HomeMy WebLinkAboutR-2011-080 Railroad Grade Separations, Phase 2 - Lincoln Ave, Agreement Supplement with Cascade Project Management, PLLCRESOLUTION NO. R- 2011 -80
A RESOLUTION authorizing the City Manager to execute a supplemental agreement with
Cascade Project Management, PLLC for continued services as the City's
Representative for the Lincoln Avenue Grade Separation Project.
WHEREAS, in January 2009, the City of Yakima issued and advertised a request for
qualifications from firms interested in providing consulting services as the City's Representative
on the Lincoln Avenue Underpass project; and
WHEREAS, as a result of that request for qualifications process, the City selected and
contracted with Cascade Project Management, PLLC, to provide the said services for the
Project; and
WHEREAS, continued engineering and consulting services are required for the Project,
as described in the Scope of Work Description included in the Supplemental Agreement; and
WHEREAS, it is requested that the City Manager have the authority to execute a
supplemental agreement for additional engineering and consulting services to represent the City
and to extend the completion date and term of this agreement with Cascade Project
Management, PLLC through July 31, 2012; and
WHEREAS, the City Council deems it to be in the best interest of the City of Yakima to
authorize the City Manager to execute a supplemental agreement with Cascade Project
Management, PLLC, for additional engineering and consulting services to represent the City on
the Lincoln Avenue Railroad Grade Separation Project and to extend the completion date and
term of the contract with Cascade Project Management, PLLC, through July 31, 2012, now,
therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
The City Manager is hereby authorized to execute a supplemental agreement with
Cascade Project Management, PLLC, for additional engineering and consulting services to
represent the City on the Lincoln Avenue Railroad Grade Separation Project and to extend the
completion date and term of the contract with Project Management, PLLC, (City Contract No.
2009 -76) through July 31, 2012. The total additional compensation authorized by said
supplemental agreement shall not exceed $28,535.67. The form of said supplemental
agreement shall be reviewed and approved by the City Attorney or his designee.
ADOPTED BY THE CITY COUNCIL this 7th day of June, 2011.
`! C
Micah Cawle , Mayor
ATTEST:
`i W-747-1 _�
AMIL
Washington State
V, Department of Transportation
RECEIVED 60060 pq
X _ as /i
JUG 2 ®2011
SupplSupplemental i4 regiment
emental
organization and Address
Cascade Project Managment, PLLC
Number 1
55332 Highway 155N
Electric City, WA � 123
Original Agreement Number
2009 -76
Phone: 360- 420 -3484
Project Number
Execution Date
Completion Date
1
STPX- NCPD -000S 062
6/7/2011
7/31/2012
Project Title
New Maximum Amount Payable
Yakima Railroad Grade Separations, Phase 2
$ 440,499.92
Description of Work
Cascade Project Management is to perform services as the Owner's Representative on the Yakima Railroad Grade
Separations, Phase 2 - Lincoln Avenue Underpass.
The Local Agency of City of Yakima
desires to supplement the agreement entered into with Cascade Project Management, PLLC
and executed on 6/16/2009 and identified as Agreement No. 2009 -76
All provisions in the basic agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
Section 1, SCOPE OF WORK, is hereby changed to read:
11
Section IV, TIME FOR BEGINNING AND COMPLETION, is amended to change the number of calendar days for
completion of the work to read: T'hic cn pn1 .meet extends, the agreement throng] July 31, 2012_
Section V, PAYMENT, shall be amended as follows:
as set forth in the attached Exhibit A, and by this reference made a part of this supplement.
If you concur with this supplement and agree to the changes as stated above, please sign in the appropriate spaces
below and return to this office for final action.
B,
DOT Form 140 -063 EF
Revised 9/2005
By: City of Yakima
_... ? -7/
RESOLUTION N0:
Q4:Z;� -
K. A. ai . , ger
Date
Exhibit A
Maximum Amount Payable Determination
REMAINING DIRECT SALARY COST (DSC) for CASCADE PROJECT MANAGEMENT
Personnel Hours Rate Cost
Project Manger 595 X $70.00 = $41,650.00
Construction Specialist 64 X $40.00 = $2,560.00
Contract Administrator 72 X $30.00 = $2,160.00
$46,370.00
Escalation of DSC for two years at 7.25% /year = 15.025% _ $6,967.09
Overhead of Salary Escalation (74.28 %) = $5,175.16
Fixed Fee of Salary Escalation (20 %) = $1,393.42
Total Increase for Personnel Costs = $13,535.67
Management Reserve Increased to $40,000.00
Original Mangement Reserve = $25,000.00
Total Increase for Mangement Reserve = $15,000.00
Maximum Amount Payable Increase = $28,535.67
Original Maximum Amount Payable: $411,964.25
New Maximum Amount Payable: $440,499.92
•
J
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON.
AGENDA STATEMENT
Item No. 17—
For Meeting of: June 7, 2011
ITEM TITLE: Consideration of Resolutions authorizing the City Manager to execute the
following supplements for continued construction oversight on the Yakima
Railroad Grade Separations, Phase 2 — Lincoln Avenue project:
A) Supplement No. 8 of the Professional Services Agreement with
Berger /ABAM Engineers, Inc.
B) Supplement No. 1 of the Professional Services Agreement with
Cascade Project Management.
SUBMITTED BY: Joan Davenport, Acting Director of Community & Economic Development
CONTACT PERSON/TELEPHONE: Doug Mayo, City Engineer — 576 -6678
SUMMARY EXPLANATION:
A) The City has a professional services agreement with Berger ABAM under which they
provide the City with project management, inspection services and engineering support
during construction of the Lincoln Avenue Grade Separation Project. Due to the difficulties
that have been encountered in constructing the bottom seal for the Lincoln Avenue
Underpass, the time and cost to construct this project have increased. This consultant
agreement is scheduled to expire in July, and, due to the increased engineering required to
develop other construction options for the bottom seal, the funds will run out by the end of
May. At this time, staff requests authorization to execute Supplement No. 8 of this
agreement, which would compensate Berger ABAM for continuing to provide project
management, construction inspection services and engineering support throughout
construction of the Lincoln Avenue Underpass. This supplement would extend the
agreement to July 31, 2012, and would carry an additional cost not to exceed of $601,482,
bringing the total amount of the Berger ABAM Consultant Agreement Number 2 to
$4,780,726. With the difficulties that have been encountered so far on this project, it is
imperative that we continue to have consistency to ensure federal reimbursement.
Continued on Paqe Iwo
Resolution. (2) Ordinance Contract (2) Other (Specify)
Funding Source: Cumulative Reserve for Capital Improvements; Fund 392
APPROVED FOR SUBMITTAL: "�'b�
City Manager
STAFF RECOMMENDATION: Approve resolutions authorizing Supplement No. 8 with
Berger /ABAM Engineers, Inc. and Supplement No. 1 with
Cascade Project Management, PLLC
BOARD /COMMISSION /COMMITTEE RECOMMENDATION:
COUNCIL ACTION:
(Page Two)
• B) The City also has a professional services agreement with Cascade Project Management
under which they are the City's Representative for the Lincoln Avenue Grade Separation
Project and provide services such as, reviewing the Contractor's schedule, provide
independent project progress and process input and review any potential claims. This
agreement is scheduled to expire in July, and due to the extended length of the project, the
.consultant is warranted salary escalation. Due to some uncertainties that have arisen, staff
deems it appropriate to increase the Management Reserve to the maximum amount
allowable. At this time, staff requests authorization to execute Supplement No. 1 of its
professional services agreement with Cascade Project Management for continuing services -
throughout construction of the Lincoln Avenue Underpass. This supplement would extend
the agreement to July 31, 2012, and would carry an additional cost not to exceed of
$28,535.67, bringing the total amount of the Cascade Project Management professional
services agreement to $440,499.92.
•
•