HomeMy WebLinkAbout04/19/2011 09 2011 1st Quarter Capital Improvement Projects Report BUSINESS OF THE CITY COUNCIL • YAKIMA, WASHINGTON AGENDA STATEMENT Item No. For Meeting of April 19, 2011 ITEM TITLE: 2011 1st Quarter Capital Improvement Projects Report SUBMITTED BY: Joan Davenport, Acting Director Department of Community and Economic Development CONTACT PERSON/TELEPHONE: Douglas Mayo, PE, City Engineer, 576 -6678 SUMMARY EXPLANATION: Attached is the Engineering Division's 1 Quarter Capital Improvement Projects Memorandum and Report which includes Water /Irrigation and Wastewater Capital Improvement Projects. Also attached is the current project spreadsheet developed by the Sewer, Water, Irrigation, Streets, Traffic and Engineering Divisions. The current project listing assists in the planning of current and upcoming projects. It helps the divisions coordinate their work so that, for example, a street is not rebuilt or seal coated just prior to planned underground work on the same street. ib New, proposed and continued construction plus construction administration for 2011 is as follows: Engineering: $ 15,000,000 Water: $ 3,000,000 Irrigation: $ 1,600,000 WasteWater Collections: $ 4,280,000 WasteWater Plant: _$ 6,120,000 (additional $7,140,000 in 2012) Total: $ 30,000,000 SEE ATTACHED MEMORANDUM AND REPORT Resolutidn _Ordinance _Contract Other (Specify) Memorandum and Report Funding Source APPROVED FOR SUBMITTAL: City Manager STAFF RECOMMENDATION: Accept Report BOARD /COMMISSION /COMMITTEE RECOMMENDATION: COUNCIL ACTION: 1 -- April 12, 2011 MEMORANDUM 1110 April 12, 2011 TO: Mayor Micah Cawley Members of City Council FROM: Joan Davenport, Acting Director of CED Doug Mayo, PE, City Engineer SUBJECT: 2011 Capital Improvement Projects: 1St Quarter INTRODUCTION This Quarterly Report information is intended to provide an overview of the 1St Quarter for capital projects scheduled for 2011, including current project status, milestones, and any new developments that may significantly alter the schedules or costs of the projects. This narrative report includes Water /Irrigation Division and Wastewater Division Capital Improvement Projects along with the Engineering Division. CAPITAL IMPROVEMENT PROJECTS Railroad Grade Separations; Lincoln Avenue (& Martin Luther King Jr. Blvd.) 1St Street to 1St Avenue; Phase 2 (MLK: Phase 3) This project consists of re- constructing Lincoln Avenue so the roadway will pass beneath the existing BNSF railroad tracks. It also includes constructing a bridge for Front Street that will bridge over Lincoln Avenue. Phase 1 of this project, which relocated utilities for both underpasses, was completed in the fall of 2007. All of the right -of -way required for both underpasses has been acquired. Phase 2 of this project, which constructs the Lincoln Avenue underpass, was awarded to Apollo, Inc. of Kennewick, on February 3, 2010. Construction began in March and this Phase should be completed around November, 2011. Due to the existing soil conditions differing from those anticipated by the design samples, the bottom seal construction method specified in the Plans required modification. We continue to work with the Contractor to determine the most economically feasible method to construct the bottom seal. This setback has extended the length of, and increased the cost of this phase. Design of Phase 3, the MLK underpass, is 95% complete and on hold until the bottom seal construction method is determined. We estimate that the required changes to the bottom seal construction method will result in the MLK Underpass project being about $2.5 million short of being fully funded. We continue to search for additional required funds and hope to go out to bid on the MLK underpass in early 2012. Projected completion date for Lincoln Avenue Underpass: 4th Quarter FY2011. • 1 Washington Avenue — BNSF Crossing Upgrade fb This project consists of upgrading the signals and improving the track crossing by installing new concrete crossing pads. The work is to be constructed by BNSF. A Notice to Proceed was sent to BNSF on August 5, 2009. BNSF installed the new crossing signal in April of 2010. They were scheduled to upgrade the track crossing in November, but it snowed the day prior to them performing this work. ♦ Project completion date: 2nd Quarter FY2011 East Nob Hill Blvd. & Fair Avenue Intersection Reconstruction Design for the complete intersection project has been funded by federal STP funds. The full project will consist of widening the intersection and installing a new mast -arm signal. The southeast corner frontage improvements were constructed as part of the Fiesta Foods development, using SIED and REET 2 monies for a portion of the cost. Due to design demands on the Engineering Division for funded construction projects this project design will be used as a filler project for engineering designers. ♦ Project design completion date: This filler work' will extend into 2011. Yakima Valley Trolley Barn & Museum Preservation Using State Enhancement funds, the City purchased the historic Yakima Valley Transportation Company Trolley Repair Barn and Substation on January 31, 2008. Environmental documentation approval was received to make repairs to the west and south walls and crane system. Bids to make repairs to the trolley barn were received on March 12, 2010, with G.M. McClure Construction submitting the low bid of $119,786.88. During construction, other needed repairs were noted, which have been added to the project. The construction project with G.M. McClure has been completed. With the remaining funds we will restore portions of the 6 -mile track, poles and the overhead system. o Project completion date: 3 Quarter FY2011. William 0. Douglas Trail, 6th Avenue & Bridge Deck Crossing This State Enhancement Grant project constructed a 10 -foot wide asphalt pathway along the west side of 6th Avenue from Hathaway, approximately 0.8 miles in length, which ties into the Greenway pathway. This new pathway connects the Fruitvale Boulevard area to the Greenway path at the Naches River. The 6th Avenue pathway project was advertised on January 13, 2010 and bids were opened on February 3, 2010. 2 Belsass and Smith, out of Ellensburg, submitted the low bid of $259,165. Construction III began on March 15th and has been completed. The project will be closed out in June. ♦ Project completion date: 2nd Quarter FY2011. William O. Douglas Trail Bridge Restoration & Trailheads The purpose of this State Enhancement Grant project was to restore the YVT Naches River Bridge including cleaning, rust removal and painting, along with filling in William O. Douglas Trail gaps by acquiring right -of -way adjacent to nineteen private parcels and to add interpretive signing. The right -of -way plans detailing the needed property acquisition for the pedestrian /bike pathway have been approved by WSDOT, but some of the property owners were not willing sellers. We are looking to purchase property in other areas to fill different gaps. The Yakima County Right of Way Division is under contract to assist us with the Right of Way process. Long Painting Co. completed cleaning and painting the YVT Trolley Bridge in October of 2009. ♦ Project completion date: 3rd Quarter FY2011. Public Works Parking Lot Reconstruction . A 2007 budget policy identified the need for $1 000 000 to complete the three- g P Y � three-year � p Y program to replace and restore the subgrade and pavement at the Public Works Complex using six identified funding sources. $300,000+ was budgeted in each year from 2007 through 2009. During the fall of 2008, $600,000 of pavement and fencing improvements were made to the yard, which replaced sections of asphalt that were in the worst condition. In September 2010 we opened bids for a project to repair a sunken concrete slab in the bus barn, install a sanitary sewer line to treat wash water and upgrade the storm drain facilities on Public Works property. Tri Valley Construction was the low bidder for $284,705. ' ♦ Project completion date: 2nd Quarter FY2011. West Nob Hill Blvd., 50th Avenue to 64th Avenue The City competed for a TIB grant at the end of August, 2008 but was unsuccessful. Huibregtse Louman & Associates (HLA) has completed the design of the project in . anticipation of Federal or TIB funding. Right of way has been acquired for the future project using monies acquired as part of the Wal -Mart development agreement. The project construction remains unfunded at this time. We continue to pursue sources of revenue. ♦ .Project completion date: To Be Determined. • 3 Coolidge Avenue, 80th Avenue to 88th Avenue This roadway reconstruction project was partially funded when it was a County roadway. With the annexation of this area we received the County's developer contributions in the amount of $213,388 along with a $150,000 Corridor Mitigation Air Quality (CMAQ) grant. The City competed for and received another CMAQ grant for an additional $389,000. The right -of -way acquisitions have been certified. Bids for this project were opened on October 4, 2010, with TTC Construction, LLC submitting the low bid of $516,448. Due to the early winter weather, construction was postponed and will begin during the month of April. This work includes paving the roadway, installing curb & gutter on both sides of the road and grading for sidewalk on the north side of Coolidge. Sidewalks and streetlights will be completed at the time of adjacent property development at the developers' expense. • Project completion date: 3rd Quarter 2011. South 16th Avenue & Washington Avenue Intersection This project consists of widening and realigning the intersection to meet the new alignment and recent construction of Valley Mall Boulevard. Right -of -Way has been acquired from all but one parcel (Ding Ho Restaurant). We have received possession and use of the Ding Ho property. The project was advertised on March 22, 2011 and • bids were opened on April 12th. The low bidder with a bid amount of $782,000 is Granite Construction Company of Yakima. Funding of $1.1 Million is through a Transportation Improvement Board (TIB) grant with local match of $300,000 from REET 2 funds. • Projected completion date: 4th Quarter FY2011. Summitview Avenue & North 66th Avenue Intersection This project consists of building a new traffic signal and the addition of left turn lanes on Summitview Avenue and 66th Avenue. Bids for the project were opened on August 4th, with Belsaas and Smith submitting the low bid of $483,786. Construction began on September 20th and was completed in March of 2011. The roadway was widened and the left -turn lanes constructed prior to Thanksgiving. The traffic signals were installed and became operational on January 5, 2011. Funding of $350,000 is through a 2008 G &O bond. A 2009 budget addition added $330,000 for the addition of the left turn lanes. This project has been completed. o Projected completion date: 1st Quarter FY2011. • 4 Capitol Theatre Production Center, Pavilion & Plaza PHASE I — Capitol Theatre - Production Center The Production Center (attached to the back of the Capitol Theatre facility) facilitates the unloading and loading of semi - trucks delivering show equipment. Upgraded electronics required for computerized lighting, staging and sound; address the need for prop and equipment storage; and parking facilities for production trucks. This project is 99.5% complete. Final punchlist items are being resolved. The project completed a base layout including all lighting and electrical equipment for a 499 seat, flexible, "Black Box" theatre affectionately dubbed the "4th Street Theatre ", on the second floor. The Capitol Theatre Company has paid for and completed additional work, purchased seating, draperies, etcetera bringing the 4th Street Theatre into operation this past October. Reconstruction of the adjacent alley with brick pavers and pervious concrete is slated for 2nd _quarter of this year. PHASE II — Capitol Theatre - Pavilion Development of the SE Corner 3rd St. & Yakima Ave. This project is pending funding. PHASE III — Pedestrian Plaza Development of a pedestrian plaza and lobby extension by closing 3rd Street to vehicular traffic between Yakima to Chestnut Avenues. This project is pending funding. TRAHO Architects is the architect for the Project. Leone, Keeble & Moen, a Joint Venture, is the competitively selected contractor for the project and oversees 29 types of subcontracted construction. The updated construction budget, including all design, inspections, fees and construction is set at $6,725,232. ♦ Projected completion date of Phase I: 2nd Quarter FY2011 Kiwanis Park, Upper Park This project consists of building three multi-use ball fields including field lighting, restroom facilities, a volleyball court, a basketball court, a skate park, a playground, a concession /restroom, new sidewalk and pathways, and parking. Funding includes $500,000 from a Recreation and Conservation Office (RCO) grant, $500,000 from YSD for field lighting, plus funding from various local service clubs. Sun Yakima LLC purchased the property adjacent to the existing Kiwanis Park, cleared the property and donated the property to the City of Yakima. The skate park has been constructed with funds donated by the Apple Valley Kiwanis Club. The playground was purchased and installed by Downtown Yakima Rotary. The basketball court has been constructed with funds donated by Yakima Southwest Rotary. A 30'x30' covered picnic shelter was constructed with funds donated by Sunrise Rotary. A project that constructed parking spaces and sidewalk connecting the walkway from Fair Avenue to Gateway Park along Maple Street was recently completed at a cost of $123,000. A project has been awarded • to Ken Leingang Excavating for $45,000 to prepare the site for the new ball fields, with 5 that work beginning as soon as weather permits. It is anticipated that the project to construct the ball fields, field lighting, the pedestrian pathway and west parking lot will be advertised for bids in late May. The concession /restroom building will be constructed with the help of local service clubs late in 2011 or in 2012. • ♦ Projected completion date: Fall 2011 Underground Storage Tanks at Yakima Airport The City received a 75% site cleanup grant from the Department of Ecology to locate, assess and develop a plan to remediate, if necessary, contamination remaining from previously removed underground storage tanks. The project has been completed; wells were placed for monitoring; and final monitoring occurred in 1St quarter 2011. Final reports are complete and the project is pending finalization by the DOE. ♦ Projected assessment and project completion date: 2 Quarter 2011 Downtown Futures Initiative Phase 4: 8th Street and East "A" Street This project is a continuation of the Yakima Downtown Futures Initiative and is funded with $1.5 million of state fund and federal funds ($1 million from a Washington State Department of Commerce grant and $500,000 of Community Development Block Grants, CDBG). The limits of this new project include: Both sides of 8th Street between 'A' Street and Chestnut and the north side of 'A' Street from 6th Street to 3 Street. Along 8th Street project construction includes new sidewalk, pedestrian street lighting (historic style, 13 foot tall lights with dual planter arms), additional planters, trees and tree grates, tree lighting, overhead festival lighting, an automatic irrigation system, wheelchair ramps and new curbing as needed. Along the Yakima Convention Center the alignment of 8 Street will curve easterly away from the Convention Center allowing for an adjacent 7,000 sq. ft. outdoor plaza for facility use. Bids for the 8th Street project were opened on June 8, 2010, with the low bid of $589,339 being submitted by Belsaas and Smith. Construction began on July 12, 2010 and the ribbon - cutting and dedication ceremony took place on October 21, 2010. As there was a delay by the factory due to quality control issues on the manufacture of the bench and trash receptacles, the benches and trash receptacles were installed the first week in January. Along 'A' Street project construction includes new sidewalk, pedestrian street lighting (historic style, 13 foot tall lights with dual planter arms), trees and tree grates, tree lighting, an automatic irrigation system, wheelchair ramps and new curbing as needed.. Bids were opened on August 10, 2010 with the low bid of $417,189 being submitted by West Coast Construction Co., Inc. Construction began on September 20th. The project was substantially complete before Thanksgiving except for the acquisition and installation of electrical panels. The electrical system was completed in January. The project should be completed in April. ♦ Projected completion date: 2 Quarter FY2011 6 South 2nd Avenue: Street Improvements, Yakima Avenue to Walnut Street 0 . This project removes the abandoned and unused trolley tracks on 2nd Avenue, and renovates the centerline of the roadway with concrete roadway and five (5) irrigated planters. Design is nearly complete for this project that is funded with REET funds of $150,000. The project should advertise for bids in late April. ♦ Projected completion date: 3rd Quarter FY2011 South 16th Avenue Grind & Overlay: Nob Hill Blvd. to vicinity Washington Avenue This project will grind the outside lanes of 16th Avenue, while the asphalt overlay will be placed over the full width of 16th Avenue increasing cross- street drainage. Additional project work includes construction or upgrading wheelchair ramps as conditions warrant. This project is funded with $500,000 of REET2; Construction will tie into the 16th & Washington Avenue intersection reconstruction project. Bids were opened in October 2010 with the low bid of $467,570 being submitted by Columbia Asphalt & Gravel, Inc. Construction is scheduled to begin in April, 2011. ♦ Projected completion date: 2nd Quarter FY2011 110 South 64th Avenue Roadway Widening: Nob Hill Blvd. to Tieton Drive This project will widen this section of 64th Avenue to a 39 -foot roadway (14'- 11' -14') with curb and gutter on both sides of the road, and a 7 -foot sidewalk on the west side of the road. Street lighting and a stormwater runoff treatment system will also be constructed. The project is funded by a $900,000 Surface Transportation Program (STP) federal grant and $200,000 from the Wal -Mart Development Project. The project will begin design this winter; right of way acquisition will be started early in 2011, with construction occurring in 2012. ♦ Project completion date: 3rd Quarter FY2012 Powerhouse / William O. Douglas Trail Connector, vicinity Willow Street This project will construct a paved pathway that will connect from the Powerhouse Canal Trail at 14th and Swan Avenues to the William O. Douglas Trail on 6th Avenue at "I" Street. Once this project is completed, the Powerhouse Trail, William O. Douglas Trail and Yakima Greenway will be connected and complete a 6.5 -mile loop. The project is funded by a Transportation Enhancement Grant of $283,278. The project should be designed this year with construction beginning in the spring of 2012. ♦ Projected completion date: 2nd Quarter FY 2012. 7 Energy Recovery Grant & Energy Efficiency and Conservation Block Grant Program • These projects are funded by a combination of American Recovery & Reinvestment Act (ARRA) funds and Energy Efficiency and Conservation Block Grant (EECBG) funds totaling $285,000 as well as incentives. The City Facilities Lighting Upgrade Project includes retrofitting with efficient lighting at City Hall, Yakima Public Affairs Channel (Y -PAC), Fire Station 94, Fire Station 95, Public Works Complex, & SE Community Center. The City Facilities HVAC Project includes Fire Station 95, Yakima Public Affairs Channel (Y -PAC), & City Hall (Council Chambers). Design of the City Facilities Lighting Upgrade Project is 95% complete and should be advertised for bids in late April. The HVAC design consultant, Hultz /Bhu Engineers Inc., from Tacoma, WA has begun designing the HVAC upgrades. It is anticipated that the HVAC Systems Upgrade project will advertise for bids in May. ♦ Projected completion date: FY 2011 Yakima Sawmill Redevelopment Staff review has begun on the multi - phased redevelopment of the former sawmill and plywood plant. Public funding sources include a commitment from the State of Washington in 2009 for up to $25 million of tax increment financing and a SIED loan in • the amount of $500,000 from Yakima County to provide for the engineering design of new roads and utilities. The City and sawmill property owners are developing a master plan for over 200 acres of interstate frontage property to include retail - commercial, office - medical, light industrial, residential and open recreation space. Project planning will continue and project design will begin this year. The City has sent out a Request for Proposals (RFP) to engineering consultants for the infrastructure design. ♦ Project completion date: To Be Determined. North 1St Street Corridor Revitalization In 2010, the City received a $25,000 planning grant through Yakima County SIED funding for the first segment of this project; a comprehensive approach to planning for future improvements to North First Street from "A" Street to the US- 12/I -82 Interchange. The North First Street Improvement Study will begin early this year to develop a design and action plan to address potential arterial street design alternates including an analysis of resulting traffic flow, streetscape and landscape improvements, and required utility upgrades. A final study document is expected to be completed by late summer 2011. Project design will begin as funding allows. ♦ Project completion date: To Be Determined. 8 • South 64th Avenue & Washington Avenue: Signal Construction This project will construct a traffic signal at this intersection. Street lighting and electrical conduits were installed with intersection construction in 2006. The project is funded by $250,000 from the Wal -Mart Development Project Design will begin mid- year with construction occurring in 2012. • Project completion date: 2nd Quarter FY2012 OTHER TASKS SERVICE TO OTHER DIVISIONS Service to other divisions continues to be provided. Miscellaneous work has included: Sewer extension and restoration projects, legal descriptions for annexations and vacations; updating irrigation, water and sewer maintenance reference maps; surveying and mapping; miscellaneous assistance to Police, Planning, Streets, Airport, Public _ Works Divisions and Public Works facilities, Yakima Convention Center, Fire Department, including remodels and miscellaneous projects, and the Capitol Theatre for capital improvement projects; Purchasing Division, etcetera. We currently have one (1) area considering pursuit of a Sanitary Sewer Local Improvement District.(LID) and one • (1) area considering pursuit of a Roadway Improvement District (RID). We recently provided or are providing engineering assistance for: • Convention Center: reroofing, partition recovering and stucco repairs. • Capitol Theatre Remodel; provided design and construction oversight. • Several small drainage improvement projects. � _ 9 . Water /Irrigation Division Capital Improvements Projects General 308 Irrigation System Phase g y 4 /Stage 1 Improvements This project consists of replacing irrigation main and services in the General 308 Irrigation District. The limits of the project are from North Naches Avenue to North 8th Street and from East " "A" Street to East "F" Street. The project will also replace a portion of the transmission main located along Hwy 12 west of North 40th Avenue. Huibregtse, Louman Associates completed the design and the project is being constructed by KRCI, LLC of Wenatchee, WA. Construction is approximately 90% complete, with only alley restoration left to take place. The project is anticipated to be completed by mid -April 2011. City Irrigation crews have also replaced various portions of the irrigation main and services in the General 308 System. ♦ Project completion date: 2nd Quarter FY2011. Capitol Hill Irrigation System Phase 2 Improvements This project consists of replacing irrigation main and services in the Capitol Hill Irrigation District. The general limits of the project are between South 7th Avenue and South 12th Avenue, West Yakima Avenue and Tieton Drive. Huibregtse, Louman Associates completed the design and the project is being constructed by Premier Excavation, Inc. of Pasco, WA. Construction is approximately 90% complete, with only alley restoration left to take place. The project is anticipated to be completed by mid -April 2011. ♦ Project completion date: 2nd Quarter FY2011. Fruitvale Canal Improvements Part of this project will replace an open ditch irrigation wasteway /canal with a piped irrigation line along East H Street from North 6th Avenue to North 9th Street. Huibregtse, Louman Associates, Inc. has completed a design report, providing a preliminary design and project costs. Project design is continuing and is expected to be completed in 2011. Project design is begin coordinated with potential street improvements on East H Street. The project will be broken into phases and be bid as funding for construction becomes available; including potential grant or other outside funds. The rest of the project is to consolidate the river diversions for Fruitvale Canal with the diversions at the Nelson Dam. Project is being designed in cooperation with the Bureau of Reclamation, Washington Depart of Fish and Wildlife, Yakima County and North Yakima Conservation District. ♦ Project completion date: On- going. 10 Gardner Park Domestic Well The project installs a new 3,000 gpm domestic well in Gardner Park, located at Cornell Avenue and West Pierce Street. Construction on the project began January 2009. The well was drilled to a depth of 1,328 feet. Well screen and casing has been installed and pump testing of the well has been completed. Golder Associates has completed the design and William Charles West of Kennewick, WA is expected to begin construction on April 11, 2011. The project report, construction approval and source approval documents have been approved by the Department of Health. The pump station is expected to be competed and the well on line late -2011. ♦ Project completion date: 4th Quarter FY2011. Water System Plan Update The last Water System Plan was completed in March 2004. An update must be completed every six years. This project will update the current plan by providing current information on the existing water system infrastructure, production and consumption data, future demand forecasting, water use efficiency, operation and maintenance, future capital improvements, rate structure and revenue forecasting. Thomas Coleman, PE Consulting Services has been hired to assist with the plan update in coordination with City staff and the Department of Health. The draft plan has been ® submitted to DOH for review and comments. ♦ Project completion date: 2nd Quarter FY2011. East Viola Avenue (1 -82 Crossing) Waterline Replacement The project will replace an undersized, deteriorating waterline crossing under I -82 at East Viola Avenue, between Rudkin Road and the Wastewater Treatment Plant. Replacement of the waterline will improve flows and reliability in this part of the water system, as well as replace a sub - standard, direct bury waterline across I -82 with a new ductile iron waterline in a steel casing within the limits of the interstate highway. Huibregtse, Louman Associates has completed the design. The project will be constructed as funding becomes available. ♦ Project completion date: On- going. Water Treatment Plant Backwash Recycle Upgrade The project will replace the unlined backwash recycle pond with new lined recycle ponds. Huibregtse, Louman Associates developed a preliminary design recommendation and report to submit to the Department of Health for approval. We also submitted a 2010 Drinking Water State Revolving Fund (DWSRF) Application, which was not approved. • 11 A DWSRF application has been submitted for 2011 and is currently being considered. Funding sources will continue to be pursued to complete the project. ♦ Project completion date: On- going. Wastewater Division Capital Improvements Projects Digester Cover Replacement Project This project was contracted in the 1St Quarter of 2009 and construction began in the 2nd Quarter of 2009. The project included the replacement of the three secondary digester covers with new membrane gas holder covers; replacement of secondary cover blowers, air piping, Motor Control Centers (MCCs), local control panel and associated digester system accessories; improvements to the Secondary Digester Control Room, and Primary Digester electrical Room; replacement of the existing Dissolved Air Flotation Thickener (DAFT) mechanical system, improvements to plant SCADA system, sludge piping improvements; modifications to the plant electrical distribution system and; dredging of an existing storage lagoon. The project is 98% complete. Air and gas leaks have been resolved and the digester covers have been in operation since the end of November 2010. • Project completion date: 2 Quarter FY2011 • Second Phase of the Speedway Race Street Interceptor The Engineering Division is designing the remainder of the Speedway Interceptor that will eliminate Race and Beech Street Lift Stations and extend a 36 inch sewer main to the sewer main at 8th. Street and Beech at the Washington Middle School. The exact route is being planned and will be determined by the ability to get a Franchise from the Washington State Dept. of Transportation (WSDOT) along I -82. The franchise has not been approved by WSDOT yet and it is hoped that this approval will be given so that Engineering can design the Interceptor this year. ♦ Projected project completion date: 4th Quarter FY2012. Wastewater Facility TMDL (Struvite) Project Design is being done by Pharmer engineering and is 95% complete. When constructed this project will begin reducing our nutrient concentrations in the wastewater effluent discharged to the Yakima River as required by the Department of Ecology. The construction will include the fabrication and installation of a reactor to harvest phosphorous and the installation of eight (8) mixers in the aeration basins to augment nutrient removal through the reactors. 12 • Design completed: 2nd Quarter 2011 • ♦ Contract bid and award: 2nd Quarter 2011 ♦ Projected project completion: 4th . Quarter FY2011. Wastewater Facility, Collection System Plan Update & initial Stormwater Comp Plan The last Water System Plan was completed in February 2004. This project will update the current facility plan by providing current information on the existing wastewater facility and collection system infrastructure, regulatory requirements, future loadings, operation and maintenance, future capital improvements, rate structure and revenue forecasting. With the adoption of the new Stormwater Regulations a comprehensive Stormwater system plan is needed and will be implemented along with the Wastewater Facility and Collection system plan update. Akel Engineering Group, Inc. was selected in the last of the 3rd quarter of 2010 to develop these plans. ♦ Project completion date: 2nd Quarter FY2012. Levee set back Project and new Wastewater Outfall Staff continues to be involved in the Gap to Gap project for flood plan restoration which P Pp J p will include the Wastewater Treatment Plant to relocate or develop a new wastewater outfall. Alternatives will be evaluated to select a new outfall location. Currently the old Wastewater spray field is being evaluated as a riparian outfall. An engineering report for alternatives like this will be developed and submitted to Ecology for approval. ♦ Project completion date: 4th Quarter FY2012. Stormwater Capital Improvements Projects Yakima Underground Injection Control (UIC) / Water Quality Retrofits This project will design and construct prototype Underground Injection Control (UIC) retrofits to the City's' existing 436 UIC facilities. The Department of Ecology is providing a grant of $280,000 for the development of different methods to retrofit existing facilities & structures. ♦ Project completion date: 4th Quarter FY2014. • 13 PRIVATE PROJECTS (Current Listing) 0 Listing private developer projects shows the amount of private projects that are "on the books" and pending or under construction with some (not all shown) that go back several more years. These projects have all been approved since February 2008 and are either pending construction, under construction, started but not completed or recently completed. The projects, most recent at top, include: Project Name _ Location Improvements Anderson Park Occidental & 64th Ave. Site Improvements Yakima Bears Executive Viewing Deck Pacific & 12th Ave. Water line alignment YV Technical Skills Center / 4 Unit Add 1118 S. 18th St. Site Improvements YVMH Spinal / Phase II 1450 N. 16th Ave. Storm Drainage J.M. Perry Parking Lot / Perry St. 1800 Perry St. Parking Lot South 81st Place Short Plat - Sewer 81st Ave & Tieton Water, sewer & new street Columbia Reach Storm Water 3107 River Rd. Storm Drainage 20th Ave. & 22nd Ave. Street Imps 20th / 22nd Ave's & River Rd. Site Improvements Cameo Court at Apple Tree / Streets Coolidge Rd. / 86th Ave. Site Improvements Grace Brethren Spanish Church 202 W. Mead Ave. Parking Lot Malibu Subdivision Chestnut & 67th Ave Site Improvements Mountain View Estates Chestnut & 66th Ave. Site Improvements Panda Express at Wal -Mart Center 6560 W. Nob Hill Blvd. Site Improvements Dr. Tew's Dental Office 9000 W. Nob Hill Blvd. Site Improvements • Cameo Court at Apple Tree / Sewer 8700 Coolidge Rd. Sewer Extension Supercold CA Storage 2002 River Rd. Storm Drainage Scenic Estates N. 80th Ave. Site Improvements Fair & Maple Convenience Store Fair Ave. & Maple St. Site Improvements Future Fun LLC Drainage 715 S. 2nd St. Storm Drainage 27th Avenue Sewer Extension 27th Ave. & Loren Court Sewer Extension Summit Crest Commercial 48th Ave. & Summitview Site Improvements Development Bob Lynch Parking Lot 1102 S. 40th Ave. Storm Drainage J.M. Perry West Parking Lot Repaving 2011 W. Washington Ave. Parking Lot Francis McSharry Short Plat 8905 Tieton Dr. Street Wellington Estates Phase 4 60th Ave. S. of Washington Site Improvements Fiesta Food Expansion 1112 E. Nob Hill Blvd. Site Improvements Living Care Parking Lot 3801 Summitview Storm water Steve Skeel Sewer Extension 83rd Ave. & Tieton Dr. Sewer Extension Hospice Care Center S. 48th Ave. Site Improvements Toscana LLC Castlevale & Kern Rd. Site Improvements Powerhouse Villa Phase 1 5321 W. Powerhouse Rd. Site Improvements Hidden Lakes Washington Ave. & 72nd Ave, Site Improvements Wilson Properties 16th Ave. N. of McKinley Sewer extension Golden Corral 1901 -1915 S. 1st St. Street improvements Hollow Creek Place Short Plat S. 27th Ave. Hollow Creek Pl. Street Improvements WestTowne Center - Riverside Mall 16th Ave., River Rd & 6th Ave Mali Site Development Rite Aid - Nob Hill Blvd Nob Hill & 24th Avenue Site, Water, Sewer & SD 14 Washington Mid School Portable Unit 510 S. 9th St. Site Improvements Franklin Middle School Portable Unit 410 S. 19th Ave. Site Improvements Hoover Elementary Sewer Extension _ 400 W. Viola Ave. Site Improvements _ Advanced Secure Storage Drainage 1913 McKinley Ave. Storm drainage • All Services Parking Lot 715 E. Viola Ave. Parking Lot AFFIRMATIVE ACTION GOALS & WIMIDBE PARTICIPATION W/M /DBE utilization has been included in the past but is not included with this report. The Engineering Division continues to request apparent low bidders of public works contracts to document their efforts to achieve the City of Yakima's goal of 10% MBE, WBE or DBE participation goal prior to contract award. However, changes in state law due to the passage of Initiative 200 prohibit certain practices by contracting agencies (i.e. the City) for the award of public works projects such as requiring W/M /DBE subcontracting. While some contractors have voluntarily reported such information in • the past, we have not received any such reporting this year. • Although we do not receive such information voluntarily, the City must still meet certain of these federal requirements and each contractor must comply with the Standard Specifications that are included on each City Public Works Contract. The City is responsible to: • Conduct pre- construction conferences during which EEO and City policies are discussed with the contractor. • • Monitor on -site compliance with the EEO and City policies. • Ensure our contractors locate, qualify, and increase the skills of minority groups, women employees, and applicants for employment as required by City policies. • Ensure the preparation of required EEO and related reports. • • • • • 15 I i l II II II I Proj Proj. Impacted Conslrctn. Notes Lead Division Project Name /Location Description of Work Project Lead Status /Schedule 0112111 Type No. Divisions Start Date Engineering, Pro t s scheduled tor comp letion ta11-2011; Underpass on Lincoln; (MLK Jr. Apollo Inc, Kennewick, was low bidder; Detours in lec i 1918 FUR Grade Separation, Phase II; Bob Desgrosellier / Water /Irrigation, Phase 11, Main Underpass wall construction continues; 1 CIP Phase II Engineering Lincoln Ave.; 1st St. to 1 sl Ave. Blvd. late in '10); Front St. over Brett Sheffield Wastewater, PW, Project, 3/10 Place; Wall columns proceed: Bottom Seal re- Work includes fuel station reconstruction, Lincoln (& MLK Jr. Blvd.) Streets, IS started; Railroad Bridge will start in April. Work on bottom seal has re- started Separation, Phase 111; Underpass on MLK Jr. Blvd. Engineering, Construction proposed starling June 2011; 1818 R/R Grade Se P P We will be read to advertise for 2 CIP Phase En eerin Martin Luther Kin Jr. Blvd., under railroad, Front Street Bob Desgroselher / Water /Irrigation, Phase III, Main Design is a t 95 %; RAN is i n hand; c y • I! gin g g Brett Sheffield Wastewater, PW, Prolecl, Nov. 11 Potential Federal Senate earmark not likely; onshuction of the MLK Underpass Ill ( "B" SI.) 1st St. to 1st Ave. over MLK Jr. Blvd. Streets, IS when the remainder of funding is secured $1,5M State TIB grant and / or STP award Fueling Station Addition @ 1st St. & Build a remote fueling station Engmeering, Public Proposed at ARCO lot, 1st SI. & Lincoln Avenue Demo of the ARCO budding is complete; Engineering / Bob Desgrosellier / II 3 CIP 2192 public Works Lincoln for City -owned vehicles ?? Richard Wormer Works 3/2011 ? after Grade Separation construction. $1005 was available ?. pump station reconsliucuon near end of project; fuel station proposals have been submitted BNSF will be placing new RxR signal work has been complete, W ashinglon Avenue - BNSF crossing Brett Sheffield / Bob Engineering, Traffic, BNSF work, BNSF has the new signal in place and is finalizing gna com pee, 4 CIP 2063 Engineering concrete crossing pads with roadway crossing reconstruction Is pending upgrade Desgrosellier Water /Inig early 2010 the crossing replacement {weather delayed this work, complete in Apnl ?) signal upgrades . • Purchase of YVT property and Strengthened shonng of west wall; neenn YVT Barn &Museum Preservation Brett Sheffield/ Project awarded to GM McClure of Yakima, I 5 CIP 2153 En gi g preserve carbarn and museum gob Desgrosellier Engineenng 12/2009 99 %complete; finalizing cleanup - straightened south wall; buildings and site More work possible with remaining funds • New pathway on 6th Avenue. T I; • W.O. Douglas Trail, 6th Avenue & Street to YVT Bridge over the Brett Sheffield / Project has been awarded 6 CIP 2166 Engineering Bridge Deck Crossing Neches River, pathway rtes to Bob Desgrosellier Engineenng Spring 2010 to Belsaas & Smith of Ellensburg; Construction has been completed. 11 ■ the Greenway work is complete &being closed out W.O. Douglas Trail Bridge Strip YVT Bndge and repaint; Brea Sheffield / Right -of -way purchases are under way for property in 7 CIP 2167 Engineering Restoration and t railheads purchase some trailhead Bob Desgrosellier Engineering 8/17/2009 Bridge Restoration and repainting is complete the Covache Canyon area; - property & interpretive signs some purchases made, & will continue Remove & rebuild P.W orks Project award 10 :Tri- Valley, low bidder; Phase 3 includes the interior parking garage Engineering/ Public Works Parking Lot Brett Sheffield /Bob All Divisions al P p drainage improvements • $1M 10/2010 Work is 95 %com lets. floor repair as well as storm drain Public Works Reconstruction @ Fruitvale Blvd Desgrosellier Public Works budgeted over 3 years Should be completed in April only repaving of the trench remains to be done • Engineering, Traffic Project tied to the Wal -Mart project. There may be Design is 90% complete; We'll submit for Widen roadway, add sewer & Brett Sheffield / Eng., Wastewater a private / public partnership on construction; some I 9 CIP 2272 Engineenng Nob Hill Blvd, 49th to 64th Avenues water utilises Bob Desgrosellier TIB grant denied RlVJ was purchased with W al -man mitigation Public Works Trust Fund Loan in May 2011; funding Construction UN- FUNDED I I ■ 2217 Coolidge Ave. 80th to 88th 82217; Project to pave 28' asphalt Engineering, Traffic Bids open 9/23/10, Project award to TTC 10 CIP 2271 En neerin Coolidge Sewer #2271; ribbon, w/ curb 8 Brett Sheffield / Construction delayed, will star) in late April, gi g ge gutter, Bob Desgrosellier Eng., Wastewater April 2017 Construction, Yakima; Work to start this year bids delayed due to extended Fi/V✓ acquisition. 2269 Coolidge Drainage #2269 includes sanitary sewer & be started in spring 2011 >" qui Engineering, Traffic, E. Nob Hill Blvd & Fair Avenue, Widen intersection all 4 legs; Brett Sheffield / Design only at this time beginning 6/2008; Design only; (Drainage system 11 CIP 2143 Engineering Wastewater, Design only Intersection Improvements purchase r/way; new signal Randy Tabert Search for funding on -going for this intersection is included.) Water /Irrigation I 16th Ave. & Washington Avenue Widen 16th to match V. Mall Brett Sheffield / Engineering, Traffic, Design completed & RNJay is in possession: 12 CIP 2232 Engineering Wastewater, Summer 2011 • Bids were opened 4/12. TIB Grant of $1 -1 Million, intersection reconstruction Blvd.; replace signal Dan Ford Water /Irrigation Granite Construction Co. is low bidder. match with $3005 BEET 2, I Engineering, Traffic Project awarded to Columbia Asphalt & Gravel, 76th Ave; Nob Hill to Washington Brett Sheffield / This project will tie to terminus of 13 CIP 2270 Engineering Grind & overlay existing asphalt Eng., Wastewater, 4/2011 Funded by REET2; Project work cannot be started I Grind & Overlay Randy Tabert Water 16th &Washington Avenue project due to weather; work to start April 18th 66th Avenue & New traffic signal with current Brett Sheffield / Construction started 9/20/10; Project paved, sidewalks are in place; Work is 100 1 II 4 CIP 2191 Engineering Engmeering, Traffic 9/20/10 g p going through final closeout Summitview Avenue Signal street alignment Dan Ford Low bidder: Belsaas & Smith, Ellensburg complete; Capitol Theatre - Utilities 6/08; TRAHO is Architect; GC /CM Contractor Leone, production Center Const. only al this time; Funded by • Engineering Facility Addition & Remodel - Bob Desgrosellier / Engineering, municipal bonds, PFDislnct & private donations from 15 CIP 2231 En New Production Center on 4th SL Phase 2 start - Keeble & Moen (Joint Venture); Project is 99 %; '(8 Black Box Theatre) (Production Center current) Michael Morales Capital Theatre 8/17/09 Placement of pavers in alley to occur m spring Theatre benefactors; Doing final 11 touchups and air - balancing, noise reduction Multi-use ball fields: RCO grant 55005 -e local$; overall design 50%; Little League / Softball Fields to be graded in 16 • CIP 2212 Engineering Upper Kiwanis Park; (Little League / Softball); Doug Mayo / Engineering, Parks 7/2010 Maple Street parking project complete; March/April, construction starts later spring; 1 Fair Ave & Maple Street lighting; volleyball; basketball, Brett Sheffield Restroom, Playground Jungle -Gym & 30'030' picnic Lighting; volleyball; parking shelter built by volunteers more parking & walking path planned I Remove Underground Storage Underground Storage Tank Removal Doug Mayo / Work is complete; DOE grant Included locating, assessing and 17 CIP 2274 Engineering Tanks & remove /replace Engineering, p at the airport Brett Sheffield Waiting for DOE review and approval of report; developing a plan to remove unused UST ineerin Airport 2009 's contaminated soil II Richardson Field Cleanup Remove & Replace 4,000 CY Doug Mayo / DOE grant included removal and replacement Project is complete and closed out; 18 CIP 2145 Engineering at the airport of contaminated soil Brett Sheffield Engmeering, Airport 2009 of 4,000 CY of contaminated soil move to completed next quarter Realign 8th Street, remove & Engineering, Streets Realign and reconstruct 8th Street from "A' to I I 19 CIP 2284 En Downtown Futures Initiative (DFI), replace sidewalk, place new Brett Sheffield / & Traffic Eng., Yakima Avenue; Rem/Rep1. sidewalks north of Belsaas & Smith: low bidder; work is complete; Engineering 7/2010 Phase 4; 8th St., 'A" to Chestnut pedestrian lighting, trees, Bob Desgrosellier Water/Irrigation, Yakima Ave., place trees, went to Council on 3/15 for closeout twinkle lights, landscaping Wastewater twinkle lights and ped lights "A" to Chestnut , Move north curb, widening Engineering, Streets West Coast Construction Is low bidder; work stoned Downtown Futures Initiative (DR), street, remove & replace DYFI -4 and HUD funding; Remaining work is asphalt Brett Sheffield / & Traffic Eng., 9/20 /10:95 %complete; Rem/Repl. sidewalks; place 20 CIP 2299 Engineering Phase 5; "A" St., 3rd to 6th Street, sidewalk- ,ouchup, restriping of angle parking and finishing Bob Desgroseher Water /Irrigation, trees, twinkle lights and ped lights on 'A' St., 3rd to II north side lighting, trees, twinkle lights, Wastewater 6th. north side only planters as weather permits ' landscaping - Roadway, Sidewalk (Pathway), Funding by $9005 of STP & $2005 of This road section to be 3lanes, 7' sidewalk on west 1 ���� 64th Avenue; Doug Mayo / 21 CIP E ngineering Storm Drainage, Street Engineering, Streets 2012 Wal -Mart mitigation; Surveying completed; side; storm drainage & street lighting; I Nob Hill Blvd. to Tieton Drive Brett Brett Sheffield R/W and design to start in 2011. design 5$ has been obligated - Reconstruct intersection, widen - Partial funding by part 0152005 of Wal -Mart This intersection reconstruction and I Tieton Dnve and 64th Avenue Doug Mayo / I 22 CIP 2282 Engineering for additional lane on Tieton Engineering, Streets 2012 mitigation; Design to start In 2011 while funding is signal addition project is lacking Intersection Drive; add signal Bred Sheffield r/way needs will be identified R/Way & construction lundmg I 11111 . 0 . I . all . I I • o • • 1 • Proj Proj. Lead Division Project Name /Location Description of Work Pro ect Lead Impacted Constrctn. Notes j Status /Schedule Type No, 4/12/11 Divisions Start Date S. 2nd Avenue, Remove trolley tracks from Doug Mayo / Design Is at 72.6 %; Remove trolley tracks & rebuild center of roadway; 23 CIP 2286 Engineering Yakima Avenue to Walnut Street roadway; add planters to pan Brett Sheffield Engineering, Sheets 2011 Funded with $150,000 REET Funds; add planters to portions of roadway center; of center of roadway Bids to be requested in spring 2011 , midblock x -walk for pedestrians? City Hall Demolition of Remove jail cells, interior walls Doug Mayo / Demolition 100% complete; Window replacement 24 CIP 1783 Engineering & asbestos abatement; g y En n g, Work and all project cleanup should he II interior 3rd and 4th Floors Bob Desgrosellier gi eerin CED 2010 complete; window sealant to be completed when Rem /Re.lace windows weather sta above Ireezin. completed by the end of Apnl( ?) I I ®® 2297 Engineenng Willow, 20th l0 241h 8 sanitary sewer Doug / En in-house; ouse; Funded through Wastewater, work being done NEW (Swan dropped, but is now back in) Brett Sheffield Wastewater (Additional easements for Swan needed) to determine easement and R/W needs Energy efficiency upgrades at Doug Mayo / Engineenng. Traffic. Design for this multi-year/multi-phase Fsergy Recovery Grant: g project is Work also includes upgrade l0 75+ street lights, Nona Engineering gRRA - funded PAL Center; SE Comm Center Dan Ford / WW 2011 Summer /Fall 2010 nearly complete; Lighting proj 2011 0 7 Survey and design started in-house; is pending final Construction to be gin early spring 2011 8 Public Works Joe Rosenlund Wastewater ater /Irri work locations HVAC tlesi.n be.innin. LID N/A Engineenng Sanitary Sewer LID - Letters sent out upon Doug Mayo / Engineering, II I "NEW Alpine Way, 68th to 71st Avenues neighborhood request Scott Schafer Wastewater ?77 LID is just in the investigative stage A petition is being circulated by neighbors II ■ Fs jnei,int 9 Doug Mayo! Powerhouse / William O. Douglas Connector of Powerhouse Path Work completes a 6.5 mile pathway loop; 9 Engineering. Water, CIP 2301 NE W Trail Connector; to WODouglas Path & Dana Kallevig Parks 2012 Survey &Design in 2011, build in 2012 Funded by a Transportation Enhancement Grant of -° vicinity Willow Street Greemvay New rights of way, public $283,278 Engineering, Streets 208 Acre privately owned site for development as a "En ineerin utilities, roads, lighting, Designs anticipated to be pedestrian friendly, office l 'Engineering' , Yakima Resources / Michael Morales / & Traffic En Revenue Development Area (RDA); ilex" business park uses, public and residential CIP 2295 - • N_ EW _ • Old Boise Cascade Sawmill Property signal(s), sidewalks, pathway, g - ' 2013? 7 7 allows stale di nation of this ro ect area I, P rty i Doug Mayo Water /Irrigation, 9 P 1 infrastructure as a "LIFT" District; SIED $ in project as well; development, facilities, recreational; RFD is cut for Wastewater pr jec infrastructure design of Phase I _ .: . . PLSA is getting survey info for WasteWaler East -West Connector, "H" Street New rights of way, public Engineering, Streets En gi neenn r all utilities, roads. lighting, Yakima County Trait 100 many Committee has had This on their project CIP 2295 gi. 9 alignment from FruiNale Blvd to 9 9. Michael Morales / & Tragic Eng., C ty is project lead; they are moving NEW ; Terrace Hls., through Yakima signal(s), sidewalks, pathway, 2013? ? ? ahead with preliminary desi n and listing for many years; Consultant has been hired to 9 Doug Mayo Water/Irrigation, P ry g create design alternatives Resources roe mlrastructure initial environmental clearances P P rty Wastewater - and pre - environmental documents Design planning for future Engineering, Skeels CIP 9999 °' Engineering North 1s1 Street Corridor street renovation, designs and Michael Morales / & Traffic Eng., TBD 2010 SIED grant provides $25K for planning Study documents to be NEW Revitalization; "A' Street to 1-82 utility upgrades • Doug Mayo Water /Irrigation, the comprehensive project completed late summer 2011 Wastewater • CIP v?ov ' . 64th Ave & W ashinglonAvenue New traffic signal with current Doug Mayo / Signal is warranted; Design late spring; The intersection should only need signal poles, mast ' ; NEW . Signal construction street alignment Rand Tabert Engineering, Traffic Fall 2011 arms & a controller base, cabinet & controller added. .. - Y funding from Wal-Mart mitigation Electrical conduits are in place. i E PENDING ONDS development; Engineering, Streets Project If funding is successful. Fs meenri Pment; new /ecf Potential: 9 g , Archie Matthews / & Traffic Eng., Pending Funding Roadway, lighting and utilities to be CIP 2312 Hines Development; N. 3rd St. 8 . street, water & lighting for new Residential units to be built through ONDS programs) , Dou Mao Water/Irrigation, PENDING g y - (Mid -!ale 2011 N. 4th SL, vicinity of '5“ Street residential units ) c onstructed as a public project; Wastewater Design 8 R/Way are under way and Habitat Icr Humanity - CIP 2221 Wastewater Final Scada Tip Out Wastewater /Facility - Continued Max Linden Wastewater/B&V 5/1/09 Project 2221, 2222, 2223 bid as one;-Bids Continue tipping out existing communications 2222 DAFT Retrofit • SCADA and wastewater - • opened 4/14/09; Apollo awarded contract • 95% systems; replace existing covers; fix pressure and 2223 Dystor Retrofit improvements - upgrades complete. flow monitoring issue; electrical distribution system upgrades CIP 2228 Wastewater Congdon Sewer Main Wastewater /Collection Sys Shelley Willson / Engineering/ ?? Unknown Ryan Anderson Wastewater CIP 2234 Wastewater Neighborhood Wastewater . Wastewater /Collection Sys Shelley Willson / Engineering/ '/? Unknown improvements Ryan Anderson Wastewater • CIP 2264 Wastewater Speedway /Race street Interceptor Wastewater /Collection Sys Shelley Willson / WW/Eng./PLSA ? Late 201177 Design for the completion of the 36" sewer line to waiting on franchise from WSDOT R an Anderson Race street LS and demo LS NEPA & SEPA to be completed soon Wastewater Sewer Collection and storm water Wastewater /Collection Sys Shelley Willson / Wastewater/ 38 comprehensive plan update and Strom Water System j Ryan Anderson Akel Eng • CIP 1911 development 10/1/2010 Completion in 2012 39 Wastewater WW Facility plan update Wastewater /Facility Ryan Anderson Wastewater/ Coleman Stall are updating portions where an engineer is not CIP 2268 Eng 6/1 /2010 Completion late 2011 needed CIP 77 Waste f Gas Evaluation and Install New Wastewater /Facility Ryan Anderson Wastewater/ Pharmer 3/1 /2011 Older Boilers are wom out and will be replaced. Agas • 40 , : NEW Boilers Engineering evaluation is being done to properly size new boilers CIP 2306 ' " Power Distribution Wastewater /Farah Completion late 2011 for future demand I Wastewater Wastewater/Facility Ryan Anderson Wastewater/ Early 2012 Start Design April 2011 Contract being developed with Pharmer Engineering 41 2305 '. Industrial Waste System Engineering for Design and Construction services 254 .- ,: a uri r u..rades New .at- en. ..tliti•na P,n i•h in. CIP 2267 i. Wastewate r,.. Struvite Reactor and A -Basin Mixers Wastewater/Facility Ryan Anderson Wastewater/ Pharmer 5/1/11 0.'9n/construct struvite reactor This will remove Phosphorus from the WW effluent to 42 2256 " - NEW .' Magnesium Tank Relocate Engineering New Meg Tank to replace old/use for new and help meet future nutrient standards. - existinn nrncesses PWTF Loan, Water right transfer complete 8/22/06. Worked with Parks Division on siting of new well at • Water/Irrigation, W W, 1/26/2009 For drill Golder and Assoc. completed design. Bid Opened Gardner Park Archeological survey complete - no Design and Install a new 3,000 grim Mike Shane / Dave Nov. 6, 2008. Awarded to Layne Christensen findings. Drilling operations completed. Golder • 43 CIP 2132 Water /Irri New well at Gardner Park Streets, En Parks, 4/11/2011 for ion pump well at Gardner Park Brown g' Company, Drilling completed as of 3/9/09 (1,328') - we on tlesi of station. Plans a1100 %- Ridgeview School welihouse Wellhouse design at 100% Protect construction Apparent Low Bidder was William Charles West at beginning April 11, 2011. $1,122,290.75. Engineer Estimate was $1,597,140. PreCon. scheduled fed 4/1/11. • . i i • • • • • • • . I! • . • Proj Proj. Lead Division Project Name /Location Description of Work Project Lead Impacted Constrctn. Status /Schedule Notes I Type No, Divisions Start Date 4/12/11 . In Progress, fined canal under Hwy 12, completed - 11 study, work needed on diversion and areas of the 1 canal- Enlarged HcA has completed report and recommendations for Water/Irrigation, Refurbish the FmlNale Canal, ge pipe from General System to Dave Brown / Streets, Stowaler, Frudvale Canal. City crews completed connection multi -year piping project from 6th Ave. to 9th St. HLA rm 44 CIP 2010 Water /Irrigation Fatvale Canal Diversion and W asleway on H 2010/2011 working on design of entire project and make ready for • St Mike Shane Parks, DOT Yakima between General and FruiNale systems near 1601 County, WDFW and Jerome. Repaired wood gates at Cowiche construction. Working with other Divisions and l Creek. Point of diversion change to Nelson Bridge agencies on joint project. applications complete, submit to DOE in Jan 2011 1, - Water facilities impacted by 45 CIP 2288 Water/Irrigation Mist. waterline Improvements. other improvements - DFI, Mike Shane / Water /Irrigation, On -going coordination with Engineenng projects, p M transportation James Dean Streets, E 2011 Majority of work to be completed by in -house stall. Misc. sidewalk & trans p Eng. sidewalk projects and misc. Transportation projects projects. - Dave Brown Tom Coleman is Consultant. Project kick -oft a6 CIP 2258 Water /Irn anon Water System Plan U dale Begin preliminary plan, Plan Mike Shane Water /Irrigation g y p due in 2010 Jell Band James Planning N/A meeting with DOH on July 23, 2009. Review of Draft submitted to DOH on January 23, 2011. Dean Chapter 2, on 12/10/2011. Recycle lagoons and new electrical Design of new recycle lagoons; Dave Brown 47 CIP 2259 Water/Irri ation g new 800 am electrical service; Mike Shane Water /Irri abon 7? Waiting funding HLA completed report for City and DOH on g service at the WTP p g g g recommendations for design. 2011 DWSRF Loan applietl for new generator Jeff Bond 1 . Internal discussion to began in January 2010 to Inter- agency agreement approved by Council, Selah determine next course of action. G 8 O (consultant) Begin process of determining Dave Brown Water /Irrigation • and Nob Hill. Funding identified in 2011 budget to 1 • 48 CIP 2261 Water /Irrigation Automated Meter Reading method, materials, process for Mike Shane Wastewater 2009 Provided study and recommendation for Yakima, begin project Mueller pilot project underway 3/1/11 II James Dean Utility Billing Selah and Nob Hill. Reported provide automated water mater reading y g recommendations specific to each agency for approx. 4 weeks. Badger meter pilot project I Installing two 20 unit pilot tests near YVCC underway. Design the water main Water/Irrigation HLA is consultant. Project design is 95% Project will be constructed as funding becomes 1 49 CIP 2262 Water /Irrigation Replace Main at 1 -82 and Viola replacement at I -82 and Viola Mike Shane Wastewater 77 Waiting funding complete. available. Irrigation System Replacement HLA is consultant Project design in the neighborhoods north of 1 gn complete. General Irrigation - Water/Irrigation Bid opening Sept. 29, 2010. Construction underway 9 bids received. KRCI, LLC low bidder at 50 CIP 2287 Water / Irrigabon E. A St., south of E. I St., east Mike Shane 2010/2011 Phase 4 - Stage 1 Wastewater, Streets and is 90% complete. To be completed by April, $863,733.55. EE $1,049,772.63. of S. 1 st SL and west of S. 10th St., SR12 at 40th Ave. • 2011. .I Irrigation System Replacement HLA is consullanL Project design complete. Capital Hill/Loma Vista Irrigation in the neighborhoods between Water /Irrigation 10 bids received. Premier Excavation, Inc- low bidder 51 CIP 2257 Water /Irrigation System Returbish Ph.2 W. Yakima Ave. to Tieton Dr., Mike Shane Wastewater, Streets 2010/2011 Bid opening Sept 22, 2010. Construction underway at $830,20021. EE $1,026,498.81- . S. 7th Ave. to S. 12th Ave. and Is 90% complete. To be completed April, 2011. • il Streets 2011 Sealcoating Program Chip -Seal roadways that had Streets, 24th, Nob Hill to Washington; Status of Sealcoaling all depends upon available II 52 CIP - wheel -paths ground Joe Rosenlund Water /Imgation mid -year 2011 m SumiMew, 7111 to 18th; funds in the sealcoating program • NEW Lincoln, 16th l0 40th and patched in 2010 Wastewater, Traffic . . . . .. COMPLETED PROJECTS Ii Co n sewer crossing for future struct sewer manhole and CIP N/A Engineering 1 64th Ave Sewer Crossing Doug Mayo / Engineering, Winter Small Works Project awarded lo: Project is complete; going through at Occidental Dana Kallevig Wastewater 2010/2011 West Coast Construction cleanup and project closeout I continuation to east Reconstruct sewer manholes Doug Maya / Engineering. CIP N/A Engineering Pierce Avenue at 3rd Avenue g, Summer 2010 Work is Complete; Project is to completed 1/4 and connections Dana Kallevig Wastewater complete; move next 1 CIP 2255 Wastewater Pretreatment offices Wastewater /Facility MaxUnden - Wastewater 6/1/09 Add office space in storage building '09 100% complete (moving to completed next 1/4) , CIP 2055 Wastewater WWTP PhaselFacilily Wastewater/Facility Max Unden B &V/Water -Irr /Cam. 6 /1 /06 WWTP improvements /upgrades - construction Apollo Inc -100% complete 1' • Improvements Electronic sec completed I CIP 2229 Engineering Nob Hill Overpass Repairs Repair deteriorated portions Brett Sheffield / Engineering 8/2009 Contract awarded to Mowat Construction Co.; Work Project is complete and closed out; of the overpass Bob Desgrosellier started 8/20/09 - through April 2010. move to completed next quarter Place several types of Surface 1 CIP 2291 Engineering J Street LID Demonstration; Water Drainage Materials in Randy Meloy / Engineenng, Streets 4/2010 RP &E of Ellensburg has contract; Project is being dosed out 7 Street, 18th to 20th Avenues roadway for drainage study Brett Sheffield project is complete and is being dosed out I 1 Remove 8 replace sidewalk, , County & City Joint 'DFI - Styled Engineering, Streets Granite Northwest is Low Bidder; • new lights, trees, twinkle lights, Brett Sheffield / Improvements; West -side of 2nd Street, & Traffic Eng., Construction is complete, 1 CIP 2285 Engineering landscaping; (New community Mark Brzoska - 10/2009 Project is being closed out j MLK to •A' Street; north side - A - Street Water /Irrigation, (Adjacent Performance Park 2nd Street westerly to alley; performance park is adjacent) Yakima County Wastewater Construction is complete) I I Public Works/ Study Transit, Streets, Fire, Initial Meetings have begun. 1 CIP West side service sub station study (No Action Taken) Chris Waarvick Police, W WT, ?/09? $5 approved through 2007 Council Budget Admin PPr 9 , Information Systems 1 28th Avenue, south of Washington Add curbing on east side, widen Brett Sheffield / Interest from private partners fell through; CIP 2241 Engineering south to Airport and rebuild roadway Bruce Floyd Engineering Cancelled 6/2010 Project to be deleted from list P Y Y project will be cancelled j I ; I 1 1 I I I 1 j 410 . • 1 • l . 0 • 11 0 ID . Proj Proj. Impacted Constrctn- Notes Type No. Lead Division Project Name /Location Description of Work Project Lead Status /Schedule • Divisions Start Date 4 /12/11 • Ped signals at 16th & Bonnie Doom New crossin si oats and Breit Sheffield / 1 CIP 2236 Engineering 41h Street & MLK; g g Engineering, Traffic 10/2008 Low bitlder: Knobel's Electric of Yakima . N. 1st St. 8 N. 16th near Hathaway painted crosswalks Dan Ford 4/2010 Construction 100% Complete. way imps; Roadway reconstruction, I: Jeld -Wen road' Brett Sh / CIP 2120 Engineering pathway addition on west side Engineering 7/2009 Low bidder: Grand NW I of Yakima 6th Avenue, Power Rd. north 650' Dan Ford 4/2010 Construction 100% Cam plete, of roadway CIP 2182 Wastewater UV Disinfection Wastewater /Facility Max Linden B&V/Water -Irr /Com. 3/1/08 WWTP improvements/upgrades - bid, contract awarded to Apollo Inc. • " • Electronic sec 100% complete; closing protect out CIP 2188 Wastewater 40th & Fruilvale sewer sleeve Wastewater /Collection Sys MaxLinden B&V/Enq/Water March/April 2007 WSDOT Project- Completed complete. waiting for WSDOT project closure 1' CIP 2278 Engineering Nob Hill Blvd, 64111 to 72nd Avenues Widen roadway, add sewer & Brett Sheffield / Engineerng, Traffic Project cleanup & closeout is underway, water utilities Bob Desgrosellier Eng., Wastewater 8/2009 Project is 700% complete 4/2010 .$950K ARRA funding received for Crty portion i i • CIP 2208 En 85th Avenue, Kail &Juanita Sewer Neighborhood sewer LID - Al Rose /BreH Engineering' 2/2009 Premier Excavatin was low bidder; Project is closed out; Engineering Local Improvement District (LID) Approx. 29 parcels Sheffield Wastewater 100 %complete final assessment hearing went to Council 4 /6/10 Simpson Lane Sewer Excavati LID; So. 13th, Neighborhood sewer LID - Bob Desgrosellier / Engineering, Scoff's Excavating Council assessment hearing Is coin I CIP 2215 Engineering 14th, 15th Streets A rox. 82 parcels Al Rose Wastewater 2/2009 9 was low bidder; g' p ete; 4/2010 1 PP P 100% complete Realign 16th Ave. south side of Engineering, Streets & • CIP 2213 Engineering 16th Avenue Realignment @ Airport airport tying to future V. Mall Brett Sheffield / Traffic, Wastewater, 7/2009 Project is 100% complete; Bob Desgrosellier Low bidder was: Granite Northwest; 100 % complete. Blvd. 8 16/Wash Water/Irrigation • Downtown Futures INliahve (DF11, Phase Remove & replace sidewalk, Engineering, Streets Reconstruct: east side 1st Street; 2nd St. both ' CIP 2216 Engineering 3; 1st SI., (o Yakima, 2ne St., to new lights, trees, twinkle lights, Brett Sheffield / & Traffic Eng., - sides, 3rd St. both sides, west side Neches all 100% complete. gine g . 7/2008 Chestnut Walnut . 3rd St.. W m landscaping Bob Desgrosellier Water /Irrigation, Yakima Ave to "A" Street; plus both sides • Yakima, (Neches "A" to Yakv) Wastewater So. 2nd SL Yakima to Chestnut Ireton Dr. Pedestrian Project, Update north side sidewalk, Brett Sheffield; Engineering, Traffic, GIP 2233 Engineering 76th Ave to 24th Avenues including wheelchair ramps Dan Ford / Wastewater, 10/2008 Construction is 100% complete 100% complete. - I • Joan Davenport Water /Irrigation CIP 1977 Engineering Nob Hill Blvd, Construct sanitary sewer, north Doug Mayo / Engineering, • g 53rd to 62nd Avenues (41 side of roadway Brett Sheffield Wastewater &2009 Premier Excavating: Project completed 100% complete. • Kiwanis Skateboard Park; New concrete Skateboard Park • CIP 2023 Engineering Bob Desgrosellier Engineering, Parks 6/2008 Bids o ned on 5/15/08 Construction Is complete; Fair Ave & Maple Street • @ IOwanis Park Parks has project funds fora few more amenities Grind and Overlay (G &O) Engineering, Traffic, rd Ave. - Grind & Overlay ; Brett Sheffield / CIP 2230 Engineering roadway & resiripe; update Wastewater, 8/2008 We extended good and overlay to just north of • Mead Avenue to Chestnut Randy Tabert Washington Avenue Project is complete wheelchair ramps Water /Irrigation I Engineering, Streets, CIP 2214 En ineerin W. Nob Hill - Grind & Overlay; Grind and Overlay (G &O) of Bob Desgrosellier good bids; grind inside lanes and sealcoat Project is complete; g g 24th Avenue l0 4th Avenue two Inside 'through' lanes Wayne Deason Water, Wastewater, 8/2008 I; yne Traffic Eng entire width in 2008 ($500,000 REET?) Streets to sealcoat in future as funding H available ' M&O Streets Poplarview Way - Check lace of plat Chris W aervick / Nob Hill Water 2008 Graded and dust abatement material applied spring I Project is complete Randy Meloy Wastewater 2007; new easement in place Rdwy River Rd. Improvements, 15th to New 3 lane roadway, C /Gutter Engineering, Streets. 1944: 8 S/Walk, ADA ramping, street Brett Sheffield / Traffic, Water / CIP Sew Engineering FruiNale, 27' Sewer trunk 6th Ave to lighting. Replace 8'sewer with Bob Des 9/19/06 This project is closed out Complete Frut 0 9 g P grosellier Irrigation, Old Union 2128 27" trunklme - Ditch, Wastewater - CIP Engineering Harman's Senior Center Parking Lot Reconstruct & repave parking Brett Sheffield / En Reconligurafion - N. 65th Ave. lot to maximize parking gineering, Parks 4/21/08 contractor done; complete 5/2/08 Protect is complete Streets 90th Ave Lerto Tinton: Lai - 72ntl Ave. to Arterial Chip Seal Wayne Deason Mid-June 2008 REET & Street Division Budget I 80111 Ave.: 7200 Avenue . Nob Alt to Coo/022; M &O Castkvalo-2xlh Ave to Powerhouse: I Powerhouse - ■Oth Ave to Ow West Gil/ Imila; Powerhouse ■Oth Ave to Lmcoki; - II ONDS development, was Brett Sheffield / Engineering, ONDS, CIP 2107 Engineering Marvin Gardens Development Wastewater, 10/15/07 This project is complete and being closed out Project is complete • private, switched to public Al Rose Water /Irrigation West Yakima Avenue Ito R & replace side Brett Sheffield / Street 8 Traffic, provemenis Project is complete; Banners are in place; working on CIP 2165 Engineering n lights, trees, twinkle lights, Water /Irrigation, 7/2007 This project is complete - Front Street to 7th Avenue landsca Bob Desgrosellier gettin ping Wastewater 9spring- loaded banner arms outside of contract R/R Grade Separation, Phase I; Utilities Relocations Engineering, Phase I - Utility ing Weslcoasl Construction is Prime; Work included 1818 Bob Desgrosellier / Water /Irrigation, Front Street and 'A' Street brick/paving in Project complete; Phase I P i CIP Engineering Lincoln Ave. & Martin Luther King Jr. surrounding the Grade 'Relocation work Brett Sheffield Wastewater , g nght -ol -way, indWes utility relocation in we soda- blasted utility markings as final step , Blvd. vicinity Separation Project began gan July 23rd existing underpasses Streets, IS area of future CIP 2087 Wastewater Speedway Interceptor SR24 phase 1- Wastewater /Collection Sys Max Linden _ 6&V/Engineering 3/19/07 Need to connect at diversion box - completed - work complete waiting for WSDOT project closure and . 82 Viola to Speedway on punch list :WWTP waiting for rebate of funds from DOT - • CIP 2087 Wastewater Speedway Interceptor Speedway to Wastewater /Collection Sys Max Linden B&V/Engineering Design/Bid/Construction inspection- Not funded yet Washington School - Memorial Hospital to En No. 30th Avenue - Reconstruction; P Bob Desgrosellier/ gmeenng, Streets, Eng has estimate for Streets & Waarvick; awaiting CIP - Engineering Tietan Drive to Walnut 30th Avenue due to damage Bruce Floyd Water /litigation, 7 / 2007 � Hospital funding; may have been sealcoated for Seal Coating completed • during their campus upgrades Wastewater temporary measure? � Fruilvale Blvd & 40th Avenue 200' + /- of 42' carrier pipe for Brett Sheffield / Street & Traffic, Superior Paving is prime; Project tied with WSDOT Sewer ring complete; CIP 2188 Engineering Water /irrigation, Feb/March 2007 construction project of new on - ramps and interchange reconstruction @ 98 %; Sewer X -ing of WSDOT on -ramp future 27' sewer trunk Bob Desgrosellier Wastewater interchange upgrade. si onal in 8 running; hail connection complete CIP 2116 Engineering Basalt Art Project, 2nd & E Yakima Basalt column placement with Brett Sheffield / Bob Engineering; Parks g 9 j lit Cornucopia & brass Sun Desgroselier 6/7/07 An work complete, on time and on budge[ 6 -20-07 Project is 100% complete; • 11 1 • li II Proj Proj. Lead Division Project Name /Location Description of Work Project Lead Impacted Constrctn. Status /Schedule Notes Type No. Divisions Start Date 4/12/11 2 western medians to be Washington Avenue Median removed for left -turn storage. Bob Desgrosellier / Engineerin Traffic, Bid, 2- 14 -07, _ CIP 2124 Engineering g ' construct spring Columbia is Prime; 6 -20-07 Pro Removal btwn 16th & 24th Ayes Eastern median gets several Randy Tabert WalerArrig 100 % complete lecl is 100% complete, new lights 8 brick pavers 2007 CIP 2169 Engineering 61h Street S/Walk Replacement, one Remove & Replace one block Bob Desgrosellier / Engineering, Traffic, Tied to Lincoln Avenue Sidewalk Construction . Spring 2007 6th Street project is 100 %complete; • block No Race Street of concrete sidewalk Larry Johnston WaterArrig Project; Block Grant funds 100% complete New sidewalk on Lincoln, Engineering, CIP 2046 Engineering Lincoln Ave. Sidewalk, 25th l0 29th adding 24th to 23rd on Linc. Bob Desgrosellier / W ater /Irri eon, Spring 2007 Columbia is Prime; Ave- & nwa urch near 18th Ave, L ga pr g Lincoln Sidewalk 100% complete 8 -11 -07 Project is 100% complete; y p and 40th Ave- near Lincoln any Johnston Streets and Traffic P i CIP 2095 Water /Irrigation PRV in 4016 Ave. Pump Station Install PRV in 40th Ave. Pump Dave Brown Water /trrigavon, Summer 2007 Old pump removed by City crews. PRV installed by Final Cost - $7,100 Rehab, work in -house Station Streets, Engineering City Crews. Work completed. CIP / 2131 Wafer /Irrigation MaClaren Reservoir Rehabilitation Repaired cracks in MaClaren Mike Shane Water /Irrigation 3/1/07 100% Complete Final Cost - 531,216 M&O Reservoir. Replaced ladder & slide gate. Repaired weir box. 2142 Water /Irrigation Front St. Water Main Replacement water main replacement for Mike Shane Water/Irrigation. and August of 2007 Water main in Front St., Lincoln and MLK installed. CIP railroad grade separation Engineering All water services transferred to new main in Front ' • project. Streets include Front from Yakima to MLK St., MLK and Lincoln. 2179 Water /Irrigation Brackett Park Irrigation System Replace the wood irrigation Mike Shane Water /Irrigation, 11/19/07 Bid opening occurred Oct 3, 2007. Jansen Inc. of Final Cost - $215,705.19 CIP Replacement pipes in the Brackett Park Streets - Ferndale, WA is contractor. HLA is consultant I; system Project is 100% complete. Final clean -up and • restora0on in spring 2008. 2181 Water /Irrigation Repair /Replace Glenn Drive Replace the pump station and Mike Shane Water /Imgation 11/01/07 Design complete. Bid opening Oct. 10, 2007. Final Cost - $326,570.45 CIP Reservoir Pump Station and Platform platform in Ore Glenn Drive POW of Pasco, WA is contractor. Work is Reservoir underway. HLA is consultant. Project is 100% complete. Replace Radios and Antennas for Replace Radios 8 Antennas for CIP 2185 Water /Irrigation Telemetry System Telemetry System Dave Brown Water Apr -07 Complete Cost $27,755.34 Decommission the Ranney Water - DOT - Decommission complete, W SDOT hauled fill. Out CIP 2218 Water/Irrigation Ranney Well Decommission Well Dave Brown Yakima County Spring of 2008 complete to adv. for hauling rest of spoil material CIP 2097 Waler/Irngalion SR 24 water main under crossing SR24 Under crossing Mike Shane Engineering, 6/1/05 100% complete Final Cost - $290.484 Wastewater 2054 & Water /Irngalion WTP Chemical Feed Improvements Chemical Feed System, New Dave Brown Water /Irngalion 6 /1 /05 100% complete Final Cost- $4,660,003 • CIP 2002 & Filter Rehabilitation Building, Pumped Flash Mix, Rehabilitate Filters CIP 2099 W ater /Irrigation West Yakima Irrigation System Replace the W. Yakima Mike Shane Water /Irrigation, 10/1/05 100% complete, dose out project. Final Cost- $798,580 I (south of Summitview) Irrigation System Streets CIP 2059 Water /Irrigation General Irrigation Phase 2- Stage 1 Replacement of the General Mike Shane Water /Irrigation, 10/1/04 100% complete. Final Cost - $2,912,300 to 3 Irrigation System 2004 - 2007 Skeels 2096 Water /Irrigation 2nd Level Reservoir Pipe New waterline in Pecks Canyon Mike Shane Engineering and 9/1/06 100% complete. Final Cost - $894,930 Improvements - Ph. 1 Rd. from Powerhouse to 1,200' Wastewater, south. Replaced/Relocated Water/Irrigation, CIP waterlines at 2nd Level Resv. Yakima County, and at intersect of 40th and Streets • Powerhouse. 2096 Water /Irngalion 2nd Level Reservoir Pipe RehabJlnstell new waterlines, Mike Shane Engineering, 1/14/08 Survey and design completed. Bid opening was Final Cost - $147,336.05 CIP Improvements - Ph. 2 drainlines and control valves at Water /Irrigation Dec. 5, 2007. Contractor is TTC of Yakima. HLA is 2nd Level Resv. Site consultant. Project is 100% complete. Irrigation System Replacement • . in the neighborhoods south of General Irrigation Pacific Ave., north of E. Nob Water/Irrigation, Bid opening occurred Sept. 26. 2007. KRCI of CIP 2180 W ater/Irrigation phase 3 -Stage 1- Hill Blvd„ east of S. Neches Mike Shane Streets Stage 1 - 11/2007 Wenatchee, WA is contractor. HLA Is consultant Final Cost - $1,329,593.67 Ave., west of Fair Ave. Also, Project is 100% complete. Custer Ave. between Lincoln and W. A Street • i Irrigation System Replacement j m the neighborhoods north of HLA is consultant. Project design complete. General Irrigation Water /Irrigation, Advertise Sept. 17, 2008. Bid Opening Oct - 2, 10 bid received- Low bid - $739,132.11, EE - CIP 2180 W ater/Irrigabon Pacific Ave-, south of E. Pine Mike Shane 11/01/08 I, Phase 3 - Stage 2- SL, east of S. 1 sl SL, west at Streets 2008. Project awarded to Jansen, Inc - of Femdale, $1,117,451.73- Final contract - $638,956.56 I Fair Ave. WA, Construction is 100 %complete- Irrigabon System Replacement in various neighborhoods Project areas include areas bounded by A) Lincoln, HLA is consultant Project design complete. i. CIP < "220 Water/Irrigation Hdlcrest, N. Hillcrest and Buena Vista SummMiew, N. 35th Ave. and Mike Shane Vvater /lnigabon, 11/91/08 Advertise Sept. 24, 2008. Bid Opening Oct 8, 6 bids received. Low bid - $633,122.02. EE - I I rrigation System Replacements N. 37th Ave., B) Tieton Dr, Streets 2008. Project awarded to Rotschy. Inc. of Yacoll, $777,877.67 Final Contact Price - $607,855.47 Bonnie Doan, S. 1615 Ave. and WA- Construction is 100% complete. ' S. 19141 Ave. and C) Chestnut, Tieton, S. 18th Ave. and S. 19th • Ave. i • • • • •