HomeMy WebLinkAboutR-2000-028 Fire Station No. 1 Remodel (Phase 2) amendment; Davis Opfer Raab ArchitectureRESOLUTION NO. R-2000- 2 8
A RESOLUTION authorizing and directing the City Manager of the City of Yakima
to execute an amendment to the architectural services agreement
with Davis Opfer Raab Architecture, P.L.L.C., for the development
of specifications for and oversight of Phase II construction
activities regarding completion of improvements to the sleeping
quarters of Fire Station No. 1, 401 North Front Street, Yakima,
Washington.
WHEREAS, the City desires that certain improvements be performed regarding
the sleeping quarters of Fire Station No. 1, 401 North Front Street, Yakima, Washington;
and
WHEREAS, on April 6, 1999, the City Council authorized execution of an
architectural services agreement with Davis Opfer Raab Architecture, P.L.L.C., to
provide professional architectural services to develop specifications for and oversee
construction activities regarding Phase I of said improvements; and
WHEREAS, during the 2000 budget process, the City Council approved $85,000
for Phase II and completion of the improvements to the sleeping quarters at Fire Station
No. 1; and
WHEREAS, the City requires professional architectural services to develop
specifications for and oversee construction activities regarding completion of said
improvements; and
WHEREAS, Davis Opfer Raab Architecture, P.L.L.C., is willing to provide
additional architectural services for completion of the project in accordance with the
attached amendment to the original architectural services agreement; and
WHEREAS, the City Council deems it to be in the best interest of the City of
Yakima to authorize execution of the attached amendment to the architectural services
agreement with Davis Opfer Raab Architecture, P.L.L.C., in order to obtain additional
architectural services regarding the completion of improvements to the sleeping
quarters of Fire Stations No. 1; now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
The City Manager of the City of Yakima is hereby authorized and directed to
execute the attached and incorporated amendment to the architectural services
agreement with Davis Opfer Raab Architecture, P.L.L.C., for the development of
(Lk)res/arch-fire sta #1 -mar OO.pm
specifications for and oversight of Phase II construction activities regarding completion
of improvements to the sleeping quarters of Fire Station No. 1, 401 North Front Street,
Yakima, Washington.
ADOPTED BY THE CITY COUNCIL this 21st day of March, 2000.
ATTEST:
City Clerk
(1k)res/arch-fire sta #1 -mar OO.pm
-/Z-6-
ary Place, Mayor
March 15, 2000
DAVIS OPFER RAAB
ARCHITECTURE
Mr. Abel Castilleja, Training Chief
Yakima Fire Department
401 North Front 'Street
Yakima, Washington 98901
RE: Fire Station No. 1 Alterations
Dear Abel,
In response to the recent increase in the scope of work, which combines the two project phases as well as adds the
alterations to the south entry of the Station, we propose a fee increase of $8,900. This increase provides for the
services of this office necessary to design and document the new areas of work added to the project, plus the hours
required to redesign the areas which had already been prepared to go out to bid. This fee also includes the additional
mechanical and electrical engineering fees associated with the scope of work increase. The scope of services
detailed in the attached Fee Calculation and provided by this fee, is as follows:
Davis ® Opfer ® Raab ® Architecture will provide services, including mechanical and electrical engineering, for the
production of Construction Documents for the proposed alterations based on design Option 2 submitted in the
February 3rd meeting. Our firm will administer the Bid Phase and aid the Fire Department in the preparation of the
construction contract. We will provide construction administration services limited to the review of shop drawings,
reasonable assistance to the contractor during construction, three site visits, the preparation of a punch list and one
visit to verify completion of the punch list items. Additionally, we will assist the Fire Department in attaining the
Operations and Maintenance Manuals, as -built drawings and other documentation required from the Contractor to
close out the project.
In the event, that the Fire Department or City wishes to make significant design changes or desires additional
construction administration services the fee will need to be increased accordingly. Our Hourly Rates Schedule is
attached to the original agreement and can be used as a basis for calculating any anticipated fee increasesf
P`- gOoO-28
811 SUMMITVIEW AVENUE SUITE 2 YAKIMA, WASHINGTON 98902 (509) 454-3299 FAX (509) 454-3254
March 15, 2000
Yakima Fire Department
Extra Services Amendment
Page 2
We are very pleased to have the opportunity to continue providing services for the Yakima Fire Department. If the
above fee proposal meets with your approval please have both copies signed and return one copy to this office. This
letter will serve as an amendment for extra services to the agreement dated March 30th for the Station No. 1
Alterations, so please attach your copy to that agreement.
Best regards,
Davis • Opfer • Raab • Architecture, P.L.L.C.
1
Sherlyn M. Davis
Accepted by: City of Yakima
By:
Dick Zais, City ager
4,43
Attest: 9q61-11-1-0-.
Karen
q-R-v-
Karen Roberts, City C141
#9812
Date: 3-22-00 City Contract No. 2000-25
3-22-00Resolution No.
R-2000-28
February 8, 2000
DAVIS • OPFER • RAAB
AR CHITECTURE
Fire Station No. 1 Alterations
Yakima Fire Department
Fee Calculation
Construction Budget:
Original Budget:
Budget Increase:
$47,000
$65,420
Total Construction Budget: $112,420
Original Project Fee: $4,700
Additional Services Required for Project Completion:
Phase
Hours Rate Fee
Design/Const. Doc.
Design 5 $85 $425
Design 20 $60 $1,200
Documentation 30 $60 $1,800
Specifications 10 $60 $600
Estimating 6 $60 $360
Bidding
Cont. Assistance 5 $60 8300
Distribution 8 $35 $280
Contract Preparation 3 $60 $180
Construction
Pre -Con 3 $60 $180
Site Visits (3) 12 $60 $720
Cont. Assistance 18 $60 $1,080
Punchlist/Close Out 8 $60 $480
128
DOR Total
Riley Engineering Fee
Mechanical/Electrical
20
$7,605
$1,300
TOTAL FEE $8,905
811 SUMMITVIEW AVENUE SUITE 2 YAKIMA, WASHINGTON 98902
(509) 454-3299 FAX (509) 454-3254
•
•
•
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No.
i3
For Meeting Of: 03/21/00
ITEM TITLE: Fire Station One Remodel, Phase II
SUBMITTED BY: Yakima Fire Department
CONTACT PERSON/TELEPHONE: Al H. Gillespie, Fire Chief, 575-6250
Martin Buehler, Battalion Chief, 575-6060
SUMMARY EXPLANATION:
This agreement will combine Phase I and Phase II of the remodel project to improve the sleeping
quarters at Fire Station One. Doing this will shorten the construction time of both projects
allowing us to expand the project to include a safer entrance to Fire Station One. Also,
combining both phases and changes infire code requirements will save money on the project
allowing us to stay within the project budget. Total cost of architectural services increased
$8,900 from $4,700 to $13,605. This is 9.3% of the total cost of the project and is within the
budgeted amount. Funding source for this agreement will come from the fire capital fund and is
budgeted for 2000.
This agreement for increased architectural fees incurred by additional services is with Davis,
Opfer, Raab Architecture. It is an amendment to the original agreement approved by Council in
1999.
Resolution X Ordinance Contract Other (Specify)
Funding Source:
APPROVED FOR SUBMITTAL:
City Manager
STAFF RECOMMENDATION: Adopt resolution
BOARD/COMMISSION RECOMMENDATION:
COUNCIL ACTION: