HomeMy WebLinkAboutR-2015-087 2016-2021 Yakima Urban Area Comprehensive Plan Capital Facilities Element for 6-Year TIP RESOLUTION NO. R- 2015 -087
A RESOLUTION to amend the Yakima Urban Area Comprehensive Plan Capital
Facilities Element to incorporate the Six -year Transportation
Improvement Program (TIP) for the period of 2016 through 2021.
WHEREAS, the City of Yakima annually prepares, reviews and adopts a Six — Year
Transportation Improvement Program for the construction of streets and arterial streets in
the City of Yakima for the ensuing six year period, all as contemplated and required by State
RCW 35.77.010 and applicable Federal law; and
WHEREAS, the City of Yakima desires to amend the Yakima Urban Area
Comprehensive Plan Capital Facilities Element to reflect the adoption of the Six -year TIP, as
contemplated and required by RCW 36.70A.070(6) to ensure compliance with the Growth
Management Act and consistency of the Comprehensive Plan and the Six -year TIP, and,
WHEREAS, this amendment is limited to incorporation of the projects listed in the
Six -year Transportation Improvement Plan for the period of 2016 to 2021 to the Capital
Facilities Element of the Yakima Urban Area Comprehensive Plan, which is contemplated
and provided under RCW 36.70A.130(2B) and RCW 35 77.010, and,
WHEREAS, public hearings were held by the Yakima City Council on the Six -year
TIP on June 2, 2015 and June 16, 2015, with proper public notice as required by RCW
35 77 010, now, therefore
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
The adopted Six -Year Transportation Improvement Program for the period of 2016
through 2021 for the City of Yakima shall be incorporated as an amendment to the Capital
facilities Element of the Yakima Urban Area Comprehensive Plan.
ADOPTED BY THE CITY COUNCIL this 16 day of June, 2015.
cah awley, Mayor
ATTEST.
t
1
\rvity Clerk * j ^��
�- • to �
•
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 10.
For Meeting of: June 16, 2015
ITEM TITLE: Public Hearing to consider: A) Resolution adopting the Six -year
Transportation Improvement Program for the years 2016 to 2021,
and to amend the Metropolitan Transportation Plan; and B)
Resolution amending the Yakima Urban Area Comprehensive Plan
Capital Facilities Element
SUBMITTED BY: Debbie Cook, Director of Utilities and Engineering
Brett Sheffield, Chief Engineer
SUMMARY EXPLANATION:
Attached is the 2016 — 2021 Six -year Transportation Improvement Program (TIP), along with an
explanation sheet that describes the information contained on the various columns of the Six -year TIP. No
new projects have been added.
Projects that that have been removed from the 2015 — 2020 TIP as they were completed or the funds were
obligated include:
• #3 Tieton Drive and 64 Avenue Intersection Improvements
• #10 E. Lincoln Avenue and 10 Street Roundabout
• #16 West Valley Middle School Safety Improvements
Project #33, N. f Street and 'I' Street Signal Upgrade, has been removed because this work is being
included in the N. 1st Street Revitalization, MLK to `N' Street project, renumbered #3.
Council and the public are welcome to add other arterial system projects to the list. The six -year TIP
project listing will be finalized at the June 18 hearing and sent to the Yakima Valley Conference of
Governments (YVCOG) after approval.
A) Each year the City is required by RCW 35.77.010 and RCW 36.81.121 to update its Six -year
Transportation Improvement Program (TIP) for submittal to the Washington State Department of
Transportation. This plan must include all transportation projects for which state gas tax revenue of
federal revenue will be used.
The current plan for 2016 — 2021 includes ten projects that are funded. Funding for the remainder of the
projects will continue to be sought. The funded projects include:
#1 — Yakima Railroad Grade Separations, Phase 4
#2 — North 1st Street Revitalization, `N' Street to SR 12
#3 — North 1st Street Revitalization, MLK to `N' Street
#4 — East Nob Hill Boulevard and Fair Avenue Intersection Improvements
#6 — Powerhouse Road Sidewalk
#7 — Yakima Valley Transportation Company Preservation
#44 — Northside Alley Pavers
#45 — S. 80 Avenue Bridge
#46 — Wide Hollow Bridge
#47 — Lincoln Avenue Corridor Safety Improvements.
Six -year Transportation Improvement Program (TIP) Background
On August 10, 2005, the President signed into law the Safe, Accountable, Flexible, Efficient
Transportation Equity Act: A Legacy for Users (SAFETEA -LU). This act is the next authorization
after the prior Transportation Equity Act of 1998 for the 21 Century (TEA -21) and previous Intermodal
Surface Transportation Efficiency Act (ISTEA) of 1991. The current act again specifies the systems on
which certain funds can be used and activities for which funds can be used and promotes the role of the
Metropolitan Planning Organizations (MPO) in the planning and programming of projects. SAFETEA-
LU requires each designated MPO to develop a Transportation Improvement Program (TIP), and the state
to develop a Statewide Transportation Improvement Program (STIP) as a condition to securing federal
funds for the transportation projects.
Projects listed in the STIP are the only projects that can be approved by the Federal Highway
Administration (FHWA) and the Federal Transit Administration (FTA) to utilize federal fund of by the
State of Washington for approved State funding agencies. The STIP is a prioritized program of
transportation projects, complied from local and regional plans, along with the Washington Transportation
System Plan (WTP), which provides a backbone for developing projects for the intermodal transportation
network in the State of Washington.
The STIP contains federally funded projects plus state and local projects that are regionally significant.
These projects have been identified through the planning process as the highest priority for the available
funding to the state's transportation program. Planning activities of state and local governments are
essential parts of integrated regional planning processes. Long range transportation planning is a part of
the comprehensive land use planning carried out by local governments. Citizen participation is an integral
part of the planning process at all levels. Local Agencies are required to develop and adopt a six -year
transportation program. All local agencies are required to hold at least one public hearing during the
development of the six -year transportation program.
Project ranking has been performed utilizing data supplied by the Street and Traffic Division. The ranking
will be integrated with other project needs and the total list will be reviewed and adjusted to the particular
need of the City of Yakima.
B) The City needs to amend the Yakima Urban Area Comprehensive Plan Capital Facilities Element to
incorporate the adopted six -year TIP for 2014 to 2019. This will ensure that we are in compliance with
the Growth Management Act and that we are consistent with the Comprehensive Plan as required. The
amendment is limited to incorporate only those projects that adopted in the STIP and is not subject to the
"once a year" change required under the laws of the Growth Management Act.
Resolution: Ordinance:
Other (Specify): Six -Year TIP
Contract: Contract Tenn:
Start Date: End Date:
Item Budgeted: Amount:
Funding Source /Fiscal Impact:
Strategic Priority:
Insurance Required? No
Mail to:
Phone:
APPROVED FOR
SUBMITTAL: City Manager
RECOMMENDATION:
Adopt the Six -Year TIP and amend the regional Metropolitan Transportation Plan and Comprehensive
Plan Capital Facilities Element.
ATTACHMENTS:
Description Upload Date Type
o Resolutions 6,8/2015 Resolution
o Six -Year Transportation Improvement Program 6/8/2015 Exhibit
o E planation Sheet 6/8/2015 Exhibit
RESOLUTION NO. R — 2015 -
A RESOLUTION adopting the Six -Year Transportation Improvement Program for the
period of 2016 through 2021 for the construction of streets and
arterials streets in the City of Yakima and amending the Metropolitan
Transportation Plan.
WHEREAS, the City of Yakima annually prepares, reviews and adopts a Six Year
Program for the construction of streets and arterial streets in the City of Yakima for the
ensuing six year period, all as contemplated and required by State RCW 35.77.010 and
applicable Federal law; and
WHEREAS, the City of Yakima desires to amend the Metropolitan Transportation
Plan to ensure compliance with the Growth Management Act and the regional transportation
plan for the construction of streets and arterial streets in the City of Yakima, all as
contemplated and required by State and Federal law, and
WHEREAS, after public hearings on the matter, held at the regular meeting of the
Yakima City Council on June 2, 2015 and June 16, 2015, with proper public notice as
required by RCW 35.77.010, the City Council finds that the plan attached hereto should be
adopted as the Six -Year Transportation Improvement Program for the period of 2016
through 2021 for the construction of streets and arterial streets in the City of Yakima, now,
therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
The Six -Year Construction Program for the period of 2016 through 2021, a copy of
which is attached hereto and by this reference made a part hereof, is hereby adopted as the
official Six -Year Transportation Improvement Program for the City of Yakima, including
proposed amendments to the Metropolitan Transportation Plan along with Street
Improvements, which are also approved.
ADOPTED BY THE CITY COUNCIL this 16 day of June, 2015.
Micah D. Cawley, Mayor
ATTEST:
City Clerk
Agency: Yakima Six Year Transportation Improvement Program
Co. No.: 39 Co. Name: Yakima Co. From 2016 to 2021
City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015
Amend Date: Resolution No.:
Project Costs in Thousands of Dollars Expenditure Schedule Federally Funded
ul
9 Project Identification Fund Source Information (Local Agency) Projects Only
0 A. PIN /Federal Aid No. B. Bridge No. c s al m Federal Funding R/W
C. Project Title v cn v 0 _ Phase
c z o d Federal State State Local Total Envir. Required
D. Street /Road Name or Number > ,� u ., 3 c., u Start Federal Fund
cp E. Beginning MP or Road - Ending MP or Road a a Y : 0 Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date
u a F. Describe Work to Be Done E g F d Phase (MM /YY)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
14 1 Yakima Railroad Grade Separations - Phase 4 01 S 0.2 T CN 1/1/2016 650 650 650 EA Yes
Lincoln Avenue 06 P
from: N. 1st Street to: N. 1st Avenue 07 G 9/1/2009
Install art as project aesthetics for the railroad grade 08 0
separations, and construct raised sidewalk on the south
side of Lincoln Avenue
Totals 0 0 650 650 650 0
14 2 North 1st Street Revitalization 3 S 0.42 P CN 1 1/1/2018 1 STP(U) I 2,7181 I 4241 3,142 3,1421
1 CE No
North 1st Street 06 T
from: 'N' Street to: SR 12 0
Improve North 1st Street by rehabilitating the pavement C
and lane markings, removing on- street parking,
enhancing street and pedestrian lighting, constructing
median islands and installing various pedestrian and
decorative elements.
Totals 2,718 424 3,142 3,142
14 3 North 1st Street Revitalization 06 P 0.98 P CN 1/1/2016 TIGER 8,000 8,000 8,000 CE Yes
N. 1st Street 12 T
from: MLK Blvd. to: 'N' Street G 12/31/2015
Improve North 1st Street by rehabilitating the pavement C
and lane markings, removing on- street parking,
enhancing street and pedestrian lighting, constructing
median islands and installing various pedestrian and
decorative elements.
Totals 8,000 0 8,000 0 0
14 4 E. Nob Hill Blvd. & Fair Ave. 1/S Improvements 03 S N/A P RW 1/1/2016 STP(U) 187 29 216 216 CE Yes
Nob Hill Boulevard 04 T CN 6/1/2018 STP(U) 1,457 227 1,684 1,684
from: E. Nob Hill Blvd. to: Fair Ave. 31 W 1/1/2018
Widen Nob Hill Boulevard through the intersection, C
construct left -turn lane, curb, gutter, sidewalk, street 0
lighting and drainage. Upgrade signal by installing mast
arm structures.
Totals 1,644 256 1,900 0 1,684
Agency: Yakima Six Year Transportation Improvement Program
Co. No.: 39 Co. Name: Yakima Co. From 2016 to 2021
City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015
Amend Date: Resolution No.:
Project Costs in Thousands of Dollars Expenditure Schedule Federally Funded
ul `w Project Identification Fund Source Information (Local Agency) Projects Only
O E A. PIN /Federal Aid No. B. Bridge No. c o Federal Funding R/W
2 C. Project Title E - �n v d Phase
o v v $ Federal State State Local Total Envir. Required
D. Street /Road Name or Number > —I v Start Federal Fund
b E. Beginning MP or Road - Ending MP or Road a i c :a o Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date
LL a F. Describe Work to Be Done E F F 5 d Phase (MM /YY)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
17 5 Powerhouse Road Sidewalk 05 S 0.6 0 CN 1/1/2016 TAP 245 245 245 CE No
Powerhouse Road 12
from: Cowiche Canyon Rd to: Mobile Home Park
Widen westbound lane to provide a 14 -foot wide
shared bike lane and construct curb, gutter and
sidewalk on the north side of the road.
Totals 245 245 245
14 6 Yakima Valley Transportation Company Preservation 03 S 0.02 0 CN 1/1/2016 STP(E) 52 52 52 CE No
Yakima Avenue
from: Yakima Avenue to: 6th Avenue
Remove and replace a portion of the existing trolley
rail in the vicinity of the intersection of 6th Avenue
and Yakima Avenue.
Totals 52 52 52
19 7 Adams Elem. /Washington M.S. Sidewalk Improvements 12 P N/A P PE 1/1/2016 SRTS 25 25 25 CE Yes
Various Streets T RW 1/1/2017 SRTS 50 50 50
from: to: 0 CN 5/1/2017 SRTS 253 30 283 283 5/1/2017
This project will make various pedestrian safety
improvements in the vicinity of Adams Elementary
School and Washington Middle School, such as,
constructing sidewalks, improving roadway crossings
and installing flashers
Totals 328 30 358 25 333
19 8 Garfield Elementary Safety Improvements 12 P N/A P PE 11/1/20161 SRTS 12 12 12 CE Yes
Various Streets T RW 1/1/2017 SRTS 20 20 20
from: to: 0 CN 5/1/2017 SRTS 128 13 141 141 1/1/2017
This project will make various pedestrian safety
improvements in the vicinity of Garfield Elementary
School, such as, constructing sidewalk, improving
roadway crossings, installing flashers.
Totals 160 13 173 12 161
Agency: Yakima Six Year Transportation Improvement Program
Co. No.: 39 Co. Name: Yakima Co. From 2016 to 2021
City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015
Amend Date: Resolution No.:
Project Costs in Thousands of Dollars Expenditure Schedule Federally Funded
ul `w Project Identification Fund Source Information Projects Only
U E A. PIN /Federal Aid No. B. Bridge No. ,� (Local Agency)
s „ m Federal Funding R/W
z c. Project Title to v d Phase
F
v v 0 Federal State State Local Total Envir. Required
D. Street /Road Name or Number ,� Start Federal Fund
T, _ a Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date
o E. Beginning MP or Road - Ending MP or Road a o- V c = o C
LL a F. Describe Work to Be Done E F F 5 d Phase (MM /YY)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
12 9 SR 12 & 16th Avenue Interchange 03 P N/A 0 PE 1/1/2017 STP(U) 86 14 100 100 CE No
Westbound ramps of SR 12 06 CN 1/1/2018 STP(U) 779 121 900 900
from: 16th Avneue to: SR 12
Construct a roundabout where the westbound ramps
intersect with N. 16th Avenue.
Totals 865 135 1000 100 900
16 10 1 -82 & Lincoln Avenue Interchange 01 P N/A 0 PE 1/1/2017 STP(U) 260 40 300 300 CE No
Lincoln Avenue P RW 1/1/2018 STP(U) 173 27 200 200 200
from: E. 'G' Street to: 1 -82 G CN 6/1/2019 STP(U) 1,730 270 2,000 2,000
Reconstruct /extend off -ramp from existing 1 -82 off -
ramp for Lincoln Avenue to E. 'G' Street.
Totals 2,163 337 2,500 0 500 200 2,000
14 11 E. Yakima Ave. & Fair Ave. U Signalization 12 P N/A P PE 1/1/2018 STP(U) () 86 14 100 100 CE No
Yakima Avenue T CN 6/1/2019 STP(U) 1 519 81 600 600
from: E. Yakima Ave. to: Fair Ave. W
Install traffic signal at the intersection of Yakima S
Avenue and Fair Avenue. 0
Totals 605 95 700 100 600
16 12 S. 3rd Avenue & W. Washington Ave. Signal 12 P N/A P PE 4/1/2017 20 20 20 CE No
S. 3rd Avenue T CN 9/1/2017 210 210 210
from: S. 3rd Ave. to: W. Washington Ave.
Upgrade the traffic signalization system 230 230 230
Totals 230 230 230
Agency: Yakima Six Year Transportation Improvement Program
Co. No.: 39 Co. Name: Yakima Co. From 2016 to 2021
City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015
Amend Date: Resolution No.:
Project Costs in Thousands of Dollars Expenditure Schedule Federally Funded
ul `w Project Identification Fund Source Information Projects Only
A. PIN /Federal Aid No. B. Bridge No. ,� (Local Agency)
U 9
s „ m Federal Funding R/W
o z C. Project Tit
to v d Phase
IF, v $ Federal State State Local Total Envir. Required
D. Street /Road Name or Number � 3 Start Federal Fund
2 T, _ a, Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date
o E. Beginning MP or Road - Ending MP or Road a i « • = o Code
LL & F. Describe Work to Be Done E F F 5 d Phase (MM /YY)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
14 13 S. 1st St. & E. Washington Ave. 1/S Improvements 03 P N/A P PE 1/1/2017 STP(U) 260 40 300 300 CE Yes
South 1st Street 06 W RW 1/1/2018 STP(U) 260 40 300 100 200
from: S. 1st Street to: E. Washington Ave. S CN 1/1/2019 STP(U) 1,211 189 1,400 1,400 1/1/2019
Realign intersection, widen E. Washington Avenue to T
accommodate an additional lane, replace curb, gutter 0
and sidewalk, and install a new traffic signalization
system.
Totals 1,731 269 2,000 400 200 1,400
17 14 S. 48th Avenue Reconstruction 03 P 1.00 P PE 1/1/2017 STP(U) 223 35 258 258 CE Yes
South 48th Avenue 05 T RW 1/1/2018 STP(U) 519 81 600 600
from: Summitview Ave. to: Nob Hill Blvd. W CN 1/1/2019 STP(U) 1,485 232 1,717 1,717 1/1/2019
S
Reconstruct and widen 48th Avenue, install curb, 0
gutter, sidewalk, street lighting and drainage system.
Totals 2,227 348 2,575 0 258 600
16 15 Tieton Dr. & S. 5th Ave. 1/5 Improvements 12 P N/A P PE 1/1/2017 STP(U) 69 11 80 80 CE Yes
Tieton Drive W RW 1/1/2018 STP(U) 104 16 120 120
from: Tieton Dr. to: S. 5th Ave. S CN 6/1/2019 STP(U) 865 135 1,000 1,000 5/1/2019
Remove existing traffic signal and construct a T
roundabout, remove and replace curb, gutter, 0
sidewalk, street lighting and drainage
Totals 1,038 162 1,200 80 1,120
16 16 E. 'H' Street Extension, Ph. 1 01 P 1.10 P PE 1/1/2017 STP(U) 432 68 500 500 CE Yes
E. 'H' Street 08 T RW 1/1/2018 STP(U) 432 68 500 500
from: 1st Street to: Yakima River W CN 1/1/2019 STP(U) 2,162 338 2,500 2,500 12/1/2018
Construct new roadway including water, sewer, curb, S
gutter, sidewalk, street lighting and storm drainage 0
system.
Totals 3,026 474 3,500 500 500
Agency: Yakima Six Year Transportation Improvement Program
Co. No.: 39 Co. Name: Yakima Co. From 2016 to 2021
City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015
Amend Date: Resolution No.:
Project Costs in Thousands of Dollars Expenditure Schedule Federally Funded
ul `w Project Identification Fund Source Information Projects Only
A. PIN /Federal Aid No. B. Bridge No. ,� (Local Agency)
U 9
s „ m Federal Funding R/W
72 2 C. Project Title ti to v d Phase
IF, a v $ Federal State State Local Total Envir. Required
D. Street /Road Name or Number > 3 Start Federal Fund
° v = a, Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date
o E. Beginning MP or Road - Ending MP or Road a i « c = o Code
LL & F. Describe Work to Be Done E F F 5 d Phase (MM /YY)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
17 17 Cascade Millsite Parkway 01 P 1.3 P PE 1/1/2016 STP(U) 350 54 404 404 CE Yes
North 10th Street 06 T RW 1/1/2017 STP(U) 2,746 429 3,175 3,175
from: 'H' Street to: Lincoln Ave. W CN 1/1/2018 STP(U) 3,837 599 4,436 4,436 1/1/2018
Construct new roadway including water, sewer, curb, S
gutter, sidewalk, street lighting and storm drainage 0
system.
Totals 6,933 1,082 8,015 404 3,175 4,436
17 18 Yakima Downtown Future Initiatives, Phase 5 06 P 0.15 P PE 1/1/2017 OTHER 500 500 500 CE No
12 T CN 4/1/2018 OTHER 5,500 5,500 5,500
from: 1st Street to: 9th Street C
Install historic lighting, sidewalk modifications and S
other improvements. Exact improvement area(s) to
be determined
Totals 6,000 500 5,500
19 19 75th Avenue Improvements 01 P 0.50 P PE 1/1/2018 STP(U) 87 13 100 100 CE Yes
75th Avenue 08 W RW 1/1/2019 STP(U) 173 27 200 200
from: Mead Ave. to: Nob HiII Blvd. S CN 1/1/2020 STP(U) 1,038 162 1,200 1,200
T
Construct a new two -lane roadway and widen 0
portions of existing roadway, install curb, gutter,
sidewalk, street lighting and storm drainage system.
Totals 1,500 100 1,400
14 20 Washington Ave. & Longfiber Rd. Intersection 03 P N/A C PE 1/1/2017 STP(U) 100 14 114 114 CE Yes
Washington Avenue 05 T RW 1/1/2018 STP(U) 100 14 114 114
from: Washington Ave. to: Longfiber Rd. 06 W CN 1/1/2019 STP(U) 688 107 795 795 1/1/2019
intersection by constructing an eastboung left -turn S
lane on Washington and a northbound left -turn lane 0
on Longfiber, install or replace curb, gutter, sidewalk,
Totals 888 135 1,023 114 114 795
Agency: Yakima Six Year Transportation Improvement Program
Co. No.: 39 Co. Name: Yakima Co. From 2016 to 2021
City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015
Amend Date: Resolution No.:
Project Costs in Thousands of Dollars Expenditure Schedule Federally Funded
ul `w Project Identification Fund Source Information Projects Only
U E A. PIN /Federal Aid No. B. Bridge No. ,� (Local Agency)
s „ m Federal Funding R/W
z C. Project Title E to -o d Phase
IF, v v ° Federal State State Local Total Envir. Required
D. Street /Road Name or Number ,� 3 u ti Start Federal Fund
0 v = a Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date
( o E. Beginning MP or Road - Ending MP or Road a o- V c = o Code
LL a F. Describe Work to Be Done E F F 5 d Phase (MM /YY)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
14 21 E. Nob Hill Blvd. &S. 18th Street 1/S Improvements 01 P 0.10 C PE 1/1/2017 STP(U) 50 8 58 58 CE Yes
E. Nob Hill Boulevard 04 T RW 1/1/2018 STP(U) 50 8 58 58
from: E. Nob Hill Blvd. to: S. 18th Street W CN 1/1/2019 STP(U) 346 54 400 400 1/1/2018
Widen south leg for double left turn from westbound S
Nob Hill, install curb, gutter, sidewalk, upgrade traffic
signal system
Totals 446 70 516 58 58 400
17 22 Powerhouse Rd. & Englewood Ave. 1/5 12 P N/A P PE 1/1/2018 STP(S) 43 7 50 50 CE Yes
Powerhouse Rd. T RW 1/1/2019 STP(S) 87 13 100 100
from: Powerhouse Rd. to: Englewood Ave. C CN 1/1/2020 STP(S) 500 78 578 578 1/1/2019
S
0
W
Realign intersection, install curb, gutter, sidewalk and
safety flashing signal. Possibly construct a
roundabout.
Totals 630 98 728 0 50 678
14 23 S. 48th Ave. & Summitview Ave. Signalization 12 P N/A P PE 1/1/2018 STP(S) 25 4 29 29 CE Yes
Summitview Avenue T RW 6/1/2018 STP(S) 25 4 29 29
from: Summitview Ave. to: S. 48th Ave. CN 1/1/2019 STP(S) 554 81 635 635 1/1/2019
Install traffic signal at the intersection of Summitview
Avenue and 48th Avenue.
Totals 604 89 693 58 635
14 24 W. Lincoln Ave. & MLK Blvd. Realignment 01 P 0.50 C PE 1/1/2017 STP(E) 424 67 491 491 CE Yes
W. Lincoln Avenue 12 T RW 1/1/2018 STP(E) 1,047 163 1,210 1,210
from: N. 5th Ave. to: Custer St. W CN 1/1/2019 STP(E) 1,801 281 2,082 2,082 1/1/2019
S
0
Realign W. Lincoln Avenue, install curb, gutter, P
sidewalks, street lighting, drainage. G
Totals 3,272 511 3,783 491 1,210 2,082
Agency: Yakima Six Year Transportation Improvement Program
Co. No.: 39 Co. Name: Yakima Co. From 2016 to 2021
City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015
Amend Date: Resolution No.:
Project Costs in Thousands of Dollars Expenditure Schedule Federally Funded
ul `w Project Identification Fund Source Information (Local Agency) Projects Only
U E A. PIN /Federal Aid No. B. Bridge No. c �+ o
s Federal Funding R/W
co z C. Project Title
to v d Phase g
o v $ Federal State State Local Total Envir. Required
D. Street /Road Name or Number > 3 v Start Federal Fund
o E. Beginning MP or Road - Ending MP or Road 2 r 3 c o Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date
LL a F. Describe Work to Be Done E F F 5 d Phase (MM /YY)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
14 25 E. Nob Hill Boulevard Reconstruction 03 P 0.85 C PE 1/1/2017 STP(U) 545 85 630 630 CE Yes
E. Nob Hill Boulevard 04 T RW 1/1/2018 STP(U) 1,090 170 1,260 1,260
from: S. 6th Street to: S. 18th Street 06 W CN 1/1/2019 STP(U) 6,532 1,020 7,552 7,552 1/1/2019
S
Reconstruct and widen roadway to 5 lanes with 0
intersection improvements, curb, gutter, sidewalk, P
street lighting and drainage system G
Totals 8,167 1,275 9,442 630 1,260 7,552
14 26 S. 72nd Ave. & W. Washington Ave. 1/5 12 P N/A P PE 1/1/2017 STP(C) 91 14 105 105 CE Yes
S. 72nd Avenue 06 T RW 1/1/2018 STP(C) 91 14 105 105
from: s. 72nd Ave. to: W. Washington Ave. 0 CN 1/1/2019 STP(C) 544 86 630 630 1/1/2019
Improve intersection by installing a traffic signal S
system or roundabout. W
Totals 726 114 840 105 105 630
17 27 S. 66th Avenue Improvements 03 P 0.76 P PE 1/1/2017 STP(E) 86 14 100 100 CE Yes
66th Avenue 04 T RW 1/1/2018 STP(E) 173 27 200 200
from: Summitview Ave. to: Scenic Dr. W CN 1/1/2019 STP(E) 1,096 164 1,260 1,260 1/1/2019
Reconstruct and widen roadway to three lanes, install S
curb, gutter, sidewalk, storm drainage system and 0
utilities.
Totals 1,355 205 1,560 100 200 1,260
14 28 N. 40th Ave. & Summitview Ave. Intersection 12 P N/A P PE 1/1/2017 STP(U) 126 17 143 143 CE Yes
N. 40th Avenue T RW 1/1/2018 STP(U) 130 20 150 150
from: N. 40th Ave. to: Summitview Dr. W CN 1/1/2019 STP(U) 692 108 800 800 1/1/2019
Improve the intersection by constructing larger S
corner radii, lengthening the turn lanes, and 0
upgrading the traffic signal system.
Totals 948 145 1,093 143 150 800
Agency: Yakima Six Year Transportation Improvement Program
Co. No.: 39 Co. Name: Yakima Co. From 2016 to 2021
City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015
Amend Date: Resolution No.:
Project Costs in Thousands of Dollars Expenditure Schedule Federally Funded
ul `w Project Identification Fund Source Information (Local Agency) Projects Only
0 E A. PIN /Federal Aid No. B. Bridge No. c �+ c ol
F Funding R/W
co 2 C. Project Title to - d Phase g
o E v $ Federal State State Local Total Envir. Required
D. Street /Road Name or Number > . v Start Federal Fund
o E. Beginning MP or Road - Ending MP or Road
2 c = o Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd 4th Type Date
LL a F. Describe Work to Be Done E F F 5 d Phase (MM /YY)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
14 29 N. 40th Ave. & Englewood Ave. Intersection 12 P N/A P PE 1/1/2018 STP(U) 43 7 50 50 CE No
N. 40th Avenue T CN 6/1/2018 STP(U) 260 40 300 300
from: N. 40th Ave. to: Englewood
Replace traffic signal poles and upgrade controller.
Totals 303 47 350 350
14 30 N. 16th Avenue & Fruitvale Blvd. 1/5 12 P N/A P PE 1/1/2017 STP(U) 126 18 144 144 CE Yes
N. 16th Avenue T RW 1/1/2018 STP(U) 173 27 200 200
from: N. 16th Ave. to: Fruitvale Blvd. 0 CN 1/1/2019 STP(U) 400 62 462 462 1/1/2019
Improve the intersection by constructing larger curb S
radii, installing ADA ramps, and upgrading the traffic W
signal system.
Totals 699 107 806 144 200 462
17 31 Rudkin Road Reconstruction 03 P 0.76 P PE 1/1/2017 STP(C) 109 27 136 136 CE No
Rudkin Road 06 T CN 1/1/2018 STP(C) 945 TPP 945 106 1,996 1,996
from: E. Viola Ave. to: Rainier PI. W
S
Reconstruct roadway, install curb, gutter, sidewalk
and storm drainage. Partner with Union Gap to
install additional sewer force main.
Totals 1,054 133 2,132 136 1,996 0
16 32 E. Mead Avenue Reconstruction 03 P 0.76 P PE 1/1/2018 STP(S) 122 TPP 23 7 152 152 CE No
E. Mead Avenue 06 T CN 1/1/2019 STP(S) 1,730 TPP 206 70 2,006 2,006
from: Rudkin Rd. to: Fair Ave. S
Partner with Union Gap to reconstruct E. Mead C
Avenue, install curb, gutter, sidewalk and storm G
drainage system. 0
Totals 1,852 229 77 2,158 152 2,006
Agency: Yakima Six Year Transportation Improvement Program
Co. No.: 39 Co. Name: Yakima Co. From 2016 to 2021
City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015
Amend Date: Resolution No.:
Project Costs in Thousands of Dollars Expenditure Schedule Federally Funded
ul `w Project Identification Fund Source Information (Local Agency) Projects Only
0 E A. PIN /Federal Aid No. B. Bridge No. c �+ c ol
F Funding R/W
co 2 C. Project Title to - d Phase g
o E v $ Federal State State Local Total 4th Envir. Required
D. Street /Road Name or Number > . v Start Federal Fund
c . 6 E. Beginning MP or Road - Ending MP or Road
2 a ., :° « o Code Cost by Fund C Funds Funds Funds 1st 2nd 3rd Thru Type Date
m
LL a E F. Describe Work to Be Done F F 5 d Phase 6th (MM /YY)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
17 33 S. 80th Avenue Improvements 04 P 1.30 P PE 1/1/2019 AIP 131 20 151 151 CE Yes
S. 80th Avenue T RW 1/1/2020 AIP 382 59 441 441
from: Tieton Drive to: Zier Road 0 CN 1/1/2021 AIP 1,667 260 1,927 1,927 1/1/2021
S
Widen roadway to three lanes, install curb, gutter, W
sidewalk, street lighting and storm drainage system. C
Totals 2,180 339 2,519 2,519
17 34 Englewood Avenue Improvements 05 P 1.00 P PE 1/1/2019 STP(C) 272 43 315 315 CE Yes
Englewood Avenue 06 T RW 1/1/2020 STP(C) 349 55 404 404
from: N. 40th Ave. to: N. 56th Ave. W CN 1/1/2021 STP(C) 2,352 340 2,692 2,692 1/1/2021
S
Widen roadway to three lanes, install curb, gutter, 0
sidewalk, street lighting and storm drainage system. C
Totals 2,973 438 3,411 3,411
17 35 Englewood Avenue Improvements 05 P 0.50 P PE 1/1/2019 STP(U) 136 21 157 157 CE Yes
Englewood Avenue 06 T RW 1/1/2020 STP(U) 173 27 200 200
from: N. 16th Ave. to: N. 24th Ave. W CN 1/1/2021 STP(U) 1,164 182 1,346 1,346 1/1/2021
S
Widen roadway to three lanes, install curb, gutter,
sidewalk, street lighting and storm drainage system.
Totals 1,473 230 1,703 1,703
14 36 Nob Hill Boulevard Sidewalk Improvements 12 P 2.50 P PE 1/1/2019 STP(S) 55 8 63 63 CE Yes
Nob Hill Boulevard T RW 1/1/2020 STP(S) 107 19 126 126
from: S. 16th Ave. to: S. 6th Street S CN 1/1/2021 STP(S) 321 57 378 378 1/1/2021
Construct sidewalk in locations where it doesn't exist W
on the south side of Nob Hill
Totals 483 84 567 567
Agency: Yakima Six Year Transportation Improvement Program
Co. No.: 39 Co. Name: Yakima Co. From 2016 to 2021
City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015
Amend Date: Resolution No.:
Project Costs in Thousands of Dollars Expenditure Schedule Federally Funded
ul `w Project Identification Fund Source Information (Local Agency) Projects Only
0 E A. PIN /Federal Aid No. B. Bridge No. c - �+ o Fe Funding R/W
2 C. Project Title E to - d Phase
o v v $ Federal State State Local Total 4th Envir. Required
D. Street /Road Name or Number > . u Start Federal Fund
c b E. Beginning MP or Road - Ending MP or Road
2 a ' :° « o Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd Thru Type Date
m
LL a E F. Describe Work to Be Done F F 5 d Phase 6th (MM /YY)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
14 37 N. 34th Ave. & Fruitvale Blvd. 1/5 Improvements 12 P N/A P PE 1/1/2018 STP(U) 63 5 68 68 CE Yes
Fruitvale Boulevard T RW 1/1/2019 STP(U) 87 13 100 100
from: Fruitvale Blvd. to: N. 34th Ave. 0 CN 1/1/2020 STP(U) 567 76 643 643 1/1/2020
S
Improve intersection by installing a traffic signal W
system, curb, gutter and sidewalk. Widen leg south
of Fruitvale to inlcude a left -turn lane
Totals 717 94 811 68 743
17 38 Englewood Avenue Improvements 03 P 1.00 P PE 1/1/2019 STP(U) 218 34 252 252 CE Yes
Englewood Avenue 05 T RW 1/1/2020 STP(U) 327 51 378 378
from: N. 24th Ave. to: N. 40th Ave. 06 W CN 1/1/2021 STP(U) 2,980 244 3,224 3,224 1/1/2021
S
Reconstruct and widen roadway to three lanes, install 0
curb, gutter, sidewalk, street lighting and storm
drainage system. Install sewer and water lines.
Totals 3,525 329 3,854 3,854
14 39 North /South Connector to West Valley 01 P 6.00 P PE 1/1/2018 STP(U) 432 68 500 500 CE Yes
Unknown Road 04 T
from: Ahtanum Rd. to: Summitview Ext. 06 W
S
Corridor study to determine the best location for a C
north /south limited access route in West Valley. City G
and County joint project. 0
Totals 432 68 500 500
14 40 18th Street Underpass 12 P N/A P PE 1/1/2017 BRAC 240 60 300 300 CE No
Yakima Avenue T CN 1/1/2018 BRAC 2,288 572 2,860 2,860
from: Yakima Ave. to: 18th Street 0
Replace the bridge on E. Yakima Avenue that crosses S
over 18th Street. W
Totals 2,528 632 3,160 300 2,860
Agency: Yakima Six Year Transportation Improvement Program
Co. No.: 39 Co. Name: Yakima Co. From 2016 to 2021
City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015
Amend Date: Resolution No.:
Project Costs in Thousands of Dollars Expenditure Schedule Federally Funded
ul `w Project Identification Fund Source Information (Local Agency) Projects Only
0 E A. PIN /Federal Aid No. B. Bridge No. c - �+ o Fe Funding R/W
2 C. Project Title E to - d Phase
o v v $ Federal State State Local Total 4th Envir. Required
D. Street /Road Name or Number > u Start Federal Fund
c b E. Beginning MP or Road - Ending MP or Road 2 r 0. ' 7, « o Code Cost by Fund Code Fu Funds Funds 1st 2nd 3rd Thru Type Date
m
LL a E F. Describe Work to Be Done F F 5 d Phase 6th (MM /YY)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
17 41 88th Avenue Improvements 06 P 0.48 P PE 1/1/2018 STP(U) 43 7 50 50 CE Yes
88th Avenue 12 T RW 1/1/2019 STP(U) 52 8 60 60
from: Tieton Dr. to: Summitview Ave. C CN 6/1/2019 STP(U) 285 45 330 330 6/1/2019
G
Construct curb, gutter, sidewalk and storm drainage
system on the east side of 88th Avenue.
Totals 380 60 440 50 390
17 42 64th Avenue Improvements 03 P 1.00 P PE 1/1/2018 STP(U) 200 32 232 200 CE No
64th Avenue 04 T CN 1/1/2019 STP(U) 1,600 249 1,849 1,849
from: Washington Ave. to: Nob Hill Blvd. 06 W
C
Widen roadway to three lanes, install curb, gutter, G
sidewalk, street lighting and storm drainage system. 0
Totals 1,800 281 2,081 200 1,849
14 43 North 1st Street Revitalization 06 P 0.98 P RW 1/1/2016 TIGER 100 100 100 CE Yes
N. 1st Street 12 T CN 1/1/2017 TIGER 8,000 8,000 8,000
from: MLK Blvd. to: 'N'Street G 1/1/2017
C
Improve North 1st Street by rehabilitating the
pavement and lane markings, removing on- street
parking, enhancing street and pedestrian lighting,
constructing median islands and installing various
pedestrian and decorative elements.
Totals 8,100 0 8,100 100 8,000
19 44 NorthsideAlleyPaver 07 S 3.5 P CN 1/1/2015 CMAQ 353 57 410 410 CE No
Alleys between Folsom Ave. and Fruitvale Blvd. T
from: 16th Avenue to: 6th Avenue C
Improve the air quality throughout this section of the 0
City by paving gravel alleys.
Totals 353 57 410 410
Agency: Yakima Six Year Transportation Improvement Program
Co. No.: 39 Co. Name: Yakima Co. From 2016 to 2021
City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015
Amend Date: Resolution No.:
Project Costs in Thousands of Dollars Expenditure Schedule Federally Funded
ul `w Project Identification Fund Source Information (Local Agency) Projects Only
0 E A. PIN /Federal Aid No. B. Bridge No. c �+ o Funding Federal Fundin R/W
2 C. Project Title E - �n - d Phase
o E v $ Federal State State Local Total 4th Envir. Required
D. Street /Road Name or Number > . v Start Federal Fund
c p E. Beginning MP or Road - Ending MP or Road 2 r o. ' : ° « 5 Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd Thru Type Date
m
LL a E F. Describe Work to Be Done F F 5 d Phase 6th (MM /YY)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
17 45 S. 80th Avenue Bridge 09 S 0.05 P PE 1/1/2016 DOE 25 0 25 25 CE
S. 80th Avenue T CN 1/1/2017 DOE 75 0 75 75
from: Wide Hollow Rd. to: PlathAve. 0
Replace existing two -lane bridge over Wide Hollow
Creek with three -lane bridge. The City's involvement
is only to pass through of an Ecology grant in
conjunction with the County's flood plain
management project.
Totals 0 100 25 75
17 46 Wide Hollow Road Bridge 9 S 0.05 P PE 1/1/2016 DOE 25 25 25 CE No
Wide Hollow Road T CN 1/1/2017 DOE 75 75 75
from: 89th Avenue to: 88th Avenue 0
Replace existing two -lane bridge over Wide Hollow
Creek with three -lane bridge. The City's involvement
is only to pass through of an Ecology grant in
conjunction with the County's flood plain
management project.
Totals 100 25
16 47 Lincoln Avenue Corridor Safety Improvements 07 S N/A P CN 1/1/2016 HSIP 300 0 300 300 CE Yes
Lincoln Avenue T
from: N. 32nd Ave. to: N. 5th Ave. 0 1/1/2016
Improve safety by installing larger signal lenses,
installing ADA compliant ramps, repairing damaged
sidewalk, installing new sidewalk, installing overhead
school flashers, etc.
Totals 0 300 300
14 48 16th Avenue Corridor Improvement 04 P 3.50 P PE 1/1/2018 STP(U) 120 17 137 137
16th Avenue T
from: SR 12 to: Washington Ave. W
C
Study to determine strategies for improving the 16th G
Avenue corridor n
Totals 120 17 137 137
Agency: Yakima Six Year Transportation Improvement Program
Co. No.: 39 Co. Name: Yakima Co. From 2016 to 2021
City No.: 1485 MPO /RTPO: YVCOG Hearing Date: 6/2/15 & 6/16/15 Adoption Date: 6/16/2015
Amend Date: Resolution No.:
Project Costs in Thousands of Dollars Expenditure Schedule Federally Funded
ul `w Project Identification Fund Source Information Projects Only
U E A. PIN /Federal Aid No. B. Bridge No. ,� (Local Agency)
s „ m Federal Funding R/W
z C. Project Title E to -o d Phase
IF, as v ° Federal State State Local Total 4th Envir. Required
D. Street /Road Name or Number > 3 Start Federal Fund
c '6 E. Beginning MP or Road - Ending MP or Road a a 2 : ° o Code Cost by Fund Code Funds Funds Funds 1st 2nd 3rd Thru Type Date
LL a F. Describe Work to Be Done E . "' C 5 d Phase 6th (MM /YY)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
14 49 40th Avenue Corridor Improvements 04 P 3.20 P PE 1/1/2018 STP(U) 120 17 137 137
40th Avenue T
from: SR 12 to: Washington Ave. W
C
G
Study to determine strategies for improving the 40th 0
Avenue corridor. S
Totals 17 137 137
14 50 Nob Hill Boulevard Corridor Improvements 03 P 2.70 P PE 1/1/2018 STP(U) 120 17 137 137
Nob Hill Boulevard 04 T
from: 1 -82 to: 16th Ave. 0
S
W
Study to determine strategies for improving the Nob C
Hill Boulevard corridor. G
Totals 120 17 137 137
14 51 S. 1st Street /Main Street Corridor Improvements 01 P 2.00 P PE 1/1/2018 STP(U) 120 17 137 137
S. 1st Street /Main Street T
from: Nob Hill Blvd. to: Barker Mill Bridge 0
Joint project with Union Gap. Stucy to determine S
strategies for improving the 1st Street /Main Street W
corridor. C
Totals 120 17 137 137
16 52 E. 'H' Street Extension, Ph. 2 01 P 0.55 P PE 1/1/2016 STP(U) 432 68 500 500 CE Yes
E. 'H' Street 08 T RW 1/1/2017 STP(U) 432 68 500 500
from: 10th Street to: 1 -82 W CN 1/1/2018 STP(U) 2,162 338 2,500 2,500 1/1/2018
Construct new roadway including water, sewer, curb, S
gutter, sidewalk, street lighting and storm drainage
system.
0 474 3,500 500 500 2,500 0
9. Appendices
A. Six Year Form Instructions
Heading
Agency Enter name of the sponsoring agency.
County Number Enter the OFM assigned number (see LAG Appendix 21.44).
City Number Enter the OFM assigned number (see LAG Appendix 21.45).
MPO /RTPO Enter the name of the associated MPO (if located within urbanized area) or
RTPO (if located in a rural area).
Hearing Date Enter the date of the public hearing.
Adoption Date Enter the date this program was adopted by council or commission.
Resolution Number Enter Legislative Authority resolution number (if applicable.)
Amendment Date Enter the date this program was amended by council or commission.
Column Number
1. Functional Classification. Enter the appropriate 2 -digit code denoting the Federal
Functional Classification. (Note: The Federal Functional Classification must be
approved by FHWA.)
Description
00- No Classification
Rural (Under 5000 pop.) Urban (Over 5000 pop.)
01 - Interstate 11- Interstate
02 - Principal Arterials 12- Freeways & Expressways
06 - Minor Arterials 14- Other Principal Arterials
07 - Major Collector 16- Minor Arterial
08 - Minor Collector 17- Collector
09 - Local Access 19- Local Access
1. Priority Numbers. Enter local agency number identifying agency project priority
(optional).
2. Project Identification. Enter (a) Federal Aid Number if previously assigned; (b)
Bridge Number; (c) Project Title; (d) Street /Road Name or Number /Federal Route
Number; (e) Beginning and Ending Termini (mile post or street names); and (f)
Describe the Work to be Completed.
3. Improvement Type Codes. Enter the appropriate federal code number.
Description
01- New construction on 07 - Resurfacing 14 - Bridge Program - Special
new alignment 08 - New Bridge Construction 21 - Transit Capital Project
02- Relocation 09- Bridge Replacement 22- Transit Operational
Project
03- Reconstruction 10 - Bridge Rehabilitation 23 - Transit Planning
04- Major Widening 11 - Minor Bridge Rehabilitation 24 - Transit Training /Admin.
05- Minor Widening 12 - Safety /Traffic Operation /TSM 31- Non Capital Improvement
06- Other Enhancements 13 - Environmentally Related 32 - Non Motor Vehicle Project
25
5. Funding Status. Enter the funding status for the entire project which describes the
current status.
S - Project is selected by the appropriate selection body and funding has
been secured by the lead agency.
P - Project is subject to selection by an agency other than the lead and is
listed for planning purposes. (Funding has not been determined.)
6. Total Length. Enter project length to the nearest hundredth (or code "00" if not
applicable).
7. Utility Code(s). Enter the appropriate code letter(s) for the utilities that would
need to be relocated or are impacted by the construction project.
C - Cable TV G - Gas
O - Other P - Power
S - Sewer (other than agency- owned) T - Telephone
W - Water
8. Project Phase. Select the appropriate phase code of the project.
PE - Preliminary Engineering only (or Planning)
RW - Right of Way or land acquisition only (or equipment purchase)
CN - Construction only (or transit operating)
ALL - All Phases: from Preliminary Engineering through Construction
9. Phase Start Date. Enter the month/day/year in MM /DDIYY format that the
selected phase of the project is actually expected to start.
10. Federal Fund Code. Enter the Federal Fund code from the table.
F TA Discretionary for Capital Expenditures
BIA - Bureau of Indian Affairs 5307 - FTA Urban Areas
BR - Bridge Replacement or Rehab. 5309(Bus)- Bus
CDBG - Community Development 5309(FG) - Fixed Guideways
Block Grant (HUD) 5309(NS) - New Starts
CMAQ - Congestion Mitigation Air Quality 5310 - FTA Elderly /Disabled
DEMO - ISTEA Demo Project (Selected) 5311 - FTA Rural Areas
Discretionary - Ferry Boat Discretionary, Public REV - Rural Economic Vitality Program
Lands Highways, or Scenic Byways STP(C) - STP Statewide Competitive Program
DOD - Dept. of Defense STP(E) - STP Transportation Enhancements
IC - Interstate Construction STP(S) - STP Safety Including Hazard and RR
IM - Interstate Maintenance STP(R) - STP Rural Regionally Selected
NHS - National Highway System STP(U) - STP Urban Regionally Selected
STP - WSDOT use only
11. Federal Funds. Enter the total federal cost (in thousands) of the phase
regardless of when the funds will be spent.
12. State Fund Code. Enter the appropriate code for any of the listed state funds
to be used on this project.
26
CAPP - County Arterial Preservation Program PWTF - Public Works Trust
CHAP - City Hardship Assistance Program RAP - Rural Arterial Program
TPP - Transportation Partnershis Program SCP - Small City Program
AIP - Arterial Improvement Program WSDOT - WSDOT funding
PSMP - Pedestrian Safety & Mobility Program OTHER - All other unidentified state funding
PTST - Public Transportation Systems Progra
13. State Funds. Enter all funds from the State Agencies (in thousands) of the phase
regardless of when the funds will be spent.
14. Local Funds. Enter all the funds from Local Agencies (in thousands) of the phase
regardless of when the funds will be spent.
15. Total Funds. Enter the sum of columns 10, 12, and 14. (Auto- calculation in the "STIP
Too" program.)
16 -19. Expenditure Schedule - (1st, 2nd, 3rd, 4th thru 6th years). Enter the estimated
expenditures (in thousands) of dollars by year. (This data is for Local Agency use.)
20. Environmental Data Type. Enter the type of environmental assessment that will be
required for this project. (This is "required" for Federally funded projects, but may be
filled in for state or locally funded projects.)
EIS - Environmental Impact Statement
EA - Environmental Assessment
CE - Categorical Exclusion
21. RAN Certification. Click Y if Right of Way acquisition is required. If yes, Enter R/W
Certification Date, if known. (This is "required" for Federally funded projects only.)