HomeMy WebLinkAboutR-2007-144 Black & Veatch Corporation / Budgeted Funds Expenditure (re: Phase 1 Wastewater Facility Plan)RESOLUTION NO. R-2007-144
A RESOLUTION authorizing the City Manager to approve use of budgeted funds for the
continued implementation of Work Packages • described in the April 23,
2003 Agreement Between City of Yakima and Black and Veatch
corporation for Professional Services.
WHEREAS, the 2004 City of Yakima Wastewater Facility Plan identifies the
requirements by regulatory mandates, growth (capacity) issues, replacement of aging facilities,
and improved efficiencies that are going to be needed over the next 20 years; and
WHEREAS, Black & Veatch Corporation completed the Facility plan, Phase One Pre -
design, Phase One Final Design, Phase One Bid Phase Services, NPDES Permit Services and
Metals Studies, continues providing Construction services for Phase One implementation, and
began the Collection System Evaluation, as described in the Agreement Between the City of
Yakima and Black & Veatch Corporation made and entered into on April 23, 2003; and
WHEREAS, Council authorized execution of budgeted funds for Design Services and
Collection System Evaluation on 7/7/04. On 12/13/05 an amendment to the professional
services agreement with Black & Veatch Corporation was authorized by Council for
implementation of the Phase One WWTP Improvements; and
WHEREAS, with additional Human Machine Interface (HMI) Software Upgrades
identified for the WWTP processes, use of additional budgeted funding for professional
engineering services and ongoing, construction services for WWTP Improvements per the
Agreement with Black and Veatch Corporation were approved on 11/07/2006; and
WHEREAS, with the addition of the Ultra Violet Disinfection System and ongoing Phase
1 construction, use of additional budgeted funding for professional services is required to
continue these projects per the Agreement with Black and Veatch Corporation; therefore
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF YAKIMA:
The City Manager is authorized to approve use of budgeted funds for the continued
implementation of Work Packages described in the April 23, 2003 Agreement Between City of
Yakima and Black and Veatch Corporation for Professional Services.
ADOPTED BY THE CITY COUNCIL this 16th day of October 2007.
City Clerk
41.Z/
David Ed er, ayor
Exhibit A
Summary of Work Packages
Work Package
Approved
Approved
Approved
Amendment #1
Approved
Approved
TOTAL
4/23/2003
5/18/2004
7/7/2004
12/23/2005
11/7/2006
requested
WP #1
Prepare Final WWTP Facility Plan
$608,000.00
$608,000.00
WP #2
WWTP Design & Bid Phase Assistance
$1,800,000.00
$1,800,000.00
1
WP #3
Quantify WW flows throughout Collection System
$400,000.00
$400,000.00
WP #4
Mandated Metals Study & addition' I NPDES studies
$200,000.00
$200,000.00
WP #5
SR 24 Permit Review and Monitoring Plan support
$150,000.00
$150,000.00
WP #6
Speedway Interceptor Route Eval. Design & Bid Phase
$450,000.00
$450,000.00
1 1 1
WP #7
Risk Management Plan Development & Assistance
$50,000.00
$50,000.00
1
WP #8
Human Machine Interface (HMI) Software upgrades
$221,000.00
$100,000.00
$321,000.00
1
WP #9
Odor Evaluation and Survey
$70,000.00
$70,000.00
1
WP #10
Construction Phase 1 and Operation and Maintenance Manual
$809,000.00
$500,000.00
$1,309,000.00
1
WP #11
Phase 1 Construction & Administration Services, Commissionln& record Drawin
s
$1,070,000
$1,070,000.00
1
TOTAL $608,000.00
$2,200,000.00
$350,000.00
$1,600,000:00
$600,000.00
$1,070,000.00
$6,428,000.00
WORK PACKAGE 11
Owner: CITY OF YAKIMA, WASHINGTON
ENGINEER: BLACK & VEATCH CORPORATION
Project: WASTEWATER COLLECTION AND TREATMENT CONSULTING SERVICES
1. OBJECTIVE — WORK PACKAGES 11
These BASIC SERVICES include engineering, consulting and construction administration
services related the following:
• Continuing construction administration services related to the Phase 1 Improvements
Project, including the Ultraviolet Disinfection Project
• Phase 1 Improvements Record Drawings
• Commissioning Services for Phase 1 and UV facilities
Additional prioritized improvements that will be considered as project funding budget is available
include the following:
• Additional minor associated improvements.
2. TIME OF PERFORMANCE
The time of performance for Work Package 11 is September 1, 2007 through December 31, 2008.
3. COMPENSATION
CITY shall pay ENGINEER for performance of BASIC SERVICES. Compensation for Work
Package 2 shall be paid to ENGINEER on the basis of labor plus reimbursable expenses.
Total compensation to ENGINEER for the Scope of Services defined for Work Package 11 shall
not exceed $ 1,070,000, plus any applicable taxes, unless specifically authorized by CITY in
accordance with subsection 5.2 of the AGREEMENT BETWEEN CITY OF YAKIMA,
WASHINGTON AND BLACK & VEATCH CORPORATION FOR PROFESSIONAL
SERVICES.
Task Series 5000 & 9000— Phase 1 Construction Administration Services
$ 760,000
Task Series 5010 — Phase 1 Record Drawings
$ 110,000
Task Series 6000 — Commissioning Services
$ 100,000
1
Task Series 8000 — Miscellaneous Services
$ 100,000
4. SCOPE OF SERVICES
The BASIC SERVICES for Work Package 11 will be executed in tasks summarized as follows:
• Task Series 5000 — Phase 1 Construction Administration Services
• Task Series 5010 — Phase 1 Record Drawings
• Task Series 6000 — Commissioning Services
• Task Series 8000 — Miscellaneous Work
• Task Series 9000 — Project Management/City Coordination
WORK PACKAGE 11
TASK SERIES 5000 — PHASE 1 CONSTRUCTION ADMINISTRATION SERVICES
ENGINEER shall provide construction administration services for Work Package 11 in accordance
with Task Series 5000 of the AGREEMENT BETWEEN CITY OF YAKIMA, WASHINGTON
AND BLACK & VEATCH CORPORATION FOR PROFESSIONAL SERVICES. ENGINEER
shall continue to provide services for a term of sixty three 63 weeks beginning September 4, 2007.
ENGINEER shall provide a full-time, on-site resident project representative through this time.
Primary tasks shall be construction phase services for the completion of Phase 1 and UV
construction. ENGINEER shall, in accordance with the AGREEMENT BETWEEN CITY OF
YAKIMA, WASHINGTON AND BLACK & VEATCH CORPORATION FOR
PROFESSIONAL SERVICES.
Assumptions:
• Total Construction Phase Services Duration: 63 Weeks (September, 2007 to November,
2008)
• Total Submittals: 25
• Total Requests for Information: 30
• Total Requests for Change: 5
• Total Change Orders: 5
• Construction Progress Meetings to occur bi-weekly.
• Eight Site Visits by Goris/Ward.
TASK SERIES 5010 — PHASE 1 RECORD DRAWINGS
ENGINEER shall provide a revised set of construction contract drawings for Phase 1
improvements including blowers, solids handling building and UV Disinfection System in
accordance with Task Series 5010 of the AGREEMENT BETWEEN CITY OF YAKIMA,
2
WASHINGTON AND BLACK & VEATCH CORPORATION FOR PROFESSIONAL
SERVICES.
TASK SERIES 6000: COMMISSIONING/OPERATIONS ASSISTANCE
ENGINEER shall assist the City in commissioning the new equipment including blowers, solids
handling building and UV Disinfection System. Primary work shall be performed by Conley
Engineering in support of the new SCADA system and controls for the new equipment.
The level of effort will be determined based upon coordination with the City during startup.
TASK SERIES 8000 — MISCELLANEOUS SERVICES (To be defined as necessary)
Supplemental Services as set forth in Section 1.5 shall be performed as the need arises and as
mutually agreed by CITY and ENGINEER. Scopes and budgets for individual tasks for
Supplemental Services shall be defined within Task Series 8000.
TASK SERIES 9000 — PROJECT MANAGEMENT / CITY COORDINATION
11
The ENGINEER shall manage the work, of its project team and conduct activities to maintain
coordination of the work with the CITY. !'
Task 9200: Progress Meetings. ENGINEER will meet with CITY staff quarterly to review the
progress of the project. These meetings will provide an opportunity for input from the CITY
regarding the activities of the project team" and for presentation and exchange of information.
ENGINEER will prepare a written summary after each meeting and distribute them among the
project team. The documents will summarize significant discussion points, decisions, and action
items arising from each meeting. ENGINEER will revise meeting summary if needed to reflect
comments from meeting participants.
Task 9300: Monthly Progress Reports: ENGINEER will submit monthly reports summarizing
the progress of the project by task, for ;its duration. The reports will be submitted along with
ENGINEER's monthly invoices. The progress reports will document progress made toward
completion of the project, and provide updated information on budget and schedule. It is
anticipated that 15 such reports will be provided during this work package.
Task 9400: Project Administration. ENGINEER will perform the general administrative duties
associated with the project, including preparation of correspondence, office administration,
administration of contracts with subconsultants, monthly invoicing, and progress monitoring.
3
Yakima Phase 11 Budget
Ward
Hunt
Gods
Project
Staff
Markvica
Structural
Discipline
QA/QC
CADD
Clerical
B&V
Conley
Other
Owner
4eimbursablf
Task
WORK ITEM
PM
EM
EM
Engineer
Engineer
Resident
Engineer
Engineers
Total
Engineering
Consultants
Contingency
Expenses
Total
Billing Rate
$225
$159
$155
$140
$100
$110
$155
$145
$155
$80
$72
Task Hours
Task Series 5000 - Phase 1 & UV Construction Support
150
420
700
2520
40
240
80
80
$499,210
$3,168
$502,378
Task Series 5000 - Phase 1 & UV Construction Support- Conley
$0
$100 000
8100,000
Task 5000A -Phase 1 Programming Services
$0
$112,900
$112,900
Task 5000B - W System Programming Services
$0
819,000
$19,000
Task Series 5010 - Record Drawings
80
0
160
500
16
$69,552
$40,448
$110,000
Task Series 6000 - Commissioning Services
8
40
80
0
40
40
$24,680
$75,320
$100,000
Task Series 8000 - Miscellaneous Work (services TBD)
$0
8100,000
8100.000
Task Series 9000 - Prosect Management/City Coordination
74
126
$25,722
$25,722 _
Total Hours
232
0
540
0
940
2520
40
280
0
580
262
5,394
Total Cost
$104,400
50
$83,700
p
594,000
$277 200
$6,200
540,600
$0
$46,400
518,864
$619,164
$347,668
50
$100,000
53,168
$1,070 000
BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT
Item No. 0
For Meeting Of 10/16/07
ITEM TITLE: Consideration of a resolution authorizing the City Manager to approve use
of 2007 budgeted funds, and preliminary 2008 budgeted funds, for the
continued implementation of Work Packages described in the April 23,
2003 Agreement Between City of Yakima and Black and ' Veatch
corporation for Professional Services.
SUBMITTED BY: Dave Zabell, ACM - Doug Mayo, WW Manager - Max Linden, Utility
Engineer
CONTACT PERSON/TELEPHONE: Max Linden/575-6077
SUMMARY EXPLANATION:
The 2004 City of Yakima Wastewater Facility Plan identifies the requirements by regulatory
mandates, growth (capacity) issues, replacement of aging facilities, and improved efficiencies
required over the next 20 years. Over the past 5 years the engineering consulting firm of Black
& Veatch Corporation has provided NPDES Permit Services, began the Collection System
Evaluation, completed a Metals Study,' completed the 2004 Facility plan, completed a Risk
Management Plan, completed the Pre -design, Final Design, and Bid Phase Services for the
Phase One WW Improvements and Speedway Interceptor Trunk Line, and has provided
continuing construction services from the spring of 2006 for the current mandated Phase One
Wastewater Improvements as described in the April 23, 2003 Agreement Between City of
Yakima and Black and Veatch Corporation for Professional Services.
(...continued on next page)
Resolution X Ordinance _ Other (Specify) to authorize use of budgeted funds for Phase
One WWTP Improvements
Contract -- Mail to (name and address):
Funding Source WW Facilities Project (478 Fund, Budgeted and WW Facilities Project (472
Fund) Budgeted
APPROVED FOR SUBMITTAL:
City Manager
STAFF RECOMMENDATION: Staff respectfully requests City Council approve the resolution.
BOARD/COMMISSION RECOMMENDATION:
COUNCIL ACTION:
(...continued from front page.)
Council authorized use of budgeted funds for all these completed activities on 4/23/2003,
5/18/2004, 7/7/2004, 12/23/2005, and on 11/7/2006. Currently $5,358,000 has been spent. See
the attached Exhibit A.
An additional $1,070,000 is required to continue the current ongoing Phase 1 construction work
(project 2055) and Ultra Violet Disinfection project (project 2182) for the remainder of 2007 and
to continue the projects in 2008. See the attached Work Package #11. This expense is shown
in the 478 Wastewater Facility Project Fund (Phase One Improvements project 2055) and 472
Wastewater Facility Project Fund (Ultraviolet Disinfection project 2182) identified in the 2007
adopted budget and 2008 preliminary budget includes appropriations to accommodate the
expenditures required to complete the first portion of Phase One improvements and
Construction Services provided by Black & Veatch Corporation. This will increase the total
authorized budget for this agreement to $6,428,000. See the attached Exhibit A.
Approval of additional engineering services provided under the agreement between the City of
Yakima and Black & Veatch Corporation for professional services, along with future
construction of Phase One WWTP improvements, will be asked for upon the 2008 budget
approval and as resources become available.