Item No. 6.E.
For Meeting of: June 7, 2022
ITEM TITLE: Project Completion and Contract Acceptance for Total Site
Services LLC - E Viola Ave Waterline Replacement Project
AC2503
SUBMITTED BY: Scott Schafer, Director of Public Works
David Brown,Assistant Director of Public Works
Mike Shane, Water/Irrigation Engineer
SUMMARY EXPLANATION:
E Viola Ave Water System Improvements Projects AC2503 and RT2564. The City of Yakima
owns, operates, and maintains the domestic water supply and distribution system which
had undersized waterlines on East Viola Avenue between S Fair Avenue and Rudkin Road with
lower flow and water quality than is recommended. This project replaced the aging 6-inch
waterline on East Viola Avenue with a new 12-inch ductile iron waterline including new valves, fire
hydrants, and water service connections; followed by the completion of a road surface
replacement.
Final inspection for this project was made with substantial completion established on November 15,
2021. The recommendation is that the project be accepted. A final payment of$59,758.98 (5%
retainage) is due from the City to Total Site Services LLC for the completion of this project.
Project Manager: Mike Shane
Contractor: Total Site Services LLC
Contract Awarded on: 6/2/2021
Contract Cost: $1,243,129.59
Retainage Due: $59,758.98
The total contract cost is for construction only and does not include engineering and other costs. City
Council action is required to accept the project and approve the final construction costs.
ITEM BUDGETED: Yes
STRATEGIC PRIORITY: Neighborhood and Community Building
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
2
RECOMMENDATION:
Accept Project
ATTACHMENTS:
Description Upload Date Type
❑ Final 4(7/2022 Backup Material
3
44 IL. LA
Mr Engineering and Land Surveying,Inc.
March 30, 2022
City of Yakima
Water & Irrigation Division
2301 Fruitvale Boulevard
Yakima, WA 98902
Attn: Mr. Mike Shane
Re: City of Yakima
E. VIOLA AVE. WATER SYSTEM IMPROVEMENTS
CITY OF YAKIMA PROJECT NO. AC2503
PWB PROJECT NO. PC20-96103-044
HLA Project No.: 20147
Dear Mr. Shane:
The City of Yakima has remitted payment to Total Site Services, LLC (TSS) for the final progress
estimate on 3/24/2022 via Check Number 182399. The remainder due to TSS is retainage
withheld in the amount of $59,758.98.
Attached, please find the previously submitted and paid Progress Estimate No. 7 & Final for the
project. As stated in our March 2, 2022 letter, it is recommended that the City of Yakima
unilaterally establish March 28, 2022 as the completion date for the project and move forward
with project acceptance and closeout.
Once the City of Yakima accepts the project as complete and the contractor submits their Affidavit
of Wages Paid with the Dept. of Labor and Industries, the Notice of Completion can be filed. Once
the necessary lien releases have been received from the Washington State Dept. of Labor &
Industries, Dept. of Revenue, and Employment Security Dept., the City shall release the retained
amount to TSS within 60-days of receipt of the final release.
Please notify our office and forward a copy of the Council resolution once the project is accepted
as complete. If you have any questions, please let us know.
Very truly yours,
Terry D. Alapeteri, PE
TDA/asr
Enclosures
Copy: Ryan Bleek, City of Yakima
Dave Brown, City of Yakima
Mike Battle, Angie Ringer, Dennis Perala, Benji Martin, HLA
G.\PROJECTS\2020\20147C\13.PROJECT CLOSEOUT\2022-03-30-20147C-Recommendation of Project Acceptance.docx
2803 River Road ❖ Yakima,WA 98902 •:• 509.966.7000 FAX 509.965.3800 • www.hlacivil.com
4
I I I 0+ LA
. 11
Engineering and Land Surveying,Inc.
November 24, 2021
Total Site Services, LLC
2780 Salk Avenue
Richland, WA 99354
Attn: Shannon Toranzo
Re: City of Yakima
EAST VIOLA AVENUE WATER SYSTEM IMPROVEMENTS
City of Yakima Project No: AC2503
PWB Project No.: PC20-96103-044
HLA Project No.: 20147C
Substantial Completion
Dear Shannon:
The work on this project was substantially completed on November 15, 2021. The City of Yakima
has full use of the project from operational and safety standpoints. However, not all contract work
is complete.
Please expedite completion of all remaining items and contract documentation including, but not
limited to; approved Affidavits, as-built drawings, and punch list completion, to allow us to close
the project as soon as possible.
Please call me at (509) 966-7000, should you have any questions.
Very truly yours,
je4wic;
Terry D. Alapeteri, PE
TDA/jld
Cc: Mike Shane, City of Yakima
Benji Martin, Dennis Perala, HLA
\\fs02\General\PROJECTS\2020\20147C\13.PROJECT CLOSEOUT\2021-11-24-20147C-Substantial Completion 11.15.docx
2803 River Road •:• Yakima,WA 98902 •:• 509.966.7000 •:• FAX 509.965.3800 www.hlacivil.com
5
City of Yakima Water&Irrigation Division E.VIOLA AVE.WATER SYSTEM IMPROVEMENTS-S.FAIR AVE.TO RUDKIN ROAD
2301 Fruitvale Boulevard PWB Project No. PC20-96103-044
Yakima,WA 98902 HLA Project No: 20147C
City of Yakima Project No.: AC2503
TO: Total Site Services,LLC Progress Estimate No.: 7 and Final
2780 Salk Avenue
Richland,WA 99354 Date: December 31,2021
item Contract Unit Estimate 7 Quantity Contract
No. Description Unit Quantity Price Quantity to Date Amount Quantity
1 Minor Change FA 1 $75,947.52 $42,008.22 $75,947.52 $ 75,947.52 380%
2B Mobilization-Alternate B LS 1 $60,452.41 100% $ 60,452.41 100%
3B Project Temporary Traffic Control-Alternate B LS 1 $27,041.81 100% $ 27,041.81 100%
4 Removal of Structures and Obstructions LS 1 $26,000.75 100% $ 26,000.75 100%
5 Crushed Surfacing Base Course TON 1,950 $24.87 -726.53 1,402.09 $ 34,869.98 72%
6B Crushed Surfacing Top Course-Alternate B TON 540 $23.95 31.77 113.11 $ 2,708.98 21%
7B HMA Cl.1/2-Inch PG 84-28-Alternate B TON 2,400 $91.80 2,432.32 $ 223,286.98 101%
8B Adjust Manhole-Alternate B EA 18 $617.85 7 $ 4,324.95 39%
9 Shoring or Extra Excavation LF 4,710 $2.22 4,791 $ 10,636.02 102%
10 Select Backfill,as Directed CY 700 $49.25 372 58 809.24 $ 39,855.07 116%
11 D.I.Pipe for Water Main 12 In.Diam. LF 2,540 $92.26 2,719 $ 250,854.94 107%
12 D.I.Pipe for Water Main 8 In.Diam. LF 2,070 $65.47 2,007 $ 131,398.29 97%
13 D.I.Pipe for Water Main 6 In.Diem. LF 100 $131.23 65 $ 8,529.95 65%
14 Butterfly Valve 12 In. EA 20 $2,285.68 20 $ 45,713.60 100%
15 Gate Valve 8 In. EA 20 $1,461.93 20 $ 29,238.60 100%
16 Remove Water Valve EA 4 $651.85 5 $ 3,259.25 125%
17 Abandon Water Valve EA 19 $205.99 19 $ 3,913.81 100%
18 Adjust Valve Box EA 6 $657.00 5 $ 3,285.00 83%
19 Hydrant Assembly EA 2 $11,083.67 2 $ 22,167.34 100%
20 Remove Existing Hydrant EA 1 $835.09 1 $ 835.09 100%
21 Service Connection 1-1/2 In.Diam. EA 1 $6,126.09 1 $ 6,126.09 100%
22 Service Connection 3/4 In.Diem. EA 63 $1,839.95 66 $ 121,436.70 105%
23 Casing Pipe in Place,18 In.Diam. EA 100 $216.61 140 $ 30,325.40 140%
24 Erosion/Water Pollution Control FA 1 $5,000.00 $214.67 $ 214.87 4%
25 Cement Conc.Traffic Curb and Gutter LF 13 $129.06 40 $ 5,162.40 308%
26 Cement Concrete Sidewalk,4-Inch Thick SY 15 $149.65 19.13 $ 2,862.80 128%
27 Controlled Density Fill CY 150 $168.24 147 $ 24,731.28 98%
i
O:IPROJECTSO02012Ot17C11U.PROGRESS ESTIMATES\PROG EST NOT-FINAU 2021.12-31-]°laic-PROS EST NO 7 E Tale1-Re,02.02.1022
6
City of Yakima Water&Irrigation Division E.VIOLA AVE.WATER SYSTEM IMPROVEMENTS-S.FAIR AVE.TO RUDKIN ROAD
2301 Fruitvale Boulevard PWB Project No. PC20-96103-044
Yakima,WA 98902 HLA Project No.: 20147C
City of Yakima Project No.: AC2503
TO: Total Site Services,LLC Progress Estimate No.: 7 and Final
2780 Salk Avenue
Richland,WA 99354 Date: December 31,2021
SUBTOTAL,WORK TO DATE $ 1,195,179.68
PLUS MATERIALS ON HAND $ -
SUBTOTALAMOUNTS $ 1,195,179.68
8.3%STATE SALES TAX $ 99,199.91
TOTAL $ 1,294,379,59
LESS TOTAL RETAINAGE $ 59,758.98
LESS AMOUNTS PREVIOUSLY PAID $ 1,138,900.11
LESS CUMULATIVE LIQUIDATED DAMAGES $ 51,250.00
AMOUNT NOW DUE $ 44,470.50
Progress Estimate Breakdown Sub-Total Sales Tax Total Retainage Payment Due Liquidated Net Pmt.Due
Damages
Progress Estimate No.1: $ 146,829.13 $ 12,186.82 $ 159,015.95 $ (7,341.46) $ 151,674.49
Progress Estimate No.2: $ 273,086.63 $ 22,666.19 $ 295,752.82 $ (13,654.33) $ 282,098.49
Progress Estimate No.3: $ 158,652.03 $ 13,168.12 $ 171,820.15 $ (7,932.60) $ 163,887.55
Progress Estimate No.4: $ 289,723.10 $ 24,047.02 $ 313,770.12 $ (14,486.15) $ 299,283.96
Progress Estimate No.5: $ 171,610.36 $ 14,243.66 $ 185,854.02 $ (8,580.52) $ 177,273.50 $ (26,650.00) $ 150,623.50
Progress Estimate No.6: $ 112,228.58 $ 9,314.97 $ 121,543.55 $ (5,611.43) $ 115,932.12 $ (24,600.00) $ 91,332.12
Progress Estimate No.7 and Final: $ 43,049.85 $ 3,573.14 $ 46,622.99 $ (2,152.49) $ 44,470.50
I hereby certify that the foregoing is a true and correct statement of the work performed under this Contract.
Mi Shane,City of Yakima Terry D.Alapeteri,PE
ACCEPTED:
I hereby accept the Final Progress Estimate and Final Contract Voucher Certification,in accordance with Section 1-09.9 of the
WSDOT Standard Specifications.
Total Site Services,LLC Date