30, 2009 Page 1 v. 5.7 - Supersedes previous editions • • • Washington State Department of Transportation Six Year Transportation Improvement Program Agency: Yakima From 2010 to 2015 Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -21 -2009 Adoption Date: City No.: 1485 MPO /RTPO: YVCOG • Amend Date: Resolution No.: ProJect Identification ProJect Costs In Thousands of Dollars Federally Funded 1 1 A. PIN /Federal Aid No. B. Bridge No. d ^ -c 2 m -Fund Source Informati Expenditure Schedule , Projects Only H m` E V a . S y (Local Agency) g u) O E C. Project Title > m o V t Federal Funding R/yv U a Z D . Street/Road Name or Number • a� y P. Cl Phase Federal Federal State 4th Required E. Beginning MP or Road - Ending MP or Road E 1 5 o Start Fund Cost by Fund . State Local Total 1st 2nd 3rd Thru Envir. Date • • F. Describe Work to be Done a (mm/dd/ Code Phase Code ', Funds Funds Funds 6th Type (MM/y)) 1 2 3 4 5 , 6 • 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 I CN 1/1/2010 STP(E) 1 525 525 525 CE 00 5 32 S 10 0 William O. Douglas Trail 08 P No i 6th Ave Pathway & Bridge Decking 0fi S , from: to: W Build pathway and Install pathway decking on Neches River bridge with • • T partner William O. Douglas Trail Fundation Totals 525 525 525 RW 1/1/2010 STP(E) 150 150 1 150 00 6 32 S N/A O CN 1/1/2010 STP(E) 285 285 285 CE Yes William O. Douglas Heritage Trails 13 Bridge Restoration & Trailhead 10 P from: to: S T 8/O1I09 Trallhead restoration, right of way acquisition partner with the William 0. W Douglas Foundation, Including restoration of bridge , cleaning, rust removal and painting Totals • 435 435 435 00 7 22 S N/A ALLI 1/1/2010 1 1 '50 50I 50 CE Street Asset Amenities (Transit) 31 No Route Maintenance, Repair and Improvements from: to: On going Improvements to bus benches, shelters and slgnage infrastructure • • Totals 50 50 50 00 8 22 S N/A ALL 1/1/2010 CMAQ 1 33 7 40I 40 Expanded Transit Service to Terrace Heights No New University & Retail Links from: to: Extension of fixed route bus service only Into the Terrace Heights area of Yakima County Totals 33 7 40 40 • Report Date: June 30, 2009 Page 2 v. 5.7 - Supersedes previous editions • 0 . e . e • T en Wash tate Department of Transportation Six Year Transportation Improvement P am 4110 • ill From 2010 to 5 Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -21 -2009 Adoption Date: • City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.: Project Identification Project Costs in Thousands of Dollars Federally Funded A PIN /Federal Aid No. B. Bridge No. c E 3 0 Fund Source Information Expenditure Schedule Projects Only • c y °' d i € o N (Local Agency) o m o C. Project Title > m 7 3 o r Federal Funding RNV c 0 a 2 D. Street /Road Name or Number a • rn « a ts Phase Federal Federal State 4th Required E. Beginning MP or Road - Ending MP or Road E I 5 °' Start Fund Cost by Fund State Local Total Thru Envir. Date g g g o y Funds Funds Funds 1st 2nd 3rd Type F. Describe Work to be Done a _ (mm/dd/yyyy) Code Phase Code 6th ( M » , 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 14 9 04 P n P RW 1/1/2010 200 • 200 200 Nob HIII Blvd C CN 6/1/2010 STP(U) 1000 TPP 1500 200 2700 2700 EA Yes Nob Hill Blvd G • from: 49th Ave to: 64th Ave O Widen, curb, gutter, sidewalk, lighting, drainage S 6/01/10 T' W Totals 1,000 1500 400 2900 2900 14 _ 10 12 S NIA P RW 1 4/1/2010 AIP 84 36 1201 40 80 CE S 16th Ave & W Washington Ave Signal & Intersection. 05 T Yes • S 16th Ave 03 from: S 16th Ave to: W Washington Ave 4/1/2010 Included in Union Gap's Valley Mall Blvd. project • ' Totals 84 , 36 120 40 80 16 11 05 S 20 G CN 4/1/2010 600 6001 600 66th Ave. & Summitview Intersection 12 , P _ 1 CE Yes N. 66th Avenue & Summitview from: N. 66th Ave. to: Summitview Ave. S Widen for lett turn lanes intersection improvements, curb, gutter, handicap T 4/1 /2010 P .9 � P W ramps lighting P 9 n9 C Totals 600 600 600 00 12 03 S 50 S CN 1/1/2010 CMAQ 540 214 7541 754 CE Coolidge Road Widening and Paving. 05 W Yes 06 P from: 80th AVE. to: 88TH AVE. T • Widen roadway and pave with curb and gutter. 9/1/2009 Totals 540 214 754 754 • Report Date: June 30, 2009 Page 3 v. 5.7 - Supersedes previous editions • • Washington State Department'of Transportation Six Year Transportation Improvement Program Agency: Yakima From 2010 to 2015 Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -21 -2009 Adoption Date: City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.: Project Costs In Thousands of Dollars Project Identification 1 Federally Funded A. PIN/Federal Aid No. B. Bridge No. d v d Fund Source Information Expenditure Schedule Projects Only 2 i E E C. Project Title , d y d 2 (Local Agency) o E 1 8 t Federal Fundin E3 Z D. Street/Road Name or Number a u1 3 % Phase Federal Federal State 4th Required za E. Beginning MP or Road E - Ending MP or Road 1 - 5 Start Fund Cost by Fund State Local Total 1st 2nd 3rd Thru Envir. Date F. Describe Work to be Done ez (mm/dd/yyyy) Code Phase Code Funds Funds Funds 6th Type (M 1 1 2 3 - 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 • ■ 00 13 21 S N/A ALL 1/15/2010 5310 96 84 180 180 CE Acquisition of new Dial-A =Ride paratransit vehicles No from: to: Purchase new vehicles to replace older, less reliable units Totals 96 84 180 180 14 14 03 P N/A PE 1/1/2010 STP(U) 173 27 200 200 E. Lincoln & 10th Street Roundabout CN 6 /1/2011 STP(U) 433 67 • 500 500 05 CN 6/1/2011 STP(U) 1125 175 1300 1300 Yes 06 from: E. Lincoln to: E. MLK Jr, Blvd. 6/1/2011 • Roundabout construction at Intersection curb, gutter, sidewalk, & street lighting • Totals 1,731 269 2000 200 1800 ALL 1/1/2010 STP(U) 1 865 1 1 135 1000 I -1000 12 15 03 P N/A o I CE • S.R.12 & 16th Avenue Interchange 06 No Interchange • from: 16th Avenue • to: S.R. 12 ' Upgrade Interchange by constructing a Roundabout 1 Totals 865 . 135 1000 1000 . 11 16 01 P N/A 0 ALLI 1/1/2011 STP(U) 865 135 10001 1 -82 & Lincoln Avenue Interchange P EA Yes 1 -82 Interchange G from: E. "G" Street' to: 1 -82 • 6/2011 Reconstruct / extend o8 -ramp from existing 1-82 off -ramp for Lincoln Avenue . to E. '0" Street. ' Totals • 865 135 1000 Report Date: June 30, 2009 Page 4 v. 5.7 - Supersedes previous editions • • r . 411 e e .. • 4111111■ Six Year Transportation Improvement Pr am 1111111 Washi fate Department of Transportation - Agge en ncy: Ya From 2010 to • Co. No.: 39 Co. Name: Yakima Co. H earing Date: 7 -21 -2009 Adoption Date: • City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.: Project Identification Project Costs In Thousands of Dollars Federally Funded A. PIN/Federal Ald No. B. Bridge No. c .m d Fund Source Information Expenditure Schedule Projects Only • (Local Agency) a .o E C. Project Title a s m d 3 a Federal Funding R/W c U o D. Street/Road Name or Number - a�' y _ t Phase Federal Federal State 4th Envir. Required o State Local Total Date E. B eg i nning MP or Road - Ending MP or Road E I- o • Start Fund Cost by Fund Funds Funds Funds 1st 2nd 3rd Thru Type (Mw F. Describe Work to be Done , a (mm/dd/yyyy) Code Phase Code 6th 1 2 3 4 5 6 7 8 1, 9 ' 10 11 . 12 13 14 . ;;15 16 17 18 19 20 21 N/A P ALL 1 14 17 12 P 1/2010 STP(U) 865 135 F 1000 1000 CE E. Yakima Avenue & Fair Avenue Signalization W , No T from: E. Yakima Avenue to: Fair Avenue S O Construct Traffic Signal Totals' 865 135 1000 1000 00 18 22 S ALL I 1/2/2010 I 5316 I 131 131 262 I 131 131 I CE Fixed route Bus Services to Moxee along SR 24 Corridor No SR 24 Hwy Corridor /Park & Ride Lots • from: to: JARC funded demonstration project to determine ridership potential to and from the Moxee area Including stops at two Park 8 Ride lots along SR 24. . Totals 131 131 262 131 131 RW 1/1/2011 STP(U) 173 27 200 1 200 CE 14 19 31 P • N/A c CN 4/1/2011 STP(U) 865 135 1000 ' 1000 Yes E Nob Hill Blvd & Fair Ave 03 • C i E Nob Hill Blvd 04 from: E Nob Hill Blvd to: Fair Ave . W 4/1/2001 Intersection widening 8 new signal, curb, gutter and sidewalk, street lighting, stormwater Totals 1,038 • 162. 1200 200 1000 PE 4/1/2010 13 13 13 16 20 12 P N/A T CN 6/1/2010 214 214 214 CE S 3rd Ave & W Washington Ave Signal No • S 3rd Ave . from: S 3rd Ave to: W Washington Ave Signal Upgrades • Totals • 227 227 227 Report Date: June 30, 2009 - Page 5 V. 5.7 - Supersedes previous editions • • • • • • i Washington State Department of Transportation Six Year Transportation Improvement Program • Agency: Yakima ' From 2010 to 2015 Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -21 -2009 Adoption Date: • City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.: Project Identification Protect Costs In Thousands of Dollars Federally Funded A. PIN/Federal Aid No. B. Bridge No. .8 y Fund Source Information Expenditure Schedule Projects Only (Local Agency) . ii g E C . Project Title al ` 8 r Federal Funding R/w v ti 2 D. Street /Road Name or Number Q k 1 � o Phase Federal Federal State 4th Required u- Z E o Fund State Local Total Required Date E. Beginning MP or Road - Ending MP or Road l - Q Start Fund Cost a Funds Funds Funds 1st 2nd 3rd Thru Type (M » F. Describe Work to be Done n (mm/dd/yyyy/ Code Phase Code 6th 1 2 3 4 5 8 7 8 9 10 11 12 13 14 ' 15 16 17 18 19 20 21 14 21 4579 12 P NIA P PE 8/1 /2010 STP(U) 252 38 290 290 EA S 1st St. - E. Washington Ave. Intersection Improvement W Yes S IsI St. S • from: S 1st St. to: E Washington Ave. 0 01/01/11 • Realign intersection, upgrade traffic signal Totals 252 38 290 290 4587 ALL 4/1/2011 STP 2268 307 2575 525 2050 17 22 03 P 1.00 P I I EA S 48th Ave. Reconstruction T Yes S 48th Avenue W • from: Summitvlew Ave. to: Nob Hill Blvd. • 4/1/2014 Widen, curb, gutter, sidewalk, lighting, drainage . Totals 2,268 307 2575 525 2050 14 23 03 P N/A 0 12 P CN 6/1/2011 STP(U) 383 61 444 444 CE South 72nd Ave & Mead Ave Intersection Yes South 72nd Ave S from: South 72nd Ave to: Mead Ave T 8/10/2010 ' New intersection, signals, curb, gutter and sidewalk , Totals 434: 69 503 503 16 24 4562 12 P N/A P ALL 4/4/2011 STP(U) 378 WSDOT 378 7561 7561 CE • Tieton Dr - S 5th Ave. Intersection Project W Yes • Tieton Drive T from: 5th Ave. Intersection to: S 4/1/2014 Replace traffic signal with roundabout Totals 378 • 378 756 756 , • Page 6 v. 5.7 - Supersedes previous editions Report Date: June 30, 2009 1 I 0 • e 4111_ ... . • Washi State Department of Transportation ' ' Year ear Transportation Improvement Pr ram 4110 -en Agency:. From 2010 to Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -21 -2009 Adoption Date: • City No.: 1485 MPO /RTPO: YVCOG . Amend Date: Resolution No.: , Project Identification • • Project Costs in Thousands of Dollars Federally Funded • A. PIN /Federal Aid No. B. Bridge No. d .c m 0 (Local Agency) Fund Source Information Expenditure Schedule Projects Only To E A '' E C. Project Title - " - Federal Funding R/W U a Z D. Street /Road Name or Number a a Phase Federal Federal State 4th Required • En*. Date u. E. Beginning MP or Road • Ending MP or Road E e ' 1 - = Start Fund Cost by Fund State Local Total 1st 2nd 3rd Thru F. Describe Work to be Done a (mm/dd/yyyy) Code Phase Code • Funds Funds Funds 6th Type (MM/Yt� 1 2 3 . 4 5 6 7 8 9 .10 11 12 13 14 15 16 17 18 19 20 21 16 25 01 P 11 0 PE 1/1/2011 STP(U) 2180 340 2520 2520 RW 1/1/2013 STP(U) . 2180 340 • 2520 2520 CE E. '' Extension 08 S CN 6/1/2014 STP(U) 1199 1871' 3070 3070 Yes E. "H° St. S from: 1st St. to: Yakima River W 1/1/2014 Construct road including water, sewer, curb, gutter and sidewalk for future • • development. • - . Totals 5,559 2551 8110 2520 5590 • 17 26 01 P 1.3 O PE 1/1/2012 STP(C) 700 108 808 808 RW 1/1/2013 STP(U) 5500 850 6350 6350 CE N. 10th St. Extension 06 S CN 6/1/2013 STP(U) 7900 • 972 • 8872 8872 Yes N. 10th St. from: R St. to: 10th Street • Lincoln Ave. T W Construct road Including water, sewer, curb, gutter, sidewalk for future • . 1/1/2013 development. - - - - Totals 14,100 1930 16030 808 15222 00 27 23 . S N/A PE 1 1/1/2010 1 I. OTHER 50 501 50 • 1 West Side Transit Center Acquire Property to Expand Operations from: to: • ' Locate and acquire property for the placement of a West Side Transit Center Operation f Totals 50 50. 50 17 28 03 S PE 1/1/2010 OTHER 75 75 75 .30 P CN 6/1/2010 OTHER 1000 . .1000 1000 CE Yakima Downtown Future Initiatives, Phase 4 05 T No 06 from: Between 1st Street to: and 8th Street - On streets to be selected but contiguous to DFI's 1, 2 & 3; Historic lighting sidewalk mods more. ' Totals 1000 75 1075 1075 • Report Date: June 30, 2009 Page 7 v.53 - Supersedes previous editions • Washington State Department of Transportation Six Year Transportation Imp Program i Agency: Yakima From 2010 to 2015 Co. No.: 39 Co. Name: Yakima Co. . Hearing Date: 7 -21 -2009 Adoption Date: City No.: 1485 • MPO /RTPO: YVCOG Amend:Date: • Resolution No.: Project Identification Project Costa In Thoueands of Dollars Federally Funded • A. PIN /Federal AId No. B. Bridge No. _ y Fund Source Information ' • Expenditure Schedule Protects Only 0 ; 'E S C. Pro act Title " In c (Local Agency) c U �� o = 1 I 3 a Federal Funding RAN a Z D. Street /Road Name or Number c o- r 3 g Phase F e d era l F e d eral State 4th Required • LL E. Beginning MP or Road - Ending MP or Road E 1 = c Start Fund Cost by Fund State Loca Total 1st 2nd 3rd Thru Envfr. Date , F. Describe Work to be Done • a (mm/dd/yyyy) Code Phase Code Funds Funds Funds 6th Type (M � 1 2 • 3 4 5 6 7 8 9 . 10 T 11 12 13 14 15 16 1 7 18 19 20 21 17 29 06 P 60 P CN 4/1/2010 OTHER 6000 6000 6000 . CE . Yakima Downtown Future Initiatives, Phase 5 12 W No S • from: 1st Street to: 9th Street T Install Historic Lighting, Sidewalk Modification & Other Improvements. O Exact improvement area(s) to be determined. Totals 6000 6000 6000 00 30 01 P N/A PE 1/1/2010 STIP (S) 60 60 120 120 CN 4/1/2011 STP(S) 180 AIP 240 420 420 CE Annual Signal Upgrades CN 4/1/2011 STIP (S) 360 360 360 No Local Selection • . from: N/A to: N/A . Upgrade signals • ' Totals 600 240 60 900 120 780 • . 00 31 07 P N/A w CN 6/1/2010 1 STP(U) 228 1 . 32 2601 260 EA Various Overlay Projects /Selected on Local Priority S No N/A from: N/A to: N/A ' • Totals 228 32. 260 260 19 32 03 P N/A P PE 1/1/2011 STP(U) 100 14 • 114 114 CN 3/1/2012 STP(U) 700 95 795 795 CE Longfiber Rd & Washington Ave • - 05 S Yes Intersection ,, from: to: 0 3/1/2012 New intersection construction and reconstruction, 3-lane and 5 -lane w/turn, curb, gutter, sidewalks. Totals 800 109 909 114 795 • • Report Date: June 30, 2009 Page 8 v. 5.7 a Supersedes previous editions • • • • e . • •. • . .. e . ..,... . •. . . .. • • . . . . • , • • . • Fri Washi State Department of Transportation Six Year Transportation Improvement Pr ram Agency: From 2010 to Co. No.: 39 . Co. Name: Yakima Co. Hearing Date: 7 -21 -2009 Adoption Date: City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.: Project Identification Project Costs in Thousands of Dollars Federally Funded . e No. e y Expenditure Schedule Projects Only m • A. P / Federal Ald No. .B. Bridge 2 �, Fund ation (Local Agency) e w ;.= o C. Project Title a a m j c v i . N C Federal Funding Source Inform R/VV g a p- 2 D. Street /Road Name or Number ag 6 A r � Phase Federal Federal State 4th Required I ' - E. Beginning MP or Road - Ending MP or Road E 1- m °' Start Fund • Cost by Fund State Local Total 1st 2nd 3rd Thru Envir. Date • F. Describe Work to be Done a. (mm/dd/yyyy) • Code Phase Code • Funds Funds Funds 6th Type (MM/yy) 1 2 3 4 . 5 . 6 — 7 8 9 10 11 12 13 .14 15 16 17 18 19 I 20 21 14 33 04. P .1 CN 4/1/2011 STP(U)• - 240 42 282 282 CE E Nob Hill Blvd & S 18th St 01 S Yes E Nob Hill Blvd - from: S 18th St to: E Nob Hill Blvd T 01/01/07 Widen south leg for double LT from west bound Nob Hill; (Tie to W SDOT Project) possible curb, gutter and sidewalk Totals 240 42 282 282 17 34 05 S .15 C . PE 1/1/2010 STP(E) 22 • 7 29 29 Zier Rd-S75thAvetoS72ndAve S CN 6/1/2011 STP(E) 75 20 95 95 CE Yes • Zier Rd 06 T from: S 75th Ave to: S 72nd Ave P Minor widening, curb, gutter and sidewalk _ 6/1/2011 Totals .. 97 27 124 124 • 00 35 07 P , N/A S PE 1/1/2011 50 50 50 Gravel Road B.S.T. CN 6!1/2011 240 240 I 240 CE No • Various Areas • irom; City WIde to: • ' Totals . 290 290 280 CN 10/1/2013 STP(S) • 8041 • I 74 578 578 16 36 • 12 P N/A T ` CE Powerhouse Rd & Englewood Ave 0 Yes 1 Powerhouse Rd . • . from: Powerhouse Rd to: Englewood Ave • S Intersection, realignment, curb, gutter, sidewalk, Safety Flashing Signal, C 10/1/2013 possible roundabout W . • Totals 504 74 578 578 • Report Date: June 30, 2009 Page 9 v. 5.7 - Supersedes previous editions • • • • • • • Washington State Department of Transportation Six Year Transportation Improvement Program -en Agency: Yakima . - From 2010 to 2015 Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -21 -2009 Adoption Date: City No.: 1485 MPO /RTPO: WCOG Amend Date: Resolution No.: Project Identification Project Costs in Thousands of Dollars Federally Funded A. PIN/Federal Aid No. B. Bridge No. c r m Fund Source Information Expenditure Schedule Projects Only .' a� g E v - (Local Agency) - O m $ E C. Protect Title d e .c Federal Funding R/W U t Z D. Street /Road Name or Number a .- rn Phase Federal Federal State 4th Emir. Required o St Lo Total Date LL E. Beginning MP or Road - Ending MP or R oa d E 1 g °' Start Fund Cost by Fund Funds Funds Funds 1st 2nd 3rd Thru Type (MM/Y17 F. Describe Work to be Done f ( mm/dd/yyyy) Code Phase Code 6th 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 PE 1/1/2013 STP(S) 25 4 29 29 14 37 12 P WA P RW 6/1/2013 STP(S) 25 • 4 29 29 CE S 48th Ave & Summitview Ave Signalization T CN 8/1/2014 STP(S) 554 81 635 635 Yes . S 48th Ave • from: S 48th Ave to: Summitview Ave 8/1/2013 Signalization Totals 604 89 693 , 693 14 38 01 P .5 W PE 1/1/2012 STP(E) 424 67 491 491 RW 1/1/2013 STP(E) 1047 163 1210 1210 CE W Lincoln Ave & 'B' St Realignment 12 T CN 1/1/2014 STP(E) 1801 281 2082 2082 Yes W Lincoln Ave S from: W 5th Ave to: Custer St . 1/1/2014 Realignment of W Uncoln Ave, sidewalks, curb, gutter, lights G C Totals 3,272 ii 511 3783 491 3292 PE 1/1/2010 PSMP 13 2 15 15 16 39 • 12 P N/A W CN 1/1/2010 PSMP 239 48 2871 287 CE • School Safety Projects No Various Locations - Citywide from: to: , Crossing flashers, sidewalks, signing, other features • • 'Totals 252 50 302 302 14 40 03 P 85 C PE 1/1/2012 STP(C) 546 84 ' 630 630 RW 1/1/2013 STP(C) ' 1090 170. 1260 1260 EA E Nob Hill Blvd. Reconstruction 04 G CN 1/1/2014 STP(C) 6539 • 1013 7552 7552 Yes E Nob Hill Blvd. 06 from: S 6th Street to: S 18th Street P S 1/1/2014 Major roadway widening and reconstruction to 5 lanes with intersection improvements, curb, gutter, sidewalks, replacement or relocation of meters T an hydrants W Totals 8,175 1267 9442 830 8812 • Report Date: June 30, 2009 Page 10 v. 5.7 - Supersedes previous editions i • • • • • 0 ' . 0 • • • Washi tate Department of Transportation S Year Transportation Improvement Pr am • -en ncy: Ya III Agency: . From 2010 to Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -21 -2009 Adoption Date: City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.: - , Project Identification Project Costs In Thousands of Dollars - Federally Funded A. PIN /Federal Aid No. B . Bridge No. 1: L ` m Fund Source Information Expenditure Schedule Projects Only c A. a� g E„ a 48 N ( Local Agency) o m $ E d C . Project Title a m 5 cg a Federal Funding /W R c U ti 2 D. Street /Road Name or Number t in r. Phase , Federal Federal State 4th Required o State Local Total Envir. Date 2 E. Beginning MP or Road - Ending MP or Road E r 5 . Start Fund Cost by Fun Funds Funds Funds 1st 2nd 3rd Thru Type (M , h .ff F. Describe Work to be Done • a (mm C ode Phase Code 6th 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 PE 1/1/2011 STP(C) 91 14. 105 . 105 CE 17 41 01 P N/A " RW 1/1/2012 STP(C) 91 14 . 105 105 S 72nd Avenue & W Washington Avenue . 12 T CN 1/1/2013 STP(C) 544 86 630 630 Yes S 72nd Ave 06 P from: S 72nd Ave to: W Washington Ave C 1/1/2013 • Intersection improvement, possible roundabout Totals 726 114 840 106 105 630 • PE 1/1/2011 STP(E) 23 6 28 28 17 42 04 P . T CN 7/1/2012 STP(E) 1088 184 1280 1260 • S 66th Avenue 03 S , Yes S 66th Ave from: Scenic Drive to: Summltview P O 7/1/2012 Widen roadway, curb, gutter, sidewalk and utilities - ' Totals 1,119 169 1288 28 1260 PE 1/1/2012 STP(U) 126 17 143 . 143 CE 14 43 12 P WA W RW 1/1/2012 STP 63 8 71 71 40th Avenue and SummiNiew Signal Upgrade T C N 6/6/2012 STP(U) 544 86 630 630 Yes 40th Avenue P from: 40th Avenue to: Summitvlew 0 6/1/2012 Signal upgrade, radius Improvements, turn lane extension Totals 733 111 844 844 ■ • PE 1/1/2012 STP 95 13 108 108 CE • 14 44 12 P N/A W RW 1/1/2012 STP 63 8 71 71 40th Avenue and Englewood • T CN 1/1/2013 STP 145 20 165 165 Yes 40th Avenue P S from: 40th Avenue to: Englewood C 1/1/2013 Replace traffic signal poles, upgrade controller Totals 303 41 344 179 165 • • v. 5.7 - Supersedes previous editions Report Date: June 30, 2009 • Page 11 • • • • Washington State Department of Transportation Six Year Tra Improvement Program • Agency: Yakima From 2010 to 2015 • t • Co. No.: ' 3g Co. Name: Yakima Co. • Hearing Date: 7 -21 -2009 Adoption Date: • City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.: • Project Identification Project Costs in Thousands of Dollars Federally Funded Y , A. PIN/Federal AId No. B. Bridge No. c v m Fund Source Information Expenditure Schedule Projects Only (Local Agency) g if; m ' u- E C. Project Title • o 3 3 $ r Federal Funding R/W U a Z D. Street/Road Name or Number a1- co t Phase Federal Federal State 4th Required U. E. Beginning MP or Road - Ending MP or Road E d Sta rt Fund Cos b Fund State Local Total Thru Envir. Date g g g y Funds Funds Funds 1st 2nd 3rd Type (MM/yy) F. Describe Work to be Done a (mMdcliWyy) Code Phase . Code 6th 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 PE 1/1/2012 STP 126 18 144 144 00 45 12 P N/A W T RW 6/1/2012 STP 63 8 71 71 CE 16th Avenue and Fruitvale Blvd . CN 1/1/2013 STP 315 43 358 358 Yes 16th Avenue S from: 16th Avenue to: Fruitvale Blvd P O 1/1/2013 Replace traffic signal poles, radius improvements, ADA ramps . Totals 504 69 573 215. 358 14 46 12 P WA W PE 1/1/2010 STP 32 5 37 37 1st Street and 1 Street T CN 1/1/2011 STP 126 17 143 I 143 CE No 1 st Street S from: 1st Street to: I Street P O Replace and upgrade traffic signal equipment Totals 158 22 180 37 143 01 P .25 0 PE 6/1/2013 STP(U) 820 189 1009 1009 . 16 47 Washington Ave. Railroad Grade Separation 3 RW 1/1/2014 STP(U) 3160.. 830 3780 3780 CE Yes Washington Ave. T from: Longflbre Road to: W 1/1/2016 Railroad grade overpass including all utilities Totals • 3,970 819 4789 4789 16 .48. 01 P 1.3 C PE 1/1/2013 STP(U) 272 ' 43 315 315 Frontage Road & "H' St. Loop G RW 6/1/2014 STP(U) 349 55 404 404 C E Yes N 8th St. from: "H" St. to: 1 -82 P • Construct new roadway, water, sewer, cutb, gutter, sidewalk and lighting for S - 1/1/2015 future development and Terrace Heights connection. T W Totals 621 98 719 719 . Report Date: June 30, 2009 Page 12 v. 5.7 - Supersedes previous editions • • • e . O . . .. • ■ WI Washi tate Department of Transportation Six Year Transportation Improvement P am Agency: Y From 2010 to 5 Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -21 -2009 Adoption Date: City No.: 1485 MPO /RTPO: YVCOG • Amend. Date: Resolution No.: • Project Identification • Project Costs In Thousands of Dollars ' Federally Funded . A. PIN/Federal Ald No. B. Bridge No. t: Fund Source Information Expenditure Schedule Projects Only :g'$ 8 y C (Local Agency) o C. Project Title Q1 T t Federal Funding R/yy c U a Z D. Street/Road Name or Number a a Phase Federal Federal State 4th Required u- E. Beginning MP or Road - Ending MP or Road E 1 i i Start . Fund Cost by Fund State Local • Total 1st 2nd 3rd Thru Emir. Date F. Describe Work to be Done p, (mMdd/yyyy) Code Phase . Code Funds Funds Funds 6th Type (M >) 1 .2 • 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 PE 1/1/2013 STP(U) 120 17 1 137 137 14 49 04 P 3. c CE 16th Ave. Corridor G 16th Ave. O • from: SR -12 to: npington Ave.Nalley Mall P • • Widen roadway, curb, gutter, sidewalk, lighting. S T W Totals 120 17 137 137 14 50 • 04 P 3.2 C PE 1 1/1/2012 1 STP(U) 1 120 17 1371 137 CE 40th Ave. Corridor C 40th Ave. G • from: SR -12 to: Washington Ave. P S Widen roadway, curb, gutter, sidewalks, lighting. W • T Totals 120 17 137 137 14 51 ' 03 P 2.7 C PE 1/1/2011 1 STP(U) 120 17 1371 137 1 CE Nob Hill Corridor • 04 G Nob Hill 0 from: 1 -62 to: S. 16th Ave. P Widen roadway, sidewalk, curb, gutter, lighting S T W Totals 120 17 137 137 14 52 04 P 2.0 C PE 1 1/1/2013 1 STP(U) 1 1201 17 1371 137 CE S. 1st St/Main St. Corridor G ■ S. 1st St./Main St. 0 . from: Nob Hill Blvd. to: Barker Mill Bridge P S Joint project with Union Gap to widen roadway, curb, gutter, sidewalk, lighting. T W Totals 120 17 137 137 • • • Report Date: June 30, 2009 Page 13 v. 5.7 - Supersedes previous editions • • • • • Wi Washington State Department of Transportation Six Year Transportation Improvement Program Agency: Yakima From 2010 to 2015 Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -21 -2009 Adoption Date: City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.: ' Project Identification Protect Costs in Thousands of Dollars Federally Funded A. PIN /Federal Ald No. B. Bridge No. d v 5 Fund Source Information EXpendlturt�Schedule Projects Only b co 8 E C . Protect Title > d m s r Federal Funding Local Agency) R/W U ti 2 D. Street/Road Name or Number a N g Phase Federal Federal State: 4th Required E. Beginning MP or Road - Ending M P or Road E f d Start Fund Cost b Fund State Local Total Envir. Date Thru g g g o y Funds Funds Funds 1st 2nd 3rd Type (MMIY') F. Describe Work to be Done a (mm/dd/yyyy) Code Phase Code 6th 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 00 53 32 P N/A CN 1/1/2010 100 100 100 EA CN 1/1/2010 900 900 900 Storm Drains/Vegetation No Local Selection from: City Wide to: City. Wide Totals 1000 1000 1000 17 54 03 P 76 yV PE 1/1/2011 STP(C) 109 27 136 136 CN 1/1/2012 STP(C) 945 TPP 945 106 1996 1996 CE Reconstruction Rudkin Rd 06 T No fludkin Rd P from: E Viola Ave to: Rainier Place S Reconstruct, excavate ballast, top course, curb, gutter, sidewalk Partner with City of Union Gap, additional sewer force main ' Totals 1,054 945 133 2132 136 1996 • 16 55 03 P .76 C PE 9/1/2010 STP(S) 122 TPP 23 7 152 152 CN 4/1/2011 STP 1730 TPP 206 70 20061 2006 CE . . E Mead Ave Reconstruction 06 G No E Mead Ave C • from: Rudkin Rd to: Fair Ave P T Partner with City of Union Gap, reconstruct, excavate ballast, top course, curb, gutter, storm, acp - T Totals 1,852 229 77 2158 152 2006 17 56 04 P 1.3 0 PE 1/1/2011 AIP 131 20 151 1 151 S Both Ave - Tieton Dr to Zier Rd C CN 4 /1/2012 AIP 382 59 441 441 EA P CN 4/1/2012 AIP 1667 260 1927 7 1927 Yes S 80th Ave T from: Tieton Dr to: Zier Rd W 4/1/2012 Major widening, curb, gutter, sidewalk S - Totals 2180 339 2519 151 2368 Report Date: June 30, 2009 Page 14 v. 5.7 - Supersedes previous editions • 0 41111 • Aft Six Year Transportation Improvement P am • Washi tale Department of Transportation - Agge en ncy: Ya ID From 2010 to 5 Co. No.: 39 Co. Name: Yakima Co. • Hearing Date: 7 -21 -2009 Adoption Date: • City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.: Project Identification Prolect Costs In Thousands of Dollars . Federally Funded A. PIN/Federal Aid No. B B No. t d - Fund Source Information Expenditure Schedule Projects Only �, g dr r t IS y (Local Agency) o fa 'E C. Project Title v J c.) .2 Federal Funding R/W c U a 2 D. Street/Road Name or Number at a a a Phase Federal Federal State 4th Required tL E o p State Local Total Emir. Date E. Beginning MP or Road - Ending MP or Road i2 • g s Start Fund Cost by Fund Funds Funds Funds 1st 2nd 3rd Thru Type (MM/YY) F. Describe Work to be Done a (mm/ddyyyy) Code Phase Code 6th 1 2 3 4 5 6 7 8. 9 10 11 12 • 13 14 • 15 . 16 17 18 19 20 21 PE 1/1/2013 STP(C) 272 43 315 315 17 57 05 P 1 . 0 W RW 6/1/2013 STP(C) 349 55 404 404 EA Englewood Ave - N 40th Ave to N 56th Ave 06 S CN 1/1/2014 STP(C) 2352. 340 2692 2692 Yes Englewood Ave P from: N 40th Ave to: N 56th Ave - o - . 1/1/2013 Widen roadway, curb, gutter, sidewalk C Totals 2,973 438 3411 3411 ' PE 1/1/2012 STP(U) 219 . 34 253 253 17 58 05 P 2 0 RW 6/1/2012 STP(U) 327 51 378 378 EA Englewood Ave - N 24th Ave to N 16th Ave 06 S CN 6/1/2013 STP(U) 2980 244 3224 3224 Yes Englewood Ave from: N 16th Ave to: N 24th Ave 6/1/2013 Widen, curb, gutter and sidewalk, water and sewer lines • Totals 3,526 329 3855 631 3224 PE 1/1/2012 STP(S) 55 8 63 63 14 59 • 12 P 2.5 P RW 6/1/2012 STP(S) 107 19 126 126 ' CE • W Nob Hill Blvd Sidewalks T CN 3/1/2013 STP(S) 321 57 378 378 Yes W Nob Hill Blvd 'from: S 16th Ave to: S. 6th St. S 3/1/2013 Install missing sidewalks on southside of Nob Hill. Totals 483 84 567 189 378 PE 1/1/2012 STP(S) 57 7 64 64 00 60 06 P 1.0 P RW 6/1/2012 STP(S) 189 25 214 214 CE Beech St Pedestrian Connection 32 T CN 1/1/2013 STP(S) 504 68 572 . 572 Yes Beech St • ' from: Fair Ave to: Chalmers/Riverside 1/1/2013 • Construct pedestrian pathway under SR82 to Greenway Totals 750 100 850 278 572 • • v. 5.7 - Supersedes previous editions Report Date: June 30, 2009 Page 15 . • • Washington State Department of Transportation Six Year Trans Improvement Program , Agency: Yakima From 2010 to 2015 Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -21 -2009 Adoption Date: City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.: • Project Identification • Project Costs In Thousands of Dollars Federally Funded A. PIN/Federal Aid No. B. Bridge No. e r d m Fund Source Information Expenditure Schedule Projects Only 1 _o E C. Project Title > a m ° 2 ' Federal Funding (Local Agency) RIN U ii Z D. Street /Road Name or Number a - rn ;o = • t Ph F Federal State 4th Required LE o = �, State Local Total Envir. Date E. Beginning MP or Road - Ending MP or Road E 1 2 ' • St F Cost by Fund Funds Funds Funds. 1st 2nd 3rd Thru a Type (MME y) F. Describe Work to be Done (mm/dd /yyyy) Code Phase Code 6th 1 2 ` 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 • 16 61 12 P 2.0 P PE 1/1/2013 STP(S) 43 7 50 50 ' RW 6/1/2013 STP(S) 86 15 101 101 CE W Lincoln Ave Sidewalks S CN ' 1/1/2014 STP(S) 572 88 660 660 Yes W Lincoln Ave from: N 56th Ave to: N 29th Ave W 1/1/2014 Sidewalks, meters and fire hydrants replacement or relocation Totals 701 110 811 811 14 62 01 p. .25 yy PE 6/1/2012 STP(U) 820 189 1009 1009 • RW 1/1/2014 STP(U) 3150 630 3780 3780 CE Mead Ave. Railroad Grade Separation T CN 1/1/2013 STP(U) 6552 1008 7560 7560 Yes Mead Ave. S from: Presson Place • to: Maryland P • , Construct railroad overpass including all utilities • 1/1/2014 . Totals 10,522 1827 12349 1009 11340 ' PE 6/1/2011 STP(U) 252 38 290 290 16 63 01 P 4.0 0 RW 1/1/2012 STP(U) 756 88 844 844 CE Citywide Pathway Connections P CN 1/1/2013 STP(U) • 1890 315 2205 • 2205 Yes Yakima S from: to: T W 1/1/2013 Cowiche Canyon Trail, Powerhouse Rd pathway, east side canal paths. . WOD Trail, Greenway including Neches Rail Spur, signage and. amenities Totals 2,898 441 3339 290 844 2205 , PE 1/1/2012 STP(U) 63 5 68 68 17 64 01 P N/A 0 CN 6/1/2012 STP (U) 567 76 643 643 CE No 34th Ave & River Rd Improvements 12 S 't. Frultvafe Blvd, T • from: 34th Ave. to: River Rd. w Intersection Improvements Including luminagon, sewer, water, curb, water and sidewalks ' • . Totals 630 81 711 711 Report Date: June 30, 2009 Page 16 V. 5.7 - Supersedes previous editions i . . iii O • . • 110 . . ASK Washi tate Department of Transportation Six Year Transportation Improvement P am Agency: • From 2010 to 5 Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -21 -2009 Adoption Date: City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.: • Project Identification Project Costs In Thousands of Dollars Federally Funded c A. PIN/Federal Aid No. B Bridge No c 5) v rn y m Fund Source Information Expenditure Schedule Projects Only s a . m 'o E C . Project Title E d 0 c c Fed Funding (Local Agency) RAN g U a 2 D. Street/Road Name or Number ur- t B z Phase Federal Federal State 4th Required tL E. Beginning MP or Road Ending MP or Road E F ° - 5 o Start Fund Cost by Fund St Local Total 1st 2nd 3rd Thru Envir. Date F. Describe Work to be Done a (mm/dd/yyyy) Code Phase Code Funds Funds Funds 6th Type (MM/YY) 1 2 3 4 5 6 7 8 9 10 11 12. 13 14 15 16 17 18 19 20 21 17 65 01 P 1.0 0 PE 1/1/2012 STP(U) 218 34 252 252 EnplewoodAve RW 6/1/2013 STP(U) 327 51 378 378 CE 0 5 S CN 1/1/2015 STP(U) 2980 • 244 3224 3224 Yes Englewood Ave 12 T from: 24th Ave to: 40th Ave W 1/1/2015 Reconstruct roadway, widen, curb, gutter and sidewalks. Sewer, water lines and street lights. Totals 3,525 329 3854 252 3602 • pE 1 1/1/2013 1 STP(U) 1 120 I I 1 17 137 137 14 66 01 P 6.0 c CE W. Yakima North/South Connector to West Valley 04 . O • Unknown road 06 o from: North - South to: in West Valley S City & County Joint protect to build/extend roadways. T • W Totals 120 17 137 137 16 67 01 P .38 S PEI 1/1/2013 I I 100 1001 100 Occidental Road Construction. W P • • from: 58th Ave, _ to: 64th Ave. T • Construct roadway Totals 100 too . 100 00 68 01 P 27 PE 1/1/2013 I 100 1001 100 86th Ave. Road Construction from: Occidental to: Coolidge • Construct roadway , . Totals 100 ' 100 100 • Report Date: June 30, 2009 Page 17 v. 5.7 - Supersedes previous editions I • • • • • • I . v74 . Washington State Department of Transportation Six Year Transportation Improvement Program Agency: Yakima From 2010 to 2015 Co. No.: 39 Co. Name: Yakima Co. Hearing Date: 7 -21 -2009 Adoption Date: City No.: 1485 MPO /RTPO: YVCOG Amend Date: Resolution No.: Project Identification Project Costs in Thousands of Dollars Federally Funded Ex enditure Schedule Pro 12 to A. PIN /Federal Aid No, B. Bridge No. e c 2 Fu Source Information P Jects Only = C. Project Title (Local Agency) R/W y F e d era l F un d i ng v D. Street/Road Name or Number 3 k a Phase. Federal Federal State 4th Required LL E. Beginning MP or Road - Ending MP or Road E . Start Fund Cost by Fund Stat Local Total Envir. Date F: Describe Work to be Done a (mm/dd/yyyy) Code Phase Code Funds Funds . Funds 1st 2nd 3rd 6th T ype (M1Vt y) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 • 16 69 04 P 1.5 W PE 1 1/1/2013 STP(U) 120 I 17 137 137 EA 64th Ave. Roadway Widening. 06 G YES P • . from: Washington Avenue. to: Tieton Drive. T Wide Roadway,Curb, Gutter, Sidewalks, Lighting, Drainage. o 7 /4/2014 Totals • 120 17 137 137 PE 1/1/2013 STP(E) 18 32 • 50 00 70 03 P N/A G YVT Railway Rehabilitation & Museum C CN 6/1/2013 STP(E) 1900 285 2185 I 50 2185 EA No 3rd Ave S from: 3rd Ave -to: Pine St T Car Bern, Museum Restoration and Pathway W P Totals 1,918 317 ' 2236 2236 PE 4/1/2011 CMAQ 24 3 27 27 16 71 01 P N/A S. CN 7/1/2011 CMAO 480 85 6461 646 CE Roadway Clty Wide Shoulder Improvements No City Wide from: to: City Wide shoulder Improvements; PM10 abatement. Totals 504 88 572 572 00 72 14 P .25 T PE 1/1/2012 STP(E) 252 34 286 288 Pedestrian Bridge 32 P CN 3/1/2013 STP(E) 3150 412 3562 3562 CE No Pedestrian Bridge O from: N 10th St to: Yakima Greenway Construct pedestrian bridge from Gateway area to Yakima Greenway; .I power, handicap accessible, lights Totals 3,402 - 446 3848 286 3562 • Report Date: June 30, 2009 Pa g a 18 V. 5.7 - Supersedes previous editions I • 40 • .. • , .. . • • •• . . . O 0 . • . . • Washi tate Department of Transportation Six Year Transportation Improvement Pr am Agency: Y . ® From 2010 to Co. No.: 39 Co. Name: Yakima Co: Hearing 'Date: 7 -21 -2009 Adoption Date: City No.: 1485 MPO /RTPO: YVCOG • Amend Date: Resolution No.: Project Identification Project Costs In Thousands of Dollars Federally Funded • c w B. Bridge No. e „ Fund Source Information Expenditure Schedule Projects Only a� 5 m A. PIN/Federal Aid No.• ge o E y 0 c y • (Local Agency) 0 o E C. Project Title " a m , o r /W • Federal Funding R U a Z D . Street/Road Name or Number' a i n B = i Phase Federal Federal State 4th Required tl E. Beginning MP or Road- Ending MP or Road E 2 5 * Start Fund Cost by Fund State Local Total Envir. Date Thru g 9 g y Funds Funds Funds 1s 2nd 3 r d Type (MrbVyy) F. Describe Work to be Done o - (mm/dd/yyyy) Code Phase Code _ 6th 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 • PE 1/1/2010 STP(E) 10 2 12 12 00 73 14 P N/A 0 S CN 7/1/2010 STP(E) 109 17 126 126 CE No William O. Douglas Pathway 32 P . • from: Pine St to: Cowiche Canyon W Pathway improvements, connections, and signage to Cowiche Canyon Trail. , ' Totals 119 19 138 138 PE 1/1/2013 STP(U) 315 38 353 353 CN 6/1/2013 STP(U) 945 • 126 1071 1071 CE 00 74 03 p N/A 0 YVTPathway 32 P No - YVT Railway Corridor. S from: - to: T • Development pathway In West Valley area Including 53rd Ave, Wide Hollow. w 64th Ave, Ahtanum Including all utilities and signage Totals 1,260 164 1424 1424 CN 6/1/2010 75 75 I 25 25 25 00 75 07 P .5 G I CE No Citywide Alleys S from: to: W T Pave alleys throughout the city. .. • Totals 75 75 25 25 25 14 75 06 P 2.64 PE 1/1/2010 ARRA- 50 50 50 CE Summitview Ave. Grind & Overlay 07 CN 6/1/2010 ARRA - 1950 1950 1950 No • from: 14th Ave to: 56th Ave wind 0.20' of ACP & replace with 0.20' of HMA, and Install required ADA • ramps Totals 2,000 2000 2000 Grand Totals for Yakima 114,050 21,592 25,563 161,205 41,298 26438 18,109 74,360 Report Date: June 30, 2009 Page 19 V. 5.7 - Supersedes previous editions