HomeMy WebLinkAboutR-2012-100 Yakima Rail Road Grade Separations Project; Berger/Abam Engineers, Inc - Supplement No. 9RESOLUTION NO. R- 2012 -100
A RESOLUTION authorizing the City Manager to execute Supplement No. 9 of the
Professional Services Agreement with Berger /ABAM Engineers, Inc., for
continued engineering support of the Yakima Railroad Grade Separations
Project.
WHEREAS, in July 2000 the City of Yakima issued and advertised a request for
qualifications from firms interested in providing consulting services for the design and
development of a grade separation railroad project; and
WHEREAS, the request for qualifications advertisement described the matter as a multi-
phase project that would later include preparation of plans, specifications and estimates and
construction project management for the Railroad Grade Separation Project ( "Project "); and
WHEREAS, as a result of that request for qualifications process, the City selected and
contracted with BERGER /ABAM Engineers, Inc., to provide the said services for the Project;
and
WHEREAS, additional engineering and consulting services are required for project
administration to construct the Project, as described in the Scope of Work Description included
in the Supplemental Agreement; and
WHEREAS, it is requested that the City Manager have the authority to execute an
additional (ninth) supplemental agreement for additional engineering and consulting services to
complete the MLK Underpass design and provide minimal engineering oversight during the
bidding and construction of the MLK Underpass, and to extend the completion date and term of
the second contract with BERGER /ABAM Engineers, Inc., through September 30, 2014; and
WHEREAS, the City Council deems it to be in the best interest of the City of Yakima to
authorize the City Manager to execute an additional (ninth) supplemental agreement with
BERGER /ABAM Engineers, Inc, for additional engineering and consulting services to
administer the MLK Boulevard Railroad Grade Separation Project and to extend the completion
date and term of the contract with BERGER /ABAM Engineers, Inc., through September 30,
2014, now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
The City Manager is hereby authorized to execute Supplement No. 9 of the Professional
Services Agreement with Berger /ABAB Engineers, Inc. for continued engineering support of the
Yakima Railroad Grade Separations Project, and to extend the completion date and term of the
contract with BERGER /ABAM Engineers, Inc, (City Contract No 2003 -53) through September
30, 2014 The total additional compensation authorized by said supplemental agreement shall
not exceed $150,000 The form of said supplemental agreement shall be reviewed and
approved by the City Attorney or his designee.
A
ADOPTED BY THE CITY COUNCIL this
City Clerk
�?*
t
17th day of July, 201
Micah y Idawley, Mayor
4
Washington State
w® Department of Transportation
Supplemental Agreement
p p g
Organization and Address
Berger ABAM Engineers, Inc.
Number 9
33301 Ninth Avenue South, Suite 300
Federal Way, WA 98003
Original Agreement Number
LA -4453
Phone. 206 - 431 -2300
Project Number
Execution Date
Completion Date
1
STPX - NCPD -000S (062)
7/17/2012
9/30/2014
Project Title
New Maximum Amount Payable
Yakima Railroad Grade Separtions
$ 4,930,726.00
Description of Work
Provide engineering services to assist City of Yakima staff during the contract bid, award, and construction of the
Martin Luther King, Jr. Boulevard Undercrossing.
The Local Agency of the City of Yakima
desires to supplement the agreement entered into with Berger ABAM Engineers, Inc
and executed on 6/20/2003 and identified as Agreement No LA -4453
All provisions in the basic agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows
Section 1, SCOPE OF WORK, is hereby changed to read
11
Section IV, TIME FOR BEGINNING AND COMPLETION, is amended to change the number of calendar days for
completion of the work to read: Work will he completed by 4eptemher 10 2614
III
Section V, PAYMENT, shall be amended as follows
Pnyment shall he increased by �l 56,666 ton maximum amount of ,%4 916,726_
as set forth in the attached Exhibit A, and by this reference made a part of this supplement.
If you concur with this supplement and agree to the changes as stated above, please sign in the appropriate spaces
below and return to this office for final action
By v By-
Consultant Signature
CITY CONTRAc�rm-�a�..',
DOT Form 140 -063 EF RESOLUTION
Revised 9/2005
Date
EXHIBIT A - SCOPE OF WORK
Supplement No. 9
CITY OF YAKIMA MARTIN LUTHER KING, JR. BLVD. GRADE SEPARATION PROJECT (MLK)
SCOPE OF WORK TO GO FROM 95% PLANS, SPECIFICATIONS, AND ESTIMATE (PS &E) TO BID
READY DOCUMENTS
PROJECT DESCRIPTION
In early 2011, BergerABAM (BA) completed the 95% PS &E for MLK and submitted it to the
City. This submittal was after the Lincoln Ave. grade separation project (Lincoln) had gone to
bid, but prior to the start of construction of Lincoln. Now that the construction of Lincoln is
nearly complete, the City and BA desire to complete the contract documents for MLK. The
scope of work for that effort is given below. It is assumed that this effort will take place over a
period of no more than three months. Note that this scope and fee assume that Lincoln will be
completed per plan with three westbound lanes within the underpass.
TASK 1- PROJECT ADMINISTRATION AND MEETINGS
BA will continue to administer the project including invoicing, subconsultant management,
record keeping, etc. It is assumed BA will have two staff members attend two meetings in
Yakima.
TASK 2 - INCORPORATE THE CITY'S 95% REVIEW COMMENTS
BA will incorporate the City's 95% review comments on the water system..
TASK 3 - INCORPARATE LESSONS LEARNED FROM LINCOLN
Modification made during the Lincoln Underpass construction will be reviewed and where
applicable, any cost saving changes will also be made on MLK.
TASK 4 - UTILITY COORDINATION
BA will coordinate with the fiber optic companies and other utilities to finalize the design of the
fiber optic crossing at MLK. BA will also confirm the current plans for other public and private
utilities.
TASK 5 - BOTTOM SEAL REDESIGN
The MLK Underpass bottom seal will be redesigned using lessons learned from the Lincoln
Avenue Underpass - tremie seals at the east and west ends of the seal and augercast drill and
fill in the deeper middle portion of the seal.
Although the tremie /drill and fill method was completed successfully on Lincoln, its cost
effectiveness was not optimized because the walls were already built and were designed in
conjunction with a grouted bottom seal that would have provided more support than was
provided during the excavation for the tremie seal. BA will start the redesign of the MLK seal
by looking at the costs per linear foot of underpass for the tremie seal and the drill and fill seal
in the area of the transition between the two methods. Based on the cost savings of the tremie
seal over drill and fill in that area, BA will look into what the added wall costs would be to
strengthen the walls in those areas such that the tremie seal could be extended further into the
City of Yakima BergerABAM, FAPWT -04 -016
Martin Luther King, Jr Blvd. Grade Separation Project February 2012
Yakima, Washington Page 1 of 2
EXHIBIT A - SCOPE OF WORK'
Supplement No. 9
underpass. Through an iterative process, the walls will be strengthened and the tremie seal
extended until a point of cost equilibrium between tremie seal and drill and fill is reached.
Once the limits of the tremie seal and drill and fill limits have been established, the revised wall
designs will be finalized and the wall and bottom seal plans and specifications will be revised.
TASK 6 - FRONT STREET FINAL DESIGN
Front Street will be modified to accommodate the new bridge built as part of the MLK
Underpass.
TASK 7 - ARTWORK
The City has chosen not to have an artwork element in the MLK design.
TASK 8 - COMPLETE AND REVISE THE CONSTRUCTION STAGING DRAWINGS
At the time of the 95% submittal, the construction staging plans were not completed and were
therefore not included in the 95% submittal. BA will complete and revise these plans as needed.
TASK 9 - UPDATE THE SPECIFICATIONS
In the year since the specifications were prepared for the 95% submittal, there have been
significant changes to the WSDOT general special provisions (GSPs) and the amendments to the
standard specifications. BA will update the specifications based on these changes. Note that if
the project does not go to bid within a few months of the submittal of the bid documents, the
GSPs and amendments will need to be updated again just prior to bidding.
TASK 10 - UPDATE THE COST ESTIMATE
BA will update the cost estimate based on the changes to the plans and specifications and on the
actual cost data from Lincoln.
City of Yakima BergerABAM, FAPWT -04 -016
Martin Luther King, Jr Blvd. Grade Separation Project February 2012
Yakima, Washington Page 2 of 2
EXHIBIT E -1 - CONSULTANT FEE DETERMINATION
(SupplemenVAmendment No. 9)
DIRECT SALARY COSTS (DSC) for BERGER/ABAM Engineers, Inc.
7/9/2012
TOTAL BERGER/ABAM FEE (DSC + SE + OH + FF + DNSC) = $ 109,600
SUBCONSULTANTS
Personnel
Hours
Rate (see note)
$
Cost
1
Project Executive
8
X $7716 =
$
617
2
Project Manager
178
X $5048 =
$
8,985
3
Project Engineer
152
X $42.55 =
$
6,468
4
Engineer
364
X $3486 =
$
12,689
5
Inspector
4
X $44.23 =
$
177
6
CADD Operator
232
X $3000 =
$
6,960
7
Admin /Clerical
12
X $28.73 =
$
345
BERGER/ABAM Hours, TOTAL
950
Subtotal Direct Salary Costs (DSC) =
$
36,241
Salary Escalation (SE) = 4.2% for 100% of work =
$
1,522
Subtotal (DSC + SE) =
$
37,763
Overhead (OH)
158.23% of (DSC + SE) =
$
59,753
Fixed Fee (FF)
32.00% of (DSC + SE) =
$
12,084
TOTAL SALARY COSTS (DSC + SE + OH + FF) =
$
109,600
DIRECT NONSALARY COSTS (DNSC)
Mileage for Site Visits & Meetings
0 miles @ $ 0 485
$
-
Boards for Public Meetings
0 sq feet @ $ 1500
$
-
Drawing Reproduction (11 X 17)
0 copies @ $ 016
$
-
Color Copies (8 5 X 11)
0 copies @ $ 1 00
$
-
Color Copies (11 X 17)
0 copies @ $ 2.00
$
-
Courier & Postage
0 packages @ 25
$
-
TOTAL REIMBURSABLE EXPENSES (DNSC) =
$
-
TOTAL BERGER/ABAM FEE (DSC + SE + OH + FF + DNSC) = $ 109,600
SUBCONSULTANTS
Huibregtse Louman Associates
$
5,000
Shannon and Wilson
$
10,000
Kennedy /Jenks
$
10,000
Hanson Professional Services
$
5,400
Transpo
$
10,000
MANAGEMENT RESERVE
TOTAL SUBCONSULTANT FEES = $ 40,400
TOTAL AUTHORIZED AMOUNT= $ 150,000
0% $
TOTAL CONTRACT AMOUNT = $ 150,000
Page 1 of 3
City of Yakima, MILK Blvd. Grade Separation
Exhibit E - Supplement No. 9 (Finalize Bid Documents for MILK)
Prepared E RLF
Date 9- Jul -12
DESCRIPTION
PROJECT
EXEC
PROJECT
MGR
PROJECT
ENGR
ENGR
INSPECTOR
CADD
ADMIN/
CLERICAL
TOTAL
TASK 1 - PROJECT ADMINISTRATION AND MEETINGS
0
40
16
0
0
0
0
56
1 1 Invoicing
8
8
1.2. Subconsultant Management
12
12
1.3. Record Keeping
4
q
1 4. Meetings
16
16
32
TASK 2 - INCORPORATE 95% REVIEW COMMENTS
0
8
8
8
0
16
0
40
2.1 Revise PS &E per Comments
8
8
8
16
40
TASK 3 - INCORPORATE LESSONS LEARNED
of
4
4
161
4
16
0
44
3.1 Meeting
0
3.2. Revise PS &E
4
4
16
4
16
44
TASK 4 - UTILITY COORDINATION
0
12
0
40
01
32
0
84
4.1 Coordinate with Fiber Optics
8
24
24
56
4.2. Coordinate with Other Private Utilities
2
8
4
14
4.3. Coordinate with Public Utilities
2
8
4
14
TASK 5 - BOTTOM SEAL REDESIGN
6
24
60
200
0
120
0
410
5.1 Determine Point of Tremie /Drill and Fill Equilibrium
4
8
24
40
76
5.2. Revise Wall Structural Calculations
2
41
16
40
62
5.3. Revise Plans
8
16
120
120
264
5.4. Geolechnical Input
4
4
8
DESCRIPTION
PROJECT
EXEC
PROJECT
MGR
PROJECT
ENGR
ENGR
INSPECTOR
CADD
ADMIN/
CLERICAL
TOTAL
TASK 6- FRONT STREET FINAL DESIGN
0
6
0
16
0
8
0
30
6.1 Finalize Decisions with the City
4
4
6.2. Add Front St. PS &E
2
16
8
26
TASK 7- ARTWORK
0
0
0
0
0
0
0
0
7 1 No Artwork is Assumed
0
TASK 8 - REVISE THE CONST STAGING DRAWINGS
0
36
0
20
0
40
0
96
8.1 Complete Drawings
36
20
40
96
TASK 9 - UPDATE THE SPECIFICATIONS
0
40
40
0
0
0
12
92
9.1 Update Specifications
40
40
12
92
TASK 10 - UPDATE THE COST ESTIMATE
2
8
24
64
0
0
0
9
10.1 Update Quantities and Estimate
1 2
8
24
64
98
BERGER/ABAM Total
1 81
1781
152
364
41
232
12
950
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT ,
Item No. i
For Meeting of: July 17, 2012
ITEM TITLE: Resolution authorizing the City Manager to execute
Supplement No. 9 of the Professional Services Agreement
with Berger /ABAM Engineers, Inc. for continued
engineering support of the Yakima Railroad Grade
Separations Project.
SUBMITTED BY: Joan Davenport, Acting Director of Community & Economic
Development
CONTACT Doug Mayo, City Engineer - 576 -6678
PERSON /TELEPHONE:
SUMMARY EXPLANATION:
The City has a professional services agreement with Berger /ABAM Engineers, Inc. for
design engineering, project management, inspection services and engineering support
during design and construction of the Yakima Railroad Grade Separations Project. The cost
for these services was $4,780,726. The existing professional services agreement is
scheduled to expire at the end of July. Due to the additional funding ($5.5 million of STP
funds) that the City recently received to fully fund the Martin Luther King, Jr. Boulevard
(MLK) Underpass, the City desires to extend the professional services agreement with
Berger /ABAM to complete the MILK Underpass design and provide minimal engineering
oversight during the bidding and construction of the MLK Underpass. This supplement
would extend the agreement to September 30, 2014, and would carry an additional cost not
to exceed of $150,000, bringing the total amount of current Berger ABAM Consultant
Agreement Number 2 to $4,930,726.
Resolution X
Contract: X
Contract Term:
Insurance Required? No
Ordinance
Mail to:
Amount: $150,000
Funding Cumulative Reserve for Capital
Source: Improvements; Fund 392
APPROVED FOR
Other
(specify)
Expiration Date: September
30, 2014
Phone:
City Manager
SUBMITTAL:
STAFF RECOMMENDATION:
Staff respectfully requests that the Council approve the resolultion authorizing the City
Manager to execute Supplement No. 9 with Berger /ABAM Engineers, Inc.
BOARD /COMMISSION RECOMMENDATION:
ATTACHMENTS:
Click to download
❑ Resolution
❑ Supplemental Agreement No. 9
❑ Exhibit A. Scope of Work
❑ Exhibit E -1. Consultant Fee Determination
❑ Berger /ABAM PSA's and Supplements
Berger ABAM Consultant Agreements and Supplements
Item
Professional Services Agmt. No. 1
Date Executed
1/19/2001
Amount
$729,400
Accumulative
Amount
$729,400
Professional Services Agmt. No. 2
6/20/2003
$1,250,000
$1,250,000
Supplemental Agreement No. 1
-
$0
$1,250,000
Supplemental Agreement No. 2
8/16/2005
$620,000
$1,870,000
Supplemental Agreement No. 3
1/16/2007
$177,284
$2,047,284
Supplemental Agreement No. 4
6/30/2008
$210,989
$2,258,273
Supplemental Agreement No. 5
12/31/2008
$217,912
$2,476,185
Supplemental Agreement No. 6
6/30/2009
$1,513,059
$3,989,244
Supplemental Agreement No. 7
6/30/2010
$190,0001
$4,179,244
Supplemental Agreement No. 8
5/17/2011
$601,4821
$4,780,726
Supplemental Agreement No. 9
7/17/2012
$150,0001
$4,930,726
Total of PSA #1 and PSA #2: $5,660,126