ITEM TITLE: Yakima Basin Integrated Plan May 2022 Project Activity Report
SUBMITTED BY: Scott Schafer, Director of Public Works
David Brown,Assistant Director of Public Works, 509-575-6204
SUMMARY EXPLANATION:
Attached is the Yakima Basin Integrated Plan May 2022 Project Activity Report which includes
the City's Aquifer Storage and Recovery project.
ITEM BUDGETED: NA
STRATEGIC PRIORITY: Partnership Development
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
RECOMMENDATION:
ATTACHMENTS:
Description Upload Date Type
D Report 5/31/2022 Backup Material
Yakima River Basin Integrated Water Resource Management Plan
YBIP Project Activity Update
May 2022
Purpose: Update on ongoing technical planning studies and project implementation
activities for the Yakima River Basin Integrated Water Resource Management Plan
(Integrated Plan)
Fish Passage Element
Cle Elum Darn Fish Passage Facilities and Reintroduction Project
The juvenile fish passage facility will use an innovative helix design to transport juvenile fish
downstream. It will allow fish to leave the reservoir as the water surface fluctuates over the top 63 feet
in elevation. This will provide downstream passage from April 1 through the beginning of June in most
years. The upstream adult fish passage facility will be a trap-and-haul facility where fish are trapped at
the base of the spillway, loaded into a truck, and then hauled for release into Cle Elum Reservoir or to
upstream tributaries.
Construction Update: The access road and spillway bridge and the secant pile vault, and tunnel bypass
contracts are complete. The last downstream section of the tunnel will be constructed as part of the
Adult Collection Facility (ACF). Reclamation anticipates awarding the ACF contract in 2022 and it will
be the final construction contract needed to complete the Cle Elum Darn Fish Passage project.
The Intake, Gate, and Helix(IGH) contractor mobilized in April 2019. After completing intake six in
the fall of 2020, the contractor continued intake construction in 2021 to complete intakes five fall 2021.
Also installed at that time were the Obermeyer Weir crest gates for intake six. In 2020,the contractor
placed and sealed in concrete the majority of the precast conduits that provide the connections from the
reservoir intakes to the secant vault leaving 40 feet for the final connection into the Secant. The final 40
feet of conduit boxes will be placed following the penetration of the secant vault at each level. Last fall
and into January 2022,the contractor tunneled through the last 40 feet to the secant piles, sawed through
and removed the cut secant pile sections, and placed the conduits at level six and five (reminder that
work needs to be complete from the lowest level up). The contractor has also been working inside the
Secant completing the helix/gate chamber separation wall and the access structure walls. Each chamber
will have an access structure that will house an elevator and stair system. More recent work inside the
secant includes construction of the floor system within the gate chamber. Levels five through one have
been completed which includes the placement of the guard gate and downstream steel pipe for each
level. These guard gates will control water flow between the intake conduits and the helix system.
Installation of the electrical and mechanical components that will be used to operate and monitor the
facility has also progressed. Work continues on the access shaft construction for the helix chamber.
Work on the remaining intakes will begin as the reservoir is drawn down.
Videos: https:llvimeo.com/508632343 (winter 2021) & https:llvimeo.com1579619438 (summer 2021)
Sockeye Study Update: In 2018, Reclamation and the Yakama Nation worked with the U.S. Geological
Survey to conduct an adult sockeye tracking test to understand their migration between Roza and Cle
Elum dams. The study found that 20 of the 20 tagged fish migrated successfully to the base of Cle Elum
Dam. In 2019,these same partners, along with Washington Department of Fish and Wildlife (WDFW),
began a sockeye tracking study in the lower Yakima River. The study reach runs from the mouth of the
Yakima River up to the Roza Dam and is evaluating potential passage issues at diversion dams,possible
WASHINGTON STATE
- BUREAU OF -
DEPARTMENT OF
1114 1IRfCLAMATIONE C O L O G Y
3
false attraction,microclimate use, and Columbia River Stranding. We expect to conduct this study over
three years depending on the study findings.
Results from the first year of the study(2019)found very low migration success rates for tagged
Sockeye primarily due to high river temperatures. Findings from 2020 continued to show that high river
temperatures limit access upstream for much of the summer, Sockeye migration can be slowed down at
diversion darns, and false attraction and predation may also be impacting upstream migration. The final
report for 2020's study is complete: Evaluation of factors affecting migration success of adult sockeye
salmon(Oncorhynchus nerka) in the Yakima River, Washington, 2020 (usgs.gov). The study for 2021
was postponed due to extreme air and river temperatures in the lower Yakima River. Reclamation,
Yakama Nation, WDFW, Ecology and other partners will resume the study this summer(2022). The
first adult Sockeye returning in the Columbia River in 2022 passed over Bonneville Dam on May 22.
Reclamation, Yakama Nation, WDFW, Ecology and other partners plan to start this year's study mid-
June.
Last year we started to test a netting system to capture and PIT tag juvenile Sockeye in Cle Elum
Reservoir. Initial test last year showed that we could successfully capture fish with this netting system.
This year, during April and May, approximately 3,600 juvenile Sockeye were capture and PIT tagged.
We are currently recording many of these fish as they pass over PIT tag antenna arrays located in the
Yakima and Columbia Rivers on their downstream migration to the ocean. About 450 tagged fish have
been detected in different location in the Yakima and Columbia Rivers with some detections below
Bonneville dam. We expect that a percentage of these fish will survive their downstream and ocean
migration and as they return as adults will be detected during their upstream migration,providing
valuable data for future management actions.
Box Canyon Creek Fish Passage
In 2018, WDFW, with input from Reclamation, Ecology, and other passage restoration experts, has
completed a conceptual design for the Box Canyon Creek Fish Passage Enhancement Project. Following
the completion of the conceptual design, Reclamation contracted with HDR to prepare a 60% project
design. HDR completed the 60%design and cost estimate late Fall 2021.
Clear Creek Darn Fish Passage
Reclamation and Ecology completed an appraisal level design for fish passage in September 2018. The
design consists of a traditional pool-and-weir-style fishway with a steel bulkhead at the upstream end
that will draw cool water from deeper in the reservoir. Situated along the left abutment of the dam,fish
would enter the fishway in the stilling basin and exit in the reservoir pool. The bulkhead will be deep
enough to maintain suitable water temperature in the fishway for Bull Trout.
Reclamation is coordinating with Ecology,U.S. Fish and Wildlife Service (USFWS), Yakama Nation,
Washington Department of Fish and Wildlife, U.S. Forest Service, National Marine Fisheries Service,
and others to complete the final ladder design. The partners met with basin biologists to define the range
of species targeted for passage and provide input for designers regarding ladder geometry. Reclamation
conducted geotechnical investigations in October 2020 and completed 30% designs on November 2,
2020. Comments from the Yakima Storage Dams Fish Passage Core Team were reviewed on January
21, 2021 and have been sent to the technical workgroup for review and comment. A Value Engineering
Study was completed February 2021. The 60%design was completed in June 2021. Ninety percent
design was completed and provided for comment in December 2021. The 90%design comments were
discussed at a technical meeting in February 2022. Final design documents were completed in March
2022. Environmental compliance and permitting is in process.
2
4
Until passage improvements are accomplished, USFWS, Reclamation, and WDFW will continue
capturing Bull Trout from below Clear Creek Dam and transporting genetically identified North Fork
Tieton River fish around the dam so they can reach spawning habitat in the North Fork Tieton
River. Fish capture and transport has been conducted 2016 through 2021. To date, 107 adult Bull Trout
have been transported above the dam.
Structural and Operational Changes Element
Cle Elum Pool Raise
The purpose of the Cle Elum Pool Raise Project is to increase the Cle Elum reservoir's capacity for
improved aquatic resources for fish habitat, rearing, and migration in the Cle Elum and upper Yakima
River,thereby fulfilling the intent of the congressional authorization, Title XII of Public Law 103-434.
Completed: Radial Gate construction was completed in April 2017. Reclamation completed
modifications to three saddle dikes as of 2018. The USFS Cle Elum River Campground recreation area
was completed in November 2017. The USFS Speelyi Day Use Area recreation area was completed in
May 2019. Shoreline protection along Salmon La Sac Road was completed in 2021.
Construction Update: Reclamation and Ecology are currently implementing shoreline protection actions
for private and public lands and facilities. Construction of shoreline protection at Wish Poosh
Campground& Boat Launch began in April 2021 and will be completed by the end of May 2022. The
Sandelin Lane shoreline protection area contract was awarded in July 2021. Construction in the Morgan
Creek Shoreline area is anticipated to begin in April of 2023. Construction in the Night Sky Shoreline
area is anticipated to begin in August 2023.Remaining shoreline protection will be implemented as
funding becomes available. Landowners and the public will be updated periodically on the project via
mail and website postings during project implementation. Reclamation and Ecology continue working
with landowners along the shoreline to acquire easements as appropriate for the project and released a
video to inform our partners and public on the project.
Video: https://youtu.be/9G3-CgBMQsE.
In addition, Reclamation sends out a quarterly update postcard to landowners around Cle Elum
Reservoir as part of outreach efforts.
Chandler Pumping Plant Electrification
Kennewick Irrigation District(KID) continues to evaluate an electrical pumping plant at Chandler. As of
May 2022, Reclamation continues to work with KID. KID is preparing updated design drawings and
operational diversion plans for review of Chandler Electrical Pumping Plant by Reclamation.
Reclamation has extended an existing Memorandum of Agreement through 2022 with KID for this
work. Reclamation and KID have regular meetings to address KID water supply issues. Reclamation is
part of the Lower River Leadership team along with Ecology, Yakama Nation, and KID to discuss a
multitude of options to meet lower river flow needs for KID. An electrical pumping plant may still be
considered by KID, however, recently KID has been reviewing other options which may including a
storage reservoir within the District.
Lower Yakima River Smolt Survival Study
The Lower Yakima River Smolt Survival Study has been monitoring smolt survival since 2018 with the
last full season of field work in 2022. Efforts are underway to complete data analysis and modeling of
Chinook salmon and steelhead survival in various river reaches associated with river flow, water
temperature, and other important variables. Preliminary results showed fish survival was higher when
3
5
river flows were higher and temperatures were cooler, and fish that were diverted into canals at Wapato,
Sunnyside, and Prosser dams had lower survival than fish remaining in the river. These results were
used to help develop the Sunnyside Dam fish guidance boom and sluice gate project. Monitoring data
indicate the Sunnyside boom and gate combination are effective at reducing the numbers of fish being
diverted into the Sunnyside Canal. Data analysis, modeling, and reporting on the results of the Lower
Yakima River Smolt Survival Study is expected to continue through 2023.
Surface Water Storage Element
Kachess Drought Relief Pumping Plant(KDRPP)
The KDRPP is proposed to access 200,000 (out of 585,000) acre-feet of inactive storage in the Kachess
Reservoir that is below the current outlet works for use in severe drought.
On April 26, 2019, Reclamation signed the Record of Decision (ROD), which does not approve
implementation of any alternatives but carries forward Alternative 4 - KDRPP Floating Pumping Plant
(FPP) for further analysis. Consistent with this decision, the remaining alternatives in the FEIS,
including the Kachess to Keechelus Conveyance, are unlikely to be carried forward. Reclamation and
Ecology will use a phased approach for further site-specific analysis in a Tier 2 NEPA process to narrow
the range of feasible alternatives for KDRPP.
The Project Proponent,the Roza Irrigation District, in coordination with Reclamation and Ecology, is
currently developing a new Proposed Action and clarifying the FPP alternative for the KDRPP Tier 2
NEPA process. This final and complete Proposed Action and Reclamation's subsequent Notice of Intent
(NOI)for the Tier 2 EIS are currently projected for later in 2022. Roza and possibly other pro-ratable
waters users (Kittitas Reclamation District(KRD), Wapato Irrigation Project(WIP) and Kennewick
Irrigation District(KID) would fund, design, construct, and operate the KDRPP.
Wymer Reservoir
Consideration of site requirements is ongoing.
Bumping Reservoir Enlargement Project
Consideration of site requirements is ongoing.
Groundwater Storage Element
Groundwater Storage—Basin-wide Analysis
The Groundwater Storage Subcommittee initiated work on several new groundwater storage
investigations and continued work developing and expanding groundwater storage projects already
underway.
New investigations/projects:
• Managed Aquifer Recharge (MAR)Evaluation of Basalts in the Konnawac Pass Area(CWU)
• Evapotranspiration and Floodplain Aquifer Storage Capacity Study(CWU)
• City of Ellensburg Phase 1 ASR Feasibility Study
• City of Moxee Phase 1 ASR Feasibility Study
• Basalt ASR Assessment(KRD)
• Central Data Repository/GIS Clearinghouse (KRD)
4
6
Continued development:
• Taneum Creek MAR Pilot Testing (KRD)
• Continue and Expand On-going Monitoring Efforts at High Priority MAR Sites (KRD)
• Toppenish Fan MAR—Marion Drain, Hunt Creek Check Structures; Optimization of Existing
Irrigation Induced Recharge Recapture Facilities (YN)
• Effects of Channel Wood Restoration on Groundwater Storage and Recharge in the Teanaway
River Valley
• Evaluation of the Hydrogeology in the Badger-Coulee Area(CWU)
Aquifer Storage and Recovery(ASR)
The City of Yakima is planning full build-out for its permitted ASR program and intends to drill two
ASR devoted wells:the first well is estimated for 2022-2023, and the second is estimated for 2025-2026.
The City has requested funds for future projects with Reclamation.
Habitat Protection and Enhancement Element
Targeted Watershed Protection and Enhancement
The Watershed Lands Conservation Subcommittee continued working on early steps in implementing
the Phase 2 acquisitions and designations elements of the Lands Plan through focused subgroup
discussions. The Subcommittee heard briefings from sponsors pursuing conservation lands acquisitions
that support Integrated Plan goals for habitat and watershed protection and will continue to provide a
forum for these discussions in the coming months.
Mainstem Floodplain and Tributaries Fish Habitat Enhancement Program
The Habitat Subcommittee is monitoring implementation of projects funded in the 2021-2023 biennial
Habitat budget. The Subcommittee has completed a draft of the budget proposal for the 2023 —2025
biennial budget.
The Subcommittee has completed the draft of its new 10-year strategic plan. The plan was revised to
reflect shifting priorities based on new information derived over the initial implementation period. The
10-year plan identifies capital projects by priority river reach.
The Subcommittee will finalize the proposed 2023 —2025 biennial budget and the 10-year plan at its
June 2022 meeting.
Enhanced Water Conservation Element
With passage of the Dingell Act in March 2019, Reclamation, Ecology, Yakama Nation, and YRBWEP
Workgroup Partners have a goal to conserve 85,000 acre-feet of water by 2029. The overall conservation
savings goal upon full Integrated Plan implementation is 170,000 acre-feet. Reclamation and Ecology
are conducting an inventory of water conservation accomplishments associated with the Integrated Plan.
Projects that county towards this goal must adhere to three parameters:
• Begin in 2013 or later
• Be an agricultural or municipal improvement project resulting in conserved water, and
• Not be part of the Title XII, Section 1203 Basin Conservation Plan.
To date, there have been 125 conservation projects implemented(completed or in progress).
Approximately $119 million invested will result in approximately 59,000 acre-feet of conserved water
5
7
($2,000 per acre-foot). A technical memorandum explaining the history, accounting, and future
framework planning for the Enhanced Water Conservation Element projects was released to the Water
Use Subcommittee in April 2021. Within this memorandum, Reclamation and Ecology have developed a
proposal for achieving the remaining portion of the initial development phase goal. In May 2022,the
Water Use Subcommittee received 8 project proposals which are under review for funding in the 2023-
2025 biennium. These proposals add up to approximately $6.5 million and would have a cumulative
conservation benefit of about 3,700 acre-feet.
Market Reallocation Element
The Kittitas Reclamation District (KRD)and Trout Unlimited (TU) continued water market research and
development as part of the Market Reallocation element of YBIP. In the last quarter,the project team
developed the draft Yakima Basin Water Market Strategy. The project team also advanced significant
technical analyses on smart market simulations (to model market activity under different scenarios) and
instream flow needs. An analysis on the administration/legal requirements for the market was
also concluded. The resulting draft strategy incorporates the different technical, legal, and policy
evaluations and provides recommendations for implementation of a smart market. Outreach continued
with COVID-19 restrictions in place.
More information about the project can be found at https://www.yakimabasinwatermarketing.org/
Proposed Projects for Consideration 111. Mr—
During implementation of the Integrated Plan, an adaptive approach is being used periodically to assess
progress towards meeting the identified instream flow objectives,the 70 percent proratable supply goal
for irrigation, and goals for other out-of-stream needs. The need for additional water supply
enhancements would depend on the effectiveness of projects that are implemented as part of the
Integrated Plan, how the Yakima basin economy develops over time, and the timing of and manner in
which climate changes affect water supply availability. From time-to-time, new projects may be
identified(and proposed)for consideration under the Integrated Plan. Reclamation, Ecology, Yakama
Nation, and the Executive Committee have developed a formalized process to consider new projects. In
December 2021, Reclamation, Ecology, Yakama Nation agreed to include YTID's proposal for change
in point of diversion to Wapatox and removal of the Tieton Diversion Dam as part of the Integrated
Plan. In addition, Upper Yakima System Storage was also included as part of the Integrated Plan.
Contacts for Information on the Integrated Plan:
Wendy Christensen, U.S. Department of the Interior, Bureau of Reclamation, Columbia-Cascades Area
Office, (509) 573-8050
Thomas Tebb, Washington State Department of Ecology, Office of Columbia River, (509) 574-3989
Project website: http://www.usbr.gov/pn/programs/yrbwep/index.html