HomeMy WebLinkAbout02/17/2015 05B 2014 4th Quarter Strategic Plan Monitoring ReportITEM TITLE:
SUBMITTED BY:
SUMMARY EXPLANATION:
See attached.
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 5.B.
For Meeting of: February 17, 2015
2014 4th Quarter Strategic Plan Monitoring Report.
Tony O'Rourke, City Manager
Resolution: Ordinance:
Other (Specify):
Contract: Contract Term:
Start Date: End Date:
Item Budgeted: Amount:
Funding Source/Fiscal Impact:
Strategic Priority:
Insurance Required? No
Mail to:
Phone:
APPROVED FOR
SUBMITTAL:
RECOMMENDATION:
ATTACHMENTS:
Description
City Manager
Upload Date
0 2014 Year end monitoring report 2/1111/20115
0 plan 2/1111/20115
0 plan 2 2/1111/20115
Type
Cover Memo
Cover Memo
Cover Memo
ECONOMIC DEVELOPMENT
Strategy
Department
1st Quarter Progress Report
2nd Quarter Progress Report
3rd Quarter Progress Report
4th Quarter Progress Report
1
Collaborate with Downtown
businesses through a Downtown
Master Plan
Economic
Development
City staff worked closely with a number of
downtown businesses on a variety of projects
including designs for a potential downtown
plaza, new events, tenant recruitment and
beautification issues
City staff worked closely with downtown
businesses on a variety of projects including
designs for a potential downtown plaza, new
events, tenant recruitment, beautification, and
parking.
The staff worked with various downtown
businesses on an application to the
Washington State Main Street program to
become a certified Main Street program.
The City Council submitted a letter of support
in the final application for the Downtown
Association of Yakima's certification. The
application was due in mid December.
2
Determine the best location for a
public plaza for community events and
activities
Economic
Development
City staff worked with an Implementation
Team, Gustafson, Guthrie, Nichol and Carl
Walker Inc. on designs for a potential public
plaza and updates to our overall downtown
parking system.
City staff continued working with the
Implementation Team, Gustafson, Guthrie,
Nichol and Carl Walker Inc. on designs for a
potential public plaza and updates to our
overall downtown parking system.
The south location and option Y -A was chosen
by the Yakima City Council as the best design
for this project.
The 2015 City budget included funds to create,
design and construct the project.
B
Attend and promote Yakima at the
International Council of Shopping
Centers annual conference in Las Vegas
Economic
Development
Planned booth design and community
promotional brochures for the RECON 2014
conference.
A four -person team (Sean Hawkins, Verlynn
Best, Liz McGree and Tom Dittmar) attended
the RECON 2014 show in Las Vegas from May
17-21.
Follow up requested materials were mailed to
a variety of contacts made at the 2014 event.
A team of Council members and staff will
attend the International Council of Shopping
Centers conference in May of 2015.
4
Produce Lunchtime Live and
Downtown Summer Nights concert
series in 2014; invest in new events
Economic
Development
Planned, booked and developed promotional
materials for the Downtown Summer Nights
concert series, Lunchtime Live and the Blues
and Brews event. Worked closely with
Townsquare Media, Radio Yakima, the North
Front Street Association and the Seasons to
successfully put these events together.
Downtown Summer Nights began its new
season on Thursday, June 12 and ran through
Aug 21. A few of the shows topped the 1,000
attendance mark and event revenue was up
67% over the first four shows. A new event on
Front Street, the Yakima Blues and Local Blues
Bash, drew 1,485 people for its inaugural year.
Downtown Summer Nights finished strong with
crowds ranging from 700-1000 each night all
summer long - even in the rain. Lunchtime Live
was down and will need to be reformatted for
2015.
The City's partnership with the Fresh Hop Ale
Festival helped bring 6,000 - 7,000 people to
the 2014 event. The City Council approved a
2015 budget that allows our newly produced
events to continue along with new events for
2015.
Form a public-private partnership to
market and promote air service and
secure a fourth flight to Seattle
Airport/
Airport staff, in conjunction with Economic
Development Manager and Idea Marketing,
developed a variety of tools to enhance the
marketing project for the Yakima Air Terminal.
These tools included the development of a new
website, www.flyykm.com, to help promote air
service in the Yakima Valley, Free Wifi in the
terminal to provide passengers both the
convenience of high speed Internet and
Launched new flyykm.com website as well as
initiated radio, television, and newspaper
advertisements throughout the Valley.
Initially, airport enplanements have increased
to bring current load factors up 4 percentage
points compared to previous year's figures.
Continued advertising air service at the Yakima
Air Terminal through a variety of media to
include radio, television, and newspapers
throughout the Valley. Airport enplanements
continue to average approximately 4-5% higher
than 2013 enplanements. The City of Yakima
applied for a Small Community Air Service
Development Grant with the U.S. Department
of Transportation in order to receive grant
The City of Yakima received notification from
the U.S. Department of Transportation of a
Small Community Air Service Development
Grant in the amount of $290,000. These funds
will be utilized to build a robust marketing
program to facilitate local advertisements
within the Yakima Valley. The airport ended
the year with a total of 57,454 enplaned
passengers, which boasted Alaska Airlines load
5
Economic
exposure to flyykm website, radio, newspaper
funds to assist with continued marketing to
factors to approximately 76%, a 5% increase
Development
and television advertising to inform residences
of air service options out of the Yakima Air
Terminal.
increase frequency of flights to Seattle as well
as an alternate destination. The requested
amount in the grant application was $290,000.
The grant announcements should be
announced in October 2014.
from 2013. A meeting with Alaska Airlines is
scheduled for early February 2015 to further
discussions on adding a fourth flight to Seattle
to accommodate the additional passenger
growth.
Replace aging asphalt, taxiway lights,
taxiway signs and airfield markings to
Airport staff, in conjunction with Huibregste,
Louman Associates, Inc., developed the
Airport Staff held three airport tenant
presentations to involve all parties who might
Airport staff, in conjunction with Huibregste,
Louman Associates, Inc., continued to develop
Airport staff, in conjunction with Huibregste,
Louman Associates, Inc., continued to develop
ensure the airport will continually
Construction Safety Phasing Plan, Preliminary
be impacted by the project. Through these
Construction Safety Phasing Plan, Preliminary
Construction Safety Phasing Plan, Preliminary
meet Federal Aviation Regulations
Engineering Plans, Preliminary Design Report,
Pre -Design Conference Checklist, and
meetings we were able to collect valuable
information and incorporate them into the
Engineering Plans, Preliminary Design Report,
Pre -Design Conference Checklist, and
Engineering Plans, Preliminary Design Report,
Pre -Design Conference Checklist, and
Construction Management Report. Through
construction plans. Proposed runway closure
Construction Management Report. Plans were
Construction Management Report. Plans were
close coordination with the Federal Aviation
schedule was distributed to various Federal
developed and submitted upon reaching 95%
revised in accordance with Federal Aviation
Administration, we were able to construct
Aviation Administration departments for their
completion for the Federal Aviation
Administration's feedback of which 100% plans
these plans to 60% completion while holding
review and feedback. Airport staff, in
Administration's review. In addition to the
will be submitted for approval in first quarter
various meetings with specific FAA
conjunction with Huibregste, Louman
above plans, airport staff, HLA, and the FAA
2015. Upon submission, the airport should
departments to ensure all applicable parties
Associates, Inc., continued to develop
worked closely to amend the airport's Sign and
receive FAA approval which will allow the City
6
Airport
were involved.
Construction Safety Phasing Plan, Preliminary
Engineering Plans, Preliminary Design Report,
Pre -Design Conference Checklist, and
Marking Plan to ensure the airport's airfield
signs and markings in the proposed project
meet current FAA standards as outlined in the
to open bids the first quarter 2015. Initial
plans for start of construction in spring 2015.
Construction Management Report. Plans were
developed and submitted upon reaching90%
completion for the Federal Aviation
Administration's review.
Advisory Circulars. Airport staff and the FAA
developed the required contracts/agreements
with the various FAA divisions involved with
the project to ensure each division's services
were reimbursed under the construction grant.
7
Develop final plans for the mill site and
right of way acquisition for the Cascade
Mill Parkway
Strategic
Projects
Right-of-way acquisition for Cascade Mill
Parkway began. Negotiations were underway
with three property owners for right-of-way
purchase. Application was made for funding of
the Fair Avenue Roundabout with the TIB
agency in August.
One ROW property was purchased, two other
properties were in the negotiation process.
City will go to bid in 2015 on the Fair Avenue
Roundabout project using LIFT funds. No TIB
grant funds were available for this project.
Final alignment options for street network
were under review. Fair Avenue Roundabout
will be constructed in 2015 with SIED Funds.
$
Environmental remediation/ cleanup
of the mill site property
Strategic
Projects
The City entered the Voluntary Cleanup
Program with Department of Ecology as a
partnership process to gain approval of the
landfill cleanup and access funds. Department
of Ecology proposed $20 million in the State
Capital Budget for landfill cleanup. The City
finalized the Remedial Investigation (RI) and
the Feasibility Study is being drafted by Landau
Associates
Additional monitoring wells and test pits were
underway at the direction of DOE on the
landfill property. Landau was hired to conduct
the testing and draft the feasibility study for
cleanup. Coordination with DOE on the VCP
was ongoing.
Data collection and analysis was underway for
the landfill parcel. Landau conducted work on
the City's behalf.
9
Retain an urban economist to assist
the City in the identification of
appropriate and feasible commercial
and job creation land uses for the mill
site
Strategic
Projects
Staff from Jones, Lang, LaSalle were under
contract to conduct a Market Analysis for the
Cascade Mill. First site visit and interviews
were in May 2014. A follow-up visit is planned
for August 2014. The final report is targeted for
4`h quarter 2014.
Final draft report presented to City Council on
October 21, 2014.
Additional tasks may be requested from JLL
when the City purchases the landfill.
PUBLIC SAFETY
Strategy
Dept.
1st Quarter Progress Report
2nd Quarter Progress Report
3rd Quarter Progress Report
4th Quarter Progress Report
1
Expand the downtown bike patrol to
run from March through October
police
No bicycle patrol during winter months.
Bicycle patrol started June 9, 2014.
Bicycle patrol continued daily through the
summer months. Patrols continued into
September for First Friday and other special
downtown events.
No bike patrol during the winter months.
2
Increase training opportunities for
newly promoted employees and
leadership development
Police
Fire
Eight officers attended the FBI-LEEDA
supervisory training leadership course. Two
new sergeants attended first level supervisory
and the FBI-LEEDA executive leadership course.
An outside instructor was contracted to teach
incident management techniques to the Fire
Department. Inside and outside instructors
were utilized for leadership training.
Five additional officers were identified to
attend the FBI-LEEDA course. Lt. Pollard
attended the Senior Management in Policing
Institute course. Chief initiated monthly
mentoring meetings with junior lieutenants. A
group of senior City staff members was
coordinated to support and mentor newly-
promoted employees. In addition, 9 officers
attended the City's leadership development
course
In March 2014, an outside instructor was
contracted to teach a 16 -hour integrated
tactical accountability class to all line officers
and acting officers. This is an interactive,
scenario -based program to teach ICS,
personnel accountability and tactical decision
making. In April 2014, a 16 -hour advanced
level of this curriculum was taught to all
lieutenants, captains, and shift commanders.
Six line level leaders are enrolled in the CYU
leadership series, and another five enrolled for
the next series. An additional five members
took fire service leadership 1, 11 and 111
classes. Chief Rizzi attended the Senior
Management in Policing institute. Staff
continued to identify and send officers to the
FBI-LEEDA course. Mentoring meetings with
Chief Rizzi and the junior lieutenants
continued.
Leadership development training was ongoing.
Officers continued to be considered for the FBI -
LEEDA training. Several commissioned and non -
commissioned employees attended the
leadership training with Bill Chiatt. Fire -
Throughout 2014 and continuing into Q4,
members who hold rank and those at the
firefighter level have been approved for
advanced instruction for both local and outside
opportunities. Examples of the coursework
include Strategy/Tactics, Leadership,
Technician -Level specialties.
3
Deployment of 74 assigned police
patrol vehicles
Police
All officers eligible for an assigned vehicle
received their vehicles. Vehicle outfitting and
assignment was completed approximately
three months ahead of schedule.
Assigned police vehicle program continued
with two additional officers receiving their
assigned vehicles after passing probation.
All vehicles have been assigned.
This item is complete.
4
Invest in 8 license plate reader systems
for the Yakima Police Department to
aid in the recovery of stolen vehicles
police
Sgt. Henne continued to research ALPR
systems.
Sole source request for ALPR system was
submitted and approved by Purchasing. The
sole source request will be placed on the
agenda in August for Council approval.
ALPR was approved by the City Council and the
order was placed. Sgt. Henne found officers
interested in having the unit installed on their
vehicles. Installation is scheduled for
December 2014.
ALPR's were installed and training was
conducted in December.
5
Hire a Gang Free Initiative manager to
ensure effective public and private
sector coordination and integration of
resources
police
A candidate for the GFI director position visited
Yakima and was interviewed
Perry Tarrant accepted the position of
Emergency Preparedness and GFI Manager and
started July 1. Perry met with Councilman
Lover, GFI Consultant Steve MagaIlan, and
other City staff involved with the Council Public
Safety Committee to begin his orientation with
the City of Yakima and GFI.
Perry oversaw the City of Yakima GFI functions.
Additionally, he coordinated the City's
emergency preparedness plan and withdrawal
from the Yakima County Department of
Emergency Management.
Complete.
6
Implement second gang unit to work
gang crimes
Police
A second full gang unit was implemented in
January 2014 when the 2nd sergeant was
assigned.
The two gang units continued to operate 7
days/week. Partnerships with federal agencies
were established for the gang unit to file gang
charges federally to increase sentences for
gang crimes.
Gang units continued to operate 7 days/week
and participate in joint operations with federal
agencies to address gang crimes.
Gang units continued to operate 7 days/week
and participate in joint operations with federal
agencies to address gang crimes.
7
Increase staffing level at Yakima Fire
Department to eliminate "brown out"
days
Fire
Overtime funding has been used liberally to
maintain a policy-driven minimum daily
staffing of 20 personnel to include six, 3-person
companies, 1 dedicated ARFF and one shift
commander
Daily staffing levels were maintained at 20 per
shift. This model has proven valuable in many
aspects, yet personnel vacancies, injuries and
fire incidents have overburdened the
department's overtime funding. This was
offset with position vacancy savings.
Through the first 3 quarters of 2014, YFD
admin authorized overtime hiring
commensurate to maintaining 6 staffed and
deployable engine, truck or rescue companies.
This investment provided appropriate
emergency response capability and prevented
any apparatus deployment "Brownout"
configurations.
Throughout 2014, apparatus staffing and
deployment has been maintained so as to not
enter into a "Brownout", or staffing shortage
configuration. In doing so, overtime costs have
far-exceeded historic expenditures.
8
Separate the Communications Center /
Dispatch Center manager position into
two different positions
Info Systems
Nearly complete. Finalized some of the more
minor tasks. Will be completely separated no
later than May 1, 2014.
This process is completed. No further reporting
necessary
N/A
N/A
9
Develop a design study for the new
joint communications center that will
be located at the County-owned
Restitution Center
Police
Design study is complete. Worked on finalizing
construction documents in preparation of
going to bid. Should be ready for bid in May
2014.
Four bids ranging from $4.2-4.6 mil were
received for communication center and were
reviewed by the county project manager. Bid
award scheduled for August 2014.
Contract was awarded to T.W. Clark.
Construction on the communications center
was ahead of schedule. Estimated occupancy
date is February 20, 2015.
Construction work continued at the new
communications center. Occupancy is still
expected in early 2015.
10
Invest in a new fire brush truck in order
to better assist local agencies
Fire
A department-specific needs assessment and
equipment research was conducted.
A contract was executed to build the apparatus
using an interlocal agreement.
Cab and chassis are completed and the balance
of the build is being accomplished.
Completion and delivery of this apparatus is
anticipated to take place during February 2015.
11
Add a fulltime parking enforcement
officer dedicated to the downtown
area
Police
This position was advertised and open for
recruitment
Candidates were in the background
investigation phase of the hiring process. We
continued to have a contracted employee
provide parking enforcement services to the
downtown area.
Luis Torrico was hired September 1, 2014 to fill
the second parking enforcement officer
position.
Oversight of Parking Enforcement was
transferred to Utility Services in December.
Reduce the current misdemeanor
Pre-Filing Diversion Program and the Charging
Pre-Filing Diversion Program and the Charging
The programs have reduced the number of
The preliminary Municipal Court caseload
caseload with pre-filing diversion
Unit were implemented in 2013. The programs
Unit were implemented in 2013. The programs
case filings as anticipated by 40 percent; from
numbers indicate that the charging unit has
program and charging unit to comply
have reduced the number of case filings as
have reduced the number of case filings as
5,300 cases in 2012 to an expected 3,200 cases
reduced the caseload as anticipated; 2014
with state mandates
anticipated.
anticipated by 40 percent; from 5,300 cases in
2012 to an expected 3,200 cases in 2014.
in 2014.
caseload numbers will be in the 3,114 range
with 156 individuals participating in the Pre-
12
Legal
Filing Diversion Program. This represents a
reduction of 41% from 2012 caseload numbers,
prior to the implementation of the Charging
Unit.
PUBLIC TRUST & ACCOUNTABILITY
Strategy Department
1st Quarter Progress Report
2nd Quarter Progress Report
3rd Quarter Progress Report
4th Quarter Progress Report
Implement quality customer service
academy for all existing and new
employees
City Manager/
Employees were trained on how to teach,
instruct, and lead coworkers through a City-
sponsored customer service academy
The first customer service training courses
were offered. Over 400 employees went
through Customer Service 101 and the
Nordstrom Model of Customer Service. A
second series of customer service training will
begin third quarter of 2014.
Implemented Customer Service 201 & Conflict
Mgmt series; hired fulltime training
coordinator; launched monthly mid-level
leadership class; 36 Public Works employees
received training on the City's harassment
policy.
597 employees went through Customer Service
101; 557 employees went through Customer
Service 201. We completed 2 lunch & learns;
128 CDL holders went through drug and
alcohol training for CDL holders; organized
traffic control supervisors course for 77
employees; 183 YPD employees received
training on the City's harassment policy; 56 YFD
employees received training on the City's
1
Human
evaluation process; implemented Incident
Resources
Command System online training targeting
Public Works, YPD, Yakima Airport, Finance.
We now can verify 310 employees have
completed ICS 100; 217 employees completed
ICS 200; 268 employees completed ICS 700 and
151 employees completed ICS 800.
Conduct Yakima's third annual citizen
Preparations began for the third annual Yakima
Preparations continued for the third annual
2014 Yakima Citizen Survey questionnaires
2014 Yakima Citizen Survey results showed
survey in late spring/early summer
Citizen Survey.
Yakima Citizen Survey, which will be conducted
were mailed out to 3000 randomly selected
that the City continued to make progress in
City Manager
during the 3rd quarter of 2014.
households during the first week of
several areas identified in previous surveys as
2
Community
Relations
September. Surveys had to be returned by
October 9. Results from the survey are
expected to be available in late October.
priorities. Notably, the "excellent/good" rating
for the "overall direction Yakima is taking"
jumped from 31% in 2013 to 38% in 2014.
3
Implement new financial systems
software program (Cayenta)
Finance/
Information
Systems
Went live with the Cayenta system on
1/6/2014. Worked through post -go -live issues.
Will continue through most of the year
because of the complexity of the system.
Since ITS did not have time to honor its
commitment to provide Cognos reports for City
users, Finance stepped up to assist users
Citywide with the Cayenta report writer so they
can track their financial status and prepare for
budget. Learning curve was still present, but it
is flattening out as Cayenta makes requested
enhancements and staff get more experience.
Finance and ITS continued working on refining
Cayenta for the users. Much effort this quarter
was spent preparing the budget for 2015.
Finance assigned a temp employee to PW to
assist in the creation of needed reports. The
Cognos software was updated and we started
producing reports. After the November
conference and the training that will occur
there, these will gain momentum. Budget is
being kept up in Cayenta so that the
accountants can print and share reports with
divisions directly. Cayenta budget add-on is
flexible and easy to use. We developed budget
reports for Cindy that can be updated with new
data on the fly and without the time and
system resources of the old system. Still have
lots of work to help divisions with job cost
reporting. Goal for 4th quarter.
Process to create new year and roll data from
2014 to 2015 was underway. Reporting is still
an issue as ITS does not have time to develop
reports. We attended the Cayenta conference
and learned about a new reporting tool that
can be maintained outside of IT so that we can
complete our CAFR and develop reports for
Finance and other divisions within the Finance
Department.
4
Examine bus routes to create more
efficient services
Public Works
Route 8 was cut in accordance with Transit's 15
passenger per hour route standard. Changed
depart time from 5:10 p.m. to 5:15 p.m. to
improve passenger accessibility. Adjusted
route times for better passenger efficiency.
Union Gap was added to Bus Book to improve
continuity between the two bus systems.
Evaluated routes while looking at our quarterly
half hour counts. The Run Cutting Program has
not been a significant part of this process as of
yet. We are currently using IT to install the
electronic ADA announcements and once this
process is complete, we will turn our attention
and utilize IT's experience to install the Run
Cutting Program and get this up and running in
an effort to become more efficient.
We continued to evaluate and monitor route
changes. We sent forth the Strategic Initiatives
for the Transit Operations Specialist position
and this was approved by Civil Service. This
position will operate the Run Cutting software
and various other computer programs to
ensure our routes are as efficient and effective
as possible. Continued to utilize IT Services to
assist us with electronic ADA announcements
and other computer/tech needs.
We continued to evaluate and monitor route
changes. We also discussed and evaluated
possible route changes during our monthly
Transit meetings. We are in the process of
filling the Transit Operations Specialist position
who will operate our Run Cutting software and
various other computer programs to ensure
our routes are as efficient as possible. We also
worked with IT to install computer tablets on
buses in order to get an exact count of our
customers at every stop, thereby providing
valuable information concerning future
changes.
5
Conduct Yakima's third annual
employee survey
City Manager/
Human
Resources
City manager met with departments to review
the results from the 2013 employee survey and
answer any questions staff members had.
City manager met with departments to review
the results from the 2013 employee survey and
answer any questions staff members had.
Continued to work on department action plans
to bring up survey scores for 2014.
3rd Annual Employee Survey launched on
December 8th, 2014.
6
Establish development teams to
ensure coordinated project review
Community
Development
We continued fine tuning the DST process and
determined how the Legal Department will be
involved in addressing the limitations and legal
requirements for right-of-way acquisition and
infrastructure installation as it relates to site
specific development proposals.
A project permit coordinator was hired to help
expedite permits. Improvements in the review
process continue with emphasis on reducing
staff delays.
The project permit coordinator was hired in
September 2014.
Internal review of development projects is a
priority for Codes and Planning in 2015.
Continued to work with other divisions to
provide excellent customer service.
7
Perform a Business Process Analysis of
the Utility Services Division
Finance
Negotiated with FCS Group to compile the
second phase of BPA with a written document
outlying division policies and procedures and
started preliminary work on researching utility
billing programs.
Entered into a contract with FCS Group on
September 16 to perform 2nd phase of BPA,
assessing current policies and procedures and
work flow to produce a "needs" document to
be used to assess new billing software.
FCS Group analyzed data and should have a
draft mid February. Began process of
evaluating Cayenta Utility billing Software in
expectation of conversion to Cayenta CIS in
2nd Qtr. 2016.
PARTNERSHIP DEVELOPMENT
Strategy
Department
1st Quarter Progress Report
2nd Quarter Progress Report
3rd Quarter Progress Report
4th Quarter Progress Report
Update YPAL facility at Miller Park -
secure funding from Washington Fruit
In March 2014, Washington Fruit & Produce
announced its commitment to contribute
$250,000 to the renovation of the YPAL facility.
The facility will be renamed "Washington Fruit
Community Center". Work was ongoing and is
expected to be completed later this year.
Work on the YPAL facility is continuing. Some
minor upgrades have been completed, but
significant structural and aesthetic
improvements are still in the design stage.
Engineering specifications are written for the
renovation project and will be ready for bid by
early September. Construction is expected to
The upgrade of the facility, now known as the
Washington Fruit Community Center,
continued to make steady progress. Potential
new uses of the facility may necessitate the
revamping of renovation plans. A new sign for
the facility will be installed in either late
October or sometime in November. We
The renovation of the Washington Fruit
Community Center made some progress in the
4th quarter of 2014. Interest from other
parties regarding potential use of the facility
necessitated a revisiting of the renovation
plans. Phase 1 of the renovation plan is
expected to kick into high gear in 2015.
1
City Manager
start late September
received the project drawings on 10/10/14.
The print shop is putting the packets together
and three contractors off the small works
roster have been invited to a site review on
10/22/14. Construction is expected to start
mid November.
Partner with the Southeast Community
The Southeast Community Center (SECC)
The three large and potentially dangerous
Water was discovered under the Southeast
A request was made by Scott Schafer, Director
Center in upgrading existing facility
Advisory Committee met for its quarterly
meeting on January 28. During each
trees along the south side of the property were
removed. The Southeast Yakima Community
Yakima Community Center on September 17,
2014. There was a small leak in a water line.
of Public Works, to the staff at the Southeast
Yakima Community Center (SEYCC) to create a
committee meeting, issues with the building
are discussed. Adrianne Garner distributed
Center Advisory Committee met on April 22,
2014 and discussed plans for building
The leak was repaired. The food bank building
was demolished in August and construction on
list of capital needs along with a ranking of
their priority. In 2015, $100,000 has been
copies of the quote to repair the restrooms and
improvements. Fifteen new T — 8 light fixtures
the new Yakima Rotary Food Bank building
earmarked for capital improvements at the
the exterior doors. Magnetic locks have been
and light bulbs were given to the Center by the
began. The playground needs to be replaced in
SEYCC. The capital needs list has been received
installed on three double exterior doors at the
City of Yakima and were installed in the
the future. Parts for the old playground are
and the two most important items are the
2
Public Works
center. New handicapped parking signs were
installed in the north and south parking lots.
Reading Room. HVAC filters were replaced.
becoming very difficult to acquire.
restroom renovation and the HVAC unit
replacement. The Southeast Yakima
Community Center Advisory Committee met
on October 28, 2014 and the capital needs of
the facility were discussed with the committee.
During 2015, bids for the restroom renovation
are to be received and the replacement of the
HVAC unit will be done.
3
Partner with Yakima Food Bank to
construct new facility
Public Works
Monthly meetings have been held.
Agreements for rebuilding the food bank were
finalized and will go to Council. An asbestos
and lead inspection was scheduled for May.
Bid packets for the demolition scheduled for
mid August. Three hazardous trees along the
south side of the property are scheduled for
removal in May. Construction is scheduled to
begin in August and completion of the project
has been projected for late November.
Operation of the food bank during the
construction will be inside the SECC.
Monthly meetings with the Food Bank
Committee continued throughout this quarter.
The three large and potentially dangerous
trees along the south side of the property were
removed. An asbestos inspection of the
building was completed by Fulcrum
Environmental. The demolition of the current
building will go out for bid in mid July.
Demolition of the building is set for August 27,
2014. Final drawings for the new facility are
being finalized. The food bank operating
agreement and the construction agreement for
the new facility has been approved by City
Council. Fundraising for the construction of
the facility is complete.
Meetings were held during this quarter with
the Yakima Rotary Food Bank Committee on
July 1, August 14, and September 25.
Demolition of the old food bank building was
started on August 28, 2014. Construction
began on the new building on September 3,
2014. A ground breaking ceremony was held
on September 8, 2014. Progress on the
building continued. The new facility is
scheduled to be completed in late November.
The Southeast Yakima Community Center
continued to allow the Yakima Rotary Food
Bank to utilize their gymnasium on Fridays to
distribute food.
Construction of the new Yakima Food Bank
occurred during this reporting period. The
facility was completed and a Grand Opening
and Ribbon Cutting Ceremony was held on
November 19, 2014. Members of City Council,
City administration, Rotarians, and local
dignitaries were in attendance. The Yakima
Rotary Food Bank is now operational in the
new facility and this strategic initiative is to be
considered complete.
4
Partner with the Capitol Theatre to
locate funding sources for the needed
repairs
Utilities &
Engineering
Discussions ongoing.
No change.
No change.
5
Attract new businesses and visitors by
partnering with Yakima County
Development Association and Yakima
Valley Tourism
Economic
Development/
City Manager
Regular attendance by City staff at all YCDA and
Yakima Valley Tourism meetings and special
occasions.
Attended new Yakima and Kittitas County
Economic Development organizational meeting
sponsored by YCDA. City staff attended YCDA
board meetings. YCDA director attends
monthly Cascade Mill status meetings and
other special projects. YCDA has been a
significant partner and is obtaining SIED funds
for various City-related projects.
Regular attendance by City staff at all YCDA and
Yakima Valley Tourism meetings and special
occasions.
Work with YCDA staff to pursue SIED funding
for development of South 21st Avenue
Extension and Airport Lane improvements for
development of new hangars and business
expansion.
6
Collaborate with Yakima County on
state transportation package
Community
Relations
City and County staff and elected officials are
partners in the I-82/East-West Corridor project,
Trans -Action Coalition, and other projects. We
share information for our lobbyist to promote
for the Yakima Valley.
The realistic possibility of a significant state
transportation package being approved during
the 2015 state legislative session is not great.
Regardless, the City and Yakima County
continued to advocate for additional
transportation funding. Additional
partnerships are being developed.
The Yakima City Council included in its 2015
State Legislative & Administrative Priorities, as
it had the previous year, passage of a statewide
transportation package. Efforts will be made
by the Council and its Olympia lobbyist to urge
support from the Yakima area's legislative
delegation.
IMPROVE the BUILT ENVIRONMENT
Strategy Department
1st Quarter Progress Report
2nd Quarter Progress Report
3rd Quarter Progress Report
4th Quarter Progress Report
Hire a graffiti abatement coordinator
ONDS continued to promote the Yak Back
Graffiti abatement program is working well.
In the third quarter, ONDS continued to
Year-end totals for graffiti are as follows:
to coordinate cleanup of graffiti sites
notification system to report and locate graffiti
Program coordinator very effective in daily
address graffiti complaints as reported through
7,482.5 hours by volunteers, 701.5 gallons of
and worked with YPD to investigate as well as
responses as well as working with volunteer
Yak Back as a priority and then secondarily
paint were used, and 19,996 locations were
enhance enforcement through education of
efforts. The Yak Back approach has been a
addressed graffiti throughout the
painted. ONDS continued to address graffiti
the public about reporting techniques and
successful vehicle in communicating the citizen
neighborhoods as crews went from location to
complaints as a priority through Yak Back. We
options.
requests to the program coordinator.
location as graffiti was spotted by the graffiti
also continued to paint over graffiti on public
1
Community
Development
coordinator. So far in 2014, volunteers have
worked 7,257.5 hours, used 575.5 gallons of
paint, and painted over a total of 17,343
locations. We continued to paint over graffiti
on public property as well as private property
when permission was given by the property
owner.
property as well as private property when
permission was given by the property owner.
Implement a pilot recycling program of
Developed project management plan for the
The Every Other Week (EOW) Pilot Curbside Project was
The solid waste program continued the every other
This was the final quarter and wrap up of the City
approximately 600 households
proposed pilot recycling program. Designed
"Welcome to Recycling � outreach and
kicked off on May 6. Household numbers were revised to
reflect the following: There were four (4) household
four
week (EOW) Pilot Curbside project with the last
collection date occurringonA April 29th. The Solid
P
of Yakima Pilot Curbside Assessment Project. The
project successfullycompleted the tasks outlined in
P
educational packet and pre -recycling survey.
recyclables and (4) yard waste collections conducted
this quarter at 537 of the possible 622 homes fora
Waste Division retained and worked with its
the Washington State Department of Ecology Grant
Mailed 571 packets to residents in the
participation rate of 86%. The average setout rate for
consultant, Green Solutions, Inc. During this
ahead of schedule and met its overall project goal
Hamilton Park/Sun Crest Annexation. Secured
the recycling route was 381 homes fora 70% setout rate.
quarter activities included: every other week
to conduct a pilot curbside recycling project to
a processor for the collected recyclable
The average setout for the yard waste collection was 322
for a 60% setout rate. Each collection averaged 3 tons for
collection of recyclables and yard waste; cart
inspections and tagging; waste composition
gather baseline data to develop recommendations
for best management practices for the diversion of
materials. Applied to the Washington State
recyclables and 9.25 tons for yard waste. A total of 11.76
analysis; distribution and assessment of the post
solid waste from the landfill. Major activities this
Dept. of Ecology for Coordinated Prevention
recyclables and 37 tons of yard waste was diverted from
pilot survey; preparing for and convening a
quarter included: analysis of data collected from
Grant Funding to support the data collection
being buried at the landfill. Staff conducted curbside
customer focus group and drafting the preliminary
the recycling project, post survey and focus group;
and analysis phase of the pilot. Work with
inspections for approximately 20% of the recycling
final report to be presented at the Council study
development of a preliminary report on the
utility services to develop a billing procedure
containers for each collection. Point of contact
educational tags were placed on each cart to inform the
session on October 28. During the pilot, the
findings; realigning of findings to correlate with a
for residents in the pilot area. Began planning
resident on how they were doing with the program.A
following tonnage was collected: 147.4 tons of
solid waste rate analysis; development of
2
Refuse
community outreach events at Kissel Park.
Recycling Star was given if a cart was clean and free of
garbage, 25.3 tons of recyclables and 58.5 tons of
recommendations for future solid waste
Developed card dissemination/roll out plan for
contamination; an OOPS tag was given listing helpful hints
yard waste. The pilot areas consisted of 622
management strategies and; presentation of final
the 571 households. Prepared materials for
on how to lower the contamination level in the carts. A
households with 537 participating in the program.
Pilot Curbside Recycling Report and proposed rate
the upcoming April 8 City Council study session
$37,500 Coordinated Prevention Grant from the State
Department of Ecology was secured to hire a consultant
The average setout rate for garbage was 89.6%,
74.5% for recyclables and 57.5% for yard waste for
increase at City Council study session on October
28th. The results of the pilot program were
on the pilot. Integrate preliminary rate study
funding as part of their study session.
to work with solid waste staff to assist with the evaluation
of the project and update the rate analysis to reflect
recycling cost and align results of the pilot program with
current and or /or projected rates. The consultant will
work with solid waste staff to discuss the results of the
pilot and prepare a presentation on the findings and
recommendations to City Council late fall.
a total diversion rate of 36%. The participant
opinion of the pilot program gathered through the
post survey and focus group revealed; 79.2% rated
the pilot program as excellent/good; 75.2
considered the program convenient; 64.9%
approved the collection frequency; 73.8% relized a
reduction in waste volume with 34.2% reducing
their waste in half and 31.7% moving from a 96 to a
32 gallon cart. 70.3% would consider signing up for
a City offered recycling service.
generally favorable. Over 90% of the households
participated in the pilot. Every other week
collection for recyclables was workable; there was
a 75% setout rate for recycling and a 57% setout for
yardwaste; 79% of the participants rated the
program as excellent/good; 75.2% considered the
program convenient; 73.8% realized a reduction in
waste volume and 70.3% would consider signing up
for a City offered recycling service. Contract with
consultant Green Solutions completed.
Complete the Collection System
Final draft of collection system plans
34 RFQs sent out to MRSC list, 4 consultant
AHBL was selected by interview board. City
AHBL under contract. Starting review of
Master Plan in order to identify system
completed. RFQ prepared for stormwater
SOQs returned and consultant interviews
manager approval to proceed was granted.
Master Plan, setting program priorities and
expansion needs
Utilities/
retention collection system alternatives and
completed.
Contract documents and scope definition are
scope of Randall Park, North 1st Street and mill
3
Engineering
design. Focus on N. 1st Street, Mill Site, and
priority one identified projects.
being drafted by Dana Kallevig and AHBL.
site designs.
4
Hire two additional code enforcement
officers to allow the City to be more
proactive in responding to code
violations
Community
Development
Two new code compliance officers have been
hired, which will allow a more concerted focus
on major commercial corridors and sign
control. Staff is now focusing on abatement of
temporary sign violations along major entry
and commercial corridors, and is also
developing an enforcement activity log that
will be updated and available weekly.
Additional Code Enforcement officers have
provided targeted emphasis on illegal or
unpermitted commercial signs. Response to
complaint driven code enforcement issues has
also improved with additional staffing. To date,
eleven major streets were reviewed with 717
business sites visited, and over 1,549 signs
removed
The Code Compliance Division is currently
transitioning to a proactive, efficient and
effective team to clean up the City.
Code compliance work unit assisted in alley
cleanup and enforcement of illegal dumping.
The work unit has completed team building
and productivity training.
5
Conduct an industrial waste rate study
Utilities/
Engineering
FCS hired to complete rate study.
FCS analyzed data, draft expected in July 2014.
FCS completed final draft. FCS will present
funding to City Council at September 30 study
session.
Complete
6
Begin the process of creating a
comprehensive connectivity network
by identifying existing sidewalks and
bicycle lanes for a connectivity master
plan
Engineering
Existing sidewalks identified. Consultant on
board to write an ADA compliance plan.
Worked with community bicycle group to
update and revise bicycle plan.
Work is ongoing on ADA plan, bicycle
consultant selected.
ADA consultant under contract. Bicycle study
is ongoing.
7
Amend the City's billboard and digital
signs regulations
Community
Development
Staff made final recommendations to the City
Council on proposed billboard regulations and
followed up with the Built Environment
Committee (BEC) at Council direction to
develop standards for billboard maintenance
and appearance. Staff demonstrated that we
have current codes in place to address
maintenance and the BEC determined that the
matter should now be considered closed.
No further review or staff work is presently
underway related to billboard and digital sign
regulation changes. Code Enforcement staff
has a targeted effort to enforce current sign
codes to correct billboard sign violations as
quickly as possible.
No changes to billboard or digital signs. Other
minor sign code amendments underway at the
direction of City Council.
Sign code amendments for temporary signs
and other problematic sections of the sign
code have been developed by staff and the City
of Yakima Planning Commission at the
direction of the City Council. The draft
amendments are scheduled for open record
public hearings before the Planning
Commission in the month of January and
before the Yakima City Council in the month of
February.
8
Reinstate the traffic engineer position
to manage the right-of-way/street cut
program
Utilities/
Engineering
Not necessary due to lessened scope of final
street cut ordinance.
Closed.
9
Rehabilitate streets by issuing a 10-
year bond of $16 million to grind and
overlay 92 lanes miles
Utilities/
Engineering
Careful preparation combined with good
audits, high level of fiscal responsibility and
written financial policies resulted in a higher
debt rating from Standard & Poor's. Bond
proceeds are invested in LGIP and being
carefully tracked with expenditures to assure
compliance with federal requirements.
Approximately 50% complete. On track to
complete on time
Timely payments are being made to contractor
in amounts exceeding $3 million per check.
This is important for contractor so they can
meet their cash flow needs. Funds are being
kept in low interest bearing account that can
be accessed within 2 days.
Complete except for change order of 32nd to
40th on Lincoln. This will be completed first
thing in the spring.
10
Install a biosolids dryer at the
wastewater treatment plant
Utilities/
Engineering
Bids were above budget available for project
completion. Project scope will be revisited
third quarter of 2014
Wastewater staff evaluated alternatives for
class A biosolids
CDM Smith prepared final report for wrap up.
Biosolids dryer will not be constructed at this
time.
Final report complete. Closed.
11
Implement phase 1 of the North 1st
Street plan
Strategic
Projects
Engineering consultant on board to develop
plans and specifications. Community workshop
held June 26, 2014 to receive comments from
stakeholders. Preferred cross section is
currently being developed and reviewed.
Council is considering a street bond to
complete the entire corridor. The federal funds
for Phase 1 have been delayed.
Design plans at 60%. Final cross section is part
of design plan. HDl continued to work with
City and utility companies to determine
feasibility and extent of undergrounding power
lines.
Design plans at 90%. Construction and bidding
will be deferred until federal grant funds
become available.
12
Work with property owners to cleanup
hazardous sites (mill site, Tiger Marts)
Legal/ City
Manager
Worked with Washington State Department of
Ecology to amend consent decree and
amended cleanup action plan.
Work with DOE to publish public notice of
cleanup and amended consent decree;
installed monitoring wells on four sites.
Hire environmental engineer to assess best
cleanup options for Tiger Oil 24th & Nob Hill
site; review monitoring well reports; submit
grant applications to DOE. Landau is working
under City direction on the landfill as site
assessment continued under DOE scrutiny to
develop background data from which an
appropriate cleanup plan can be generated.
Quarterly water sampling of south properties
initiated as well as soil sampling protocol
requested by DOE.
Monitoring wells installed and water sampling
will continue for approximately six months into
2015. DOE requires a minimum number of
months to collect a useable data base to
determine extent of gasoline plume. As results
are generated, our environmental engineers
and DOE will be able to refine appropriate
cleanup options for each site.
Upgrade existing City Hall building
Upgrades to City Hall began during the 1st
City Hall improvements were ongoing. New
Carpeting is scheduled to be completed
Carpeting was completed in the Y-PAC control
quarter and are expected to be completed
ceiling tiles were installed and the painting was
10/25/14. Utility counters, cabinets, new
room in on 11/1/14. HR/Economic
during the 2nd quarter. Improvements include
new paint and carpeting throughout most of
finished. Carpeting, utility counters, cabinets,
new doors and signage to be completed by mid-
doors, MLK awning, and signage to be
completed by mid-December 2014. Flower
Development new office constructed along
with Y-PAC office carpet completed 1/3/15.
City Manager/
the public areas on the first floor along with
ADA enhancements.
October, if not sooner
beds and medians around City Hall will be
cleaned out, new plants and rocks were added.
Back flow valves for fire system and drinking
water will be installed by 1/31/15. Utility
counters, cabinets and new glass should be
completed mid-February, new doors, MLK
awning mid-March, majority of signage was
completed in December 2014, reader board
work will be completed by 1/31/15. Exterior
13
Community
Development
painting will take place in April. Flower beds
and medians around City Hall on both 2"d and
3rd Street were cleaned (brush and dirt
removed) and fiber cloth installed along with
rock 11/15/14, plants have been purchased
and will be installed March or April as weather
permits. Basement hallways were painted by
our Info Systems staff.
CITY OF YAKIMA 2014 STRATEGIC PRIORITIES—Year end report
Strategic JHitiativc: economic Deveeops.lcht
Strategies
• Collaborate with downtown businesses through a Downtown Master Plan.
• Determine the best location for a public plaza for community events and activities.
• Attend and promote Yakima at the International Council of Shopping Centers annual conference in Las Vegas.
• Produce Lunchtime Live and Downtown Summer Nights concert series and invest in new events.
• Form a public-private partnership to market and promote air service and secure a fourth flight to Seattle.
• Replace aging asphalt, taxiway lights, taxiway signs and airfield markings to ensure the airport will continually
meet Federal Aviation Administration regulations.
• Pursue cleanup of the mill site property.
• Retain an urban economist to assist the City in the identification of appropriate and feasible commercial and job
creation land uses for the mill site property.
1st Quarter
1. Worked with Carl Walker and Gustafson,
Guthrie, Nichol on designs for a potential public
plaza and downtown parking plan.
2 Planned, booked, and developed promotional
materials for the Downtown Summer Nights and
Lunchtime Live concert series.
3. Developed a new website, www.flyykm.com, to
market the airport, established free Wi-Fi
capability in the terminal for passengers, and
created new radio, newspaper, and television
ads to inform people of air service options out of
Yakima.
4. Developed the Construction Safety Phasing
Plan, Preliminary Engineering Plans, Preliminary
Design Report, Pre -design Conference Checklist
and Construction Management Report for the
airport improvement project.
Maasaram a Gatconas-2014
2nd Quarter
1. Four City representatives attended the
International Council of Shopping Centers
annual conference in Las Vegas. Several follow
up meetings will be scheduled with business
owners, managers, agents and representatives.
2. Downtown Summer Nights kicked off June 12.
Some shows exceeded 1,000 people. Event
revenue increased 67% over the first four shows.
3. FLYYKM website was launched in conjunction
with print and television marketing.
Enplanements were up 4% over 2013.
4. Executed contract with Jones, Lange, LaSalle for
a market analysis for the Cascade Mill property.
5. Right of way acquisitions and negotiations were
in process in the second quarter
3rd Quarter
1 A construction safety phasing plan and
engineering plans for the Yakima Airport
improvements were finalized.
2. City Council selected plaza design.
3. Followed up with RECON contacts.
4. Downtown Summer Nights finished strong with
700-1000 participants at each event.
Cascade Mill Site
4th Quarter
1. The Airport was notified it received a $290,000
Small Community Air Service Grant from the
federal govemment.
2. Year end enplanements increased 5%.
3. Partnered with the Fresh Hop Ale Festival
helping to bring 6000-7000 people to Downtown
Yakima.
4. Submitted letter of support for the Downtown
Association of Yakima's Main Street Program
application.
5. Year end Alaska Airlines load factor increased
from 71% to 76%.
6. Received final Cascade Mill Site economic
analysis report.
CITY OF YAKIMA 2014 STRATEGIC PRIORITIES—Year end report
Strategic JNitiative: Psis eic Safety
Strategies
• Expand the downtown bike patrol to run from March through
October.
• Increase training opportunities for newly promoted employees and
leadership development.
• Deploy 74 assigned police patrol vehicles.
• Invest in 8 license plate reader systems for the Yakima Valley.
• Hire a Gang Free Initiative manager to ensure effective public and
private sector coordination and integration of resources.
• Implement second gang unit to work gang crimes.
1st Quarter
1 Eight officers attended the FBI-LEEDA
supervisory training leadership course.
2. All officers eligible for an assigned vehicle
received their vehicles.
3. Second full gang unit was implemented in
January 2014.
4. Finalized job classifications for the Dispatch
Center Manager and Communications Center
Manager positions.
5. Completed a space analysis of the law and
justice building. Results will be available in the
second quarter.
6. Prosecutors were able to reduce caseloads
through the pre -filing diversion and charging unit.
• Increase staffing level at Yakima Fire Department to eliminate "brown out" days.
• Separate the communications/dispatch center manager position into two different
positions.
• Develop a design study for the new joint communications center that will be located
at the County -owned Restitution Center.
• Invest in a new fire brush truck in other to better assist local agencies.
• Add a full time parking enforcement officer dedicated to the downtown area.
• Reduce the current misdemeanor caseload with pre -filing diversion program and
charging unit to comply with state mandates.
Measr+ra ee Gwtcofes-2014
2nd Quarter
1. The bike patrols were deployed in June.
2. Five additional officers were identified for the FBI
-LEEDA course. In addition, 9 officers are
attending the City's leadership development
course.
3. Staff researched license plate reader systems
for 8 police vehicles.
4. Perry Tarrant was hired as the GFI and
Emergency Management Director. He started
July 1, 2014.
5. Contracted for an employee to provide parking
enforcement services to the downtown area.
6. Through the second quarter, caseload numbers
were reduced by 40 percent.
3rd Quarter
1. Yakima Police Department officers went through
a 16 -hour integrated tactical accountability class.
2. The police chief attended the Senior
Management in Policing Institute.
3. The automated license plate readers were
ordered.
4. An agreement between the City and County was
finalized and awarded for construction of the
new communications center.
5. Hired second parking enforcement officer.
4th Quarter
1. Reduced 2014 caseloads by 41% - 3,114 cases
in 2014 compared to 5,300 in 2012 due to new
charging unit and diversion programs.
2. Automated license plate readers were installed
and officers were trained how to use them.
3. Transferred parking enforcement responsibilities
to Utility Services.
4. Entered into a $1.2 million contract to provide
fire services to Union Gap.
5. Year end Part 1 crimes fell compared with
2013.
CITY OF YAKIMA 2014 STRATEGIC PRIORITIES—Year end report
Strategic JHitiative: Padeic Trust 8 AccvahtaNdity
Strategies
• Implement quality customer service academy for all existing and
new employees.
• Conduct Yakima's third annual citizen survey in late spring / early
summer.
• Implement new financial software system (Cayenta).
1st Quarter
hoto from City of Yakdtha UriwerA tratnin9
P
1. Employees were trained on how to teach,
instruct, and lead coworkers through a City -
sponsored customer service academy.
2. Started preparations for the third annual
customer survey.
3. Went live with the Cayenta system; still working
through some issues.
4. Route 8 was cut in accordance with Transits 15
passenger per hour route standard. Changed
departure times from 5:10 p.m. to 5:15 p.m. at
the Transit Center to accommodate the business
people who need transit service after work.
• Conduct Yakima's third annual employee survey.
• Establish development teams to ensure coordinated project review.
• Perform a Business Process Analysis of the Utility Services
Division.
Photo from City of Yakima University training
Ateastiraoee Outcomes -2414
2nd Quarter
1 Developed custom questions for citizen survey.
The survey will be mailed in the third quarter with
results to us in October.
2. Offered first series of customer service training.
Over 400 employees went through Customer
Service 101 and the Nordstrom Model of
Customer Service.
3. Cayenta system was fully implemented.
4. Evaluated transit routes and considered
modifications.
5. City manager met with several departments and
reviewed the results of the employee survey.
6. Hired a project permit coordinator to help
expedite permits.
7 Negotiated with FCS Group to complete the
second phase of BPA with a written document.
3rd Quarter
Photo tri C.
+ty of Yakinia Univers
ily training
1. The City implemented Customer Service 101
and conflict management courses for staff.
2. The new financial system, Cayenta, was
installed and staff was able to run reports out of
the new system.
3. The City hired a project permit coordinator to
facilitate and expedite the DST process.
4th Quarter
1. The 2014 Citizen Survey results were received,
resulting in key improvements over 2013.
2. The City conducted customer service training
programs for all City employees.
3. Staff members attended the 2014 Cayenta
conference in order to expand knowledge of the
new system.
4. The 2014 Employee Survey was conducted with
an 89% participation rate. Results are expected
in February.
5. Produced a balanced and prudent 2015 budget
that includes no tax or fee increases.
CITY OF YAKIMA 2014 STRATEGIC PRIORITIES—Year end report
Strategic Jhitiative: PartNars4ip Deveeopsest
Strategies
• Update YPAL facility at Miller Park—secure funding from Washington Fruit.
• Partner with the Southeast Community Center in upgrading existing facility.
• Partner with Yakima Food Bank and Rotary to construct a new facility at the Southeast
Community Center.
• Partner with the Capitol Theatre to locate funding sources for needed repairs.
• Attract new businesses and visitors by partnering with Yakima County Development Association
and Yakima Valley Tourism.
• Collaborate with Yakima County on state transportation package.
1st Quarter
Washington Fruit & Produce committed to
contribute $250,000 to the renovation of the
YPAL facility. The facility will be renamed
Washington Fruit Community Center.
2. The Southeast Community Center was
remodeled and updated.
3. Agreements for rebuilding the food bank were
finalized and will be going to Council for
approval.
Masa ra bG a Outcomes -2014
2nd Quarter
1 Work on the YPAL facility continued in the
second quarter.
2. The three large, dangerous trees along the south
side of the Southeast Community Center
property were removed.
3. RFPs for the demolition of the old food bank will
go out the third quarter of 2014.
4. City and County staff partnered on the I-82/East-
West Corridor project, Trans -Action Coalition,
and other projects.
5. Shared project information with the City's
Olympia lobbyist to promote for the Yakima
Valley.
3rd Quarter
A new food bank was built and opened at the
Southeast Community Center.
2. Washington Fruit Community Center
improvements continued in the third quarter.
4th Quarter
1 The City reviewed a list of capital needs at the
Southeast Community Center. The required
improvements will be made in 2015.
2. Renovations at the Washington Fruit Community
Center started in 2014 and will wrap up in 2015.
3. Entered into a new partnership to assist the
Central Washington State Fair Association with
Sundome operational costs.
4. Initiated Yakima Craft Beverage marketing and
branding plan.
CITY OF YAKIMA 2014 STRATEGIC PRIORITIES—Year end report
Strategic JNitiative: Juiprove Me $aiet 6,1'41,0, 0010d
Strategies
• Hire a graffiti abatement coordinator to coordinate cleanup of graffiti
sites
• Implement a pilot recycling program of approximately 600 house-
holds
• Complete the collection system master plan in order to identify sys-
tem expansion needs
• Hire two additional code enforcement officers to allow the City to be
more proactive in responding to code violations
• Conduct an industrial waste rate study
• Amend the City's billboard and digital sign regulations
1st Quarter
1. ONDS continued to promote the Yak Back
notification system to report and locate graffiti
and worked with YPD to investigate as well as
enhance enforcement through education of the
public.
2 Developed project management plan for the
proposed pilot recycling program.
3 Two new code compliance officers were hired.
Focused on abatement of temporary sign
violations along major entry and commercial
corridors.
5. FCS hired to complete the industrial waste rate
study.
6. Staff made final recommendations to the City
Council on proposed billboard regulations and
followed up with the Built Environment
Committee on Council direction to develop
standards for billboard maintenance and
appearance.
• Reinstate the traffic engineer position to manage the right of way/
street cut program
• Rehabilitate streets by issuing a 10 -year bond of $16 million to grind
and overlay 92 lane miles
• Install a biosolids dryer at the wastewater treatment plant
• Implement Phase 1 of the North 1st Street plan
• Work with property owners to cleanup hazardous sites (mill site,
Tiger Marts)
• Upgrade existing City Hall building
Measaratiee GatcvtNes-2014
2nd Quarter
1. Graffiti abatement program is working well.
2. The Curbside Recycling Project was kicked off
on May 6. There were four household
recyclables and four yard waste collections
conducted this quarter for 537 of the possible
622 homes, for a participation rate of 86%.
3. Through the second quarter, code compliance
officers visited 717 businesses, and 1,549
temporary signs were removed.
4. Worked with consultant and community bicycle
group to update the revised bicycle plans.
5. Worked with Washington State Department of
Ecology to publish public notice of cleanup and
amended consent decree for Tiger Mart
properties.
6. City Hall improvements continued in the second
quarter.
3rd Quarter
1. The curbside recycling program collected 147.4
tons of garbage, 25.3 tons of recyclables, and
58.5 tons of yard waste through the third quarter
of 2014.
2. A consultant was selected for the Bicycle Master
Plan.
3. FCS completed the industrial waste rate study.
4 The City hired an environmental engineer to
assist in the clean up of the Tiger Oil sites.
5 ONDS volunteers removed graffiti at 17,343
locations through the third quarter.
4th Quarter
1.
Completed on time and on budget 92 lane miles
of grind and overlay.
2 A stormwater monitoring well was installed at the
Tiger Oil locations.
3 The City contracted with AHBL to create a
stormwater master plan for North 1st Street,
Randall Park, and mill site.
4. Completed City Hall improvements.
Strategic
Js+itiatives
2014
Strategies
2014
MaasaratMe
Outcomes
CITY OF YAKIMA 2014 STRATEGIC PRIORITIES -Year end overview
ecomorr1ic Devedoporierit
Paoeic Safety
1. Collaborate with downtown businesses through a
Downtown Master Plan.
2. Determine location for a public plaza for community
events and activities.
3. Attend the International Council of Shopping
Centers annual conference.
4. Produce Lunchtime Live and Downtown Summer
Nights concert series and invest in new events.
5. Form a public-private partnership to market and
promote air service and make necessary
improvements.
6. Cleanup the mill site and Tiger Mart properties.
7. Retain an urban economist to review the best use
of the mill site.
1 Worked with Carl Walker and Gustafson, Guthrie,
Nichol on designs for a potential public plaza and
downtown parking plan.
2. Planned, booked, and developed promotional
materials for Downtown Summer Nights, Lunchtime
Live, and new cultural concert series, Viva la
Musica, at Miller Park.
3. Developed new website and marketing materials
for Yakima Airport and construction documents for
the airport improvement project. Increased Airport
load factor 5% and received $290,000 grant award.
4. Marketed Yakima at the International Council of
Shopping Centers annual conference in Las Vegas.
5. Executed contract with Jones, Lange, LaSalle for a
market analysis for the Cascade mill site property.
6. Worked with ecology to remediate the Tiger Mart
hazardous sites.
1. Operate bike patrol from March through October
and add a fulltime parking enforcement officer for
downtown.
2. Increase training opportunities.
3. Deploy 74 assigned police vehicles (APV).
4. Invest in 8 license plate reader systems.
5. Hire a Gang Free Initiative Manager and
Emergency Management Director.
6. Implement second gang unit.
7. Increase staffing levels at Yakima Fire Department
to eliminate brownout days.
8. Develop a new joint communications center and
hire a new manager.
9. Invest in a new fire brush truck.
10.Implement pre -filing and diversion programs to
reduce caseload filings.
1.
Deployed bike patrols during the summer and had
a fulltime parking enforcement officer for
downtown. Business owners and citizens were
extremely happy and felt a sense of security.
2. Reduced caseload filings by 41 percent.
3. Perry Tarrant was hired as the GFI/Emergency
Management Director. Brad Coughenourwas
hired as the Communications Center Manager.
4. Conducted needs facility study for police depart-
ment. Built a new communications center.
5. Purchased 8 license plate reader systems that will
be installed in January.
6. Through the APV program the City was able to
respond and/or solve some crimes almost
immediately.
7. 156 individuals participated in prefiling/diversion
programs.
PaOeic Mot 8
Accoar+tal iieity
1. Implement quality customer service academy for
existing and new employees.
2. Conduct Yakima's third annual citizen survey in late
spring / early summer
3. Conduct Yakima's third annual employee survey.
4. Establish development teams to ensure coordinat-
ed project review.
5. Perform a business process analysis of the Utility
Services Division.
6. Implement new financial software system
(Cayenta).
1. Employees were trained on how to teach, instruct,
and lead coworkers through a City -sponsored
training program.
2. Completed third annual citizen survey.
3. Implemented Cayenta software program.
4. Evaluated transit routes and schedules and
adjusted them to make them more efficient.
5. Hired a Project Permit Coordinator to help expedite
the permitting process.
6. Offered customer service 201 and conflict
management as well as various other training
programs to City employees.
7. Produced a balanced and prudent 2015 budget
without any tax or fee increases.
8. Conducted third annual employee survey.
Partaersliip Deveeoprrier+t
1. Update YPAL facility and rename it Washington
Fruit Community Center.
2. Partner with the Southeast Community Center
(SECC) in upgrading the facility.
3. Partner with Yakima Food Bank and Rotary to
construct a new food bank at the SECC.
4. Partner with the Capitol Theatre to locate funding
sources for the needed repairs.
5. Attract new businesses and visitors by partnering
with Yakima County Development Association and
Yakima Valley Tourism.
6. Collaborate with Yakima County on state
transportation package.
1. Washington Fruit contributed to the renovation of
the YPAL facility.
2. The Southeast Community Center food bank was
demolished and rebuilt.
3. Entered into new partnership to assist the State
Fair with Sundome operational costs.
4. Initiated Yakima Craft Beverage marketing and
branding plan.
5. Collaborated with Yakima County on state
transportation package, which failed to pass the
State Legislature.
Jrri prove tae $aiet
er+viroarriemt
1. Hire a graffiti abatement coordinator to coordinate
cleanup of graffiti sites.
2. Implement a pilot recycling program.
3. Complete the collection system master plan in
order to identify needs.
4. Hire two additional code enforcement officers to
allow the City to be more proactive in responding to
code violations.
5. Conduct an industrial waste rate study.
6. Amend the City's billboard and digital sign regula-
tions.
7. Grind and overlay 92 lane miles; install new side-
walk ADA ramps.
8. Install a biosolids dryer at the wastewater treatment
plant.
9. Implement phase 1 of the North 1st Street plan.
1. Conducted pilot recycling program of 600
households.
2. Hired two new code compliance officers.
3. Council approved new sign and billboard
regulations.
4. Worked with consultant and bicycle group to review
bike plans.
5. Made interior improvements at the Yakima Airport.
6. Removed graffiti from 19,996 locations.
7. Installed new carpet in City Hall, updated the
signage, and painted the walls.
8. Completed 92 lane miles of grind and overlay.